Vous êtes sur la page 1sur 15

DAFTAR SATUAN BAHAN DAN UPAH

I DAFTAR BAHAN SATUAN HARGA SATUAN


1 2 3 4
1 Semen PC 50 Kg Zak Rp. 90,000.00
2 Semen PC Kg Rp. 1,800.00
3 Semen Warna Zak Rp. 100,000.00
4 Semen Warna Kg Rp. 2,500.00
5 Kerikil Cor / Kerikil Kali Pilihan M3 Rp. 750,000.00
6 Pasir Urug / Sirtu Timbunan M3 Rp. 200,000.00
7 Pasir Pasang M3 Rp. 350,000.00
8 Pasir Beton M3 Rp. 350,000.00
9 Tanah Timbunan M3 Rp. 200,000.00
10 Batu Kali M3 Rp. 400,000.00
11 Batu Bata Press/Tela Bh Rp. 2,500.00
12 Batu Roster/Krawang Bh Rp. 3,500.00
13 Batu Pecah/Kerikil Beton M3 Rp. 750,000.00
14 Keramik 40 x 40 cm Bh Rp. 18,853.70
15 Keramik 30 x 30 cm Bh Rp. 7,582.14
16 Keramik 30 x 60 cm Bh Rp. 21,052.63
17 Keramik 33 x 33 cm Bh Rp. 10,500.00
18 Keramik 20 x 25 cm Bh Rp. 4,500.00
19 Keramik 20 x 20 cm Bh Rp. 2,200.00
20 Keramik 20 x 20 cm Warna Bh Rp. 2,400.00
21 Keramik 10 x 20 cm Bh Rp. 1,100.00
22 Keramik 10 x 30 cm Bh Rp. 2,527.38
23 Keramik 10 x 40 cm Bh Rp. 4,713.42
24 Keramik 10 x 50 cm Bh Rp. 7,500.00
25 Keramik 10 x 60 cm Bh Rp. 14,583.33
26 Keramik 50 x 50 cm Bh Rp. 37,500.00
27 Keramik 60 x 60 cm Bh Rp. 87,500.00
28 Batu Candi M2 Rp. 560,000.00
29 Batu Palimanan/Limestone M2 Rp. 480,000.00
30 Paving Block Bh Rp. 6,500.00
31 Floor Hardener Kg Rp. 35,000.00
32 Waterproofing Coating Coat Klg Rp. 90,000.00
33 Waterproofing Cement Base Kg Rp. 26,000.00
34 Kayu Klas I ( Balok ) M3 Rp. 4,500,000.00
35 Kayu Klas I ( Papan ) M3 Rp. 5,300,000.00
36 Kayu Klas II ( Balok ) M3 Rp. 2,200,000.00
37 Kayu Klas II ( Papan ) M3 Rp. 2,200,000.00
38 Kayu Bekisting/ Terentang M3 Rp. 2,000,000.00
39 Kayu Mangi - Mangi/ Balok 5 10 Btg Rp. 20,000.00
40 Formika Lbr Rp. 340,000.00
41 Teakwood 90 x 220 cm Lbr Rp. 165,000.00
42 Plywood 3 mm 122 x 224 cm Lbr Rp. 65,000.00
43 Plywood 4 mm 122 x 224 cm Lbr Rp. 75,000.00
44 Plywood 6 mm 122 x 224 cm Lbr Rp. 90,000.00
45 Plywood 9 mm 122 x 224 cm Lbr Rp. 155,000.00
46 Gypsum Board 9 mm 120 x 220 cm Lbr Rp. 120,000.00
47 Kalsiboard 6 mm 120 x 220 cm Lbr Rp. 135,000.00
48 Kalsiboard 4,5 mm 120 x 220 cm Lbr Rp. 110,000.00
49 Kalsiboard 3,5 mm 120 x 220 cm Lbr Rp. 80,000.00
49 Shunda Plapond PVC M2 Rp. 325,000.00
50 List PVC Shunda Plapond M' Rp. 22,000.00
51 List Profil Kayu M' Rp. 13,000.00
52 List Profil Gypsum M' Rp. 10,000.00

1 Daftar Harga Material, Upah Kerja 2017


1 2 3 4
53 Benang Glos Rp. 5,750.00
54 Paku Biasa Kg Rp. 20,000.00
55 Paku Beton Bh Rp. 1,200.00
56 Paku Tripleks Kg Rp. 25,000.00
57 Paku Seng Kg Rp. 25,000.00
58 Paku Genteng Metal Kg Rp. 25,000.00
59 Paku Gypsum Kg Rp. 20,000.00
60 Paku Sekrup Hitam Kg Rp. 180,000.00
61 Ramset Bh Rp. 2,500.00
62 Dinabolt Bh Rp. 10,000.00
63 Besi Beton Segala Ukuran ( Polos ) U24 Kg Rp. 12,000.00
64 Besi Beton Segala Ukuran ( Ulir ) U24 Kg Rp. 13,500.00
65 Besi Profil Kg Rp. 16,150.00
66 Besi Streep 2x3 M' Rp. 38,500.00
67 Wiremesh Kg Rp. 17,500.00
68 Kawat Ikat/ Bendrat Kg Rp. 25,000.00
69 Kawat Ram/ Harmonika M2 Rp. 22,500.00
70 Kawat Las Kg Rp. 75,000.00
71 Cat Dasar/ Prime Coating (Resistant Sealer) Kg Rp. 90,000.00
72 Cat Meni/ Dasar Kg Rp. 50,000.00
73 Cat Kayu/ Kilat Kg Rp. 30,000.00
74 Cat Tembok Luar Jotun Kg Rp. 100,000.00
75 Cat Tembok Dalam Jotun Majestic Kg Rp. 80,000.00
76 Cat Plapond Kg Rp. 20,000.00
77 Cat Tembok Avitex Kg Rp. 20,000.00
78 Cat Tembok Vinilex Kg Rp. 35,000.00
79 Cat Oplosan Nippon Kg Rp. 30,000.00
80 Teak Oil Ltr Rp. 60,000.00
81 Politur Ltr Rp. 65,000.00
82 Residu/Ter Ltr Rp. 25,000.00
83 Minyak Cat Thiner A Ltr Rp. 30,000.00
84 Minyak Bekisting Bh Rp. 15,000.00
85 Minyak Pelumas Ltr Rp. 50,000.00
86 Solar Ltr Rp. 8,000.00
87 Soda Api Kg Rp. 5,500.00
88 Plamir Kayu Kg Rp. 20,000.00
89 Plamir Tembok Kg Rp. 50,000.00
90 Silikon Bh Rp. 50,000.00
91 Cornice Gypsum 20 Kg Zak Rp. 70,000.00
91 Cornice Gypsum 20 Kg Kg Rp. 3,500.00
92 Cotton Plaster Rol Rp. 15,000.00
93 Lem Kayu Kg Rp. 30,000.00
94 Kertas Gosok Lbr Rp. 5,000.00
95 Kuas Rol Kecil Bh Rp. 30,000.00
96 Kuas Rol Besar Bh Rp. 60,000.00
97 Kuas Biasa Eterna 1" - 4" Bh Rp. 20,000.00
98 Genteng Metal Multiroof s 10 (uk. 80 x 105 cm) Licin Lbr Rp. 130,000.00
99 Genteng Metal Multiroof s 10 (uk. 80 x 105 cm) Kasar Lbr Rp. 150,000.00
100 Genteng Metal Sakuraroof/ Merpatiroof s 6 (uk. 80 x 75 cm) Lbr Rp. 75,000.00
101 Nok Genteng Metal Multi Roof Bh Rp. 85,000.00
102 Nok Genteng Metal Sakura Roof Bh Rp. 35,000.00
103 Seng Gelombang BJLS 0.30 Lbr Rp. 85,000.00
104 Seng Plat BJLS 0.30 Lbr Rp. 30,000.00
105 Atap Galvalum BMT 30 TCT 0,35 mm Colour Coat M2 Rp. 150,000.00
106 Nok Galvalum/Zincalum 0,30 mm M' Rp. 43,000.00
107 Cladding BMT 0,35 mm TCT 0,4 mm Color Coat B 832 Fumira M2 Rp. 140,000.00
108 Alumunium Foil Polynum Double Sided 8 mm M2 Rp. 149,500.00
109 Lisplank Zincalum 0,30 mm M' Rp. 45,000.00

2 Daftar Harga Material, Upah Kerja 2017


1 2 3 4
110 Mur Baut Dia. 12 - 14 mm Bh Rp. 10,000.00
111 Kunci Tanam 2 Slaag Bh Rp. 250,000.00
112 Kunci Tanam Door Lock Inside Bh Rp. 300,000.00
` 113 Kunci Tanam Antik Bh Rp. 350,000.00
114 Grendel Pintu Bh Rp. 12,500.00
115 Grendel Jendela Bh Rp. 10,000.00
116 Handel Pintu Biasa Bh Rp. 150,000.00
117 Engsel Pintu Kuningan Bh Rp. 20,000.00
118 Engsel Jendela Kuningan Bh Rp. 20,000.00
119 Hak Angin Kuningan Bh Rp. 5,000.00
120 Panel Instalasi Bh Rp. 2,000,000.00
121 Wall Flashing Bh Rp. 30,000.00
122 Kloset Jongkok Bh Rp. 500,000.00
123 Kloset Duduk TOTO Bh Rp. 2,660,000.00
124 Wastafel TOTO Bh Rp. 1,800,000.00
125 Bak Cuci Stainless Steel Satu Lubang Bh Rp. 250,000.00
126 Water Drain + Assesories Set Rp. 150,000.00
127 Kran Air Dinding/Wall Tap TOTO Bh Rp. 101,000.00
128 Tempat Sabun TOTO Bh Rp. 180,000.00
129 P Trap TOTO Bh Rp. 456,000.00
130 Grab Bar TOTO Bh Rp. 875,000.00
131 Kran Air Washtafel TOTO Bh Rp. 765,000.00
132 Kran Air Washtafel Leher Angsa TOTO Bh Rp. 704,000.00
133 Single Lever Bath dan Shower Mixer TOTO Bh Rp. 2,050,000.00
134 Head Shower TOTO Bh Rp. 1,100,000.00
135 Jet Washer TOTO Bh Rp. 616,000.00
136 Floor Drain Alumunium Biasa Bh Rp. 160,000.00
137 Urinoir Bh Rp. 2,000,000.00
138 Sekat Urinoir Bh Rp. 1,500,000.00
139 Kaca Polos 5 mm Biasa M2 Rp. 250,000.00
140 Kaca Pinase Blue 5 mm M2 Rp. 300,000.00
141 Kaca Ryben 5 mm M2 Rp. 185,000.00
142 Kaca Nako/Louvers 5 mm Lbr Rp. 150,000.00
143 Gagang Kaca Nako Louvers Set Rp. 130,000.00
144 Pipa PVC 1/2 " RUCIKA M' Rp. 11,250.00
145 Pipa PVC 3/4 " RUCIKA M' Rp. 13,750.00
146 Pipa PVC 1 " RUCIKA M' Rp. 18,750.00
147 Pipa PVC 2 " WAVIN M' Rp. 20,000.00
148 Pipa PVC 3 " WAVIN M' Rp. 38,750.00
149 Pipa PVC 4 " WAVIN M' Rp. 63,750.00
150 Pipa PVC 5 " WAVIN M' Rp. 70,000.00
151 Pipa PVC 6 " WAVIN M' Rp. 112,500.00
152 Pipa PPR80 - PN20 M' Rp. 23,750.00
153 Pipa Galvanis 1/2 " M' Rp. 32,500.00
154 Pipa Galvanis 3/4 " M' Rp. 45,833.33
155 Pipa Galvanis 1 " M' Rp. 58,333.33
156 Pipa Galvanis 1/5 " M' Rp. 80,000.00
157 Pipa Galvanis 2 " M' Rp. 108,333.33
158 Pipa Galvanis 3 " M' Rp. 250,000.00
159 Pipa Stainles 2 " M' Rp. 53,333.33
160 Pipa Listrik PVC AW 5/8 " M' Rp. 2,000.00
161 Lampu TL 20 Watt Bh Rp. 95,000.00
162 Lampu TL 40 Watt Bh Rp. 145,000.00
163 Lampu TL 2 x 20 Watt Bh Rp. 200,000.00
164 Lampu TL 2 x 40 Watt Bh Rp. 310,000.00
165 Lampu Pijar 10 - 100 Watt Bh Rp. 15,000.00
166 Lampu SL 20 Watt Bh Rp. 50,000.00
167 Kabel NYA 2 x 2,5 mm M' Rp. 13,000.00

3 Daftar Harga Material, Upah Kerja 2017


1 2 3 4
168 Kabel NYA 3 x 2,5 mm M' Rp. 17,500.00
169 Stop Kontak Bh Rp. 35,000.00
170 Saklar Double Bh Rp. 27,000.00
171 Saklar Tunggal Bh Rp. 25,000.00
172 Hollow 2 x 4 cm Btg Rp. 37,950.00
173 Hollow 4 x 4 cm Btg Rp. 46,000.00
174 Truss C75.100 Btg Rp. 82,000.00
175 Seal Tape Bh Rp. 20,000.00

II DAFTAR UPAH SATUAN HARI/ORANG

1 Mandor o/h Rp. 180,000.00


2 Kepala Tukang o/h Rp. 175,000.00
3 Tukang o/h Rp. 170,000.00
4 Pekerja o/h Rp. 135,000.00

4 Daftar Harga Material, Upah Kerja 2017


ANALISA HARGA SATUAN
No. Jenis Pekerjaan Kode Sat. Koef. Harga Satuan (Rp)Jumlah Harga (Rp)
2 1 M2 PEMBONGKARAN KERAMIK
A Tenaga
Pekerja L.01 O/h 0.3300 135,000.00 44,550.00
Mandor L.04 O/h 0.0330 180,000.00 5,940.00
Jumlah Tenaga Kerja 50,490.00
B Peralatan

Jumlah Harga Alat


C Jumlah (A+B) 50,490.00
D Overhead & Profit (15%) 15% x C 7,573.50
E Harga Satuan Pekerjaan (C+D) 58,063.50

3 1 M2 PEMBONGKARAN PLAPOND
A Tenaga
Pekerja L.01 O/h 0.1200 135,000.00 16,200.00
Mandor L.04 O/h 0.0120 180,000.00 2,160.00
Jumlah Tenaga Kerja 18,360.00
B Peralatan

Jumlah Harga Alat


C Jumlah (A+B) 18,360.00
D Overhead & Profit (15%) 15% x C 2,754.00
E Harga Satuan Pekerjaan (C+D) 21,114.00

4 1 M2 PEMBONGKARAN RANGKA PLAPOND


A Tenaga
Pekerja L.01 O/h 0.1500 135,000.00 20,250.00
Mandor L.04 O/h 0.0150 180,000.00 2,700.00
Jumlah Tenaga Kerja 22,950.00
B Peralatan

Jumlah Harga Alat


C Jumlah (A+B) 22,950.00
D Overhead & Profit (15%) 15% x C 3,442.50
E Harga Satuan Pekerjaan (C+D) 26,392.50
6 1 M2 PEMBONGKARAN ATAP SENG GELOMBANG BIASA
A Tenaga
Pekerja L.01 O/h 0.0500 135,000.00 6,750.00
Mandor L.04 O/h 0.0250 180,000.00 4,500.00
Jumlah Tenaga Kerja 11,250.00
B Peralatan

Jumlah Harga Alat


C Jumlah (A+B) 11,250.00
D Overhead & Profit (15%) 15% x C 1,687.50
E Harga Satuan Pekerjaan (C+D) 12,937.50

7 1 M3 PEMBONGKARAN KASO RENG KAYU ( KAYU AKAN DIPAKAI LAGI )


A Tenaga
Pekerja L.01 O/h 0.1000 135,000.00 13,500.00
Tukang Kayu L.02 O/h 0.0250 170,000.00 4,250.00
Kep. Tukang L.03 O/h 0.0030 175,000.00 525.00
Mandor L.04 O/h 0.0050 180,000.00 900.00
Jumlah Tenaga Kerja 19,175.00
B Peralatan

Jumlah Harga Alat


C Jumlah (A+B) 19,175.00
D Overhead & Profit (15%) 15% x C 2,876.25
E Harga Satuan Pekerjaan (C+D) 22,051.25

5 1 M3 PEMBONGKARAN KUDA - KUDA DAN LOTENG KAYU ( KAYU AKAN DIPAKAI LAGI )
A Tenaga
Pekerja L.01 O/h 2.6660 135,000.00 359,910.00
Tukang Kayu L.02 O/h 4.0000 170,000.00 680,000.00
Kep. Tukang L.03 O/h 0.4000 175,000.00 70,000.00
Mandor L.04 O/h 0.1330 180,000.00 23,940.00
Jumlah Tenaga Kerja 1,133,850.00
B Peralatan

5
No. Jenis Pekerjaan Kode Sat. Koef. Harga Satuan (Rp)Jumlah Harga (Rp)
-
Jumlah Harga Alat -
C Jumlah (A+B) 1,133,850.00
D Overhead & Profit (15%) 15% x C 170,077.50
E Harga Satuan Pekerjaan (C+D) 1,303,927.50

6 1 M3 GALIAN TANAH BIASA SEDALAM 1 M


A Tenaga
Pekerja L.01 O/h 0.7500 135,000.00 101,250.00
Mandor L.04 O/h 0.0250 180,000.00 4,500.00
Jumlah Tenaga Kerja 105,750.00
B Peralatan

Jumlah Harga Alat


C Jumlah (A+B) 105,750.00
D Overhead & Profit (15%) 15% x C 15,862.50
E Harga Satuan Pekerjaan (C+D) 121,612.50

7 1 M3 URUGAN KEMBALI
A Tenaga
Pekerja L.01 O/h 0.1920 135,000.00 25,920.00
Mandor L.04 O/h 0.0190 180,000.00 3,420.00
Jumlah Tenaga Kerja 29,340.00
B Peralatan

Jumlah Harga Alat


C Jumlah (A+B) 29,340.00
D Overhead & Profit (15%) 15% x C 4,401.00
E Harga Satuan Pekerjaan (C+D) 33,741.00

8 1 M3 MEMBUAT BETON TUMBUK (1 PC : 3 PS : 5 KR)


A Bahan
Semen Portland Kg 218.0000 1,800.00 392,400.00
Pasir Beton M3 0.5200 350,000.00 182,000.00
Batu Pecah M3 0.8700 750,000.00 652,500.00
Jumlah Harga Bahan 1,226,900.00
B Tenaga
Pekerja L.01 O/h 1.6500 135,000.00 222,750.00
Tukang Batu L.02 O/h 0.2500 170,000.00 42,500.00
Kep. Tukang L.03 O/h 0.0250 175,000.00 4,375.00
Mandor L.04 O/h 0.0800 180,000.00 14,400.00
Jumlah Tenaga Kerja 284,025.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 1,510,925.00
E Overhead & Profit (15%) 15% x D 226,638.75
F Harga Satuan Pekerjaan (D+E) 1,737,563.75

9 1 M3 MEMBUAT BETON TUMBUK (1 PC : 3 PS : 6 KR)


A Bahan
Semen Portland Kg 197.0000 1,800.00 354,600.00
Pasir Beton M3 0.5700 350,000.00 199,500.00
Batu Pecah M3 0.8700 750,000.00 652,500.00
Jumlah Harga Bahan 1,206,600.00
B Tenaga
Pekerja L.01 O/h 1.6500 135,000.00 222,750.00
Tukang Batu L.02 O/h 0.2500 170,000.00 42,500.00
Kep. Tukang L.03 O/h 0.0250 175,000.00 4,375.00
Mandor L.04 O/h 0.0800 180,000.00 14,400.00
Jumlah Tenaga Kerja 284,025.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 1,490,625.00
E Overhead & Profit (15%) 15% x D 223,593.75
F Harga Satuan Pekerjaan (D+E) 1,714,218.75

10 1 M 3 MEMBUAT PONDASI BETON BERTULANG ( 150 Kg BESI + BEKISTING )


A Bahan
Kayu Klas II ( Papan ) M3 0.2000 2,200,000.00 440,000.00
Paku Biasa 5 cm - 12 cm Kg 1.5000 20,000.00 30,000.00
Minyak Bekesting Ltr 0.4000 15,000.00 6,000.00

6
No. Jenis Pekerjaan Kode Sat. Koef. Harga Satuan (Rp)Jumlah Harga (Rp)
Besi Beton Polos Kg 157.5000 12,000.00 1,890,000.00
Kawat Beton Kg 2.2500 25,000.00 56,250.00
Semen Portland Kg 336.0000 1,800.00 604,800.00
Pasir Beton M3 0.5400 350,000.00 189,000.00
Batu Pecah M3 0.8100 750,000.00 607,500.00
Jumlah Harga Bahan 3,823,550.00
B Tenaga
Pekerja L.01 O/h 5.3000 135,000.00 715,500.00
Tukang Batu L.02 O/h 0.2750 170,000.00 46,750.00
Tukang Kayu L.02 O/h 1.3000 170,000.00 221,000.00
Tukang Besi L.02 O/h 1.0500 170,000.00 178,500.00
Kepala Tukang L.03 O/h 0.2620 175,000.00 45,850.00
Mandor L.04 O/h 0.2650 180,000.00 47,700.00
Jumlah Tenaga Kerja 1,255,300.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 5,078,850.00
E Overhead & Profit (15%) 15% x D 761,827.50
F Harga Satuan Pekerjaan (D+E) 5,840,677.50

11 1 M 3 MEMBUAT KOLOM BETON BERTULANG ( 150 Kg BESI + BEKISTING )


A Bahan
Kayu Klas II ( Papan ) M3 0.2000 2,200,000.00 440,000.00
Paku Biasa 2 cm - 10 cm Kg 2.0000 20,000.00 40,000.00
Minyak Bekesting Ltr 2.0000 15,000.00 30,000.00
Besi Beton Polos Kg 157.5000 12,000.00 1,890,000.00
Kawat Beton Kg 2.2500 25,000.00 56,250.00
Semen Portland Kg 168.0000 1,800.00 302,400.00
Pasir Beton M3 0.2700 350,000.00 94,500.00
Batu Pecah M3 0.4050 750,000.00 303,750.00
Kayu Klas II ( Balok ) M3 0.0750 2,200,000.00 165,000.00
Jumlah Harga Bahan 3,321,900.00
B Tenaga
Pekerja L.01 O/h 5.3000 135,000.00 715,500.00
Tukang Batu L.02 O/h 0.2750 170,000.00 46,750.00
Tukang Kayu L.02 O/h 1.3000 170,000.00 221,000.00
Tukang Besi L.02 O/h 1.0500 170,000.00 178,500.00
Kepala Tukang L.03 O/h 0.2650 175,000.00 46,375.00
Mandor L.04 O/h 0.2650 180,000.00 47,700.00
Jumlah Tenaga Kerja 1,255,825.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 4,577,725.00
E Overhead & Profit (15%) 15% x D 686,658.75
F Harga Satuan Pekerjaan (D+E) 5,264,383.75

12 1 M 3 MEMBUAT BALOK BETON BERTULANG ( 150 Kg BESI + BEKISTING )


A Bahan
Kayu Klas II ( Papan ) M3 0.2400 2,200,000.00 528,000.00
Paku Biasa 5 cm - 12 cm Kg 2.4000 20,000.00 48,000.00
Minyak Bekesting Ltr 1.6000 15,000.00 24,000.00
Besi Beton Polos Kg 157.5000 12,000.00 1,890,000.00
Kawat Beton Kg 2.2500 25,000.00 56,250.00
Semen Portland Kg 252.0000 1,800.00 453,600.00
Pasir Beton M3 0.4050 350,000.00 141,750.00
Batu Pecah M3 0.6070 750,000.00 455,250.00
Kayu Klas II ( Balok ) M3 0.1050 2,200,000.00 231,000.00
Jumlah Harga Bahan 3,827,850.00
B Tenaga
Pekerja L.01 O/h 4.7620 135,000.00 642,870.00
Tukang Batu L.02 O/h 0.2060 170,000.00 35,020.00
Tukang Kayu L.02 O/h 1.2370 170,000.00 210,290.00
Tukang Besi L.02 O/h 1.0500 170,000.00 178,500.00
Kepala Tukang L.03 O/h 0.2500 175,000.00 43,750.00
Mandor L.04 O/h 0.2380 180,000.00 42,840.00
Jumlah Tenaga Kerja 1,153,270.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 4,981,120.00
E Overhead & Profit (15%) 15% x D 747,168.00
F Harga Satuan Pekerjaan (D+E) 5,728,288.00

7
No. Jenis Pekerjaan Kode Sat. Koef. Harga Satuan (Rp)Jumlah Harga (Rp)
13 1 M2 PLESTERAN 1 Pc : 4 Pp, TEBAL 15 mm
A Bahan
Semen Port Land Kg 6.2400 1,800.00 11,232.00
Pasir Pasang M3 0.0240 350,000.00 8,400.00
Jumlah Harga Bahan 19,632.00
B Tenaga
Pekerja L.01 O/h 0.3000 135,000.00 40,500.00
Tukang Batu L.02 O/h 0.1500 170,000.00 25,500.00
Kepala Tukang L.03 O/h 0.0150 175,000.00 2,625.00
Mandor L.04 O/h 0.0150 180,000.00 2,700.00
Jumlah Tenaga Kerja 71,325.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 90,957.00
E Overhead & Profit (15%) 15% x D 13,643.55
F Harga Satuan Pekerjaan (D+E) 104,600.55

14 1 M2 ACIAN
A Bahan
Semen Port Land Kg 3.2500 1,800.00 5,850.00
Jumlah Harga Bahan 5,850.00
B Tenaga
Pekerja L.01 O/h 0.2000 135,000.00 27,000.00
Tukang Batu L.02 O/h 0.1000 170,000.00 17,000.00
Kepala Tukang L.03 O/h 0.0100 175,000.00 1,750.00
Mandor L.04 O/h 0.0100 180,000.00 1,800.00
Jumlah Tenaga Kerja 47,550.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 53,400.00
E Overhead & Profit (15%) 15% x D 8,010.00
F Harga Satuan Pekerjaan (D+E) 61,410.00

15 1 M 2 PASANG LANTAI KERAMIK 20 X 20 CM


A Bahan
Ubin Keramik 20 x 20 cm Bh 26.5000 2,200.00 58,300.00
Semen Portland Kg 10.4000 1,800.00 18,720.00
Pasir Pasang M3 0.0450 350,000.00 15,750.00
Semen Warna Kg 1.6200 2,500.00 4,050.00
Jumlah Harga Bahan 96,820.00
B Tenaga
Pekerja L.01 O/h 0.6200 135,000.00 83,700.00
Tukang Batu L.02 O/h 0.3500 170,000.00 59,500.00
Kepala Tukang L.03 O/h 0.0350 175,000.00 6,125.00
Mandor L.04 O/h 0.0300 180,000.00 5,400.00
Jumlah Tenaga Kerja 154,725.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 251,545.00
E Overhead & Profit (15%) 15% x D 37,731.75
F Harga Satuan Pekerjaan (D+E) 289,276.75

16 1 M 2 PASANG DINDING KERAMIK 20 X 25 CM


A Bahan
Keramik 20 x 25 cm Bh 20.0000 4,500.00 90,000.00
Semen Portland Kg 11.3800 1,800.00 20,484.00
Pasir Pasang M3 0.0180 350,000.00 6,300.00
Semen Warna Kg 1.5000 2,500.00 3,750.00
Jumlah Harga Bahan 120,534.00
B Tenaga
Pekerja L.01 O/h 0.6000 135,000.00 81,000.00
Tukang Batu L.02 O/h 0.4500 170,000.00 76,500.00
Kepala Tukang L.03 O/h 0.0450 175,000.00 7,875.00
Mandor L.04 O/h 0.0300 180,000.00 5,400.00
Jumlah Tenaga Kerja 170,775.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 291,309.00
E Overhead & Profit (15%) 15% x D 43,696.35
F Harga Satuan Pekerjaan (D+E) 335,005.35

8
No. Jenis Pekerjaan Kode Sat. Koef. Harga Satuan (Rp)Jumlah Harga (Rp)

17 1 M 2 PASANG LANTAI KERAMIK 30 X 30 CM


A Bahan
Keramik 30 x 30 cm Bh 11.8700 7,582.14 90,000.00
Semen Portland Kg 10.0000 1,800.00 18,000.00
Pasir Pasang M3 0.0450 350,000.00 15,750.00
Semen Warna Kg 1.5000 2,500.00 3,750.00
Jumlah Harga Bahan 127,500.00
B Tenaga
Pekerja L.01 O/h 0.7000 135,000.00 94,500.00
Tukang Batu L.02 O/h 0.3500 170,000.00 59,500.00
Kepala Tukang L.03 O/h 0.0350 175,000.00 6,125.00
Mandor L.04 O/h 0.0350 180,000.00 6,300.00
Jumlah Tenaga Kerja 166,425.00

9
No. Jenis Pekerjaan Kode Sat. Koef. Harga Satuan (Rp)Jumlah Harga (Rp)
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 293,925.00
E Overhead & Profit (15%) 15% x D 44,088.75
F Harga Satuan Pekerjaan (D+E) 338,013.75

18 1 M 2 PASANG KACA, TEBAL 5 MM


A Bahan
Kaca M2 1.1000 250,000.00 275,000.00
Jumlah Harga Bahan 275,000.00
B Tenaga
Pekerja L.01 O/h 0.0150 135,000.00 2,025.00
Tukang Kayu L.02 O/h 0.1500 170,000.00 25,500.00
Kepala Tukang L.03 O/h 0.0150 175,000.00 2,625.00
Mandor L.04 O/h 0.00075 180,000.00 135.00
Jumlah Tenaga Kerja 30,285.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 305,285.00
E Overhead & Profit (15%) 15% x D 45,792.75
F Harga Satuan Pekerjaan (D+E) 351,077.75

1 M 2 PASANG KACA, TEBAL 5 MM + RANGKA Rp. 1,157,687.75

19 1 M 2 RANGKA HOLLOW
A Bahan
Rangka Hollow 4 x 4 Btg 0.4200 46,000.00 19,320.00
Rangka Hollow 2 x 4 Btg 0.1500 37,950.00 5,692.50
Ramset Bh 2.0000 2,500.00 5,000.00
Jumlah Harga Bahan 30,012.50
B Tenaga
Pekerja L.01 O/h 0.3500 135,000.00 47,250.00
Tukang Gypsum L.02 O/h 0.3500 170,000.00 59,500.00
Kepala Tukang L.03 O/h 0.0035 175,000.00 612.50
Mandor L.04 O/h 0.0018 180,000.00 324.00
Jumlah Tenaga Kerja 107,686.50
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 137,699.00
E Overhead & Profit (15%) 15% x D 20,654.85
F Harga Satuan Pekerjaan (D+E) 158,353.85

20 1 M 2 PLAFOND KALSIBOARD 4,5 MM


A Bahan
Kalsiboard Lbr 0.3640 110,000.00 40,040.00
Paku Gypsum Kg 0.1100 70,000.00 7,700.00
Jumlah Harga Bahan 47,740.00
B Tenaga
Pekerja L.01 O/h 0.1000 135,000.00 13,500.00
Tukang Gypsum L.02 O/h 0.0500 170,000.00 8,500.00
Kepala Tukang L.03 O/h 0.0050 175,000.00 875.00
Mandor L.04 O/h 0.0050 180,000.00 900.00
Jumlah Tenaga Kerja 23,775.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 71,515.00
E Overhead & Profit (15%) 15% x D 10,727.25
F Harga Satuan Pekerjaan (D+E) 82,242.25

21 M' PASANG LIST GYPSUM PROFIL


A Bahan
List Plapond Gypsum M' 1.0500 10,000.00 10,500.00
Cornice Zak 0.0150 70,000.00 1,050.00
Jumlah Harga Bahan 11,550.00
B Tenaga
Pekerja L.01 O/h 0.0600 135,000.00 8,100.00
Tukang Gypsum L.02 O/h 0.0600 170,000.00 10,200.00
Kepala Tukang L.03 O/h 0.0006 175,000.00 105.00
Mandor L.04 O/h 0.0030 180,000.00 540.00
Jumlah Tenaga Kerja 18,945.00

10
No. Jenis Pekerjaan Kode Sat. Koef. Harga Satuan (Rp)Jumlah Harga (Rp)
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 30,495.00
E Overhead & Profit (15%) 15% x D 4,574.25
F Harga Satuan Pekerjaan (D+E) 35,069.25

22 1 Bh PASANG KUNCI TANAM 2 SLAAG


A Bahan
Kunci Tanam Dua Slaag Bh 1.0000 250,000.00 250,000.00
Jumlah Harga Bahan 250,000.00
B Tenaga
Pekerja L.01 O/h 0.0100 135,000.00 1,350.00
Tukang Kayu L.02 O/h 0.5000 170,000.00 85,000.00
Kepala Tukang L.03 O/h 0.0100 175,000.00 1,750.00
Mandor L.04 O/h 0.0050 180,000.00 900.00
Jumlah Tenaga Kerja 89,000.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 339,000.00
E Overhead & Profit (15%) 15% x D 50,850.00
F Harga Satuan Pekerjaan (D+E) 389,850.00

23 1 Bh PASANG KRAN DINDING


A Bahan
Kran Air Dinding Bh 1.0000 101,000.00 101,000.00
Seal Tape Bh 0.0250 20,000.00 500.00
Jumlah Harga Bahan 101,500.00
B Tenaga
Pekerja L.01 O/h 0.0100 135,000.00 1,350.00
Tukang Batu L.02 O/h 0.1000 170,000.00 17,000.00
Kepala Tukang L.03 O/h 0.0100 175,000.00 1,750.00
Mandor L.04 O/h 0.0050 180,000.00 900.00
Jumlah Tenaga Kerja 21,000.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 122,500.00
E Overhead & Profit (15%) 15% x D 18,375.00
F Harga Satuan Pekerjaan (D+E) 140,875.00

24 1 M 2 PENGECATAN PLAFOND LAMA


A Bahan
Cat Penutup Kg 0.1300 20,000.00 2,600.00
Alat Bantu Ls 1.0000 17,000.00 17,000.00
Jumlah Harga Bahan 19,600.00
B Tenaga
Pekerja L.01 O/h 0.0200 135,000.00 2,700.00
Tukang Cat L.02 O/h 0.0320 170,000.00 5,440.00
Kepala Tukang L.03 O/h 0.0032 175,000.00 560.00
Mandor L.04 O/h 0.0025 180,000.00 450.00
Jumlah Tenaga Kerja 9,150.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 28,750.00
E Overhead & Profit (15%) 15% x D 4,312.50
F Harga Satuan Pekerjaan (D+E) 33,062.50

25 1 M 2 PENGECATAN TEMBOK LAMA DENGAN CAT JOTUN


A Bahan
Cat Dasar Kg 0.1200 80,000.00 9,600.00
Cat Penutup 2 x Lbr 0.1800 80,000.00 14,400.00
Jumlah Harga Bahan 24,000.00
B Tenaga
Pekerja L.01 O/h 0.0280 135,000.00 3,780.00
Tukang Cat L.02 O/h 0.0420 170,000.00 7,140.00
Kepala Tukang L.03 O/h 0.0042 175,000.00 735.00
Mandor L.04 O/h 0.0025 180,000.00 450.00
Jumlah Tenaga Kerja 12,105.00
C Peralatan

Jumlah Harga Alat

11
No. Jenis Pekerjaan Kode Sat. Koef. Harga Satuan (Rp)Jumlah Harga (Rp)
D Jumlah (A+B+C) 36,105.00
E Overhead & Profit (15%) 15% x D 5,415.75
F Harga Satuan Pekerjaan (D+E) 41,520.75

26 1 M 2 PENGECATAN BIDANG KAYU LAMA


A Bahan
Cat Dasar/Meni Kg 0.1700 50,000.00 8,500.00
Cat Penutup Kg 0.1700 30,000.00 5,100.00
Jumlah Harga Bahan 13,600.00
B Tenaga
Pekerja L.01 O/h 0.0700 135,000.00 9,450.00
Tukang Cat L.02 O/h 0.0750 170,000.00 12,750.00
Kepala Tukang L.03 O/h 0.0075 175,000.00 1,312.50
Mandor L.04 O/h 0.0025 180,000.00 450.00
Jumlah Tenaga Kerja 23,962.50
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 37,562.50
E Overhead & Profit (15%) 15% x D 5,634.38
F Harga Satuan Pekerjaan (D+E) 43,196.88

27 1 M 2 PENGECATAN SEMPROT (AIRLESS SPRAY) DENGAN MENGGUNAKAN SPOID (COMPRESSOR) 1 LAPIS


A Bahan
Cat Besi Kg 0.3000 30,000.00 9,000.00
Jumlah Harga Bahan 9,000.00
B Tenaga
Pekerja L.01 O/h 0.4000 135,000.00 54,000.00
Tukang Cat L.02 O/h 0.7000 170,000.00 119,000.00
Kepala Tukang L.03 O/h 0.2000 175,000.00 35,000.00
Mandor L.04 O/h 0.2000 180,000.00 36,000.00
Jumlah Tenaga Kerja 244,000.00
C Peralatan
Compressor
Jumlah Harga Alat
D Jumlah (A+B+C) 253,000.00
E Overhead & Profit (15%) 15% x D 37,950.00
F Harga Satuan Pekerjaan (D+E) 290,950.00

12
REKAPITULASI
KEGIATAN : REHABILITASI BANGUNAN RUMAH SAKIT
PEKERJAAN : BELANJA JASA KONSULTAN PERENCANAAN KEGIATAN RENOVASI
LOKASI : RUMAH SAKIT UMUM DAERAH KAB. MIMIKA
TAHUN : 2018

NO JENIS PEKERJAAN JUMLAH ( Rp )

I PEKERJAAN PEMBONGKARAN 17,185,632.50


II PEKERJAAN TANAH PONDASI DAN LANTAI 2,849,436.42
III PEKERJAAN STRUKTUR BETON 8,257,616.75
IV PEKERJAN KUDA - KUDA DAN ATAP 28,345,400.00
V PEKERJAAN PLAFOND 50,297,644.53
VI PEKERJAAN PENGECATAN 117,353,137.82
VII PEKERJAAN KUNCI 3,160,477.75
VIII PEKERJAAN INSTALASI LISTRIK 3,562,500.00
IX PEKERJAAN LAIN - LAIN 37,867,625.00
X PEKERJAAN AKHIR 3,850,000.00
A REAL COST 272,729,470.77
B PPn 10% 27,272,947.08
C JUMLAH 300,002,417.84
D DIBULATKAN 300,000,000.00

Terbilang : TIGA RATUS JUTA RUPIAH,-

Timika, Mei 2018

PEJABAT PEMBUAT KOMITMEN


RUMAH SAKIT UMUM DAERAH (RSUD)
KABUPATEN MIMIKA

Dr. SIELTIEL
NIP. 19840331 201004 1 001
OWNER ESTIMATE (OE)/HPS
KEGIATAN : REHABILITASI BANGUNAN RUMAH SAKIT
PEKERJAAN : BELANJA JASA KONSULTAN PERENCANAAN KEGIATAN RENOVASI
LOKASI : RUMAH SAKIT UMUM DAERAH KAB. MIMIKA
TAHUN : 2018

HARGA SAT. JML HARGA


NO JENIS PEKERJAAN SAT VOL
( Rp. ) ( Rp. )
1 2 3 4 5 6
I PEKERJAAN PEMBONGKARAN
1 Pembongkaran Kuda-kuda (kayu akan dipakai lagi) m³ 2.50 1,303,927.50 3,259,818.75
2 Pembongkaran Plapond m² 195.00 21,114.00 4,117,230.00
3 Pembongkaran Rangka plapond m² 195.00 26,392.50 5,146,537.50
4 Pembongkaran Keramik Lantai dan Dinding m² 1.00 58,063.50 58,063.50
5 Pembongkaran Beton (inc.bak air 3 bh) m³ 1.00 1,103,982.75 1,103,982.75
6 Pembongkaran Lampu - Lampu, Detector dan speaker ls 1.00 2,000,000.00 2,000,000.00
7 Pembongkaran AC Cassete bh 3.00 500,000.00 1,500,000.00
Jumlah Biaya Pek. Pembongkaran 17,185,632.50
II PEKERJAAN TANAH PONDASI DAN LANTAI
1 Pek. Galian Tanah m³ 1.08 121,612.50 131,341.50
2 Pek. Urugan Kembali Hasil Galian m³ 0.27 33,741.00 9,110.07
3 Pek. Pondasi Telapak/Foot Plat uk. 100 x 100 cm m³ 0.20 5,840,677.50 1,168,135.50
4 Pas. Kembali Keramik Lantai 30 x 30 cm m² 1.00 338,013.75 338,013.75
5 Pas. Kembali Keramik Lantai 20 x 20 cm km/wc m² 3.00 289,276.75 867,830.25
6 Pas. Kembali Keramik Dinding 20 x 25 cm km/wc m² 1.00 335,005.35 335,005.35
Jumlah Biaya Pek. Tanah Pondasi Dan Lantai 2,849,436.42
III PEKERJAAN STRUKTUR BETON
1 Pek. Kolom Beton 20/30 cm m³ 0.24 5,264,383.75 1,263,452.10
2 Pek. Ringbalk Beton 20/25 cm m³ 1.05 5,728,288.00 6,014,702.40
3 Pek. Plesteran Beton m² 5.90 104,600.55 617,143.25
4 Pek. Acian m² 5.90 61,410.00 362,319.00
Jumlah Biaya Pek. Struktur Beton 8,257,616.75
IV PEKERJAN KUDA - KUDA DAN ATAP
1 Pek. Konstruksi Kuda - Kuda Kayu Klas I 5/10 (tambahan) m³ 2.00 9,735,325.00 19,470,650.00
2 Pas. Kembali Konstruksi Kuda - Kuda Kayu Klas I 5/10 (upah) m³ 2.50 3,249,900.00 8,124,750.00
3 Pek. Silikon ls 1.00 750,000.00 750,000.00
Jumlah Biaya Pek. Kuda-Kuda dan Atap 28,345,400.00
V PEKERJAAN PLAFOND
1 Pek. Pasang Kalsiboard 4,5 mm + Rangka Hollo m² 195.00 240,596.10 46,916,239.50
2 Pek. Pasang Kembali Gypsum yang Rusak (bag. luar bang.) m² 8.64 86,945.75 751,211.28
3 Pek. List Gipsum m¹ 75.00 35,069.25 2,630,193.75
Jumlah Biaya Pek. Plafond 50,297,644.53
VI PEKERJAAN PENGECATAN
1 Pek. Cat Dinding Jotun majestic (luar dan dalam) m² 1,658.66 41,520.75 68,868,807.20
2 Pek. Cat Plafond Nipon Vinilex (luar dan dalam) m² 809.95 33,062.50 26,778,971.88
3 Pek. Cat Kilat (kusen,pintu,jendela,lisplank depan) m² 358.00 43,196.88 15,464,481.25
4 Pek. Cat Semprot Kaca (menggunakan compressor) m² 21.45 290,950.00 6,240,877.50
Jumlah Biaya Pek. Pengecatan 117,353,137.82
VII PEKERJAAN KUNCI
1 Pas. Kunci 2 slaag bh 4.00 389,850.00 1,559,400.00
2 Pas. Handle Pintu Samping psg 1.00 750,000.00 750,000.00
3 Pas. P Trap Washtafel bh 1.00 500,000.00 500,000.00
4 Pas. Kaca Mati Ryben 5 mm (teras depan) m² 1.00 351,077.75 351,077.75
Jumlah Biaya Pek. Kunci 3,160,477.75
VIII PEKERJAAN INSTALASI LISTRIK
1 Pas. Kembali Instalasi Penerangan titik 15.00 237,500.00 3,562,500.00
Jumlah Biaya Pek. Instalasi Listrik 3,562,500.00
IX PEKERJAAN LAIN - LAIN
1 Pek. Perbaikan Dinding Retak ls 1.00 2,000,000.00 2,000,000.00
2 Pas. AC 2 PK bh 2.00 10,000,000.00 20,000,000.00
3 Pembuatan Meja Beton Washtafel bh 1.00 770,000.00 770,000.00
4 Pas. Kran Air km/wc bh 3.00 140,875.00 422,625.00
5 Pek. Rangka Besi Hollow Gantungan Skeren/horden ls 1.00 4,875,000.00 4,875,000.00
6 Pek. Bongkar dan Pasang Kembali Daun Pintu Kaca ls 1.00 600,000.00 600,000.00
7 Pek. Rangka Besi UNP u. Gantungan Lampu Operasi bh 2.00 4,600,000.00 9,200,000.00
Jumlah Biaya Pek. Lain-Lain 37,867,625.00
X PEKERJAAN AKHIR
1 Pembersihan Area Kerja (luar dan dalam bangunan,km/wc) buang keluar lokasi pek. ls 1.00 3,000,000.00 3,000,000.00
2 Photo Dokumentasi ls 1.00 850,000.00 850,000.00
Jumlah Biaya Pek. Akhir 3,850,000.00