REF DISCIPLINE ACTIVITY LOCATION
REQ.
Arch First fix for supports for gypsum board New Dish washer area --
Arch Final fix for gypsum board New Dish washer area --
Civil Insulation + test for the floors New Dish washer area --
Arch Gypsum board partition around the pipes New Dish washer area --
Genaral Preparing the dishwasher new area to start work New Dish washer area
Daily & Weekly Reporting Procedure TMG Projects Page 1 of 1 Document No: PEG-1134-PP-18-03-FM Rev 0
Revision Date: Dec 2018