Académique Documents
Professionnel Documents
Culture Documents
The Team
2016/MBA/WE/13 Danushanth, SY
Executive Summary
ABC is a global product specialist that develops, manufactures and markets high-quality
gaskets for plate heat exchangers. The factory is located at Boralesgamuwa. ABC consists of
two energy intensive plants which manufacture two products namely; Rubber Compound and
Gaskets for Plate Heat Exchangers.
Presses, Ovens and Extruders consume 20%, 18% and 15% of the total electricity
consumption at ABC respectively.
Specific Energy Consumption (SEC) for gasket production is 47 MJ/kg and the base load is
1,468 GJ. SEC for rubber compound production is 0.164 kWh/ kg (0.590 MJ/ kg) and the
base load is 49,051 kWh (177 GJ).
Contents
Executive Summary ...................................................................................................................ii
1 Introduction ........................................................................................................................ 1
2 Methodology....................................................................................................................... 2
Collected data are analyzed in the following Sections of the report. ..................................... 3
4 Energy-Production Correlation......................................................................................... 10
6 Lighting ............................................................................................................................ 13
7 Recommendations ............................................................................................................ 14
7.2.1 Option 01: Modify Electric Ovens into Steam Power ....................................... 15
7.2.2 Option 02: Modify Electric Ovens by Adding Soft Starters .............................. 15
7.4 Carry out Leak Surveys regularly and Fix Leaks of Compressed Air Lines ............ 16
7.6 Replace High Bay Lamps with more Energy Efficient Types .................................. 17
7.8.2 Install a Power Meter for the Ovens Section and maintain the maximum
demand by shifting the starting times of ovens ................................................................ 19
References ................................................................................................................................ 22
List of Tables
List of Figures
Figure 1: Electrical Distribution ................................................................................................ 4
Figure 2: Installed Capacities Distribution ................................................................................ 6
Figure 3: Energy Balance for Transformer 01 and Transformer 02 .......................................... 8
Figure 4: Electrical Energy Balance .......................................................................................... 9
Figure 5: Energy- Production Correlation for Gasket Production ........................................... 10
Figure 6: Energy- Production Correlation for Rubber Compound Production........................ 11
Figure 7: Single Layer Operation while Steam supplied to all three Layers ........................... 14
Figure 8: Using a Soft Starter .................................................................................................. 15
Figure 9: Compressed Air Leakages ........................................................................................ 16
Figure 10: Unnecessary Lighting ............................................................................................. 18
Figure 11: Industrial Fans Turned On Unnecessarily During Breaks...................................... 19
Figure 12: An Un-insulated Steam Header and a Steam Leak ................................................ 20
Figure 13: Load Profile of Transformer 01.............................................................................. 23
Figure 14: Load Profile of Oven No. 2 .................................................................................... 23
Figure 15: Voltage Imbalance of Transformer 01 ................................................................... 24
Figure 16: Current Imbalance of Transformer 01 .................................................................... 24
Page |1
1 Introduction
Energy is one of our most pressing environmental concerns. While demand for energy is
growing rapidly, its conventional source – fossil fuels – is declining in availability and
discouraged due to adverse environmental consequences. Therefore, Renewable Energy is
sought for from the supply side whereas Energy Efficiency is encouraged from the demand
side (IEA, 2018). As far as environment is concerned, the greenest unit of energy is the one
saved rather than the one used no matter how cleaner it is generated; hence the importance of
demand side energy efficiency is emphasized. According to Roy (2018), if 1 USD is needed
for a particular supply side intervention, less than 0.5 USD is needed for an equivalent
demand side intervention.
In Sri Lanka, Industries account for 30% of electricity sales of the Utility (CEB, 2017).
Therefore, industries have a major role to play in Energy Efficiency. This study intends to
conduct an Energy Audit in a selected factory belonging to an energy intensive industry, as a
case study to identify energy efficiency measures which can be implemented to reduce its
energy consumption.
ABC is a rubber products manufacturer under the ABC brand located at Boralesgamuwa.
ABC operates around the clock except one shift from 10.00 pm on Sundays to 6.00 am on
Mondays. ABC consists of two energy intensive plants that manufacture two products
namely; Rubber Compound and Gaskets (for Plate Heat Exchanger). Rubber Compound is
manufactured in the Mixing Plant which incorporates a DC motor drive and a dump mill. Part
of the output of the Mixing Plant is used in the Gasket Production Plant where the compound
is processed by extrusion, compression molding and post curing. The rest of the Mixing Plant
output is dispatched to another factory in Horana. This Energy Audit was carried out from
19th to 23rd November, 2018.
1.1 Objectives
Analyze the present energy consumption of the factory to establish its Energy Balance
Analyze correlation between Energy and Production to establish Specific Energy
Consumption (SEC)
Identify Energy Losses and provide recommendations for improving Energy Efficiency
Page |2
2 Methodology
The energy audit for ABC factory was completed within one week as follows.
2.1 Time Duration
19 to 23rd November, 2018
th
November DENT ELITEpro SPTM Power Meter Logged data at the common sub panel of
20 Kyoritsu Power Meter Nitrogen Plant, Ovens and Boiler
Logged data at Nitrogen Plant
November DENT ELITEpro SPTM Power Meter Logged data at pumps, induced and
22 Kyoritsu Power Meter forced draft fans of boiler, Oven 15,
Chiller and CNC 5
November DENT ELITEpro SPTM Power Meter Retrieved data
23 Kyoritsu Power Meter Measured pressures of press water lines
Collected installed capacities
Collected historical energy data
3 Electricity Consumption
This chapter analyses the electricity consumption at ABC.
Utility electrical power is supplied through four transformers as shown in Figure 1. Supplies
through transformers 1, 2 and 4 are delivered and metered at 400/230 Volt nominal whereas
the supply through transformer 3 is delivered and metered at 33,000 Volt nominal.
Transformer 1 supplies solely Gasket Production Plant which includes Extruder Section,
Presser Section, Air Compressor, Finished Goods Stores and Factory Services. Transformer 2
feeds the Dump Mill, Chiller, Post Curing Section (Ovens and Nitrogen Generators),
auxiliary equipment of the firewood boiler and offices. Transformer 3 is dedicated to the DC
motor drive of the Mixing Plant and Transformer 4 supplies the Tool Shop. A stand by
generator of 1,860 kVA is used as a backup to the Utility power supply.
Standby
Generator
(1,860 kVA)
kVA)
Mixing Gasket
Note: Consumption under Transformer 4 is not considered in the analysis due to its less
significance compared to the other three transformers.
Page |5
Presses 1,377.400
Ovens 985.900
AC 101.970
Lights 98.821
Compressors 93.000
Pumps 65.700
Fans 36.040
Total 4,497.813
Page |6
Figure 13 in Annex 01 shows the load profile of the gasket production plant supplied through
Transformer 01 from 12.00 noon of November 19, 2018 to 12.00 noon of November 20,
2018. A summary of electrical parameters is provided in Table 3.
The recorded power factor above implies that the capacitor bank installed at the Gasket
Production Plant performs the reactive power compensation function properly. Therefore,
there is no further room for demand reduction by improving the power factor.
Load profiles of supplies through Transformers 2 and 3 could not be recorded because, main
circuit breaker of Transformer 2 was not accessible and Transformer 3 is a high tension
supply.
The loads in a three phase system should be evenly distributed among the three phases to
maintain the voltages and currents balanced (sinusoidal and equal in magnitude with
individual phases 1200 apart). Unbalanced voltages can result in adverse effects on equipment
and power system, which is intensified by the fact that a small unbalance in the phase
voltages can cause a disproportionately larger unbalance in the phase currents. Under
unbalanced conditions, the power system will incur more losses and heating effects and be
less stable because when the phases are balanced, the system is in a better position to respond
to emergency load transfers. The allowable limit of load imbalance at a facility is 1% and
10% for voltage and current respectively (Jouanne, 2001).
Figure 15 and Figure 16 in Annex 2 show the variation of voltage imbalance and current
imbalance of the supply through Transformer 01 respectively during the same period of the
load profile in Figure 13. Accordingly, both voltage and current imbalances are within
accepted limits.
Monthly energy balance was estimated based on real time measurements, check meter data
and assumptions to generalize the operating times. Therefore note that these figures are
approximate and may have slight variations depending on the actual operation.
Page |8
Figure 3 shows the energy balance of electricity supplies through Transformer 01 and
Transformer 02. Note that lighting and ventilating loads are not quantified separately because
they are supplied together with the production machinery and negligible compared to the
quantified loads.
Table 4 and Figure 4show the monthly electrical energy balance of the total facility.
resses
20%
4 Energy-Production Correlation
Based on electricity bills and check meter readings, the Engineering Department of ABC
estimates its monthly energy consumption for each product. Such historical records were
available for a period of five years. Nevertheless, those data have not been analyzed to derive
meaningful information in order to use energy more efficiently and effectively.
Therefore, based on those historical data, a regression analysis is carried out to find out the
energy-production correlation by establishing the Base Load and the Process Load. Base load
is the energy incurred due to components like offices which are independent of production.
Process load or Specific Energy Consumption (SEC) is the amount of energy required per
unit product.
Accordingly the SEC for gasket production is 47 MJ/kg and the base load is 1,468 GJ. Base
load is 25% of the average monthly energy consumption for gasket production (5,983 GJ
according to historical data).
Figure 6 shows the energy-production regression analysis for Rubber Compound Production.
P a g e | 11
Unlike for gasket production, energy and production data distribution for rubber compound
shows a relatively high inconsistency. Data for the most recent twelve months available
shows a satisfactory consistency with respect to other periods. Therefore, only those twelve
months is considered for the regression analysis. Accordingly, the SEC for rubber compound
production is 0.164 kWh/ kg (0.590 MJ/ kg) and the base load is 49,051 kWh (177 GJ). This
implies that as an average 44% of the energy consumption (monthly average is 112,415 kWh)
contributes to the base load which can be the cause of inconsistency of energy-production
data distribution.
These established SEC values can be used as baselines to evaluate the performance of energy
efficiency measures implemented at ABC in the future, including those recommended further
in this report.
P a g e | 12
5 Thermal Comfort
Thermal comfort is the condition of mind that expresses satisfaction with the thermal
environment. This is an important goal of ventilating and air conditioning. Many factors
affect thermal comfort among which air temperature and relative humidity are prominent.
6 Lighting
Present artificial lighting installations of ABC are summarized in Table 6.
Illuminance (Lux)
Location
Measured Acceptable
Plant Area
Inspection Area 1 589 1,000
Gasket Manufacturing 432 500
Testing Laboratory 165 300
Dump Mill Area 146 150
Extruder Area 200 500
Mixer Area 81 150
Office and General Area
Corridor 130 100
Factory office 60 300
R&D Mixing 315 300
Lunch Room 144 150
Wash Room 38 100
In areas where the measured illuminance levels are less than that of acceptable, it is
encouraged to maintain these lower values assuming that they are acceptable to the
occupants.
P a g e | 14
7 Recommendations
Based on the above analysis and observations made during the audit, this section provides
recommendations for improving energy efficiency at ABC. Quantification of savings, their
investment requirements, and financial feasibility lie beyond the scope of this Project. Those
can be determined for each recommendation on a case by case basis upon the interest of
implementation by the management of ABC, subsequent to the perusal of recommendations
which follows.
These thermal losses may be reduced up to 50% by reducing the Press outer surface average
temperature from 900C to around 600C. This can be easily achieved with an extra insulation
layer for both top and bottom plates. 25mm wood layer with currently available asbestos
sheet is suitable for insulation within the working temperature range. It is advisable to check
the feasibility of wood strength according to the working pressure of the beds.
Most of the Presses have two layers of mold with three layers of heating plates. During the
audit it was observed that a considerable number of Presses of this model worked with single
mold while steam is supplied to all three layers as illustrated in Figure 7.
Figure 7: Single Layer Operation while Steam supplied to all three Layers
P a g e | 15
By inserting a temporary insulation layer in between the unused molds and closing the third
steam line thermal losses can be further minimized. These can be implemented after
considering additional cost for the insulation material (wood) and maintenance cost.
However, soft starters take considerable time to raise the temperature up to set value.
Therefore, attention should be paid of processing time variation with soft starter.
Except for the two water circulation pumps of the Extruders, all the other pumps are centric
branded pumps used for cooling system of Presses. According to random spot measurements,
actual operating pressure of the cooling system is less than 1bar or 30 water feet. But the
rated best efficiency point pressure for these water pumps is 60 water feet. This implies that
the existing pumps are largely oversized for the requirement causing them to run at a lower
efficiency. Therefore, it is recommended to replace these with new pumps of rated pressure
of 30 water feet through Variable Speed Drive (VSD).
7.4 Carry out Leak Surveys regularly and Fix Leaks of Compressed Air Lines
A lot of compressed air leakages were observed during the audit as shown in Figure 9.
If there are no leaks, in principle, the compressor will not start again. But in practice, the
compressor will start again after a few minutes because air leaks cause the pressure to
drop to the cut-in pressure. Record the duration between stop and start (Toff)
Record the duration of on-off cycles (Ton and Toff) by allowing a number of such cycles to
repeat
Table 8 shows the measurements and results of the leak test.
Rectification of these leaks will lead to approximately 20% of energy saving of the
compressor. Compressed air line accessories must be maintained properly to reduce this leak.
Special attention must be paid on flexible hoses used in this system.
7.6 Replace High Bay Lamps with more Energy Efficient Types
250 W High Bay Lamps can be replaced by either CFL or LED of around 100 W.
Further, temperature of an already air conditioned area will not drastically increase due to the
lack of cooling effect for half an hour in the evening. Therefore it is recommended to turn off
all Split AC units half an hour before leaving the offices.
7.8.2 Install a Power Meter for the Ovens Section and maintain the maximum demand
by shifting the starting times of ovens
As discussed in Section 7.2, Ovens contribute to a substantial amount of the maximum
demand of the electricity supply through Transformer 02 due to the high inrush at the outset
of each batch. Therefore, if a power meter capable of displaying the power demand (kVA)
can be installed to the Oven Section, a significant demand reduction can be achieved by
scheduling the batches so that the starting inrush of ovens will not overlap.
P a g e | 20
ABC has already focused on Energy Management at the top management level and taken a
lot of initiatives in that regard. Given below are some simple suggestions to transcend it to
the operational level.
Form an operational team for energy management with defined targets
P a g e | 21
Extend Kaizen to improve energy efficiency from ideas of employees at the operational
level and reward them upon successful implementation
Display awareness boards
o Switch off fans/ bulbs
o Close unused steam lines
o Close cooling water line when not running
o National importance of energy saving and national energy news
o Display energy consumption and power demand on each energy intensive
equipment
Train the staff on energy efficiency measures and encourage to practice them frequently
(ex: compressor leak test)
The ultimate goal should be to get certified under the ISO 50001 Energy Management
System Standard.
P a g e | 22
References