Académique Documents
Professionnel Documents
Culture Documents
1 INTRODUCTION
Purpose
Scope
Related Manuals
2 RESPONSIBILITIES
Assignment of Tasks
3 INITIAL TASKS
Pre-Award Activities
Pre-Construction Meeting
Filing System
Correspondence and Correspondence Control
Insurance and Bonds
Schedule Submittals
4 PERFORMANCE
Changes
Commitment Approvals
Schedule
Requests for Information (RFI'S)
Technical Transmittals
Claims
Backcharges
5 MONITORING/REPORTING
Daily Report
Progress Review and Coordination Meetings
Progress Measurement and Payment
Quality Surveillance
Safety and Health
Environmental
6 CLOSEOUT
7 SPECIAL TOPICS
7.1 Contract Law
7.2 Basis for Claims
7.3 Negotiation
7.4 Interface Coordination
7.5 Labor and Industrial Relations
7.6 Force Accounts
7.7 Liquidated Damages
7.8 Delays and Extension of Time
7.9 Acceleration
7.10 Suspension of Work
7.11 Differing Site Conditions
7.12 Terminations
7.13 Project Environmental Controls
INDEX
FORMS
Introduction
TABLE OF CONTENTS
1.1 Purpose......................................................................................................................................1
1.2 Scope.........................................................................................................................................1
TABLE OF CONTENTS
SECTION 1. INTRODUCTION Page i
1 INTRODUCTION
1.1 Purpose This Guide establishes standard practices for managing subcontracts.
Responsibilities
TABLE OF CONTENTS
TABLE OF CONTENTS
SECTION 2. RESPONSIBILITIES Page i
2 RESPONSIBILTIES
2.1.1 Purpose The purpose of this section is to provide a comprehensive list of tasks which
should be performed to manage a contract successfully.
2.1.2 Background Effective management of a contract includes making sure that each of the
essential task is assigned and performed. The complexity and size of the
individual contract and available project resources will affect the decision of
which tasks are essential for the contract. However, certain tasks should be
considered essential for all contracts (e.g., daily reports, change control
procedures, correspondence log and files, insurance and safety/health
requirements.
2.1.3 Procedure The method of communicating and assigning the functional responsibilities for
each contract is by a Division Of Responsibility (DOR) Matrix (Exhibit
2.1.3.).
Contractor
Contract Input to Material Development of Coordinate Input to pricing Prepare Material Identify company Develop and Review bids,
Formation - Assignment proforma package and proposal Requisition (MR), or customer provide schedule provide input to
Regional Office Schedule document and development, section technical scope, furnished utilities, requirements and bid evaluation
Issued Contracts determination of pre-bid meeting specifications and facilities and cost estimates for criteria, bid
mandatory prime and drawings services contract package evaluation and
contract bidding/award of bid clarification
flowdowns contract meeting
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Pre-bid Meeting Develop agenda; Chair and Review change Review quality Cover site Describe cost and Explain Safety
bidding conduct meeting; management, control, field operational schedule reporting and Health Plan,
procedure; cover project insurance, engineering requirements, labor requirements and project
commercial scope, work progress requirements relations, contractor requirements
aspects; prepare rules, general reporting and interface and
meeting minutes conditions; ethics payment coordination
and code of documentation
conduct
Assigned to:__________
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
✶
For contracts which the company is managing on behalf of a customer, the DOR should be modified to include customer representative interfaces.
Notes:
1. The Project Manager or Site Manager, in conjunction with the Contracts Manager, is responsible for assignment of the functions listed in this matrix. All tasks must be assigned and the
responsible employee trained and familiar with the task.
2. If the nature of the contract or available project resources dictate that a task will not be assigned and performed, indicate "Not Performed" in the "Assigned To" box.
3. All employees are responsible for providing the necessary support to an employee assigned responsibility for a given task or function.
Pre-construction Define Company Prepare agenda, Discuss Cover Labor Cover Safety and Cover schedule Cover contract Review ethics
Meeting Authorized conduct meeting construction Relations Health and progress administrative and code of
Representative operations requirements requirements reporting requirements conduct
requirements requirements including
such as facilities, submittals and
equipment, invoicing
coordination
Assigned to:__________
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Lead _______________ Labor Relations Dept. Assigned to:__________ Assigned to:__________ Assigned to:__________
Correspondence Designate Log Assign actions Report and Prepare outgoing Review outgoing Review and sign Archiving and
and Notices recipient for all correspondence follow up open correspondence, correspondence all outgoing permanent
contract and maintain files action items log and monitor for compliance correspondence storage
correspondence open items with contract and
(except as noted procedures
below)
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__ALL_____ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Requests for Designate Log RFI's, Assign action Report and Review and sign Review RFI's "after
Information recipient maintain Files follow-up open outgoing responses the fact" for
(RFI's) action items commercial
impact
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
File/Route Contract files Drawings Technical Schedule Payment files Expediting reports Inspection reports Progress
Miscellaneous documents submittals photos
Documents (other than
drawings)
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Insurance and Obtain and re- Verify validity of Verify insurance Maintain tickler
Bonds view Insurance Insurance and bonding system for
Certificates and Certificates and companies are policy
bond commit- letters on company's expirations
ment letters for approved list
contract
compliance
Contractor Develop list of Receive and log Assign action Conduct or Conduct or Approve Monitor closure
Technical contractor contractor items and coordinate coordinate cost and contractor of contractor
Submittals submittals submittals monitor status technical schedule reviews of submittals submittal
of open items reviews technical submittals requirements
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Contract Set Milestone Obtain initial Verify schedule Coordinate sub- Approve schedule Monitor progress Obtain/review Review claimed
Schedule dates contractor submittal meets mitted schedule submittal against approved periodic schedule impacts
schedule contract with project contract schedule updates from affecting critical
requirements schedule contractor path/
milestones
Lead:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Contract Process Evaluate whether Issue Change Issue notices if Direct acceleration Direct
Schedule company or 3rd contract Order to confirm contract to recover schedule acceleration to
(Cont'd) Party milestone date justified and milestone dates advance
backcharges changes are agreed upon are in jeopardy milestone dates
arising from late justified changes relative to contract
schedule to contract dates
performance schedule
Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Assigned to:__________
Invoices and Check invoices Verify billed work Verify contract Verify proper Approve payments
Payments for accuracy and agrees with requirements are deductions
that pricing is approved met before made for
according to progress payments issued retention,
contract backcharges or
other offsets
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Contract Initiate requests Review requests Prepare Change Sign Change Issue, control and Track costs for all Negotiate
Changes for changes for changes Notices, Change Notices monitor Change changes pending changes
Orders and Notices negotiated settle-
Amendments ments
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Contractor Receive and log Evaluate Evaluate Evaluate Prepare responses Authorize Plan and conduct Approve final
Proposals contractor technical merit schedule merit commercial to contractor negotiation limits negotiations settlements
proposals merit
Assigned to:__________
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Assigned to:__________
Daily Reports Observe, Review Daily Review Daily Log and retain
assemble and Reports for Reports for Daily Reports
report significant commercial Project
information significance significance
(Prepare Daily
Reports)
Quality Inspect work in Inspect off- Verify inspec- Determine Review contractor's Determine best Monitor close-out
Surveillance progress and site/shop tions comply acceptance or proposed remedial of open quality
coordinate with fabrications with contract rejection of work remedial actions action and direct issues
contractor requirements contractor
Assigned to:__________
Assigned to:__________
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Daily Report of Obtain reports Summarize data Approve reports Retain originals
Force Account from contractor and report with contractor
invoices
Backcharges Identify scope of Determine if Prepare notices Obtain Establish unique Summarize daily Approve
backcharge work; work is of backcharge contractor cost code for data and reports backcharge
prepare summary backchargeable approvals backcharge work settlements
and verify work is
properly coded
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Safety and Health Obtain copy of Monitor Obtain name of Identify and Prepare notices to Sign/approve Transmit notices, Verify
Contractor's contractor comp- designated evaluate contractor violation notices maintain log and contractor
Safety and liance with Safety contractor violations monitor status of corrective
Health Program and Health employee for violation notices actions
Program safety & health
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Environmental Identify project Obtain copy of Prepare a Review Identify Facilitate the Monitor the Prepare a
agencies. contractor's permitting plan contractor environmental preparation and progress of Construction
environmental written or matrix permit design criteria and review process of permit acquisition Environmental
regulations and Environmental requirements incorporate into the Environmental Control Plan
constraints Compliance and monitor design basis Impact (CECP)
Program (ECP), compliance Assessment, if
if required and required
obtain name of
designated
contractor
employee for
ECP
Lead:__________ Assigned to:__________ Assigned to:__________ Assigned to:_________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:_________ Assigned to:__________
Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Contract Chair meetings Prepare agenda, Obtain periodic Review most Evaluate near term Coordinate Resolve schedule Approve update
Progress meeting minutes updates of recent as-built (3 week/4 week) contractor's plan conflicts -ed contractor
Review/ and monitor contractor's schedule data look ahead with other working
Coordination action items working schedules contractors' plans schedules and
Meetings schedules and Company's any changes to
Plan working
schedules
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Claims or Monitor and Receive and log Monitor labor, Conduct fact Evaluate technical Evaluate schedule Evaluate Prepare
Disputes mitigate potential contractor claims equipment and finding merit merit commercial merit response to
claim situations material usage contractor
on a daily basis.
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Claims or Authorize Plan and conduct Prepare cost Approve final Prepare Contract Issue Contract
Disputes negotiation and negotiation and commitment settlement Change Order or Change Order or
(continued) set limits changes and Amendment (if Amendment and
obtain approvals required) obtain signatures
Assigned to:__________
Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Final Inspection Prepare final Assemble, status Coordinate and Prepare Coordinate
and Acceptance acceptance punch list perform final Contract completion of
package walk down, Closeout Contract Closeout
recommend final Checklist Checklist
acceptance
Lead__________ Assigned to:_________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Warranty Claims Prepare warranty Notify contractor Monitor timely Evaluate Monitor completion Inspect/accept
claim response proposed of remedial action remedial action
remedial action
and direct best
solution
Lead__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________ Assigned to:__________
Initial Tasks
TABLE OF CONTENTS
TABLE OF CONTENTS
SECTION 3. INITIAL TASKS Page i
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
TABLE OF CONTENTS
SECTION 3. INITIAL TASKS Page ii
3 INITIAL TASKS
3.1.1 Purpose The purpose of this Section is to provide guidance to jobsite personnel with
respect to their participation in the pre-bid and pre-award process.
Pre-Bid Site Visits and Pre-Bid Meetings are held to provide prospective
bidders an opportunity to evaluate jobsite conditions and to obtain clarification
of bid or work scope requirements.
Bid Clarification Meetings are held with selected bidders prior to contract
award to review their proposals and to allow further clarifications, if
necessary.
Pre-Award Meetings are held with the selected contractor to assure that a
clear, mutual understanding of the work to be awarded has been reached.
3.1.2 Procedure The following general guidelines apply to all meetings held prior to award:
— Confirm that all addenda issued during the bidding process have
been incorporated in the contract scope, specifications and
drawings.
Contractor:
6. Conclusions
A. Questions
B. Minutes will be provided by the company and sent to all attending Bidders, company
Departments and Owner
1. Site conditions under which the work will have to be performed. __________
6. Site investigation program (i.e. borings, samples, test pits, borrow pits, quarries). __________
9. Contractor participation in the company's safety and first aid programs. __________
10. Other work which will or may be in progress during the term of the contract. __________
11. Scope of work for the contract and any unusual or difficult construction that may
be required. __________
12. Point out building sites, access roads, borrow pits, and other important site
features. __________
13. Work of a similar nature, if underway on the site, to show the required standard
of workmanship. __________
14. On foreign jobs, available communications set-up for on-job and external to job. __________
15. Location of disposal areas for cleanup purposes, and cleanup areas where more
than one contractor is working. __________
16. Full scope of the project and the facilities yet to be performed that will have an
influence on the work of the contract being bid. __________
17. Details of the work which might involve premium time. __________
1. General Introduction
1.1 Introduction; Individual greetings and Attendance Sheet signature
1.2 Purpose; Review and sign finalized contract
1.3 Distribution; Provide contractor copy of Contract Documents.
2.1 RFP Changes; Discuss agreed changes and indicate where incorporated in the
Contract Documents.
A. Specifications; Technical Department (Engineering and Construction) input as
required
B. Drawings; Technical Department input as required
C. Terms and Conditions
2.2 Contract Interpretation; Review Terms and Conditions utilizing the General and
Special Conditions definitions in Appendix I of the Contracts/Subcontracts
Formation Manual.
4. Jobsite Requirements
4.1 Jobsite Procedures; Construction to review Jobsite Procedures which bid
was based on (key procedures should have been issued at Pre-bid Meeting).
4.2 Jobsite Update
4.3 Labor Agreements and Trade Council Meetings
5. Contract Signing
5.1 Contractor Copy; Contractor takes home signed copy.
5.2 Company Copy; Copied to provide conformed copy distribution and then maintained
in Procurement contract formation file.
5.3 Customer Copy; Only when the company is agent a third signed original is provided,
otherwise conformed copy(ies) will suffice.
6.1 Point of Contact; Exchange notification with contractor under the General
Condition titled NOTICES.
6.2 Meeting Minutes; Announce meeting minutes will be prepared and distributed to
all parties and Company/customer departments in attendance.
Pre-Award Action Checklist (EXHIBIT 3.1.4)
Contract Number:_____________________Contractor:______________________________
Contract
Scope:________________________________________________________________________
1. Pre-bid: Company/Customer provided materials, facilities and construction services YES NO
reviewed.
Comments:
6. Bid Evaluation: Bidder’s schedule and construction plan reviewed and resolved. YES NO
Comments:
8. Bid Evaluation: Bidder's Safety and Health Plan and experience reviewed and YES NO
determined to be satisfactory?
Comments:
10. Pre-Award: Issued for Construction drawings reviewed -- all bid period YES NO
comments/changes incorporated.
Comments:
Name:_______________________________ Date:______________________________
3.2.2 Procedure A meeting agenda will be developed. (Refer to Exhibit 3.2.2-A for a sample
Pre-Construction Meeting Agenda.)
Contract:_______________________________________________________________________
______
Contractor:_____________________________________________________________________
____
A. Meeting purpose
B. Introductions
II. Organization
A. Yours
B. Contractor
C. Authorized representatives
1. Yours
2. Contractor
A. Your policy
B. Contractor Safety Action Plan
C. First aid
D. Fire protection and prevention
E. Sanitation and housekeeping
F. Review contractor's proposed usage of hazardous materials
G. Hazardous Material handling and disposal
H. Citations
I. Drug Testing/Fitness for Duty (as applicable)
IV. Environmental
A. Your Policy
B. Contractor Environmental Control Plan
C. Environmental permit requirements
D. Hazardous waste generation and management
E. Asbestos inspection and notification
F. Compliance monitoring
V. Construction
A. Scope
A. Pre-job conference
B. Craft access
C. Project Labor Agreement
D. Job Rules
E. Daily Force Report
F. Reporting disputes
G. Badging
H. Work assignments
I. Jurisdictional procedures (disputes/grievances)
A. Project/construction schedule
• Initial submittal and requirements for approval
• Periodic updates
B. Manning curves
C. Contractor-furnished equipment and material (schedule and coordination)
D. Four-week rolling schedule
E. Progress review meetings
F. Coordinating work areas with others
G. Coordination meetings
IX. Drawings
A. Design drawings and their distribution
B. Drawing control
C. Contractor drawing submittals, approvals and schedules
X. Other Submittals
A. Fabrication procedures, if required
B. Construction procedures
C. QA/QC procedures
D. Health and Safety Plan
A. Correspondence
1. Addressee
2. Control and distribution
3. Requirement for sequential serialization
4. Formal notices
D. Payments
1. Progress payment schedule
2. Progress measurement and approval
3. Invoice and Certificates of Payment
4. Submittals required prior to payment
(see Mobilization Payment Checklist in Section 5.3)
5. Force Account Work
E. Backcharges
1. Notices
2. Procedure
3. Performance
1. Conflicts of Interest
2. Gifts
G. Warranty Procedures
H. Project Schedule Reviews and Coordination Meetings
I. Contract Close-out Procedures
Labor, Personnel and Work This provision establishes the contractor’s obligation to
Rules comply with project labor agreements and provides the
basis for settling jurisdictional disputes. It also establishes
the company’s right to remove unacceptable personnel.
Publicity and Prior written permission is required from the company
for any Advertising announcements, photographs and videos or
release of any information regarding the contract or
Project.
Safety & Health The contractor must comply with the requirements of the
company’s Safety & Health Plan and shall have sole responsibility
to implement its own Safety and Health Program. Please appoint a
Safety & Health Representative for your work and inform the
company of your designation in writing.
Environmental Requirements This provision emphasizes the contractor’s obligation to
comply with environmental laws, regulations and
practices to minimize adverse impact to the site,
personnel on the site and adjacent environmentally
The provisions of the contract relating to changes will be strictly observed. Insofar as possible, changes
will be covered by Change Order prior to execution of the work, but if the demand of time or the nature of
the work makes that impossible, the company may issue written instructions (Change Notices) to proceed
with the change. Any such work undertaken without such written instructions will be at your own risk and
any resulting charges may not be allowed. Change Orders will be issued only for work authorized by the
company. This policy will be firmly enforced and all invoices for work not covered by the contract or by
Change Orders will be returned unpaid.
All correspondence you receive from the company will carry sequential serial numbers. Please ensure that
all letters which you send to the company are likewise numbered. All correspondence to and from the
company will be required to be identified with the contract number, be dated, and carry a unique sequential
serial number. Letter logs will be exchanged on a monthly basis to ensure no letters have been lost or
misplaced.
All correspondence you receive from the company will carry sequential serial numbers. Please ensure
that all letters which you send to the company are likewise numbered. All correspondence to and from the
company will be required to be identified with the contract number, be dated, and carry a unique sequential
serial number. Letter logs will be exchanged on a monthly basis to ensure no letters have been lost or
misplaced.
For example:
Letters To:
Smith Construction Company
Letters To:
Company (Contract No. )
_____________________[Contracts representative] has been assigned for your portion of this project.
[Contracts representative] will work with your field supervisory personnel and will be your primary contact
with respect to construction procedures and technical compliance. When you encounter field problems
that require our assistance, please bring them to the attention of [Contracts representative]. We expect
that with the help of [Contracts Representative] you will be able to resolve such problems, but if any
should persist, please feel free to contact me.
We will require [three] copies of all correspondence from your designated representative which shall be
addressed to the attention of the, .
If we can otherwise assist you in any way, do not hesitate to call on us. We feel that your success will be
our success and we will extend our cooperation and assistance to the fullest degree possible.
Contract Number:________________________________________Contractor:_____________________
Contract Scope:________________________________________________________________________
Name:______________________________________________ Date:___________________________
3.3.1 Purpose The Contract Management Files must contain all pertinent original contract
data and documents and be organized to allow for efficient storage,
identification and retrieval.
The files should be integrated into the project's document control program.
3.3.2 Procedure A complete contract file set will be maintained for each contract. The
following file subjects, as a minimum, will be included:
• Conformed Contract
• Amendments
• Internal Approval
• Daily Reports
• Inspection Reports
• Construction Schedules
• Drawing File
• Backcharge File
• Claims File
• Warranty File
• Closeout File
At the conclusion of the project all closed contract files will be dispositioned
in accordance with project procedures. All contract files that may have a
bearing on open claims or other unresolved matters are to be separately
dispositioned in accordance with project procedures.
B. DISCUSSION
3.3.3 Filing Index The Contract Management Files will conform to approved project document
control procedures and utilize the approved project document control
computer tracking program. A Sample Contract Management File Index is
provided in Exhibit 3.4.3.
GENERAL FILES
CONTRACT FILES
As each contract is awarded and Construction assumes responsibility from Procurement Contract
Formation, individual files are established in the following typical major groups:
2.0 CONTRACT
2.1 Master Bid Package
2.2 Pre-Award Documentation (See Procurement Procedures)
2.3 Contract (Conformed Copy)
2.4 Change Notice Log
2.5 Change Notices
2.6 Change Order/Amendment Log
2.7 Contract Change Orders/Amendments (Conformed)
2.8 Commitment Authorizations
2.9 Insurance Correspondence
2.10 Payment/Performance Bond Correspondence
2.11 Contract Fact Sheet
3.0 ADMINISTRATION
3.1 Backcharge Register
3.2 Backcharge Notices
3.3 Contractor Schedules
3.3.1 Contract Schedule
3.3.2 Construction Schedules
3.3.3 Non-Manual Manpower Schedule
4.0 COMMUNICATIONS
4.1 Correspondence Log
4.2 General Correspondence Files
4.2.1 Correspondence with Customer
4.2.2 Out-going Correspondence to Contractor
4.2.3 Incoming Correspondence from Contractor
4.2.4 Inter-Office Correspondence
4.3 Log/General Facsimile Files
4.4 Contacts File (Discussions/Telephone)
4.5 Minutes of Meetings
4.6 Memos for Record
4.7 Transmittal Memo Receipts
5.0 REPORTS
5.1 Daily Force Reports
5.2 Contractor Daily Report
5.3 Progress Reports
5.4 Work Interruption Reports
5.5 Inspection Reports
5.6 Accident Reports
5.7 Progress Photo/Video File
8.0 PAYMENTS
8.1 Contractor Invoices/Applications for Payment
10.0 WARRANTIES
10.1 Log
10.2 Vendor Backcharges
10.3 Site Backcharges or Rework Accounts
11.0 CLAIMS
11.1 Contractor Proposal/Claims Log
11.2 Contractor Proposals (Claims)
11.3 Claims Analysis
11.4 Statements/Depositions (Personnel Concerned)
11.5 Claims Correspondence
11.4.1 Customer Correspondence
11.4.2 Company/Contractor Correspondence
11.6 Claims Reports to Management
11.7 Claims Settlement Agreements
3.4.2 Effective Make an exceptional effort to eliminate any chance of communications being
Correspondence misunderstood. Clear communication is essential to contract management
success. Everyone on the project team should understand that all contractual
communications may have legal ramifications, or at a minimum, be one of
the primary tools available to reconstruct facts if a dispute arises.
Correspondence should have a well defined purpose. Separate topics should
be addressed in separate letters. Clear, simple language should be used.
Ideas should be presented logically.
To maximize the value and effectiveness of correspondence:
• Serialize all contract correspondence
3.4.3 Procedure Correspondence to and from each contractor will be sequentially numbered
for each contract.
All outgoing and incoming correspondence will be logged, action/reply
responsibility assigned, and replies recorded. Correspondence control logs
should be checked weekly to ensure that all open items are taken care of and
to provide follow-up. Larger projects are encouraged to electronically "sort"
the logs and distribute an open correspondence report weekly as a control
device. Ideally the project should exchange logs monthly with the contractor
to confirm agreement on open and closed items as well to confirm receipt of
correspondence requiring no response.
Original documents will be retained in the Contract Management Files and
only copies will be circulated.
Email, while an attractive convenience, is not to be used for contract
correspondence unless each transmittal is serially numbered, logged, signed and
controlled in the same manner as hard copy correspondence.
By establishing designated points of contact, you can control the flow of
correspondence. The authorized signatory should be identified to the contractor
in writing and no others should sign correspondence. However, various people on
the project team may originate correspondence. An appropriate counterpart in the
contractor's organization should be identified as contractor's addressee. (Multiple
originators and multiple addressees results in lack of coordination and
consistency.)
Contract management correspondence control will conform to approved
project document control procedures and utilize the approved project
document control computer tracking program. A Sample Contract
Management File Index is provided in Exhibit 3.3.3.
3.4.4 Exhibits Correspondence Log - Incoming (Exhibit 3.4.2-A)
Correspondence Log - Outgoing (Exhibit 3.4.2-B)
REPLY
LETTER REQUEST DATE ACTION CONTRACTOR
SERIAL NO. DATED SUBJECT NO YES REPLY ASSIGNED ANSWERING LETTER
Expedition
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Contract Scope:________________________________________________________________________
3. All letters to contractor including email are being logged and tracked. YES NO
Comments:
4. All letters from contractor, including email are being logged and tracked. YES NO
Comments:
6. Open items are statused and updated (at least bi-weekly). YES NO
Comments:
9. YES NO
Comments:
Name:___________________________________ Date:___________________________
3.5.1 Scope This procedure outlines the requirements for obtaining, verifying and
monitoring contractor Certificates of Insurance and bonds.
3.5.2 Insurance Certificates of Insurance are submitted by a contractor to confirm that the
insurance policies required by the contract have been obtained. Because
insurance policies can expire by their terms, their expiration dates must be
monitored and policies extended as necessary.
3.5.3 Bonds A performance bond is a surety company's guarantee that the obligations
that the contractor undertakes pursuant to the contract will be performed,
including those that extend past final acceptance (e.g., warranty). A
payment bond ensures that the contractor's suppliers and subcontractors are
paid for the work and/or material they supply. Performance and payment
bonds are typically issued together as a package for a single premium.
Bonding
requirements, if any, are contained in the contract. Performance and
payment bonds should be in a penalty amount equal to 100% of the contract.
There is no reduction in bond premium for a reduced bond penalty.
The contractor should submit performance and payment bonds which meet
contract requirements immediately following contract award. Typically, the
successful bidder's bid bond is not returned until receipt of satisfactory
performance and payment bonds. Note that bonds do not normally need to
be updated during the course of the work. If extra work is added that is
equivalent to another contract, it will be necessary to obtain another bond to
cover this work.
Verify that the bonds conform to the contract requirements and have been
issued.
Verify that the bond(s) conform to the contract requirements. The surety
should be on the U.S. Department of Treasury's approved list of sureties.
Reference Special Topics Section 7.2 "Basis for Claims" pages 27 and 28.
PURPOSE
To establish responsibility for acquiring initial contractor submitted Certificates of Insurance and to
provide guidelines for determination of the validity of such Certificates.
DEFINITIONS
A Certificate of Insurance establishes that the contractor has appropriate insurance to cover claims for
which the contractor is responsible.
REQUIREMENTS
Attachment A is a sample Insurance Certificate. The sections below provide explanations and
directions. The numbers also correspond to the sections on the Certificate.
2. The name and address of the agent or broker who placed the insurance coverage for the contractor.
3. The name and address of the contractor who provided the evidence of insurance on the Certificate.
Verify that the name of the contractor is the same as the name in the contract.
4. The names of the insurance companies providing the insurance for the insured.
When there is any question about a contractor purportedly having valid insurance coverage,
contact the insurance company directly referencing the policy number.
5. Letter designation will indicate which insurance company is providing insurance coverage from the
list of insurance companies under Companies Affording Coverage.
The company requires that the Commercial General Liability policy be on an Occurrence
Form. This form provides coverage for a loss that happened during the policy term even if
Verify that the types of insurance and the limits of coverage being provided are
consistent with the contract requirements. If in doubt, have the Certificate reviewed by
the Risk Management Department.
8. The policy effective date must be effective on or before the contract inception date.
9. The policy expiration date must expire on or after the contract completion date.
If the expiration date is before the contract completion date, Procurement (or Contract
Administration if the contract has been transferred to the field) must monitor to insure
receipt of renewal certificates.
10. Generally the typed entries and special request items will appear in this space on the Certificate of
Insurance and may also include the "per project" limit mentioned above.
"XYZ Corporation (Owner) and the company are included as additional insureds except for
Worker's Compensation for the Fixed Project, #xxxxx, but only with respect to liability arising
out of the operation for the Owner and the Company by or for the contractor. Such
insurance shall be primary with any other insurance maintained by the additional insured
excess thereto."
The project name, contract number, and the specific company entity named as additional
insured as well as the Customer/Owner, if required, must appear. (While in practice the
additional insured provision is show in item 10; it is preferable to have this provision shown on a
separate endorsement attached to the Certificate.)
11. The certificate holder is the company entity which requested the Certificate of Insurance from the
contractor.
12. The company requires thirty (30) days notice of material alteration to the contractor's policies or
cancellation.
The standard cancellation provision does not include a provision for notice of termination or
material alteration and there is no industry standard for amending the Certificate. Look for
a typed entry or require the standard Certificate to be modified.
13. The Certificate of Insurance must be signed to be valid. It can be signed by the agent, the broker,
or the insurance company.
Contract Number:_______________________Contractor:____________________________
Contract Scope:________________________________________________________________________
1. Insurance Certificates have been obtained from contractor PRIOR to mobilization. YES NO
Comments: ______________________________________________________
3. Expiration dates have been entered into the tickler system. YES NO
Comments: ______________________________________________________
6. Insurance and bonding companies have been checked through the Risk Management YES NO
Department.
Comments: ______________________________________________________
7. Validity of Insurance Certificates and bonds have been verified with the insurance YES NO
company as appropriate.
Comments: ______________________________________________________
9. YES NO
Comments: ______________________________________________________
Name:____________________________________ Date:____________________________
3.6.1 Purpose The contractor is usually obligated by the terms of the contract to submit a
resource loaded, precedence diagram schedule as an early deliverable for
approval. The contractor’s schedule must show the logical sequence,
construction methods, and estimated durations of activities necessary to
meet the milestones and completion dates established in the contract.
Approval of the contractor’s schedule indicates that it appears to be a
reasonable plan and commits us to cooperate in its implementation. The
contractor is committed to perform in accordance with the plan unless
revisions are subsequently submitted and approved. Changes to the
schedule may also be directed pursuant to the Changes clause.
Project Controls should participate in the review and approval of all
contractor schedules and revisions. They should also review periodic
updates which report progress against the current approved plan and
fragmentary networks submitted in support of contractor proposals for
adjustments to the contract milestones or completion dates based upon
critical path analysis.
3.6.2 Procedure • Verify that the contractor submits the initial schedule as required by
contract.
• Assure the schedule is in the form required by the contract. If the
contract requires a CPM schedule, and the contractor submits a
bar chart, approval in this form may act as a waiver of the CPM
requirement.
• Assure the schedule meets the milestones required by contract.
• Analyze the submitted schedule for reasonableness of network
logic, durations, the occurrence of float, completeness, appropriate
levels of detail, and the identification of critical paths.
• Assure that completion dates shown earlier than contemplated by
the milestones do not adversely affect the work of others (or cash
flow constraints).
• Review to see how the contractor's schedule supports the overall
project schedule.
• Review to see if the work of others supports the contractor's
schedule.
• Assure work as planned is consistent with parameters of the site,
e.g., no double shift if the site is working one shift.
TABLE OF CONTENTS
SECTION 4. PERFORMANCE Page i
4 PERFORMANCE
4.1 CHANGES
4.1.1 Purpose This section describes activities and documentation required to handle
Contract Changes effectively.
4.1.2 Background Change Orders, which can be issued unilaterally, allow you to compensate
the contractor based on your determination of an equitable adjustment (time
and money) when agreement cannot be reached. The contractor may elect to
continue to pursue additional compensation, but the incentive to do so is
diminished considerably because of the amount already paid. Amendments
should be used for contract modifications outside the general scope of work
of the contract, or to change the basic provisions of the contract (i.e., outside
the operation of the Changes clause) and require bilateral agreement.
4.1 CHANGES
SECTION 4. PERFORMANCE Page 1 of 63
CONTRACT/SUBCONTRACT MANAGEMENT
MANUAL
The original contract plus all of the Change Notices, Change Orders and
Amendments constitute the complete contract.
Not all additional work is Extra Work. This is a complicated area with
broad guidelines. See the section below under Discussion titled “Extra
Work”.
4.1 CHANGES
SECTION 4. PERFORMANCE Page 2 of 63
CONTRACT/SUBCONTRACT MANAGEMENT
MANUAL
The scope of each change should be clearly defined and coordinated with the
on-site team by the originator. The designated contract administrator should
assume responsibility for such coordination and clarification as may be
required as soon as the contract administrator becomes aware of the
proposed change.
The change approval process should include cost and schedule analysis in all
cases. The cost estimate is also required for the committed authorization if it
is intended to issue a directed change.
The current status of all Change Notices must be formally monitored and
recorded in a Change Notice Log.
4.1 CHANGES
SECTION 4. PERFORMANCE Page 3 of 63
CONTRACT/SUBCONTRACT MANAGEMENT
MANUAL
The term "claim" has often been applied to any unsolicited proposal, but
should only be applied to disputed requests. This is particularly important to
observe on Government projects, for which the acceptability of proposal
preparation/negotiation costs differ for changes vs. claims. For additional
information on claims see Sections 4.6 and 7.2.)
• Change Order/Amendment
• Commitment authorization
• Change Summary -- a narrative describing why the change was made
• Technical Documents (e.g., drawings, sketches, DCNs)
• Change Notice(s)
• Contractor's proposal, if submitted
• Cost analysis (or price justification)
• Schedule analysis
• Correspondence
• Record of negotiation
• Time sheets, invoices or other supporting documentation, if
appropriate
4.1 CHANGES
SECTION 4. PERFORMANCE Page 4 of 63
CONTRACT/SUBCONTRACT MANAGEMENT
MANUAL
4.1.4.4 Extra Work Generally speaking, increases in scope can almost always be directed. Extra
Work is work that is a significant departure from the contracted general
scope (e.g., directing a tank subcontractor to install a building). Determining
whether scope increases are "in scope" increases or “out of scope” Extra
Work, can be a gray area. Adding one more pump and 500 feet of pipe to a
mechanical subcontract scope that already includes pumps and pipe should
be a directed change. Adding a 250 MW turbine generator to the same
contract probably should not be directed as a change.
Depending on the nature and scope of the Extra Work, attention must be
given to whether modifications to the insurance, bonding [including
agreement by the bonding company], and warranty provisions of the contract
will be required.
It is rare for contractors to flatly refuse a directed change because if the work
is later determined to be within the general scope of the contract, they may be in
default and liable for significant reprocurement costs. Changes "within the
general scope of the contract" should be very broadly interpreted.
All negotiations with a contractor must be documented. All proposed
settlements should be approved internally prior to negotiation with the
contractor. (Refer to Section 7.3, Negotiation, for a discussion on
negotiation preparation and strategy).
4.1.5 Procedure A Change Notice is prepared and will include all related data, drawings and
documentation that are available at the time of its issuance. (Reference
Exhibit 4.1.4-A for the Change Notice form.) Change Notices authorizing
work to proceed require internal approval. (Reference Section 4.2.)
Each Change Notice will be sequentially numbered and entered in the Change
Notice Log. (Reference Exhibit 4.1.4-B for the Change Notice Log form.)
The approved Change Notice will be transmitted to the contractor. All
transmittals to contractors will contain a serialized letter number.
4.1 CHANGES
SECTION 4. PERFORMANCE Page 5 of 63
CONTRACT/SUBCONTRACT MANAGEMENT
MANUAL
Once contractor proposals are negotiated and adjustments are agreed upon,
they will be incorporated into the contract by either a Change Order or
Amendment. (Reference 4.1.4-D and 4.1.4-E for the Change Order and
Amendment Forms.) Each Change Order and Amendment should be given
a unique sequential number, which is entered into a Change Order/ Amendment Log
for each contract. (Reference Exhibit 4.1.4-F for the Change
Order/Amendment Log form.) It is important that the cross-references in the
logs are completed to ensure a change can be tracked from
Its inception (Change Notice or Proposal) to its incorporation in a Change
Order or Amendment.
4.1.6 Equitable The Changes article of the contract will generally provide words to the effect
Adjustments that:
"If any change under this clause directly or indirectly causes an
increase or decrease in the contractor's cost of, or the time required
for, the performance of any part of the work under this contract,
whether or not changed by any order, an equitable adjustment shall
be made and the contract modified accordingly."
Prompt and fair resolution of changes is contractually required and will also
best serve your long-term interests. The following material is intended to
provide general guidance, not procedural direction. The terms of the contract
and Project Procedures will dictate the basis for negotiating equitable
adjustments.
Schedule Adjustments
Adjustments to the contract period of performance generally will be based on
the effect the change has on the time required to perform the contract work.
However, there are many factors to consider in evaluating the actual impact
of a change on a contractor's schedule. For example, even though changed
work may require some time to perform, the change may not affect any work
on the critical path of the current approved schedule. Consequently, it
would be inappropriate to modify the contract milestones or completion date.
4.1 CHANGES
SECTION 4. PERFORMANCE Page 6 of 63
CONTRACT/SUBCONTRACT MANAGEMENT
MANUAL
Price Adjustments
Price adjustments will fall into one or a combination of three categories:
lump sum, unit price or cost reimbursable. The preferred method of pricing
a change generally follows the base contract pricing. The contract Changes
article normally provides you the right to prescribe the pricing method,
regardless of the base contract pricing method, e.g., unit rates in lieu of lump
sum.
If the change is negotiated after the work is performed, you may both take
advantage of the actual costs incurred to assist in establishing an appropriate
price for the change. Do not, however, rely solely on cost records if a "lump
sum" settlement is being negotiated after the work is partially performed or
completed. Cost records are a tool to evaluate proposed settlement values and
are not necessarily an indicator of the reasonable amount the company is
obligated to pay. The contractor is entitled to an equitable adjustment for the
change. That may or may not be reflected in the amount that the contractor
has spent depending upon its productivity, skill and efficiency.
The estimated cost is based on the expected direct costs for material, labor
and equipment, to which negotiated factors are applied for the indirect costs
(scaffolding, cleanup, etc.), for overhead (site facilities, site management,
etc.) and for general and administrative expenses (home office support, etc.).
Note that it may be expedient to establish the factors for indirects, overhead
and G&A early in the project to be used for changes, avoiding renegotiation
of the rates for each change.
Where available and appropriate for the nature of the change, the contract
4.1 CHANGES
SECTION 4. PERFORMANCE Page 7 of 63
CONTRACT/SUBCONTRACT MANAGEMENT
MANUAL
unit prices should be used to price quantity changes. Changes that add work
for which no applicable unit rates exist will necessitate the establishment of
new unit prices, as will changes for which established unit prices are
inappropriate. Unit prices are actually a form of fixed price and negotiated
new unit prices will be based on the estimated cost for the changed work,
plus a reasonable profit, similar to the method described above for lump sum
work.
Cost plus fixed fee contracts typically include language that requires
adjustment in the "fixed" fee for changes. The "negotiated" fee adjustment
is not necessarily based on the ratio of the original fee to the original
estimated cost. The fee for each change should be evaluated for its own
impact based on the traditional consideration of risk, investment and
resources.
The unit rate for labor normally includes a markup for supervision, tools,
overhead and profit. The percentage markups for materials may cover the
labor effort to purchase, inspect, expedite, warehouse and handle the
materials plus a profit.
4.1 CHANGES
SECTION 4. PERFORMANCE Page 8 of 63
CONTRACT/SUBCONTRACT MANAGEMENT
MANUAL
Force Accounts
Force Accounts are actually an accounting mechanism (holding accounts) for
work being performed prior to agreement on a price. (Refer to the Special
Topics Section entitled “Force Accounts” for a discussion of the application
of Force Accounts.) The terms Force Account and T&M are often used
(incorrectly) interchangeably. This can lead to misunderstandings if the
contractor has a different view of the terminology. (Reference Special Topics
Section 7.6 "Force Accounts".)
Settlement Finality
Use this language when preparing a Change Order or Amendment:
"The price adjustment and time extension (if any) granted
under this Change Order (Amendment) constitute payment in
full for the work covered by this Change Order (Amendment),
including without limitation, all direct costs; indirect costs;
overhead costs; general and administrative expenses; profit;
and all effects (direct, indirect, and consequential, including
impacts, and "ripple effects") on the work, covered by this
Change Order (Amendment) on all contract work, whether or
not changed by this Change Order (Amendment)."
4.1.7 Cost Records For fixed price contracts (lump sum or unit price) changes should be issued
for Changes and negotiated on a fixed price basis. This objective assumes the scope of
the changed work is well enough defined and understood to support
preparation of a fixed price estimate. On all changes you should implement
cost tracking upon initiation of the change to develop sufficient information
on which to base pricing (i.e. time sheet review, material and equipment
usage reports review).
4.1 CHANGES
SECTION 4. PERFORMANCE Page 9 of 63
CONTRACT/SUBCONTRACT MANAGEMENT
MANUAL
4.1 CHANGES
SECTION 4. PERFORMANCE Page 10 of 63
Subcontract Change Notice
COMPANY:
OWNER:
JOB NO.:
This change notice is forwarded for your signature. Please complete this form as required and return the original to this
office. A copy has been included for your files.
DESCRIPTION OF CHANGE:
PRICING METHOD:
LS UP NEW UP T&M COST RE N/A
Expedition
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
[Date]
XYZ Corp.
123 Adams St.
Richland, WA 99352
Attention: [Contractor's Authorized Representative]
The reference letter indicates that XYZ Corp. considers the Post Weld Heat Treatment of the Liquid
Effluent Tank to be out of scope and requests a Change Notice to proceed with the work. The company
considers this work to be in scope work [OPTION: "but will research this matter and advise
separately as to a final decision"].
In accordance with Article ___, entitled Contract Interpretation, XYZ Corp. is hereby directed to proceed
with the Post Weld Heat Treatment and, if XYZ Corp. still considers this work to be out of scope, treat
such work as if it were a change and segregate costs and maintain separate cost records. This direction is
not to be construed by XYZ Corp. as the company's acceptance that this work is a change, but does
protect both the interests of the company with respect to continuation of the work and the interests of
XYZ Corp. should this work be determined later to be a bona fide change.
Please signify your intent with respect to this matter in the space provided below. If you have any
questions, please contact [contract administrator] at (509) 377-1234.
4.1 CHANGES
SECTION 4. PERFORMANCE Page 20 of 63
Daily Summary of Time
and Material Work
CONTRACT NO.: COMPANY:
CURRENCY:
BC NO.:
LOCATION: DATE:
LABOR EQUIPMENT
NO. HOURS TOTAL TOTAL EQUIP.
MEN CLASS. ST OT RATE WAGES SUBSISTENCE NO. DESCRIPTION HOURS RATE AMOUNT
TOTAL OTHER
REMARKS
TITLE TITLE
Expedition
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Contract Scope:________________________________________________________________________
1. Verify that changed work is not actually part of original contract scope. YES NO
Comments:
4. Change Notices have initiated cost commitment changes, if necessary, and proper YES NO
approvals have been obtained.
Comments:
5. Cost and schedule impacts of Change Notices have been identified. If no cost YES NO
changes, this, too, has been noted.
Comments:
7. YES NO
Comments:
8. YES NO
Comments:
Name:________________________________________ Date:____________________________________
4.1 CHANGES
SECTION 4. PERFORMANCE Page 24 of 63
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Contract Scope:________________________________________________________________________
2. Schedule impact or change, if any, is noted on the Amendments. Changes with no YES NO
impact will be noted as such.
Comments:
3. All Change Notices or unsolicited contractor requests (proposals) are available and on YES NO
file as back up.
Comments:
4. The file contains estimates, schedules, notes, meeting minutes or other documents YES NO
which substantiate the agreed upon price.
Comments:
5. There are statements in the file regarding what caused the changes. YES NO
Comments:
6. Verify that the Commitment Authorization has been approved and signed by someone YES NO
with appropriate delegated authority.
Comments:
8. Verify that the Change Orders/Amendments have been approved and signed by YES NO
someone with appropriate delegated authority.
Comments:
Name:________________________________________ Date:____________________________________
4.1 CHANGES
SECTION 4. PERFORMANCE Page 25 of 63
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Contract Scope:________________________________________________________________________
1. Contractor proposals are immediately identified, separately logged and acknowledged. YES NO
Comments:
2. Contractor proposals are evaluated to verify if they are clearly changed work or are YES NO
claims.
Comments:
4. The company is aware of all Contractor proposals and is focusing additional efforts on YES NO
documenting contractor performance.
Comments:
5. Contractor proposals are closed by Change Order or formally rejected in writing. YES NO
Comments:
6. At time of closure, alternative positions and possible negotiation positions are YES NO
prepared.
Comments:
7. Records of negotiations and settlements, if any are included in the contract file. YES NO
Comments:
8. Change Orders and Amendments have been prepared and approved to reflect YES NO
settlements, if any.
Comments:
Name:________________________________________ Date:____________________________________
4.1 CHANGES
SECTION 4. PERFORMANCE Page 26 of 63
4 PERFORMANCE
4.2 INTERNAL APPROVALS
4.2.1 Purpose This section defines the procedure for preparing and executing Commitment
Authorizations and will be used in conjunction with Section 4.1 "Changes."
4.2.2 Procedure Assemble all documentation which is relevant to the proposed commitment
change.
Prepare a concise change narrative if it will help convey the intent and
purpose of the proposed change.
Prepare an internal approval document. Verify the proper approval
authorities have been identified.
Retain the original change document for the Contract Management Files.
The supporting documentation will include:
• Commitment Authorization
• Change Notice/Change Order/Amendment
• Company's cost study or estimate
• Records of negotiations
• Pertinent correspondence or a summary of correspondence
references
1
For unit price contracts for which adequate funding exists, quantity releases are not considered commitments.
Contract Scope:________________________________________________________________________
Comments:
Name:________________________________________ Date:____________________________________
4.3.2 Procedure It is important to identify exactly the schedule submittal requirements of the
contract. It is essential these requirements be rigorously enforced. Allowing
a contractor not to submit scheduling information may result in a waiver of
those requirements.
Once a revised schedule is approved, it becomes the basis for future progress
measurement.
Retain copies (hard copy and, as appropriate, electronic) of all approved
schedules and updates. Formal written approval of schedules is required.
In reviewing a revised schedule:
• Assure that the schedule reflects changed work.
• Assure the schedule incorporates any approved time extensions.
• Assure that the contract milestone dates are not changed except as
modified by Change Order or Amendment . If the contractor has
changed milestone dates, this may constitute a request for an
extension of time and should therefore be addressed/resolved with
the contractor. (Refer to Section 4.6 "Claims", subsection 4.6.3.)
The contractor's schedule should be marked up (maintained) in accordance
with the contract requirements. This mark-up should be retained as it
reflects actual progress. All legitimate delays should be incorporated in the
schedule as they occur. When all tasks are complete the final mark-up
constitutes the as-built schedule.
NOTE: See Section 5.2 for a discussion of Progress Review and
Coordination Meetings and Special Topics Section 7.4 "Interface
Coordination".
Refer to Special Topics Section 7.8 "Delays and Extension of
Time" and Section 7.9 "Acceleration".
4.3 SCHEDULE
SECTION 4. PERFORMANCE Page 37 of 63
4 PERFORMANCE
4.4.1 Purpose This procedure provides for controlled identification, notification and
resolution of contractor initiated technical questions.
4.4.2 Definitions Request for Information (RFI) -- a contractor initiated technical question.
An RFI is initiated if the contractor:
• Is unable to understand the technical documents (i.e., scope,
specifications, drawings or data).
• Discovers or perceives a conflict, ambiguity, error or omission in or
among the technical documents.
• Has an alternate/substitute material or method to propose that will
not adversely affect cost or schedule.
4.4.3 Discussion RFI's often represent, in shear numbers, the single largest form of
documentation on the project. Further, some RFI's may affect the
contractor's ability to continue a portion of work until its question is
answered. Consequently it is critical that an efficient, effective and timely
mechanism for dealing with such technical questions be implemented
immediately upon contract inception (prior to mobilization, if the contractor
is performing initial design or other preparatory work offsite).
RFI's are not change documents and cannot be used to direct a change in
contract requirements. If a technical response represents a compensable
change, it must be issued by Change Notice.
4.4.4 Procedure Each project should develop a project instruction for RFI's to be given to
each contractor. (Refer to Exhibit 4.4.4-A for a sample instruction.)
Immediately after a contract is awarded the contractor should be provided the
instruction sheet and a supply of RFI forms. Even if the pre-construction
meeting is delayed, the contractor should be informed immediately of the
intended RFI procedure. Performing this bit of housekeeping will help to
ensure that the contractor utilizes the standard format for dealing with
technical questions, rather than a format of its own.
To administer the RFI process, the project will identify for each contract an
individual to be designated recipient for the RFI's on that contract. This
individual is responsible for ensuring that RFI's that may affect ongoing
work receive appropriate expedited responses.
Upon receipt of an RFI, the designated recipient will ensure that the RFI is
logged and that an individual is assigned to take the necessary action. (Refer
to Exhibit 4.4.4-B for a sample RFI Log form.) RFI's that indicate a specific
date for a required response should be monitored for a response and, if no
response has been issued three (3) days before the response is due, the
individual responsible for follow up should contact the assigned person to
ensure that the response will be issued on time. RFI's that indicate an
immediate response is required should be responded to as quickly as possible,
within reason and with due care. The target for responding to most RFI's
should be within three (3) working days and for all RFI's within two (2)
weeks.
or simply
4.4.5 Exhibits Request for Information (RFI) Contractor Instructions (Exhibit 4.4.4-A)
Request for Information (RFI) Log (Exhibit 4.4.4-B)
This procedure provides for controlled identification, notification and resolution of contractor initiated
technical questions. A Request for Information (RFI) is a contractor initiated technical question. An RFI
is initiated if the contractor:
• Has an alternate/substitute material or method to propose that will not adversely affect
cost or schedule.
Upon determination that an RFI is required, the contractor should prepare its question on the attached form,
log the RFI using a sequential numbering system (e.g., the first RFI is [Job #]-RFI-0001, and deliver the
RFI to _________________________).
RFI's that indicate a specific date for a required response should be monitored for a response and, if no
response has been issued three (3) days before the response is due, the originator should contact the
company to ascertain the status of the response. The company will target to respond to most RFI's with
three (3) working days and all RFI's within two (2) weeks.
RFI's are not authorized change documents and cannot be used to direct a change in contract requirements.
If the company's response on the RFI has a cost and/or schedule effect, it is the contractor's responsibility
to immediately advise the company with a contractor change proposal. Work undertaken without company
authorization is at the contractor's risk and expense.
OF:
LOCATION
REQUESTED BY SUBCONTRACTOR
REPLY REQUIRED BY
Information to Subcontractor
TO: FROM:
OF: OF:
REQUESTED INFORMATION
Expedition
4 PERFORMANCE
4.5 TECHNICAL TRANSMITTALS
4.5.1 Purpose This procedure outlines responsibilities for transmitting company design
documents to contractors and for processing technical submittals received
from contractors.
4.5.2 Discussion Poor control of technical documents can lead to uncontrolled changes to the
contract and can raise questions about design configuration control and,
ultimately, the quality of installed work. It is important that all team
members understand and follow the project's technical document change and
transmittal procedures.
Drawings included in the contract at the time of contract award are considered
the base set of drawings.
The base set of drawings is issued by Engineering and incorporated into the
original contract.
Prior to the Pre-Award Meeting, the bid set of drawings will be updated to
reflect changes during the pre-award phase and reissued in the status of
"Issued for Construction." All changes from the bid set to the Issued for
The list of contract specifications, drawings and data will be kept current and
updated every time drawings are changed or new drawings issued.
Contract Number:__________________________
Contractor:____________________________________
Contract Scope:
1. Cost/Schedule reviews have been performed for all revised or added drawings. YES NO
Comments:
2. Change Notices, Change Orders and Amendments are being processed for all YES NO
contracts and include an accurate accounting of drawing revisions.
Comments:
3. Change Notice for added and revised drawings are processed within the time YES NO
periods required by this procedure.
Comments:
4. YES NO
Comments:
5. YES NO
Comments:
6. YES NO
Comments:
7. YES NO
Comments:
8. YES NO
Comments:
Name:________________________________________ Date:____________________________________
4.6.1 Purpose This procedure describes the process for analysis, evaluation, and resolution
of contractor claims for price or schedule adjustments.
Definition:
4.6.2 Scope A wide variety of causes may give rise to claims from contractors. Some
typical causes are:
4.6 CLAIMS
SECTION 4. PERFORMANCE Page 47
of 63
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
For the orderly administration of contracts, all members of the project team
should endeavor to avoid claims by:
• Identifying potential claims and taking steps to mitigate
• Frank discussions with contractors to discourage spurious claims
• Application of contract provisions for relief where justified
• Prompt resolution of acknowledged changes
4.6.3 Procedure Submittals — Encourage the full and complete submittal of the factual
causes, contractual basis, quantified impact, documentary evidence, and
proposed resolution from the contractor. Submittals should address:
Requested Schedule Extensions — Note that any claim for time extension,
with or without money, should be expeditiously resolved i.e., rejected or
negotiated to conclusion. Unanswered requests for time extensions, where
the contractor has been compelled to accelerate its work to meet schedule in
the absence of a response, may be treated by the contractor (and by the
courts) as "Constructive Acceleration". Even if it is impractical to make an
immediate determination whether the contractor is entitled to a schedule
extension, it is generally quickly determinable if a time extension is
acceptable (whether or not justifiable) to the project. If an extension is not
acceptable, you should direct the contractor to complete on time and
simultaneously advise the contractor that you are evaluating the merits of its
requested schedule extension. (Refer to Exhibit 4.6.3-A for a sample
"Directive To Maintain Schedule" letter.) If the extension is justified, the
contractor will be entitled to compensation for acceleration. If the extension
is not justified, the contractor has maintained the schedule at its own cost.
4.6 CLAIMS
SECTION 4. PERFORMANCE Page 48 of 63
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
4.6 CLAIMS
SECTION 4. PERFORMANCE Page 49 of 63
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
4.6 CLAIMS
SECTION 4. PERFORMANCE Page 50 of 63
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
4.6.4 Claims Because claims may arise and not be resolved, contracts will generally
Defense provide for a method of handling disputes. These may range from resolution
of protests in accordance with a specified procedure, settlement through
arbitration, or recourse to litigation. The specific contract clauses must be
clearly understood before undertaking resolution of a claim.
4.6 CLAIMS
SECTION 4. PERFORMANCE Page 51 of 63
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
3. Determine the facts, using information from all relevant sources. Most
claims are based upon factual disputes and a full knowledge of the true
facts is essential in reaching a correct conclusion.
Defense Preparation
3. Concurrency: If both the customer and the contractor are at fault, the
law may not provide for recovery or for the apportionment of damages
4.6 CLAIMS
SECTION 4. PERFORMANCE Page 52 of 63
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
to either side. Seek a legal opinion based on the actual circumstances and
be guided by that opinion.
a. Constructive notice
Exhibit 4.6.4 provides a sample response for a claim which has been
submitted without proper notice.
Counterclaims
4.6 CLAIMS
SECTION 4. PERFORMANCE Page 53 of 63
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
customer.
4.6.5 Disputes Occasionally it is not possible to resolve a claim. The contract may contain a
disputed article that provides a procedure for resolution of disputes. Such a
procedure may indicate the steps and sequence of events to resolve the
dispute, or may only provide that "the parties agree to attempt in good faith
to resolve disputes". Detailed procedures, if provided, should be followed
carefully.
It should be a goal to resolve all contractor claims at the project level through
negotiations between parties who have the best knowledge of the facts and
circumstances. Where this is not possible, it may be necessary for the
dispute to be resolved through a third party. The most costly and time-
consuming process is litigation which should therefore be avoided if at all
possible. Alternative Dispute Resolution (ADR) processes (such as
mediation, expert panels, and dispute review boards) can be considered.
4.6 CLAIMS
SECTION 4. PERFORMANCE Page 54 of 63
EXHIBIT 4.6.3-A
DIRECTIVE TO MAINTAIN SCHEDULE
[SAMPLE]
DATE_________________
ADDRESSEE
__________________________________
__________________________________
__________________________________
__________________________________
Please provide an estimate of this cost as soon as possible and, in any event, within
[ ] days.
May 9, 1993
Dear Sir:
Raising this issue more than two years after the construction
drawings were issued, more than 16 months after the work
was commenced, and after the work is essentially complete
has denied us the opportunity to either return to the tender
scheme, consider alternatives, or implement special
monitoring of the operation. We consider your request at
this time to be unreasonable and, in accordance with Section
36 of the General Specifications, will not be given further
consideration.
Yours truly,
4.6 CLAIMS
SECTION 4. PERFORMANCE Page 57 of 63
4 PERFORMANCE
4.7 BACKCHARGES
4.7.1 Purpose This procedure describes the process for generating and collecting costs
against a contractor who has provided goods or services that are not in
compliance with the contractor's obligations under the contract.
4.7.2 Discussion Contracts often have express provisions for backcharges describing the
administrative requirements for notice and pricing terms. If so, they must be
followed. However, legitimate backcharges may be generated and collected
pursuant to other contract provisions or basic legal rights as well.
• Notice
• Cost determination
• Pricing
• Collection
4.7.3 Procedure When rework or other corrective action for defects is determined to be
necessary or when you intend, out of necessity to perform work on behalf of
the contractor (e.g., cleanup, material offloading or providing construction
equipment), you should prepare a written notice to the responsible contractor
identifying the nature of the problem and asking the contractor to perform the
necessary work. If safety or other urgent considerations dictate, the notice
may explain and provide that correction is being undertaken by you or others.
(Note that if you have another contractor perform the backcharge work, you
should require adequate cost records to support the backcharge.)
4.7 BACKCHARGES
SECTION 4. PERFORMANCE Page 58 of 63
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
4.7 BACKCHARGES
SECTION 4. PERFORMANCE Page 59 of 63
Daily Summary of Backcharge Work
CONTRACT NO.: COMPANY:
CURRENCY:
BC NO.:
LOCATION: DATE:
LABOR EQUIPMENT
NO. HOURS TOTAL TOTAL EQUIP.
MEN CLASS. ST OT RATE WAGES SUBSISTENCE NO. DESCRIPTION HOURS RATE AMOUNT
TOTAL OTHER
REMARKS
TITLE TITLE
APPROVED BY CONTRACTOR:
(FOR WHOM BACKCHARGE WORK IS BEING PERFORMED):
TITLE
COMPANY
Expedition
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Monitoring/Reporting
TABLE OF CONTENTS
TABLE OF CONTENTS
SECTION 5. MONITORING/REPORTING Page i
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Confirmation of Noncompliance with Contract Safety and Health Requirements (EXHIBIT 5.5.3-B)29
Safety and Health Checklist (EXHIBIT 5.5.6).................................................................................. 30
5.6 ENVIRONMENTAL ................................................................................................................ 31
5.6.1 Purpose.............................................................................................................................. 31
5.6.2 Discussion ......................................................................................................................... 31
5.6.3 Procedure ............................................................................................................................. 32
5.6.4 Checklist .............................................................................................................................. 33
Environmental Checklist (EXHIBIT 5.6.4)....................................................................................... 32
TABLE OF CONTENTS
SECTION 5. MONITORING/REPORTING Page ii
5 MONITORING/REPORTING
5.1 DAILY REPORT
5.1.1 Purpose This section identifies the information required on the Daily Report of a
contractor's activities.
Daily Reports must be complete and factual. Utmost care must be exercised
in preparing Daily Reports.
A Daily Report will be completed for each day a contract is active. The
reports will be sequentially numbered, beginning with 001 for the first day of
work. (Refer to Exhibit 5.1.2 for a Daily Report form.) Preparation of the
Daily Report is primarily the responsibility of your representative who is
monitoring the physical work (e.g., field engineer, contract coordinator,
contract supervisor). (Although on short-staffed projects there may be a
temptation to have the contractors prepare and submit Daily Reports for your
concurrence, it is to be avoided because of a contractor's natural tendency to
"shade" facts or include/exclude items based on its own best interests.) Each
Daily Report will be signed by the preparer and submitted for management
review no later than the morning of the following day. The original report will
be retained in the contract master file.
Also, if work is not performed for a number of days, one Daily Report may
be prepared stating the specific dates covered by the report.
Shift -- The shift and the starting and ending times will be indicated.
• Weather
• Surveillance
• Direction/Instructions
• Conflicts
• General
SUBCONTRACTOR: PROJECT:
SPECIAL COMMENTS:
EQUIPMENT
DESCRIPTION SOURCE UNITS TYPE WORK AREA REMARKS
09/02/1999 09/02/1999
X X
Expedition
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Contract Number:____________________________
Contractor:_______________________________
Contract Scope:
1. Daily Reports include contractor's first day on site, days not worked and cover all YES NO
shifts
Comments:
2. Daily Reports cover all calendar days and are sequentially numbered YES NO
Comments:
7. YES NO
Comments:
8. YES NO
Comments:
5.2.1 Purpose Progress Review and Coordination Meetings are held to evaluate the progress
of a contractor; review schedules; discuss past, current, and potential
problems; and resolve interfaces and restraints. Generally there are two
types of meetings:
5.2.2 Procedure Progress Review Meetings – Progress Review Meetings are generally
conducted once a week or as project or contract conditions warrant.
Coordination Meetings are held periodically (e.g., weekly, or on an as-needed
basis). An agenda will be prepared by the company and sent to all
participants in advance of each meeting. (Refer to Exhibit 5.2.2. for a
sample Progress Review Meeting Agenda).
The meeting participants will:
• Evaluate the contractor's progress since the last meeting and compare
it to the scheduled progress.
• Discuss the schedule and the proposed plans and progress for the next
schedule period.
• Cash Flow
• Manpower Projections
• Quantity Installation
• Design and vendor drawing submittals
• Equipment Deliveries
Coordination Meetings -- Coordination Meetings are conducted to schedule
work area accessibility, equipment and schedule coordination among the
contractors and you. An agenda for the meeting will be prepared by you and
distributed to the participants in advance of the meeting. Coordination
Meetings are generally held weekly or as work schedules require.
The meeting participants will:
• Discuss outstanding action items from previous meetings, their status
and resolution.
• Discuss foreseeable interfaces and potential conflicts between
contractors. Address foreseeable constraints to the flow of work,
including constraints caused by other parties (e.g., you, other
contractors, customer, government authorities).
• Determine action items and assign responsibility.
Contract Number:____________________________
Contractor:_______________________________
Contract Scope:
1. Meeting frequency is appropriate for this contract and are being held as scheduled. YES NO
Comments:
3. Action items, due dates and responsibilities are being identified. YES NO
Comments:
8. YES NO
Comments:
9. YES NO
Comments:
Contract Number:____________________________
Contractor:_______________________________
Contract Scope:
1. Meeting frequency is appropriate for this contract and are being held as scheduled. YES NO
Comments:
3. Action items, due dates and responsibilities are being identified. YES NO
Comments:
7. YES NO
Comments:
8. YES NO
Comments:
9. YES NO
Comments:
Contract Number:____________________________
Contractor:_______________________________
Contract Scope:
2. Initial schedule has been approved and contractor has been formally notified. YES NO
Comments:
5. Schedule submittals meet contract requirements for form and substance. YES NO
Comments:
7. As-built schedule contains sufficient data to reconstruct events at a later date. YES NO
Comments:
8. Contractor submits a revised schedule for each claim of additional time indicating the YES NO
cause and effect.
Comments:
9. YES NO
Comments:
− Standby hours
− Executed to date
− Downtime hours
− Pending
5.3.1 Purpose This procedure outlines actions required before progress payment requests
are transmitted for payment.
5.3.2 Procedure The contractor's progress payment schedule will be approved prior to
commencement of contract work.
• Contract schedule
• Insurance Certificates and bonds
JOB NO.:
SUBCONTRACTOR'S NAME SUBCONTRACT NUMBER NOTES:
SUBCONTRACT
INVOICE NO.
TECHNICAL REVIEW
PROJECT CONTROLS
CONTRACT SUPERVISOR
COORDINATOR
CONTROLLER
CONCUR WITH INVOICE PROCEED WITH CONCUR WITH INVOICE PROCEED WITH
PAYMENT IN FULL PAYMENT IN FULL
REJECT INVOICE-RETURN TO REJECT INVOICE-RETURN TO
SUBCONTRACTOR SUBCONTRACTOR
CONCUR WITH INVOICE IN PART. PROCEED WITH CONCUR WITH INVOICE IN PART. PROCEED WITH
PARTIAL PAYMENT IN THE AMOUNT OF PARTIAL PAYMENT IN THE AMOUNT OF
QUALIFICATION FOR REDUCTION OF PAYMENT
ACCOUNT AMOUNT
Expedition
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Terms of Payment:
Time of Payment: Invoices submitted monthly. Agreed to measure for payment prior to the 15th of each
month.
1. As siding arrives on site, contractor must furnish bills of material. The company representative
reviews contractor material receiving reports. Receiving reports will show square footage and number
of pounds shipped.
Contractor provided a unit price breakdown with bid showing material cost represented 50% of price.
Procedure - Agreed with contractor on what material receiving reports represent, such as all material
for Face "A" of building XYZ. Then allow progress payment based on 50% of that square footage.
Procedure - Based on a joint walkdown, drawings will be marked up showing what has been installed.
For example, the Face "A" drawings may show that it is agreed that 1/3 of the square footage is
installed. This can be figured roughly using dimensions on the drawings.
3. Penetrations
Procedure - As penetrations are installed, they will be colored green on the marked up drawings. For
example for Face "A" the green circles represent penetrations. Alongside each green circle is marked
the size of the penetration, such as 48" - perimeter.
Note only one set of drawings will be kept, and progress will be added as work is complete. The
drawings will show break marks for what is on Progress Payment #1, #2, etc.
4. The marked up drawings will be kept at Bill Smith's desk. Bill Smith is assigned responsibility for
this work. As each face is completed, the marked up drawing will be transferred to the Progress
Payment drawer for contract XYZ.
Contract Number:____________________________
Contractor:_______________________________
Contract Scope:
1. Contractor has submitted and the company has approved a contract schedule. YES NO
Comments:
4. Contractor has submitted an acceptable Safety and Health Action Program. YES NO
Comments:
8. Progress payment schedule and payment procedures are approved and in place. YES NO
Comments:
9. YES NO
Comments:
Contract Number:____________________________
Contractor:_______________________________
Contract Scope:
2. The invoice has been reviewed for contract and/or commercial compliance. YES NO
Comments:
5. Controller concerns or comments have been acted upon and closed out. YES NO
Comments:
6. All offsets such as retention and backcharges have been reconciled. YES NO
Comments:
7. YES NO
Comments:
8. YES NO
Comments:
9. YES NO
Comments:
5.4.1 Purpose This section addresses issues that may arise with respect to your quality
surveillance of the contractor's work in progress. Refer to Section 6.1 of this
Manual for a discussion of acceptance of the work.
The contractor is responsible for completing the work in accordance with the
contract and, where your inspections are required for work in progress, for
notifying you in a timely manner to permit inspections.
• Portions of the work that are ready for testing and acceptance when
partial acceptance is permitted in the contract. (Refer to Section 6.1
of this Manual.)
Inspect the work. Avoid giving direction to the contractor regarding potential
corrective actions. The results of your inspections will be formally
documented.
5.5.1 Purpose This section provides an outline for monitoring a contractor's Safety and
Health Program and for handling contractor safety and health violations.
The Project Safety and Health Program is intended to implement safe work
practices which must be observed by all jobsite employees. Contractors must
adhere to the Project Safety and Health Program and its requirements. The
fundamental principle is that contractors are responsible for developing the
safety and health program for their employees and for ensuring the safety and
health of their own employees.
The contractor is responsible for performing work in a safe manner and for
conforming to established Federal, state, local and contractual safety and
health requirements. The contractor is also responsible for providing a safe
and healthy working environment for its employees, including correcting
unsafe working conditions.
5.5.2 Definitions Imminent Danger Violations -- Any conditions or practices in any place of
employment where an immediate danger exists which could reasonably and
immediately be expected to cause death or serious physical harm.
5.5.3 Procedure Obtain the contractor's Safety and Health Program and forward it within 30
calendar days after contract award and prior to commencing work at the
jobsite, unless otherwise specified in the contract.
Serious Violation
Non-Serious Violation
• If the condition is not corrected within the time stipulated in the notice,
the contractor's site representative will be contacted to resolve the
matter.
• If the safety and health violation is not corrected after a second notice,
or if the contractor has continued to repeat violations, the situation
will be referred to management to pursue remedies under the contract.
5.5.4 Contract When work is stopped or suspended, a confirming letter citing the contract
Compliance provision under which the action was taken will be issued to the contractor.
Contract Number:____________________________
Contractor:_______________________________
Contract Scope:
1. The contractor is required to submit a Safety and Health Action Program and/or a Fire YES NO
prevention Plan.
Comments:
2. The contractor has submitted the name of its person responsible for safety and health YES NO
compliance.
Comments:
3. Safety and health submittals required by the contract have been obtained from the YES NO
contractor.
Comments:
4. Safety and health submittals have been reviewed and acknowledged by the company YES NO
Safety and Health Services.
Comments:
6. Company Safety and Health Services confirms contractor's safety and health and fire YES NO
prevention plans comply with the company's requirements.
Comments:
7. The contractor's workers compensation insurance coverage has been confirmed by the YES NO
company (if required).
Comments:
8. A copy of the contractor's Hazard Communication Program has been submitted to the YES NO
company.
Comments:
1. EMR
1A. List your firm's Interstate Experience Modification Rate (EMR) for the three most recent years and
total hours worked.
19_____ 19_____ 19_____
a. EMR __________ _________ __________
b. Hours Worked __________ _________ __________
1B. If the state where the jobsite is located has an EMR rating system, provide the state EMR for the
three most recent years and total hours worked.
19_____ 19_____ 19_____
a. EMR __________ _________ __________
b. Hours Worked __________ _________ __________
2. SAFETY PERFORMANCE
2A. List safety performance incident rates for the three most recent years:
19_____ 19_____ 19_____
2B. Use your OSHA No. 200 Log to fill in the three most recent years:
19_____ 19_____ 19_____
a. Number of lost workday cases. __________ _________ __________
b. Number of restricted workday cases. __________ _________ __________
c. Number of cases with medical attention only. __________ _________ __________
d. Number of fatalities. __________ _________ __________
4. Are accident reports (OSHA 200) and report summaries sent to the following and how often?
c. Safety Director
d. President of Firm
5. Do you hold site safety meetings for field employees both Manual and Non-Manual?
Yes No
How Often?
Weekly Bi-Weekly Monthly Less Often, As Needed
7. How are accident records and accident summaries kept? How often are they reported?
No Yes Monthly Annually
a. Accidents totaled for the entire company
b. Accidents totaled by project
(1) Subtotaled by superintendent
(2) Subtotaled by foreman
8. How are the costs of individual accidents kept? How often are they reported?
No Yes Monthly Annually
a. Costs totaled for the entire company
b. Costs totaled by project
(1) Subtotaled by superintendent
(2) Subtotaled by foreman
(Page 3 of 5)
CONTRACT NO.________________________ COMPANY__________________________
CONTRACTOR ________________________ COMPANY
JOB NO. ________________________
9. List key Safety and Health personnel planned for this project. Please list name, expected position and
safety performance on last three projects (OSHA Recordable and Lost Workday Case Incident (LWCI)
rates). When a project has not been specified, list key company personnel.
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
(Page 4 of 5)
CONTRACT NO.________________________ COMPANY__________________________
CONTRACTOR ________________________ COMPANY
JOB NO. ________________________
Yes No Yes No
a. Safe work practices e. First aid procedures
b. Safety supervision f. Accident investigation
c. Toolbox meetings g. Fire protection and prevention
d. Emergency procedures h. New worker orientation
How Often?
Weekly Bi-Weekly Monthly Less Often, As Needed
15.Do you have/require Material Safety Data Sheets (M.S.D.'s) for material/chemicals/equipment?
Yes No
If yes, explain field procedure for informing craft workers about potential hazards:
(Page 5 of 5)
CONTRACT NO.________________________ COMPANY__________________________
CONTRACTOR ________________________ COMPANY
JOB NO. ________________________
16. List three (3) client references that could verify the quality and management commitment of
your safety program.
________________________
________________________
________________________
5.6.1 Purpose This procedure describes methods for monitoring a contractor’s Project
Environmental Control Program and other relevant environmental issues.
(This section references contractor’s activities; it should be noted, however,
that your responsibility for environmental activities and oversight of our
contractors or a customer’s contractors varies depending on the contract
and scope of work, and should be identified on a project specific basis).
5.6 ENVIRONMENTAL
SECTION 5. MONITORING/REPORTING Page 31 of 33
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
5.6.3 Procedure Monitor the contractor’s program for obtaining, reviewing and making
available the Material Safety Data Sheets to all affected parties.
5.6 ENVIRONMENTAL
SECTION 5. MONITORING/REPORTING Page 32 of 33
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Notify the contractor in writing of any delay or stop work actions taken due
to environmental issues (e.g., discovery of contaminated soil, tanks) citing
why it was taken, the contract provision and a response date. Log and track
open environmental items.
Notify, in writing the contractor or the customer of any activity of which you
become aware that appears to be out of compliance with the project’s
procedures or regulatory requirements.
5.6 ENVIRONMENTAL
SECTION 5. MONITORING/REPORTING Page 32a of 33
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Contract Number:____________________________
Contractor:_______________________________
Contract Scope:
2. Contractor has provided lists of hazardous materials it will use and the list has YES NO
been approved by the company Safety and Health Services before the
contractor starts work.
Comments:
3. Contractor has submitted the name of the person responsible for environmental YES NO
compliance.
Comments:
4. Required documents such as MSDS and proof of spill control procedures have YES NO
been obtained from contractor.
Comments:
5. Contractor has agreed to remove all hazardous materials/waste that it has YES NO
brought onsite.
Comments:
7. YES NO
Comments:
8. YES NO
Comments:
5.6 ENVIRONMENTAL
SECTION 5. MONITORING/REPORTING Page 33 of 33
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
5.6 ENVIRONMENTAL
SECTION 5. MONITORING/REPORTING Page 32a of 33
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Closeout
TABLE OF CONTENTS
TABLE OF CONTENTS
SECTION 6. CLOSEOUT Page i
6 CLOSEOUT
6.1 CONTRACT CLOSEOUT
6.1.1 Purpose This section covers the final inspection and actions required to close out a
contract. Contract close-out means that all contractual obligations have
been discharged by both parties. This includes all commercial, technical and
administrative obligations contained in the contract and requires formal
resolution of all changes, requests for time extension, claims and
backcharges.
6.1.2 Procedure The contractor will provide notice of work that is complete and ready for
final inspection. (Refer to Exhibit 6.1.2-A.)
A joint inspection of the work will be conducted by you, the customer (if
appropriate) and the contractor.
When all check items on the Contract Closeout Checklist are complete,
issue a Certificate of Final Acceptance (reference Exhibit 6.1.2-E) and
provide the contractor with a form for a Release and Certificate of Final
Payment (reference Exhibit 6.1.2-F). In certain instances, and as approved
by Management, a Partial Release and Certificate of Payment may be used
(Exhibit 6.1.2-G.) (Note: Some states, such as California and Arizona
prescribe the type of form that must be used in order for the waiver and
releases to be valid.)
After receiving a signed Release and Certificate of Final Payment from the
contractor, the contractor's final invoice may be processed, including release
of retention in accordance with the provisions of the contract. (Note: A
reasonable retention may continue to be withheld if necessary to ensure
timely resolution of claims against a contractor, but should not be withheld
simply to induce a contractor to settle on a claim against you or the
customer. In some instances, the contractor in lieu of continuing to withhold
retention if both parties agree could provide an irrevocable Letter of Credit.)
6.1.3 Exhibits Contractor Request for Inspection of Completed Work (Exhibit 6.1.2-A)
Contractor Demobilization Checklist (Exhibit 6.1.2-B)
Contract Closeout Checklist (Exhibit 6.1.2-C)
Certificate of Acceptance (Partial Acceptance) (Exhibit 6.1.2-D)
Certificate of Final Acceptance (Exhibit 6.1.2-E)
Release and Certificate of Final Payment (Exhibit 6.1.2-F)
Partial Release and Certificate of Payment (Exhibit 6.1.2-G)
[NAME OF SUBCONTRACTOR]
and
[CONTRACTOR]
for
[TYPE OF WORK]
at
[LOCATION OF OWNER'S PREMISES]
the Undersigned hereby certifies and represents that it has made full payments of all costs, charges and expenses
incurred by it or on its behalf for work labor, services, materials and equipment supplied to the foregoing premises
and/or used in connection with the Work under said Subcontract.
The Undersigned further certifies that to its best knowledge and belief, each of its subcontractors and materialmen
has made full payments of all costs, charges and expenses incurred by them or on their behalf for work, labor,
services, materials and equipment supplied to the foregoing premises and/or used by them in connection with the
Undersigned's work under said Subcontract and has obtained releases to that effect.
As additional consideration for this payment, the Subcontractor agrees to the fullest extent of the law to, indemnify and
hold harmless the said Owner and Contractor from and against all costs, losses, damages, claims, causes of action,
judgments and expenses, including attorney's fees, arising out of or in connection with claims against the said
Owner or Contractor which claims arise out of the performance of the work under the Contract and which may be
asserted by the Subcontractor or any of its suppliers, contractors of any tier or any of their representatives, officers,
agents or employees except for those claims listed above, and except for claims arising out of the sole negligence
or willful misconduct of the party indemnified or held harmless.
The foregoing shall not relieve the Undersigned of its obligations under the provisions of said Subcontract, as
amended, which by their nature survive completion of the Work including, without limitation, warranties,
guarantees and indemnities.
[NAME OF SUBCONTRACTOR]
SIGNED TITLE
Expedition
Partial Release and Certificate of Payment
COMPANY: JOB NO.:
[NAME OF SUBCONTRACTOR]
and
[CONTRACTOR]
for
[TYPE OF WORK]
at
[LOCATION OF OWNER'S PREMISES]
the Undersigned hereby certifies and represents that it has made full payments of all costs, charges and expenses
incurred by it or on its behalf for work labor, services, materials and equipment supplied to the foregoing premises
and/or used in connection with the Work under said Subcontract through .
[DATE]
The Undersigned further certifies that to its best knowledge and belief, each of its subcontractors and materialmen
has made full payments of all costs, charges, and expenses incurred by them or on their behalf for work, labor,
services, materials and equipment supplied to the foregoing premises and/or used by them in connection with
the Undersigned's work under said Subcontract through .
[DATE]
As additional consideration for this payment, the Subcontractor agrees to the fullest extent of the law to, indemnify
and hold harmless the said Owner and Contractor from and against all costs, losses, damages, claims, causes of
actions, judgments and expenses, including attorney's fees, arising out of or in connection with claims against the
said Owner or Contractor which claims arise out of the performance of the work under the Subcontract through
and which may be asserted by the Subcontractor or any of its suppliers, contractors of
[DATE]
any tier or any of their representatives, officers, agents or employees except for those claims listed above, and
except for claims arising out of the sole negligence or willful misconduct of the party indemnified or held harmless.
The foregoing shall not relieve the Undersigned of its obligations under the provisions of said Subcontract, as
amended, which by their nature survive completion of the Work including, without limitation, warranties,
guarantees and indemnities.
[NAME OF SUBCONTRACTOR]
By:
Title
Expedition
6 CLOSEOUT
6.2 BENEFICIAL OCCUPANCY
6.2.1 Purpose The contract may expressly provide for the customer to take possession and
use all, or any part, of the contractor's completed or partially completed work
at any time during the life of the contract. The customer may use the area for
any purpose it chooses, ranging from occupying a portion of a structure to
turning a system over to a third party for testing or use. "Beneficial
Occupancy" is the term used to describe the situation where the customer
takes possession of a discrete part of the contractor's work such as:
6.2.2 Procedure Immediately prior to taking Beneficial Occupancy, the area should be
carefully inspected with the contractor to establish the status of work
remaining to be completed or corrected.
[ADDRESSED TO CONTRACTOR]
Dear ________________________,
In accordance with the General Condition, entitled "Use of Completed Portions of the Work," the customer
intends to take possession of a portion of the contract work on _______________, 199__). The work
which the customer will occupy is described as
Based upon the joint inspection of that area made with you on ____________________, the work shown
on the attached list remains to be completed or corrected. Please contact the undersigned to arrange a
schedule for completion of these work items which will be acceptable to the customer.
Effective upon the customer taking Beneficial Occupancy, you are relieved of responsibility for any
damage which may occur as the result of the occupancy or use of the work, and of maintenance of work or
systems within the area.
Beneficial Occupancy of this area does not constitute acceptance of the work or of the contract. You are
reminded that the warranty duration extends ___________ months from the Final Acceptance of the
Project as a whole by the customer. That date is currently forecast to be ___________. We recommend
you periodically contact ______________ if you wish to be kept apprised of the actual acceptance date.
COMPANY
_____________________________________________
CONCUR
_____________________________________________
[CONTRACTOR'S NAME]
The point at which work is substantially completed may not be defined in the
contract and, if it is not, is a matter of judgement on the part of you, the
customer and the contractor. Normally, it occurs when:
• All major work under a contract is completed and only cleanup and
punch list correction remains
• The work under the original scope is complete and the contractor is
working only on changed or added/extra work which may extend
beyond the original contract completion date
Completion of all items on the Punch List will be tracked against the firm
dates established by the Certificate of Substantial Completion. Reinspection
to record satisfactory completion of each item will be carried out by
representatives of the contractor, the customer, and company.
In the event that the contractor fails to satisfactorily complete any or all of
the items on the Punch List by the required dates, the customer retains the
right to have the work performed by others and the cost deducted from any
funds due the contractor.
6.3.3 Exhibits Letter from you to the owner advising that a contractor has achieved
Substantial Completion [Sample] (Exhibit 6.3.2-A)
[ADDRESSED TO CUSTOMER]
Substantial Completion
Dear ,
It has been determined that [all work under the contract] [a portion of the work under the contract] is
substantially complete. The work has been inspected by representatives of [customer], the contractor, and
company to determine the status and a Punch List of all incomplete or deficient work has been developed.
A date for completion of all items on the Punch List has been established and a re-inspection will be held on
that date to assure that all remaining items have been completed.
Attached herewith for your review and concurrence is the Certificate of Substantial Completion for the
work, together with the listing of remaining work to be completed by the contractor. You will note that it
specifies the responsibility for future maintenance of the work described.
After your review, please sign and return the Certificate to the undersigned for issuance to the contractor.
COMPANY
_____________________________________________
____/__
Attachment
[ADDRESSED TO CONTRACTOR]
Attention:
Project Manager
Dear ,
It has been mutually agreed that [all work under the contract] [a portion of the work under the contract] is
substantially complete. In accordance with the General Conditions, attached herewith is a fully executed
Certificate of Substantial Completion covering [all work under the contract] [that part of contract work
described in the Certificate] and the Punch List of remaining items has been resolved. As reflected in the
Certificate, the work is determined to be substantially complete as of .
The provisions of warranty as described in General Conditions continues to be in full force and effect, and
are supplemented by other requirements of the technical specifications. Maintenance of the work
subsequent to [will be performed by others] [will remain your responsibility until Final
Completion and Acceptance of the contract by the customer].
Please note that a formal billing for all costs or fees which you believe to be due under the contract must be
submitted within thirty (30) days of the date of the Substantial Completion, or .
COMPANY
_____________________________________________
____/__
Attachment
Response Required:
Date:
____________________________________
FACILITY/AREA :
_________________________________________
DESCRIPTION OF FACILITY/AREA :
_________________________________________
CONTRACTOR :
_________________________________________
CONTRACT NO. :
_________________________________________
This is to certify the work described above has been substantially completed in accordance with the
contract and associated documents. The facility/area designated above has been inspected by
representatives of all parties, and is complete with the exception of the attached Punch List which
contractor agrees to complete by the date designated.
The extended warranty period commences on the date the remedial work is completed as described in the
punch list or from the date of Final Acceptance of the Project as a whole, whichever is later.
INSPECTION CERTIFICATE
CONTRACTOR:_____________________________ DATE:_____________________________
ACCEPTED BY
COMPANY:__________________________________DATE:_____________________________
CUSTOMER
Depending upon the nature and scope of the contractor's work, the following
types of events will require a walkthrough and inspection to develop a Punch
List:
1. To initiate a Punch List effort, the following action items will occur:
• The company will notify the customer of a Punch List walkthrough. This walkthrough
is communicated via a formal letter issued a minimum of one week prior to the schedule
walkthrough.
c) Date required for final input from all parties on Punch List effort
2. Consolidation of Punch List input and issuance to contractor will be completed as follows:
a. Compile all Punch List input from various disciplines and other sources, and check for
duplication
3. Reinspection and sign off of completed items will be the responsibility of [designated
company representative] to coordinate with [the customer's representative(s)].
6.5 WARRANTY
6.5.1 Purpose Your contract with the Owner generally provides that you are directly
responsible for warranting work performed and/or you are to obtain
warranties from its suppliers and contractors. In either circumstance, you
will endeavor to obtain warranties from contractors that match the extent of
your liability with respect to duration and with respect to coverage (e.g.,
including incidental cost of removal, replacement, re-testing, etc.). Recovery
under the warranty requires that you follow the procedural requirements in
the warranty clause(s).
6.5.2 Procedure Construction contracts should contain a warranty provision in the General
Conditions for material and workmanship. Be advised that the technical
specifications may require a longer warranty on specific materials or
equipment (roof, mech/elect. equipment, etc). These modified warranty
requirements should be shown in the Special Conditions.
Contractors and their subcontractors returning to the site for warranty work
must comply with all site safety and security rules in effect at that time.
6.5 WARRANTY
SECTION 6. CLOSEOUT Page 23 of 27
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Upon completion of the corrective work and any required re-testing, the
work will be inspected and accepted by all parties. The contractor will be
notified by letter of the customer's acceptance. (Reference Exhibit 6.5.2-C
for a sample letter confirming correction work has been performed.)
In the event the contractor does not correct a deficiency within a reasonable
time after written notification, or if time does not permit correction by the
contractor, you or the customer may have the deficiency corrected by others
and charge the contractor for the cost of the work. The contractor will be
notified in accordance with the Project Backcharge Procedure that the
corrective work is proceeding. Alternatively, for practical reasons, you may
decide not to have the rework performed and adjust the contract value
accordingly. Refer to Section 4.7 "Backcharges" of this Manual.
Subtier Work
Warranty claims for work that was originally supplied, fabricated, or installed
by a subtier should be directed to the contractor, not to the subtier. You
have no contractual relationship with the subtier, and it is the contractor's
responsibility (and option unless the contractor refuses to act) to determine
who will perform the warranty work, and how it will be performed.
"Full Wrap" Warranties
6.5 WARRANTY
SECTION 6. CLOSEOUT Page 24 of 27
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
____________________________
____________________________
____________________________
Attention:
Gentlemen:
Confirming our verbal notice, you are hereby notified in accordance with the Warranty Provision of
Contract General Conditions Article [ ] of the following defect in the work:
At intersection with the PF-027 tour bridge column lines A and 6-7, the
bottom insulation installed between metal studs in the west cavity wall is
sagging.
You are [directed to take immediate action] [directed to advise your proposed measures] to correct this
problem by no later than September 8, 1992. Please contact the undersigned to establish a schedule for
your corrective work.
COMPANY
_____________________________________________
6.5 WARRANTY
SECTION 6. CLOSEOUT Page 25 of 27
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
(Contractor)
Attention:
Gentlemen:
The deficiency described in reference letter has been corrected. The corrective work has been re-inspected
and appears to meet all of the requirements of the contract technical specifications.
Please note that the extended warranty period for this corrective work begins as of the date of this letter.
COMPANY
_____________________________________________
6.5 WARRANTY
SECTION 6. CLOSEOUT Page 27 of 27
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Special Topics
TABLE OF CONTENTS
TABLE OF CONTENTS
SECTION 7. SPECIAL TOPICS December 1995, Revision 2 Page i
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
TABLE OF CONTENTS
SECTION 7. SPECIAL TOPICS December 1995, Revision 2 Page ii
7 SPECIAL TOPICS
7.1 CONTRACT LAW
However, contractors are business people. They are usually pressed for time
and are aggressively seeking to underbid a number of competitors. In order to
be the low bidder, they estimate only those costs that they feel the contract
terms will permit the owner to insist upon in the way of performance. They
are not expected to exercise clairvoyance or spend time and money looking for
hidden ambiguities in the bid documents. They are protected if they
innocently construe in their own favor an ambiguity that is equally subject to
different construction. In the case of patent ambiguities or discrepancies, the
contractor's duty to seek clarification before bidding should be brought to the
attention of contractors when questions of intent or interpretation arise.
Rules of Precedence
The following are some basic rules to help address the resolution of
ambiguities:
The parties are largely free to establish any order of precedence they
wish by specifically incorporating language in the contract which
establishes the precedence of one part of the contract over another.
In the absence of such express instructions, the following rules
generally apply:
The reason behind this is that the written words are the immediate
language in terms chosen by the parties themselves for the
expression of their meaning. Accordingly, such written words are
deemed worthy of greater weight than typed words intended for
general use.
4. Parol Evidence
5. Course of Conduct
When the agreement is not clear on its face, you may refer to the
"course of conduct of the parties" up to the time of the dispute as to
how they interpreted the provision; or you may bring in the
"standard practice of the industry," or what may have been the
"interpretation of other parties to the identical contract
provision," or the "record of negotiations" between the parties
prior to execution of the contract.
6. Entire Agreement
1. Clerical Errors
2. Unilateral Mistake
Disclosure Requirements
1. Intentional Misrepresentation
2. Unintentional Misrepresentation
3. Full Disclosure
Performance Requirements
1. Substantial Performance
2. Impossibility of Performance
First, the impossibility involved must be bona fide and not simply a
question of hardship or inconvenience. Second, the contractor
seeking to be excused must not have assumed the risk of
impossibility. Third, the performance will not be excused if the
impossibility stems even to a limited extent from negligence or lack
of diligence on the part of the contractor.
3. Hardship or Inconvenience
Breach of Contract
Termination
3. Mutual Agreement
5. Impossibility of Performance
6. Operation of Law
The conditions contemplated by the first part of the clause are physical in
nature. Also, they are either below the surface or latent, meaning hidden,
dormant, or not manifest; they must be at the site and they must differ
from what is described in the contract documents. The entitlement can
result from errors in surveying or exploratory drilling of the site, from
incomplete presentation of drilling logs, from omission of subsurface
water information or omissions from the drawings. It can even arise from
conditions inferred from equipment or methods indicated in the plans or
specifications.
However, it is incumbent upon the contractor to examine the site of the
work carefully, and if there are cores available for inspection, it should
examine them. In fact, every representation made to the contractor must
be carefully documented so that a determination can be made whether the
actual conditions encountered are materially different from those
represented. Most of the problem areas involve grossly inaccurate
estimated quantities, inaccurate portrayal of subsurface water or rock
conditions, misrepresentation of soil conditions, borrow pits, contour
lines, or failure to show accurately existing utility lines.
To come under the second part of the clause, the condition must have been
unknown when the parties entered into the contract. Furthermore, if a
reasonable investigation would have disclosed the condition, this could be
fatal to the contractor's claim. For example, if a contractor is working
near the Rocky Mountains, its general experience should give it the
knowledge that there will likely be subsurface rocks or boulders.
Likewise, if the contractor is working in some parts of Florida, it is
certainly aware of the nearness of the water table to the surface. Thus,
the contractor cannot successfully claim that it has encountered an
"unknown" condition of unusual and not to be expected character.
Refer to Special Topics Section 7.2 "Basis for Claims" p. 21 and Section
7.11 "Differing Site Conditions."
2. Added Work
Additional quantities ordered during the progress of the work generally
entitle a contractor to claim extra compensation on a lump sum job.
While additional quantities of work added during the course of
construction may not entitle a contractor to claim for additional
compensation on a unit price contract, this would be subject to
interpretation as to whether the work added is of the same "nature and
character" as the work contemplated in the original unit item of the
contract. The work added under unit prices need not be exactly the same
as under the original contract; however, there should be a reasonable
compatibility. Furthermore, the contractor may in fact agree to accept
unit prices even if the work is not compatible as long as the contractor
feels the unit price compensation is adequate.
3. Reduction of Work
A reduction in the quantity of work may be a proper basis for a price
adjustment (increase) for the units of work actually performed under a
unit price contract. The rationale is that the contractor has spread the
fixed components of cost over the estimated quantities. A significant
quantity underrun results in under-recovery of the fixed costs. It is
generally considered that an increase or decrease in the volume of work to
be performed not exceeding plus or minus 20% of an item of work whose
total value is less than 5% of the contract amount will have no substantial
impact on the contractor. Conversely, if the quantity of an item which
exceeds 5% of the contract is varied by more than plus or minus 20%,
there may be significant impact on the contractor's financial position due
to its inability to recover its fixed costs. Therefore, it is desirable that the
contract should state the permissible variation in quantities. Such a
statement will go a long way to avoid disputes.
Note that this language provides relief for the contractor solely as a result
of a quantity variation; it does not provide relief in the event the contractor
simply failed to meet its estimated levels of productivity.
4. Increased Difficulty of Performance
Whether the work is increased in quantity or not, unanticipated difficulties
which interfere with performance (the risk of which was not assigned to
the contractor under the terms of the contract), may be a proper cause for
the contractor to claim extra compensation. This may be true when the
5. Delays
Time is money. This is probably an overworked phrase but it never is
truer than in the context of this subject. Delay is generally acknowledged
to be the most common, costly and complex problem encountered on
construction projects. Because of the overriding importance of time both
to you, in terms of performance and to the contractor in terms of money, it
is the source of frequent disputes, claims, and law suits. To control this
situation insofar as possible, the contract is formulated to identify known,
potential delay situations in advance and to define and fix obligations in
order to preclude controversies. A substantial number of the contract
clauses address this subject in one way or another.
It is not required that a delay extends contract performance beyond the
contract completion date to establish entitlement. A contractor may
complete the work ahead of schedule but still receive additional
compensation if it could have finished earlier had it not been for your
delay. The law does, however, require that the contractor establish a
direct cause-and-effect relationship between your breach of a contractual
obligation and the delay. In addition, the contractor has the burden of
establishing that its costs increased as a result of the delay.
You will find in practice that not everything in the contract can be taken at
face value and applied in cookbook fashion. Circumstances play a large
part in determining which clause or clauses will be applied to a particular
delay claim. Also, contract law encompasses concepts of reasonableness
and fair dealing, implied obligations and warranties, etc. A good general
understanding of the principles involved and the operation of the
applicable clauses is essential to make appropriate decisions and to take
the proper action in delay situations. (Reference Special Topics Section
7.8 "Delays and Extensions of Time.")
Types of delays are many and varied but they can be grouped in four
broad classifications according to how they operate contractually. They
are:
A. NON-EXCUSABLE DELAYS
B. EXCUSABLE DELAYS
C. COMPENSABLE DELAYS
D. CONCURRENT DELAYS
B. Excusable Delays
When a delay is caused by factors that are not foreseeable and are
beyond the contractor's reasonable control, it may be "excusable".
This term has the implied meaning that neither party is at fault
under the terms of the contract and have agreed to share the risk and
consequences when "excusable" events occur. The contractor will
not receive compensation for the cost of the delay, but it will be
entitled to additional time to complete its work (and relief from any
contractually imposed liquidated damages for the period of delay).
You are not entitled to the earlier completion date, but also are not
obligated to the contractor for the contractor's delay costs.
Excusable delays are typically provided for by the "Delays and
Extensions of Time" clause in the General Conditions. A typical
provision reads as follows:
f3. Suspension
“The Company may by written notice to Contractor,
suspend at any time the performance of all or any portion
of the Work to be performed under the contract...
If Contractor intends to assert a claim for equitable
adjustment under this clause, it must pursuant to the
General Condition titled “Changes” and within ten (10)
calendar days after receipt of notice to resume work,
submit the required written notification of claim and within
twenty (20) calendar days thereafter its written proposal
setting forth the impact of such claim.”
From time to time during the course of the work, it may be
necessary or desirable to suspend all or part of the work. In
this eventuality, the contractor is required to take the actions
enumerated in the provision. In order to establish a claim
for an equitable adjustment, the contractor must show that
the suspension was in no way caused by its own wrongdoing
or fault.
D. Concurrent Delays
Concurrent delay occurs when both you and the contractor are
responsible for the delay. Generally, if the delays are inextricably
intertwined, the contractor cannot be faulted for delay (forced to
accelerate, or be liable for liquidated damages) nor can it recover
delay damages against you in such circumstances. (Reference
Special Topics Section 7.8 "Delays and Extensions of Time.")
Until the development of CPM schedule analysis, there was no
reliable method available to distinguish the impact of contractor
delays from the impact of your delay. With the sophisticated
computerized techniques now available, however, it has become
possible sometimes to accurately segregate the impacts of
apparently concurrent delays.
If there is some basis for doing so, a court will apportion the fault
and allocate delay damages accordingly. However, delays on the
critical path cannot be offset by delays on a float path, and the
rights of the parties will be determined solely in accordance with the
critical path delays.
The critical path is commonly defined as the longest chain (in terms
of time) of interrelated activities through the project (from beginning
to end). Because this chain of activities takes the longest time to
complete, it is "critical" to completion of the project. If one of the
critical activities is delayed by one day and no pressure is applied to
need to manage jobs that extend over long periods of time and which
involve changing and sometimes unforeseeable circumstances. On the
other hand, the contracts impose relatively few express obligations on you
other than payment. However, there are a number of implied obligations
or implied warranties to which you are held.
Some of these were mentioned above in the paragraph on non-excusable
delays. We mentioned a gray area where overstepping the bounds of
reasonableness might change a non-excusable delay into a compensable
delay. The burden of proof, of course, as in any claim situation, would be
on the party pressing the claim. Some other implied warranties would
include:
(A) Sufficient Plans and Specifications: This is the most widely
recognized implied warranty in a construction agreement. Inasmuch
as all delays due to defective specifications are per se unreasonable,
if you provide plans and specifications that are incomplete or
ambiguous and the contractor does not have sufficient time to seek
and receive adequate clarification, the resulting delay is
compensable (unless there is concurrent contractor-caused delay).
(B) Timely Review of Shop Drawings, Payment Requests, and
Change Notice Proposals: You must render a decision within the
period of time specified in the contract. If no time limitation is
stated, a standard of reasonableness is implied, typically two to
three weeks.
In issuing changes and making decisions, it is not unreasonable to
consume a reasonable period of time to process the change or to
ensure the correctness of the decision. The contractor should expect
some periods of time when it might halt work in a specific area
while changes are being made, just as it expects bad weather,
holidays and absenteeism. However, it is not anticipated that such
interruptions will be for an unreasonable amount of time.
(C) Proper Coordination of the Work: With the advent of the
construction management approach, this has become a growing
source of delay claims. When you have authority to coordinate and
sequence the work, you have a duty to do so in a proper and
efficient manner.
(D) Site Access: Courts disagree on the extent to which access to the
jobsite is guaranteed. As a general rule, you must, at a minimum,
do all that is reasonably possible to provide sufficient access. A
delay will be compensable if you cause the lack of access or knew in
advance that there would be an access problem and failed to divulge
this information to the contractor. The most common sources of
delay claims in this area are: failure to provide initial access to the
7. Constructive Acceleration
If a contractor is entitled to a time extension, but the project schedule
requirements determine that a time extension is unacceptable, the
contractor may be directed to hold the original schedule despite an
excusable delay. Such direction may constitute "Constructive
Acceleration." (Reference Special Topics, Section 7.9 "Acceleration.")
• industry standards
• expert analysis
• bid comparisons
Exculpatory Clauses
Many contracts contain exculpatory clauses which attempt to shift the risk of
unknowns to the contractor. These clauses disclaim responsibility for the
completeness or accuracy of the data provided and place responsibility on the
contractor for any problems that might result from relying on such data should
it prove to be defective or misleading. The concept is that the contractor is
Liens
A lien is a claim against property. Generally, in construction when a laborer
or a contractor does work on real property or a supplier furnishes material
which is incorporated into the work on the real property, the person providing
the labor or material can place a lien on the real property if the person is not
paid. In the case of a laborer or a contractor or a subcontractor who does
work on the real property, the lien is known as a mechanic's lien. In the case
of the supplier of materials, the lien is known as a materialman's lien.
7.3 NEGOTIATION
The objective of negotiations is not simply for one party to convince another
party that it is right or wrong. The objective of negotiations is to find a
combination of issues and price(s) that is acceptable to both parties. This is
first a process of education, then a process of persuasion.
Ÿ Confidence - Let the other side know you are comfortable with
your position and with your grasp of their
position
7.3 NEGOTIATION
SECTION 7. SPECIAL TOPICS Page 29 of 67
.
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Negotiating Strategy
The Lead Negotiator should clearly understand the policy philosophy and the
aims and objectives of the negotiating team. A pre-negotiation plan is to be
developed on all matters to be discussed. The team members should rely on
their experience in researching and developing the pre-negotiation plan. The
Lead Negotiator should coordinate negotiation objectives with the Site or
Project Manager to make sure that the customer's and the project goals are
achieved. For all negotiations involving a potential commitment in excess of
$1 million (and other commitments when approval is at all in doubt),
appropriate commitment authority should be obtained in advance of
negotiations to avoid having to renege on negotiated points.
Negotiation Session
7.3 NEGOTIATION
SECTION 7. SPECIAL TOPICS Page 30 of 67
7 SPECIAL TOPICS
7.4 INTERFACE COORDINATION
7.4.1 Purpose The designated contracts representative has the primary responsibility to
ensure that the contractor performs in accordance with the contract. It is
important to realize that although assigned only specific contracts, this
individual plays a major role in the total project team effort to construct a
quality project within the schedule and budget. To be successful in this
objective, the various contracts representatives must work in close
conjunction and harmony with each other as well as with others on the
project team to minimize or eliminate interface problems.
7.4.2 Initial Steps Keep in mind that the contractor has been living with the contract for a long
time before it was even awarded. You will be at a definite disadvantage if
you wait until the contractor arrives at the site to "come up to speed." The
first step is to be thoroughly familiar with the contract documents.
Remember to "RTFC — Read the Full Contract." You should be thoroughly
familiar with the contract before the work begins. The formation of a
company contract is a lengthy process involving participation by
Engineering, Construction, Contracts, Procurement, Legal, Project Controls
and sometimes the customer. The process is structured and provides several
opportunities for the contracts representative to participate in the pre-award
activities:
If it is not possible to attend all of these meetings, the agenda and minutes of
the meetings located in the contract files should be reviewed. The bid
tabulation, the recommendation to the customer and other bid period
correspondence are important sources of background information.
This meeting is where the ground rules for working with the contractor
should be discussed and the last level of detail established. At this time it is
particularly important to note two basic provisions of the Contract General
Conditions which typically appear in contracts. They are:
1. "Independent Contractor...
Contractor represents that it is fully experienced, properly qualified,
registered, licensed, equipped, organized, and financed to perform the
Work under this contract. Contractor shall act as an independent
contractor and not as the agent for you or Owner in performing this
contract, maintaining complete control over its employees and all of its
suppliers and subcontractors. Nothing contained in this contract or any
purchase order or subcontract awarded by Contractor shall create any
contractual relationship between any such supplier or subcontractor
and either you or Owner. Contractor shall perform its work hereunder
in accordance with its own methods subject to compliance with the
contract."
These clauses establish that the contractor is solely responsible for all its
work and operations and establishes the channel of communication
through which interface coordination problems are resolved.
By this time, individual contractor work areas, access routes, storage and
lay-down areas and priority of work operations have been established. Many
front end problems can be avoided through the foresight and active
involvement of the contracts representative at this stage.
• Is fabrication on schedule?
7.4.3 Construction The contracts representative is the key player in overall coordination and
Coordination control. This individual must be kept aware of all problems, potential
problems, and the status and daily progress of the contract. This is
accomplished through daily communications with other contract
representatives, review of the Daily Reports, and monitoring jobsite
activities. The Construction Manager should be kept fully informed and
advised of contract status and schedule through established jobsite channels.
"You, the Owner and other contractors may be working at the site
during the performance of this Contract, and Contractor's work, or
use of certain facilities, may be interfered with as a result of such
concurrent activities. You reserve the right to require Contractor to
schedule the order of performance of its work in such manner as
will minimize interference with the work of any of the parties
involved."
Bear in mind that this provision is part of each interfacing contract and
therefore applies equally to all contractors. The key words are "minimize
interference with the work of any of the parties involved."
By being fair and reasonable, using good judgment, and thinking and
planning ahead, the contracts representative can minimize potential for such
claims.
The astute observer may have noticed that there is a gray area here.
Whatever is best for the project may stretch the limits of cooperation beyond
what was intended by the contract. The contracts representative will
frequently be operating in gray areas. How well those situations are handled
will be the true measure of this person's stature and worth to the project. If a
contractor is fairly entitled to additional compensation or time as a result of a
"coordination" decision, the contracts representative should be prepared to
support and justify an appropriate contract change.
7.4.4 Interfaces Probably the most troublesome problem in managing major contracts in
congested areas is "interferences." As a general rule, two objects cannot
occupy the same space. An HVAC duct cannot be installed in its allotted
space if someone else installed a pipe or support or a cable tray first. The
best solution of course is to know the drawings. However, because much of
the work is field routed and, also, because field changes occur, you need to
keep in touch with what is going on generally. Communicate with your
direct-hire superintendents and other contracts representatives monitoring
contracts in the same area. If a space is allotted for a particular contractor's
work, make sure it stays open and thereby avoid an expensive "fix."
Whatever the decision is, make it in a timely manner. In most cases, this
decision can and should be made the same day the interference occurs. It is
important to document fully these kinds of agreements, clearly stating each
party's responsibilities. If they are of relatively minor significance they
should, as a minimum, be noted in the "Daily Report."
7.4.5 Schedule Because Project Controls plays a major role in the successful management of
Coordination the project, it is vital that each contracts representative works in close
conjunction with the scheduler.
Project Controls evaluates the contractor's reports and plots the contractor's
progress on the project master schedule. To manage the project successfully
and efficiently, it is mandatory that both the contracts representatives and
Project Controls work closely together to foresee and eliminate possible
conflicts that would be cause for project schedule slippage.
7.4.6 Coordination with Many (but not all) major contracts include a provision in the Special
Procurement Conditions for you or the customer to furnish some or all of the equipment or
materials. Procurement plays an important role in the total project effort in
that it is responsible for the issue and administration of purchase orders and
the receipt and issue of customer-furnished material and equipment.
Materials delivered too long before they are needed may adversely affect cash
flow or create storage and handling problems. On the other hand, materials
or equipment delivered late are likely to delay not only a contractor but could
impact and delay other contractors or even the total project and result
ultimately in disputes or claims. Material purchase and delivery schedules
are initially coordinated with construction requirements. Consider expediters
to assist in obtaining a smooth flow of manufactured equipment and
prefabricated materials, including contractor-furnished equipment and
materials.
The contracts representative must keep fully informed of the progress of the
various parts of the work and the status of related procurement activities to
ensure that all elements are in balance.
Purchase orders sometimes may require that a manufacturer's representative
be present during the installation of the equipment by a contractor. When
this occurs, the contracts representative, in monitoring the contractor's
progress, will coordinate with the contractor and the manufacturer to
establish the required date for the manufacturer's representative to be onsite.
7.4.7 Coordinating The contractor is typically obligated by the terms of its contract to keep its
Clean-Up and work areas in a neat, clean and safe condition.
Housekeeping
Because work in and around a construction site can be confined and create
very close working conditions among contractors, daily cleanup is an
absolute necessity. Enforcement of this contract provision must be exercised
regularly and vigorously. A clean job is a safer job and most likely a more
efficient one.
7.4.8 Other It is immediately evident from a review of the General and Special
Coordination Conditions of the contract that the administration of all the provisions will
Interfaces require the involvement or assistance of numerous participants. The contract
is likely to interface at some time or other with:
7.4.9 Sub-Tier The contracts representative must not do any coordinating between a
Subcontractors contractor and its subcontractors or subcontractors of different contractors
engaged on the project. This type of coordination is the function and
responsibility of the contractor(s). Subcontractors are not to be regarded as
separate contractual entities, but should be treated as part of the contractor's
force. Conflicts between subcontractors should be brought to the attention of
the contractor's field representative.
7.4.10 Conclusion Contractors are required by contract to cooperate with other contractors.
Situations frequently occur that require the contracts representative to
coordinate the work of one contractor with that of other contractors and/or
with Supervision. The contract also gives rise to extensive and varied
interface coordination requirements.
When the problem involves interface conflicts with two or more contractors,
the meetings should be arranged between the contractors, with you acting
only as a moderator and encouraging solutions directly between the
contractors by mutual cooperation.
7.5.1 Purpose Your responsibilities relating to the labor and industrial relations obligations
of contractors will be dependent upon whether the project is being performed
on a union, open shop or merit shop basis. This guideline generally describes
how to monitor a contractor's conformance to site labor relations
requirements on a union project, where this responsibility is within the scope
of your responsibilities.
7.5.2 Procedure Become familiar with applicable labor agreements and site work rules.
Contract Scope:
2. Company Labor Relations has been notified of contractor's scope, labor requirements YES NO
and mobilization schedule.
Comments:
5. Contractor's daily labor management is routinely monitored and deficiencies noted on YES NO
Daily Reports.
Comments:
6. When required, contractor submittals such as certified payrolls are available and YES NO
submitted on time.
Comments:
7. YES NO
Comments:
8. YES NO
Comments:
Name:________________________________ Date:_____________________________
7.6.1 Purpose This procedure describes the process for identifying, documenting, verifying
and dispositioning force accounts. Specific responsibilities for initiating such
accounts, approving charges, tracking and closing-out such accounts must be
assigned on a project basis between Field Engineering, Project Controls and
Contract Administration.
7.6.2 Discussion Several circumstances give rise to the need for force accounts which are an
accounting method for accumulating costs as incurred with concurrent
approval by you in the field. Typical applications are:
• Reasonable
• Necessary
• Actual
If backcharges or warranty claims are involved, the final costs will be priced
in accordance with contract agreements or normal pricing practices and
submitted for collection in accordance with project procedures.
CURRENCY:
BC NO.:
LOCATION: DATE: 03/30/1999
LABOR EQUIPMENT
NO. HOURS TOTAL TOTAL EQUIP.
MEN CLASS. ST OT RATE WAGES SUBSISTENCE NO. DESCRIPTION HOURS RATE AMOUNT
TOTAL OTHER
REMARKS
TITLE TITLE
Expedition
7 SPECIAL TOPICS
7.7 LIQUIDATED DAMAGES
One of the more difficult and complex aspects of delay analysis is the
resolution of concurrent delays. If a critical path delay is caused by (or is the
responsibility of) one party, that party bears the responsibility for the delay.
For example, if a delay on a fixed price project is a contractor-caused delay,
in the absence of any other circumstances, the contractor would be
responsible for the additional costs necessary to make up for the delay (or be
responsible for you or your customer's actual damages or contractually
specified liquidated damages to the extent project completion is delayed).
However, sometimes all or a portion of one delay may overlap or occur
concurrently with all or a portion of another delay. Such delays are referred
to as "concurrent". Their implications for contract management are
important to understand. (Refer to Special Topics Section 7.2 "Basis for
Claims" pg. 22.)
If there are two delays (occurring simultaneously and with the same delay to
the critical path) and one is the responsibility of the contractor and the other
is the company's responsibility, each party must bear the financial
consequences of the delay but the contractor would typically be entitled to a
time extension for the duration of the delay (i.e., an "excusable delay"
equivalent to force majeure). If you were to refuse to grant a time extension
and the contractor was compelled to accelerate its work to meet the original
schedule, the additional costs incurred by the contractor would be to you or
your customer’s account (even though the contractor's delay was concurrent
with your’s).
Contractor delays which are not excusable (i.e., are the fault or responsibility
of the contractor) must be overcome by the contractor by accelerating the
work. Otherwise, you may be entitled to assess liquidated damages at a
specified amount per day of delay (if the contract so provides).
Alternatively, if liquidated damages are not specified in the contract, you
may be entitled to actual damages sustained by you or your customer
because of the contractor's inexcusable delays. Such damages may be
withheld from the contractor's retention or amounts otherwise due to
contractor.
Note: For additional discussion on delays, see Section 7.2 "Basis for
Claims" pps. 15-23.
Float Ownership
Activity delays shall not automatically mean that an extension of the contract
completion date is warranted or due the contractor. A Contract Change
Notice or delay may not affect existing critical activities or cause non-critical
activities to become critical. A Change Notice or delay may result in only
absorbing a part of the available total float that may exist within the
schedule, thereby not causing any effect on any interim milestone date or the
contract completion date.
Total float is defined as the amount of time between the early start date and
the late start date, or between early finish date and the late finish date, for
each and every activity in the schedule. Float is not for the exclusive use or
benefit of either you or the contractor. Extensions of time to interim
milestone dates or the contract completion date under the contract will be
granted only to the extent that equitable time adjustments to the activity or
activities affected by the Change Notice or delay exceeds the total float of the
affected activity or subsequent paths and extends any interim milestone date
or the contract completion date.
7.9 ACCELERATION
The steps which the contractor must follow to establish the basis for recovering its
acceleration costs are the following:
Ÿ The contractor must then actually accelerate the work. (The acceleration
effort need not be entirely successful. A good faith and reasonable
attempt is all that is required, yet all costs expended in good faith will be
compensable.)
Unless these steps are carefully followed giving you the opportunity to decide
whether it is willing to extend completion of the project or alternatively whether it
will pay for the costs of acceleration, the contractor may not be able to recover its
costs for accelerating the work.
7.9 ACCELERATION
SECTION 7. SPECIAL TOPICS Page 53 of 67
7 SPECIAL TOPICS
7.10 SUSPENSION OF WORK
Suspension notices should be absolutely clear when issued to define the scope
of the suspension and any special instructions. Suspension caused by
contractor problems should cite the nature of contractual liability for such
problems and should describe a course of action required to lift the
suspension. Any notice to suspend or to resume work must be in writing
from your authorized representative.
One of the most common types of variation, as well as one of the most
contentious, is the differing site condition. Contract clauses vary concerning
entitlement, but most contain the same elements.
Even if the contract does not contain a Differing Site Conditions clause, the
contractor may still be able to recover the costs and time resulting from
the differing site conditions which were encountered. If you have
misrepresented the conditions, or has withheld pertinent information from the
contractors bidding the project, the contractor may still have entitlement.
Note: Refer to Special Topics Section 7.2 "Basis for Claims" pgs. 12 & 13.
7.12.1 Purpose This procedure describes the process for terminating the services, in whole or
in part, of contractors; either for default or for convenience (optional
termination for you or your customer's convenience).
7.12.2 Discussion Terminations have potentially significant, long range implications and must
have adequate management and legal review to ensure an understanding of
probable liabilities and to evaluate direct hire or contracting alternatives to
achieve project objectives.
Under many contracts, you have the right to terminate all or a portion of the
incomplete work under a clause entitled "Termination for Convenience" or
"Optional Termination." Although the Termination article may refer to the
Changes article for determination of compensation, Termination for
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 56 of 67
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 57 of 67
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Appropriate grounds for termination for default are normally set out in the
contract and include continued and uncorrected defective work, failure to
complete, failure to make progress and insolvency. Termination for default
requires extensive Legal and management involvement. Prior to taking
action that leads directly to a termination for default, the following steps will
be taken:
Notify the contractor and its surety of the defect or non-performance and
your intent to partially or entirely terminate for default and provide a
reasonable opportunity in the notice for the contractor to remedy the
problems. (Refer to Exhibits 7.12.3-B.1, 7.12.3-B.2, and 7.12.3-B.3 for
sample Cure Notice Letters.)
If the problems are not resolved, proceed with the following steps:
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 58 of 67
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
• Demobilization of personnel
• Retention of equipment, tools and materials
• Turnover or transition of work to others
• Cancellation or assignment of purchase orders and
subcontracts
• Protection of work in progress
7.12.4 Exhibits Notice Letter — Schedule Submittal Unacceptable [Sample] (Exhibit 7.12.1)
Termination for Convenience Letter [Sample] (Exhibit 7.12.3-A)
Cure Notices [Sample] (Exhibits 7.12.3-B.1; 7.12.3-B.2; and 7.12.3-B.3)
Termination for Default Letter [Sample] (Exhibit 7.12.3-C)
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 59 of 67
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
[Date]
Dear _______________:
The referenced submittal contains proposed schedule dates which do not meet the contract milestone dates.
The proposed dates are not acceptable. Please take appropriate action to recover the schedule and submit,
within five (5) days, a revised submittal which reflects completion of contract work in accordance with the
contract milestone dates.
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 60 of 67
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
[Date]
Dear _______________:
[Contractor's name] is hereby notified in accordance with the General Conditions, Article __, entitled
OPTIONAL TERMINATION, that the contract is terminated for convenience. By copy of this letter,
contractor's Surety is also advised of this Notice.*
[Provide specific instructions with respect to disposition of work in progress, sub-tier suppliers and
subcontractors, and similar direction, in accordance with the termination article.]
* If the contract has no performance bond, delete the reference to the bonding company and the cc.
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 61 of 67
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
[Date]
Dear _______________:
Reference 1 directed [contractor's name] to take action to correct repeated quality deficiencies in its work,
"whether or not contractor considered such action to be a change."
[Contractor's name] has indicated, [Reference 2, if refusal is by letter] [by its actions, if contractor just
declines to accept work, but will not formally acknowledge its refusal] that it does not intend to proceed
with the direction in Reference 1.
The Contract General Conditions, Article __, entitled CONTRACT INTERPRETATION, provides, in
part: "At all times CONTRACTOR shall proceed in accordance with the work in accordance with the
determinations, instructions, and clarifications of COMPANY."
The contract General Conditions, Article __, entitled TERMINATION FOR DEFAULT, provides, in part:
"...CONTRACTOR shall be considered in default of its contractual obligations under this contract if it
abandons or refuses to proceed with any or all work, including modifications directed pursuant to the
clause entitled 'CHANGES'."
It is the company's determination that the reference direction is appropriate. This letter is formal notice that
[contractor's name] is to demonstrate by its actions that it intends to comply immediately with the direction,
and further, that [contractor's name] is to provide within three (3) days, written confirmation of its intent to
comply with the company's direction. By copy of this letter, contractor's Surety is also advised of this
Notice.*
* If the contract has no performance bond, delete the reference to the bonding company and the
cc.
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 62 of 67
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Dear _______________:
The company has determined that [contractor's name]'s performance is endangering the contract milestone
dates.
The Contract Special Conditions, Article __, entitled COMMENCEMENT, PROGRESS AND
COMPLETION OF THE WORK, provides in part: "If at any time, CONTRACTOR'S actual progress is
inadequate to meet the requirements of this contract, COMPANY may notify CONTRACTOR to take
such steps as may be necessary to improve its progress."
The Contract General Conditions, Article __, entitled TERMINATION FOR DEFAULT, provides, in part:
"...CONTRACTOR shall be considered in default of its contractual obligations under this contract if it...
fails to make progress so as to endanger performance of this contract."
The Contract Special Conditions, Article __, entitled COMMENCEMENT, PROGRESS AND
COMPLETION OF THE WORK, provides, in part: ” If within a reasonable period as determined by
COMPANY, CONTRACTOR does not improve performance to meet the Contract Milestones ....
COMPANY may require an increase in CONTRACTOR’S labor force, the number of shifts, overtime
operations, additional days of work per week, expedited shipment(s) of equipment and materials, and an
increase in the amount of construction plant and equipment, all without additional cost to COMPANY."
[Contractor's name] is directed to take appropriate action to recover the schedule and to submit, within
three (3) working days, a revised submittal which reflects completion of contract work in accordance with
the contract milestone dates. [Provide details whether contractor is specifically directed to increase its
labor force, the number of shifts, overtime operations, additional days of work per week and an
increase in the amount of construction plant as is necessary to achieve the contract milestone dates.]
By copy of this letter, contractor's Surety is also advised of this Notice.*
* If the contract has no performance bond, delete the reference to the bonding company and the
cc.
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 63 of 67
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
[Date]
Dear _______________:
The referenced submittal contains proposed schedule dates which do not meet the contract milestone dates.
The proposed dates are not acceptable.
The Contract Special Conditions, Article ____, entitled COMMENCEMENT, PROGRESS AND
COMPLETION OF THE WORK, provides, in part: "If at any time, CONTRACTOR'S actual progress is
inadequate to meet the requirements of this contract, COMPANY may notify CONTRACTOR to take
such steps as may be necessary to improve its progress."
The Contract General Conditions, Article _____, entitled TERMINATION FOR DEFAULT, provides, in
part: "...CONTRACTOR shall be considered in default of its contractual obligations under this contract if
it...fails to make progress so as to endanger performance of this contract..."
[Contractor's name] is directed to take appropriate action to recover the schedule and to submit, within
three (3) days, a revised submittal which reflects completion of contract work in accordance with the
contract milestone dates. By copy of this letter, contractor's Surety is also advised of this Notice.*
* If the contract has no performance bond, delete the reference to the bonding company and the
cc.
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 64 of 67
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
[Date]
Dear _______________:
The reference letter, copy attached, provided specific instructions and a schedule to cure a material breach
of the contract. The period for curing the failure has lapsed. [Contractor's name] has not cured the failure,
and is hereby notified in accordance with the General Conditions, Article __, TERMINATION FOR
DEFAULT that the contract is terminated.
By copy of this notice, contractor's Surety is also advised of this notification of termination for default.
The Surety has ten (10) days from the date of receipt of this letter to respond with respect to its intent
to complete the work.*
[Provide specific instructions with respect to disposition of work in progress, sub-tier suppliers and
subcontractors, and similar direction, in accordance with items (g) through (k) of the termination
article.]
* If the contract has no performance bond, delete the reference to the bonding company and the
cc.
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 65 of 67
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Contract Number:__________________________
Contractor:____________________________________
Contract Scope:
2. Alternate work completion plan has been prepared and approved. YES NO
Comments:
4. The Site Manager has approved the contract termination package. YES NO
Comments:
5. Company management and Legal have approved the termination package. YES NO
Comments:
7. YES NO
Comments:
8. YES NO
Comments:
Name:____________________________________________
Date:________________________________________
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 66 of 67
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Contract Number:__________________________
Contractor:____________________________________
Contract Scope:
2. The contractor has been given a Notice of Default with a reasonable period to "cure" YES NO
the default.
Comments:
3. A contingency plan has been prepared to deal with the results of the contract YES NO
termination addressing work completion.
Comments:
4. A detailed description with adequate supporting back up of why the contract is being YES NO
terminated (termination package) has been prepared.
Comments:
5. The Site Manager has approved the contract termination package. YES NO
Comments:
9. Contractor's Surety has been contacted to determine when/whether it will complete YES NO
the work.
Comments:
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 68 of 67
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Name:____________________________________________
Date:________________________________________
7.12 TERMINATIONS
SECTION 7. SPECIAL TOPICS Page 69 of 67
7 SPECIAL TOPICS
7.13.1 Purpose The proliferation of federal, state, local, and international environmental
regulations and public concerns has increased the need for environmental
planning for construction projects of all kinds.
Complicating the planning process is the multitude of agencies, organizations
and authorities that have cognizance over the various environmental aspects
of a project. Their overlapping and sometimes conflicting requirements
must be factored into the early planning of a project.
7.13.2 Overview - Environmental Controls planning begins during the project proposal or bid
Strategic cycle. Working with your environmental specialists, the proposal and
Planning project managers should review the Request for Proposal for
environmental requirements. Research may be required to identify
significant legislative or community requirements that may affect the project
but which are not mentioned in the bid documents. The potential cost of
compliance activities, the compatibility of the project location, design, and
layout with environmental requirements, and the time required to obtain
permits, agency reviews and other approvals are important elements in
evaluating a prospective project.
7.13.3 Phase I - The effectiveness of the initial planning will set the tone of the project.
Planning Clear understanding of the areas of responsibility and authority among the
customer, the project designers, and the constructor is essential. The
Project Division of Responsibility, often reduced to a matrix for ease of
understanding, should include such topics as:
• Environmental Constraints
One of the early steps in project planning or development is the
identification of environmental constraints that may affect the project.
Environmental requirements are reviewed to identify which, if any, have
the potential to have a significant impact on the project’s location,
design, layout, cost, schedule, or viability. These environmental issues
or constraints are important to identify early to determine if any are
incompatible with the project development basis, including feasibility,
and to avoid unnecessary cost and schedule implications for you, the
customer, or contractors.
• Permitting Plan
The final phase of the planning stage is a permitting plan or matrix,
listing and scheduling applicable permits and licenses that must be
obtained by you in the performance of its work. (Refer to Exhibit
7.13.2). This information assists in the identification of those which the
customer or Project will obtain, those you are responsible to obtain (if
any), and those which are to be included in the scope of contractors.
7.13.4 Phase II - During the design phase of the project, the strategy for environmental
Design compliance established in the planning phase can be integrated into the
engineering activities.
• Contracting Plan
The requirements for environmental compliance, including flowdown of
requirements from the prime contract, must be included in all contracts
and, in many cases, in material purchase orders. When the project
develops the construction contract terms and conditions it must include
environmental compliance, training and certification requirements.
• Preconstruction Surveys
The terms and conditions of a project’s permits may require project-
specific preconstruction surveys to document the presence, extent, and
condition of environmental resources (e.g. sensitive plants, fish and
wildlife, cultural resources). These surveys are often required during
specific timeframes, may involve approved survey areas and
techniques, and often must be documented and submitted to an
agency(ies) prior to start of construction. The need for and
responsibility for timing of such surveys should be communicated to
contractors in advance of construction mobilization to avoid initiation of
site activities prior to satisfying these regulatory requirements.
• Personnel Training
In almost every aspect of construction, personnel must acquire specific
training for performance of various aspects of the work. The selection
of contractors who can provide environmentally trained personnel is
critical. Appropriate training of customer, your or other project
personnel is of equal importance, not only at the inception of the project
but on a continuous basis throughout the life of the project. The
development and implementation of an environmental training plan and
training records may be a valuable asset to the project.
7.13.6 Phase IV - The planning and process development actions taken during the planning,
Construction design and preconstruction phases of the project will be implemented at the
work site. Contract management will include oversight that contractors are
operating in accordance with the project environmental controls. Site
activities include a number of key elements as follows:
• Regulatory Reporting
Two types of reporting to regulatory agencies may be necessary on a
project. First, routine reporting may be required under permit or other
approval conditions (e.g. construction inspection reports, monitoring of
sensitive resources). Second, reporting may be required in response to
non-routine events on the jobsite (e.g. spills or releases of hazardous
substances). Routine reporting requirements will be identified in the
CECP and should be complied with by jobsite personnel. Reporting
requirements should also be communicated to contractors, as
appropriate.
• Document Control and Records Retention
Documenting the design, quality and construction performance is a
basic project requirement. Added to these standard processes should
be the documentation of compliance with environmental regulations and
the heath and safety status of personnel engaged in the work. These
requirements should be incorporated into the project document control
program to insure that the performance is recorded and maintained in a
complete and cost effective manner.
INDEX Page 1 of 7
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
INDEX Page 2 of 7
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Checklists
Contract Amendment, Section 4, pg 23
Contract Change Notice, Section 4, pg 24
Contract Change Order, Section 4
Contract Closeout, Section 6, pg 5
Contractor Proposals, Section 4, pg 26
Contractor Demobilization Checklist, Section 6, pg 4
Coordination Meeting, Section 5, pg 10
Cost Commitment, Section 4, pg 29
Daily Report, Section 5, pg 6
Environmental, Section 5, pg 33
Insurance and Bonds, Section 3, pg 38
Invoice Processing, Section 5, pg 20
Labor Relations, Section 7, pg 45
Mobilization Payment, Section 5, pg 19
Pre-Award Action, Section 3, pg 7
Pre-Bid and Site Inspection Visit, Section 3, pg 5
Pre-Construction Meeting, Section 3, pg 18
Progress Review Meeting, Section 5, pg 9
Safety & Health, Section 5, pg 30
Schedule, Section 5, pg 11
Technical Transmittals, Section 4, pg 46
Termination For Convenience, Section 7, pg 66
Termination For Default (Cause), Section 7, pg 67
Claims, Section 4, pg 47-57
Basis For, Section 7, pg 12-28
Flowchart, Section 4, pg 56
Log, Section 4, pg 14, 49
Closeout, Section 6, pg 1-9
Certificate of Final Acceptance, Section 6, pg 1, 7
Checklist, Section 6, pg 1, 5
Demobilization (See Demobilization)
Files, Section 3, pg 20
Inspection (See Inspection)
Lien, Release of, (See Release and Certificate of Final Payment)
Partial Release and Certificate of Payment, Section 6, pg 1, 8a
Punch List (See Punch List)
Records Retention, Section 3, pg 20; Section 6, pg 5
Release and Certificate of Final Payment, Section 6, pg 1, 8
Substantial Completion (See Substantial Completion)
Completion, Acceptance (See Closeout)
Commitment Approvals, Section 4, pg 27-36
Commitment Authorization, Section 4, pg 27-36
Commitment Register, (See PTS Commitment Register)
Concurrent Delay (See Delay)
Contract Law, Section 7, pg 1-11
Convenience Termination (See Termination)
Coordination, Section 7, pg 35-43
Meeting, Section 5, pg 8, 10
INDEX Page 3 of 7
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Correspondence
Action Items, Section 3, pg 25, 26
Control, Section 3, pg 25, 26
Logs, Section 3, pg 27, 28
Closeout, Section 3, pg 25
Effective Correspondence, Section 3, pg 25,26
Filing System, Section 3, pg 19-24
Contract Administration Filing Index, Section 3, pg 22-24
Point of Contact, Section 3, pg 15,16,26
Records Retention, Section 3, pg 20
Credit Review, Section 3, pg 8
Critical Path (See Schedule)
Cure Note (See Termination)
INDEX Page 4 of 7
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Kickoff
Letter, Section 3, pg 14-16
Meeting, Section 3, pg 9-18; Section 7, pg 36-37
INDEX Page 5 of 7
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
Meetings
Coordination, Section 5, pg 8, 10-11
Minutes/Action Lists, Section 3, pg 1
Pre-Award, Section 3, pg 1-3, 6, 7
Pre-Bid, Section 3, pg 1-2, 4-5
Pre-Construction, Section 3, pg 3, 9-18
Progress Review, Section 5, pg 7, 9
Site Visit, Section 3, pg 1-2, 4-5
Mobilization
Notice of, Section 3, pg 10, 17; Section 7, pg 37
Payment, Section 5, pg 12
MSDS (Material Safety Data Sheet, see Environmental)
INDEX Page 6 of 7
CONTRACT/SUBCONTRACT MANAGEMENT MANUAL
INDEX Page 7 of 7