Prepare the bed for the laying of PCC with 95% compaction.
Laying of PCC bed including rebar mesh.
Laying of Precast Trench in proper alignment and slope.
Backfilling of sides of installed trench with proper compaction up to 95%.
Note:
1. Concrete, Rebar Mesh, Precast Trench is supplied to you by RIMAL.
2. All Manpower required for the above said work will be supplied by
you.
3. All changes & rectifications will be done by your side. The work shall
be carried out as per consultant’s specification.