INTERIOR ROUNDABOUT SIGNBOARDS [42]

RIMAL GLOBAL TECHNICAL SERVICES LLC


Project Start: Sun, 5/19/2019
Display: Weekly

19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10 17 24 31
May May Jun Jun Jun Jun Jun Jul Jul Jul Jul Aug Aug Aug Aug Sep Sep Sep Sep Sep Oct Oct Oct Oct Nov Nov Nov Nov Dec Dec Dec Dec Dec Jan Jan Jan Jan Feb Feb Feb Feb Mar Mar Mar Mar Mar Apr Apr Apr Apr May May May May May
'19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20

ASSIGNED BUDGET PLAN PLAN PLAN ACTUAL ACTUAL ACTUAL


WBS TASK DESCRIPTION
TO QTY
PROGRESS
START END DAYS START END DAYS
REMARKS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54

1 DESIGN AND APPROVAL Moosa 192 0% 19/May/19 21/Jul/19 64

MAS Submittal/ Approval for Signboards 192 0% 19/May/19 29/May/19 11

Necessary Approval from PDO/ROP 0% 30/May/19 14/Jun/19 16

Approval of Permit Holder (If Any) 0% 15/Jun/19 22/Jun/19 8

Order for Precast Foundations & Sign Boards 192 0% 23/Jun/19 21/Jul/19 29

Site Survey 0% 16/Jun/19 6/Jul/19 21

Location-01 Moosa 0% 26/Jun/19 10/Jul/19 15 30/Dec/99 30/Dec/99 1

Mobilization of resources 0% 26/Jun/19 27/Jun/19 2

Safety arrangement prior to work 0% 2/Jul/19 3/Jul/19 2

Excavation 0% 4/Jul/19 4/Jul/19 1

Installation of Precast Foundation 0% 5/Jul/19 7/Jul/19 3

Installation of Sign Boards 0% 8/Jul/19 10/Jul/19 3

Location-02 Moosa 0% 10/Jul/19 24/Jul/19 15 30/Dec/99 30/Dec/99 1

Mobilization of resources 0% 10/Jul/19 11/Jul/19 2

Safety arrangement prior to work 0% 16/Jul/19 18/Jul/19 3

Installation of Precast Foundation 0% 19/Jul/19 21/Jul/19 3

Installation of Sign Boards 0% 22/Jul/19 24/Jul/19 3

Location-03 Moosa 0% 24/Jul/19 7/Aug/19 15 30/Dec/99 30/Dec/99 1

Mobilization of resources 0% 24/Jul/19 25/Jul/19 2

Safety arrangement prior to work 0% 30/Jul/19 1/Aug/19 3

Installation of Precast Foundation 0% 2/Aug/19 4/Aug/19 3

Installation of Sign Boards 0% 5/Aug/19 7/Aug/19 3

Location-04 Moosa 0% 7/Aug/19 21/Aug/19 15 30/Dec/99 30/Dec/99 1

Mobilization of resources 0% 7/Aug/19 8/Aug/19 2

Safety arrangement prior to work 0% 13/Aug/19 15/Aug/19 3

Installation of Precast Foundation 0% 16/Aug/19 18/Aug/19 3

Installation of Sign Boards 0% 19/Aug/19 21/Aug/19 3

Location-05 Moosa 0% 21/Aug/19 4/Sep/19 15 30/Dec/99 30/Dec/99 1

Mobilization of resources 0% 21/Aug/19 22/Aug/19 2

Safety arrangement prior to work 0% 27/Aug/19 29/Aug/19 3

Installation of Precast Foundation 0% 30/Aug/19 1/Sep/19 3

Installation of Sign Boards 0% 2/Sep/19 4/Sep/19 3

Location-06 Moosa 0% 4/Sep/19 18/Sep/19 15 30/Dec/99 30/Dec/99 1

Mobilization of resources 0% 4/Sep/19 5/Sep/19 2

Safety arrangement prior to work 0% 10/Sep/19 12/Sep/19 3

Installation of Precast Foundation 0% 13/Sep/19 15/Sep/19 3

Installation of Sign Boards 0% 16/Sep/19 18/Sep/19 3

Location-07 Moosa 0% 18/Sep/19 2/Oct/19 15 30/Dec/99 30/Dec/99 1

Mobilization of resources 0% 18/Sep/19 19/Sep/19 2

Safety arrangement prior to work 0% 24/Sep/19 26/Sep/19 3

Installation of Precast Foundation 0% 27/Sep/19 29/Sep/19 3

Installation of Sign Boards 0% 30/Sep/19 2/Oct/19 3

Location-08 Moosa 0% 2/Oct/19 16/Oct/19 15 30/Dec/99 30/Dec/99 1

Mobilization of resources 0% 2/Oct/19 3/Oct/19 2

Safety arrangement prior to work 0% 8/Oct/19 10/Oct/19 3

Installation of Precast Foundation 0% 11/Oct/19 13/Oct/19 3

Installation of Sign Boards 0% 14/Oct/19 16/Oct/19 3

Location-09 Moosa 0% 16/Oct/19 30/Oct/19 15 30/Dec/99 30/Dec/99 1

Mobilization of resources 0% 16/Oct/19 17/Oct/19 2

Safety arrangement prior to work 0% 22/Oct/19 24/Oct/19 3

428655480.xlsx Construction Schedule


19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10 17 24 31
May May Jun Jun Jun Jun Jun Jul Jul Jul Jul Aug Aug Aug Aug Sep Sep Sep Sep Sep Oct Oct Oct Oct Nov Nov Nov Nov Dec Dec Dec Dec Dec Jan Jan Jan Jan Feb Feb Feb Feb Mar Mar Mar Mar Mar Apr Apr Apr Apr May May May May May
'19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '19 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20 '20

ASSIGNED BUDGET PLAN PLAN PLAN ACTUAL ACTUAL ACTUAL


WBS TASK DESCRIPTION
TO QTY
PROGRESS
START END DAYS START END DAYS
REMARKS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54

Installation of Precast Foundation 0% 25/Oct/19 27/Oct/19 3

Installation of Sign Boards 0% 28/Oct/19 30/Oct/19 3

Location-10 Moosa 0% 30/Oct/19 13/Nov/19 15 30/Dec/99 30/Dec/99 1

Mobilization of resources 0% 30/Oct/19 31/Oct/19 2

Safety arrangement prior to work 0% 5/Nov/19 7/Nov/19 3

Installation of Precast Foundation 0% 8/Nov/19 10/Nov/19 3

Installation of Sign Boards 0% 11/Nov/19 13/Nov/19 3

Location-11 Moosa 0% 13/Nov/19 27/Nov/19 15 30/Dec/99 30/Dec/99 1

Mobilization of resources 0% 13/Nov/19 14/Nov/19 2

Safety arrangement prior to work 0% 19/Nov/19 21/Nov/19 3

Installation of Precast Foundation 0% 22/Nov/19 24/Nov/19 3

Installation of Sign Boards 0% 25/Nov/19 27/Nov/19 3

Location-12 Moosa 0% 27/Nov/19 11/Dec/19 15 30/Dec/99 30/Dec/99 1

Mobilization of resources 0% 27/Nov/19 28/Nov/19 2

Safety arrangement prior to work 0% 3/Dec/19 5/Dec/19 3

Installation of Precast Foundation 0% 6/Dec/19 8/Dec/19 3

Installation of Sign Boards 0% 9/Dec/19 11/Dec/19 3

Handover Moosa 0% 11/Jul/19 12/Dec/19 155 30/Dec/99 30/Dec/99 1

Location-01 0% 11/Jul/19 11/Jul/19 1

Location-02 0% 25/Jul/19 25/Jul/19 1

Location-03 0% 25/Jul/19 25/Jul/19 1

Location-04 0% 22/Aug/19 22/Aug/19 1

Location-05 0% 5/Sep/19 5/Sep/19 1

Location-06 0% 19/Sep/19 19/Sep/19 1

Location-07 0% 3/Oct/19 3/Oct/19 1

Location-08 0% 17/Oct/19 17/Oct/19 1

Location-09 0% 31/Oct/19 31/Oct/19 1

Location-10 0% 14/Nov/19 14/Nov/19 1

Location-11 0% 28/Nov/19 28/Nov/19 1

Location-12 0% 12/Dec/19 12/Dec/19 1