Académique Documents
Professionnel Documents
Culture Documents
5 KPa
4 3 2 1
ISO A1 594mm x 841mm
1.0 GENERAL 4. NON-LOAD BEARING FEATURE COLUMNS
5. ALL SECONDARY STEELWORK THE CONCRETE SHOULD BE COMPACTED WELL TO ACHIEVE THE REQUIRED DENSITY WITHOUT ANY
1.1 THIS SHEET SHALL BE READ AS PART OF THE STRUCTURAL DRAWINGS AND IS DEEMED TO BE PART OF THE 6. STRUCTURAL STEELWORK CONNECTIONS HONEYCOMBS AND VOIDS. THE CONTRACTOR TO DECIDE THE REQUIREMENT OF SELF-COMPACTING
CONTRACT DOCUMENTS. 7. STRUCTURAL SUPPORT FOR MEP SERVICES CONCRETE FOR THE PROJECT. ADMIXTURES ARE TO BE ADDED TO ACHIEVE THE FULL COMPACTION OF THE
1.2 STRUCTURAL DRAWINGS SHALL BE READ AND VERIFIED IN CONJUNCTION WITH RELEVANT ARCHITECTURAL, 8. SHADE STRUCTURES AND CANOPIES CONCRETE ON SITE.
D ELECTRICAL, MECHANICAL, PLUMBING AND OTHER STRUCTURAL DRAWINGS. FOR MAIN SETTING OUT AND LEVELS 9. METAL ROOFING SYSTEM
REFER TO THE ARCHITECTURAL DRAWINGS. ANY DISCREPANCIES OR CONFLICT IN THE SETTING OUT LINES, 10. BALUSTRADE AND CRASH BARRIER
LEVELS, DETAILS, LOCATIONS, SIZES, REINFORCEMENT ETC. OF THE STRUCTURAL MEMBER SHALL BE BROUGHT TO 11. STRUCTURAL GLASS 4.80 OPENINGS, SLEEVES
THE ATTENTION OF THE ENGINEER PRIOR TO COMMENCEMENT OF THE WORK. 12. INTERIOR SIGNAGE
1. NO HOLES, SLEEVES OR PENETRATIONS SHALL BE PLACED VERTICALLY OR HORIZONTALLY THROUGH BEAMS UNLESS
13. PRODUCTION OF SHOP DRAWINGS
1.3 DO NOT SCALE THE DRAWINGS. ALL DIMENSIONS SHALL BE READ FROM THE DRAWING OR COMPUTED. APPROVED BY THE ENGINEERS.
14. EXPANSION JOINT DETAILS
ELEVATIONS ARE IN METERS, DISTANCES AND REINFORCEMENT BAR SIZES ARE IN MILLIMETERS. 15. STRUCTURAL DETAILS AT TRANSFORMER AND LV ROOMS AS PER DEWA DRAWINGS 2. NO HOLES TO BE MADE IN SLABS UNLESS APPROVED BY THE ENGINEERS. PROJECT
16. STRUCTURAL DETAILS FOR ROAD BLOCKER
1.4 ALL LEVELS ARE ARE ASSUMED TO BE RELATIVE TO DUBAI MUNICIPALITY DATUM U.N.O 4.9 CONSTRUCTION JOINTS
THE DESIGN OF THE PRIMARY STRUCTURE CONSIDERS THE INTERFACE WITH THESE STRUCTURES (LOADING REACTIONS,
1.5 SLEEVES SHALL BE PROVIDED AT LOCATIONS INDICATED ON DRAWINGS OR AS DIRECTED BY THE ENGINEER.
ADDITIONAL REINFORCEMENT SHALL BE PROVIDED AROUND OPENINGS AS REQUIRED BY THE ENGINEER.
OPENINGS. ETC.) AND WERE DETAILED TO ACCOMMODATE THESE ELEMENTS INTO THE DESIGN. 1. THE CONTRACTOR SHALL SUBMIT TO THE ENGINEER FOR APPROVAL A PLAN SHOWING THE LOCATION OF ALL DOWNTOWN DUBAI
3.0 LOADING CONSTRUCTION JOINTS.
1.6 ALL CONCRETE WORK SHALL CONFORM TO THE RECOMMENDATIONS OF C.I.R.I.A. `GUIDE TO CONCRETE
CONSTRUCTION IN THE GULF REGION.
3.1 SUPERIMPOSED (DEAD LOADS AND LIVE LOADS) 2. HORIZONTAL CONSTRUCTION JOINTS SHALL NOT BE MADE IN BEAMS, UNLESS APPROVED BY THE CONSULTANT OR DEVELOPMENT
ENGINEER.
1.7 THE CONTRACTOR SHALL PRODUCE SHOP DRAWINGS AND SCHEDULES AS REQUIRED FOR COMPLETION OF THE DEAD LOADS AND LIVE LOADS ARE SHOWN ON THE LOAD MAP DRAWINGS. FORTE
3. VERTICAL CONSTRUCTION JOINTS MAY BE LOCATED BETWEEN MIDSPAN AND THIRD POINT OF SLABS OR BEAMS AFTER
WORKS AND RECORD DRAWINGS OF THE AS-BUILT AND BUILDER WORKS FOR THE CONSULTANT'S APPROVAL. 3.2 WIND LOADS REVIEWED AND APPROVED BY THE ENGINEERS. Dubai, UAE
1.8 THE CONTRACTOR IS RESPONSIBLE FOR PRODUCING FULLY DETAILED G.A. AND REINFORCEMENT DRAWINGS. THESE WIND LOADING ARE AS PER WIND-INDUCED STRUCTURAL RESPONSES REPORT NO. RWDI # 1501691
DATED MAY 30, 2016. 4. CONTRACTOR SHALL SUBMIT SHEAR FRICTION AND THE ADDITIONAL REQUIRED REINFORCEMENT CALCULATION AT
ARE TO BE SUBMITTED TO THE ENGINEER FOR HIS REVIEW WELL IN ADVANCE OF CASTING STRUCTURAL ELEMENTS, CONSTRUCTION JOINTS (AT ANY LOCATION) FOR ENGINEER REVIEW AND APPROVAL.
SHOWING ALL SLEEVING REQUIREMENTS INCLUDING SIZE AND LOCATION OF ALL MECHANICAL AND ELECTRICAL
OPENINGS AND DEPRESSIONS IN THE SLAB. SOME OF THESE MAY BE DEPENDENT UPON CHOICE OF MECHANICAL 3.3 SEISMIC LOAD - UNIFORM BUILDING CODE 1997 5. WATER STOPS SHALL BE PROVIDED FOR ALL CONSTRUCTION JOINTS BELOW GROUND WATER TABLE LEVEL AS PER
1. OCCUPANCY CATEGORY = II CLIENT
FITS. PERMIT TIME FOR NECESSARY REVISIONS OR ADJUSTMENT TO ENSURE THE STRUCTURAL INTEGRITY OF THE SOIL INVESTIGATION REPORT. REINJECTABLE INJECTION HOSES TO BE USED AT ALL CONSTRUCTION JOINTS IN
AFFECTED ELEMENTS. ADJUST SHOP DRAWINGS PRIOR TO CONSTRUCTION TO CONFORM NECESSARY CHANGES. 2. SEISMIC IMPORTANCE = I = 1.0 CONTACT WITH THE GROUND.
HERE GROUPS OF SLEEVES ARE LOCATED THEY MUST NOT BE SUCH AS TO AFFECT THE INTEGRITY OF STRUCTURAL 3. SITE CLASS SC (AS PER GEOTECHNICAL REPORT)
MEMBERS. 4. CA = 0.24G
5. CV = 0.32G
5.0 REINFORCEMENT Emaar Properties PJSC
1.9 OPENINGS SMALLER THAN OR EQUAL TO 200MM WIDTH ARE NOT SHOWN ON THE STRUCTURAL DRAWINGS. 6. SEISMIC DESIGN CATEGORY = 2B 5.1 THE REINFORCEMENT USED IN THE R.C WORKS SHALL BE ROUND, DEFORMED TYPE 2 BARS MARKED AS (T)
Building 3, Level 1
7. BASIC SEISMIC FORCE RESISTING SYSTEM BEARING WALL SYSTEM = ORDINARY REINFORCED
1.10 TECHNICAL SPECIFICATIONS AND WRITTEN INSTRUCTIONS OR DECISIONS OF THE CONSULTANT SHALL TAKE CONCRETE SHEAR WALL NOT BE EXCEED 0.51 FOR GRADE 460 P.O.Box 9440, Dubai, UAE
PRECEDENCE OVER THESE NOTES. 8. RESPONSE MODIFICATION FACTOR , R = 4.5 5.2 REINFORCEMENT DETAILS SHOWN ARE INDICATIVE. THE CONTRACTOR SHALL PREPARE DETAILED SHOP T +97143673333 tel
1.11 ALL DISCREPANCIES SHALL BE BROUGHT TO THE ATTENTION OF THE CONSULTANT ENGINEER BEFORE DRAWINGS & FULL BAR BENDING SCHEDULES IN ACCORDANCE WITH THE DESIGN DRAWINGS AND SHALL BE www.emaar.com
PROCEEDING WITH THE WORK ON SITE. 10.EQUIVALENT STATIC FORCE PROCEDURE AND MODAL RESPONSE SPECTRUM ANALYSIS USED CUT AND BENT IN ACCORDANCE WITH ACI 315-09 FOR THE ENGINEER'S APPROVAL AT LEAST FOUR WEEKS
AS PER ASCE 7-05 SEC. 12.9. PRIOR TO COMMENCEMENT OF R.C. WORK AND AFTER COORDINATING WITH ALL CONCERNED PARTIES.
1.12 ALL MATERIALS USED SHALL COMPLY WITH THE REQUIREMENTS OF THE SPECIFIED
CODES, STANDARDS AND ORDINANCE OF RELEVANT BUILDING AUTHORITIES UNLESS NOTED OTHERWISE IN THE 3.4 TEMPERATURE LOAD CONSULTANT
5.3 LAP LENGTHS AND ANCHORAGE LENGTHS OF REINFORCEMENT SHALL BE AS PER ACI 318M-08. ADDITIONAL
PROJECT SPECIFICATION AND / OR DRAWINGS. LAPPING IF REQUIRED TO BE PROVIDED WITH ENGINEER'S APPROVAL. THE MINIMUM LAP LENGTH OF
VARIATION.
1.13 ALL DIMENSIONS AND LEVELS SHOWN ON THE DRAWINGS SHALL BE VERIFIED BY THE CONTRACTOR. ANY DISCREPANCIES
SHALL BE BROUGHT TO CONSULTANT'S ATTENTION PRIOR TO CONSTRUCTION. 3.5 LATERAL PRESSURE OF SOIL (PRESUMED)
REINFORCEMENT SHALL BE THE MAXIMUM OF 45 BAR DIA IN GENERAL AND 50 DIA FOR TENSION OR THE
VALUES OF THE BELOW TABLE REINFORCEMENT. AECOM
1.14 THE CONTRACTOR SHALL ENSURE THAT DURING CONSTRUCTION, NO PART OF THE STRUCTURE IS OVERSTRESSED BY TENSION SPLICE LENGTH SCHEDULE LTS (mm)
AECOM MIDDLE EAST LIMITED
C 1. UNIT WEIGHT OF (ABOVE WATER TABLE) SOIL
EXCESSIVE CONSTRUCTION LOADS UNTIL THEIR COMPLETION. TEMPORARY BRACING AND PROPPING TO BE PROVIDED 2. UNIT WEIGHT OF (BELOW WATER TABLE) SOIL U-Bora Tower, Level 43, Business Bay,
WHERE REQUIRED. HORIZONTAL BAR WITH LESS HORIZONTAL BAR WITH MORE
3. BUOYANT WEIGHT OF SOIL
THAN 300mm CONCRETE THAN 300mm CONCRETE BELOW COMPRESSION SPLICE LENGTH PO Box 51028, Dubai, UAE
1.15 THE CONTRACTOR SHALL IMPLEMENT SITE SAFETY POLICIES IN ACCORDANCE WITH THE PROJECT REQUIREMENTS AND 3.6 MATERIAL UNIT WEIGHT (mm) +971-4-439-1000 tel +971-4-439-1001 fax
SHALL BE RESPONSIBLE FOR THE SAFETY OF THE WORKERS AT ALL TIMES. THE CONTRACTOR SHALL ENSURE BAR SIZE BELOW BAR OR VERTICAL BAR BAR BAR SIZE (APPLICABLE TO ALL CONCRETE
CLEANLINESS AND THAT THERE ARE NO LEFT OVER TIMBERS OR BURIED FORMWORKS WHICH CAN CAUSE TERMITE 1. CONCRETE www.aecom.com
INFESTATION. 2. WATER GRADES AND BAR TYPES)
3. STEEL 36 MPa >40
1.16 THE CONTRACTOR SHALL SUBMIT A METHOD STATEMENT FOR ALL ELEMENTS OF WORK AND SHALL NOT PROCEED
4. SOLID BLOCK - MPa 36 MPa >40
- MPa T10 375
UNTIL CONSULTANT'S WRITTEN APPROVAL IS GIVEN. THE METHOD STATEMENT SHALL PROVIDE THE CONTRACTOR'S
PREFERABLE OPTIONS WHERE SUCH OPTIONS ARE AVAILABLE.
5. HOLLOW BLOCK T10 475 450 620 585 T12 450 CONSULTANT
6. AAC BLOCK T12 570 540 740 700
1.17 THE CONTRACTOR SHALL COMPLY WITH ALL REQUIREMENTS OF THE LOCAL REGULATIONS AND REQUIREMENTS OF ALL T14 525
CONCERNED AUTHORITIES. 4.0 CONCRETE
T14 665 630 865 820 T16 575
4.1 ALL CONCRETE WORKS SHALL CONFORM TO THE ACI 318M-08. A GRADE OF C62/50 INDICATES THAT CONCRETE
1.18 TRIAL PITS MUST BE TAKEN BY CAREFUL HAND EXCAVATION TO LOCATE EXISTING SERVICES. IN THE EVENT OF EXISTING T16 760 720 985 935 T20 725
PAVED AREAS AROUND THE PLOT LINE REQUIRING EXCAVATION FOR LOCATING SERVICES, A SEPARATE ROAD CUTTING
N.O.C WILL HAVE TO BE OBTAINED FROM THE ROAD DEPARTMENT BEFORE CUTTING IS TO BE MADE. T20 950 900 1235 1170 T22 800
CONCRETE MIX DESIGN SHALL COMPLY WITH ACI 301-05 AS FOLLOWS:
1.19 ALL EXISTING SERVICES AND ROAD STRUCTURES WILL HAVE TO BE PROTECTED AT ALL TIMES. MUNICIPALITY BEARS NO T22 1290 1220 1680 1590 T25 900
RESPONSIBILITY TOWARDS ANY COLLAPSE OF SIDE WALLS OR ANY OTHER MISHAPS OCCURRING TO ANY PART MIX NUMBER 1 2 3 4 T25 1460 1390 1905 1810 T28 1000
WHATSOEVER. GRADE 20/20 62/50 62/50 85/68
T28 1640 1560 2135 2030 T32 1150
MIN. CEMENTITIOUS CONTENT kg/m 200 380 380 380
Filename: \\AEAUH1NTAP1\PROJECT\003 PROJECT RECORDS\60345201.00_D1-D2TOWERS\8 PRODUCTION\8.5 ST\CAD\GENERAL\SHEET\60345201-G-ACM-DG-ST-0003-00.DWG
1.20 CONCRETE SHALL BE CURED BY AN APPROVED MEANS IN ACCORDANCE WITH THE SPECIFICATIONS. T32 1875 1780 2440 2315 CONSULTANT
CEMENT TYPE OPC OPC OPC OPC
1.21 UNLESS CAMBERS ARE SHOWN ON THE DRAWINGS OR THE ENGINEER DIRECTS OTHERWISE PROVIDE THE FOLLOWING
STANDARD CAMBER: MAX. FREE w/c RATIO 0.55 0.40 0.40 0.40
FINAL REQUIREMENT. CONCRETE MOVEMENT DUE TO SHRINKAGE EFFECT NEED TO BE CALCULATED AND DETECTED
FROM THE PROVIDED JOINT WIDTH TO CONCLUDE A NET JOINT WIDTH AT THE FINAL STAGE (EXPANSION JOINT FIXING 5.5 CLEAR COVER TO REINFORCEMENT INCLUDING LINKS, STIRRUPS, AND TIES SHALL BE AS FOLLOWS:-
600 COULOMBS PASSING AT 28 DAYS IN RCP (RAPID CHLORIDE PERMEABILITY TESTING) WITH 50% OR 65 % SHEET TITLE
TIME) EQUAL TO WHAT PROVIDED ON THE DRAWINGS. a) STRUCTURE IN CONTACT WITH GROUND (BASEMENT)
PILE CAPS/RAFT UNDER TOWERS = 100mm Bottom, 75mm Sides & 50mm Top
Project Managment Initials (As Required)
2.0 DESIGN MEASURES FOR CONTROL OF TEMPERATURE OF CONCRETE ARE TO BE CARRIED OUT. BASEMENT RAFT SLAB = 75mm Bottom & 50mm Top GENERAL NOTES - (SHEET 1 of 2)
CORROSION INHIBITOR TO BE ADDED TO CONCRETE MIX IN THE BASEMENT. WALL AND COLUMN = 50mm
2.1 CONSULTANT DESIGN GROUND BEAM = 50mm
CONCRETE TO SUIT CLASS 2 SULPHATE CONDITION CATEGORIZED BY BS 5628 PART 1 1997 TABLE 7A,B AND C SLAB AT GRADE LEVEL = 50mm
DESIGN AND CONSTRUCTION OF REINFORCED CONCRETE STRUCTURAL MEMBERS, SHALL BE IN ACCORDANCE
Last Plotted date: 2017-09-03
Last Modified by: DELARAH
WITH ACI318M-08 AND THE STRUCTURAL STEEL MEMBERS TO BS 5950 b) SUPER STRUCTURE
ADEQUATE COVER SHALL BE PROVIDED AS INDICATED IN THE DRAWINGS (SEE NOTE 5.5) COLUMNS (INTERNAL) = 40mm
2.2 CONTRACTOR DESIGN CONCRETE CRACK WIDTH TO BE LIMITED AS INDICATED IN THE DRAWINGS (SEE NOTE 7.0) COLUMNS (EXTERNAL) = 40mm
BEAMS (INTERNAL) = 40mm SHEET NUMBER
THE CONTRACTOR IS RESPONSIBLE FOR THE DESIGN OF ALL TEMPORARY WORKS (SHORING FOR EXCAVATION, OTHER REQUIREMENTS TO ENSURE A DURABLE CONCRETE INCLUDE THE FOLLOWING (GENERALLY): BEAMS (EXTERNAL) = 40mm
DEWATERING, SIGNAGE... ETC) AND THE FOLLOWING ITEMS OF PERMANENT SLABS (INTERNAL) = 30mm
SECONDARY WORKS: (SUBJECT TO ENGINEER'S REVIEW AND APPROVAL) MAXIMUM CHLORIDE ION PERMEABILITY - 1300 COULOMBS AT 28 DAYS. 60345201-G-ACM-DG-ST-0003-00
SLABS (EXTERNAL) = 30mm
1. SWIMMING POOL DETAILS MAXIMUM WATER ABSORPTION - AS PER BS 1881 SHALL BE 1.5% WALLS (INTERNAL) = 40mm
Designer:
D1 D2 Forte Tower, Dubai, UAE Zebian Aluminium & Glass Industries LLC Page 221 of 221