Goal:

Mori Seiki NLX3000 install


Objective: Project Due Date:
Complete all necessary power, air and fabrication 7/30/2019
needs in preparation for late July installation.

Steps Description Tasks Assigned To Status Resource List completion date


B.J. Baldwin evaluation
1 Independent earth ground installation
7/15/2019
Brian in progress Tom Yingery ( t.yinger@bjbaldwin.com ) 7/19/2019

Design and get prints to Jeff Keith is cutting parts for tubing, Kevin or Kenny
2 Design/fabricate transformer stand
for laser cut
Brian in progress
will have it welded by 7/17/2019
7/19/2019

Design/fabricate stand for 120VAC and knife Design and get prints to Jeff Keith is cutting parts for tubing, Kevin or Kenny
3 switch for laser cut Brian in progress will have it welded by 7/17/2020 7/19/2019

60A Bus box, 3/4 conduit,


4 Prepare layout for electrical power THHN wire, fittings, Hangers, Brian completed Add links to project resources here 7/19/2019
location
3/4 or 1/2 black pipe, fittings, Brian
5 Prepare layout for pneumatic power
ball valves, quick connect etc.
completed Add links to project resources here 7/26/2019

6 Order all necessary equipment electrical/pneumatic Brian in progress Add links to project resources here 7/26/2019

7 Pneumatic install all associated tasks Brian not started Add links to project resources here 7/26/2019

8 Electrical Install all associated tasks Brian not started Add links to project resources here 7/26/2019

PLACE HOLDER FOR EARTH GROUND INSTALL


9 DATE N/A Brian not started Add links to project resources here

Transformer stand and


10 All fabricated parts sent for paint MANUF. electrical stand to be painted Brian in progress Add links to project resources here 7/19/2019
BLACK

Page 1 of 1