Académique Documents
Professionnel Documents
Culture Documents
Instruction: Project shall keep this filled check list for Record & Verification (Not to be sent to Engineering
dept.)
ASP Team Leader / ASP QA person is responsible to fill up this check list & submit back to Project.
Site Details Site No. LWDWL01.Site Name. WADWALI . Circle .MH&G . Customer.
…AURANGABAD……… ASP Details ASP Name. Aerial .Team Leader / Supervisor Name. Sushil
Kumar . Equpt. Details RBS Type. ..Site Type –GBT Other Status - New Site / Expansion / Swap/ Other
1 EARTHING
1.1 Incoming Earthing and lightning system
Critical OK
1.1.1 Indoor & Outdoor ECB installation & connection to G.I. Strip / main
earth terminal, continuity checked till earth pits
OK
1.1.2 Major
Earth cable size 16 mm² Cu Min / 50 mm² G.I. for ECB to main earth /
MET.
1.1.3 OK
Connection at all ECB & G.I. strip properly tightened. All ECBs are Major
interconnected.
1.4.2 Conductor passed through C clamp and insulation cap at other end. Major OK
C-clamp is not loose.
1.4.3 Cable lugs of earthing cables are crimped, connected properly (indoor Critical OK
& outdoor). Right size lugs used with no insulation tape.
Other Point
1.6
Any Other Point
2 CABINET INSTALLATION
Assembly and alignment of cabinet, levelling is done correctly. No NA
2.1 scratches / dirt on cabinet Major
2.2.1 Base frame grouted to floor. Cabinet fastened to base frame (Front &
Back) & clamped to wall / ladder correctly. Bolts tightened. Major NA
2.2.2
Minimum gap between indoor cabinet and wall >5 cm
Major NA
2.2.3
Outdoor RBS – Installation frame, Mounting base / base frame is
levelled & fixed to foundation. Grouting done. Distance washer Major NA
used at foundation & installation frame.
2.3 Radio cabinet jumper connection and Labels
2.3.2 Jumper bending is > Min. radius / Bend not close to connector. Major OK
2.3.3 Labelling is done. Laid neatly & fastened with plastic ties (indoor). Minor OK
3 EQUIPMENT IN CABINETS
3.1 Door filter (indoor Cabinet) - Available, installed correctly & Clean Major OK
OK
3.5 Fan units are operational Major
3.6 AC Mains Connection & Setting ( Outdoor Cabinet)
3.6.1 AC mains connections are correct & tight Major OK
3.6.2 Correct setting / strapping done for 1- phase / 3- phase connection OK
Major
OK
4.3 Extra length of cables stored in cable chute kept at ladder Minor
4.4 Signal & Power/ earth cable separation at DF Cable chute / Tx cabinet Major OK
OK
4.5 Alarm cable shield connected to clamp in DF Major
5 CABLING
OK
5.1 Separation between power(AC, DC & Earthing Cables) and signal Major
cables(PCM,ALARM etc.) maintained on ladder, cable tray, & cabinet
5.4 Assembly of cable ladder and trays –no sharp edges, proper joints, Major OK
wall support and pendulums at correct place.
NA
6.9 DC cables connected to correct fuses / MCBs in SMPS / BBS Major
7.1 Module Installation – TX rack, AMM, Fan unit, DDU, DF, IF cable Major
adopter installed at correct position with proper screws / fasteners.
7.2 Fan unit installed with Air-plates at AMM correctly & earthing Major
terminated. Temp at MMU is < 45 °C
7.3 Earthing of Modules done correctly & all modules earthing cable Critical
connected to ECB individually & termination is tight.
Major
Neat cable routing, labelling is correct and connectors tightened
7.4 Cabling – All cables in Tx are laid & routed correctly. Excess length is Minor
kept in proper roll / winded up. All cables & AMM modules labelled.
8 ANTENNA FEEDERS
8.2 Feeders running and laying on cable ladder is ( straight & correct Major
OK
No stress on feeders & neatly laid
Major
NA
8.4 Space between feeder clamps in tower 0.9 mtr max. for 7/8 feeder. Major
8.5 Feeder and antenna / TMA jumper markings done correctly near Major NA
connectors at both ends
8.6 Feeder – jumper connectors & Sealing
8.6.1 Connectors are made as per instructions & tightened. Major
8.6.2 Sealing of connectors done correctly with self-fusing tape & PVC tape Major NA
8.6.3 Self-fusing tape is not protruding from the PVC tape sealing Major
8.7 Earthing kit on feeders outdoor
8.7.1 Correct earthing kit used & Installed correctly before the bend (600
Major NA
mm from feeder bend) at tower & before cable inlet
8.7.2 Earthing kits are earthed at tower & roxtec ECB & connection
Major NA
tightened. No more than 2 earthing terminated at single point
8.7.3 Additional earthing kit installed at every 30 mtr, if antenna height is 40
Major NA
mtr / all the earthing kits installed at specified location as per IE doc.
NA
8.7.4 Earthing kits are sealed & no chances of water entry
Critical
8.11 Drip loop on feeders entry is correct & no chances of water entering Major
along the feeders.
8.12 VSWR Reading (ASP to fill the measured data & provide Cell A: Cell B: Cell C:
printout)
1.29 1.09 1.09
9 ANTENNAS
OK
9.1 Antenna mounts / support are fitted correctly & tightened. Major
NA
Antenna clamps / fittings are fixed correctly. Lock nuts of antenna
9.2 clamps are tightened. Major
9.4 Antenna Height as per IE / RF data document – ASP to provide data & to be verified
in L2 Audit
RTT Site : Buiding height = G + N (No of floor) = 4 + 3XN Mtr
Tower Foundation Ht. = As per measurement OK No of Floor : ………….. Buid.
Ant. Ht = 1-Tower section height X No of section, where ant. Height:………………….mtr
Installed – Height of Section top to Ant. Center point
Tower Foundatio Height
GBT : Tower Foundation Ht. = As per measurement :………………….. mtr
Ant. Ht = 1-Tower section height X No of section, where ant.
Installed – Height of Section top to Ant. Center point
No. of Tower Section (where Ant.
Installed) :……………..
9.5 Antenna direction and tilt angles as per IE Document. Antenna Major NA
mounts are exactly vertical.
9.7 TMA, ASC / RET are installed correctly & clamped to tower. Earthing Critical OK
is done & Jumper laid & connected correctly with connector sealing.
10.3 All connectors tightened and sealed correctly. AGC screw caped Major _
10.4 Radio Cables labelled correctly at both ends. Label is weatherproof. Major _
10.5 Radio link cable running and laying on cable ladder – straight Major _
10.6 Radio link cable fixing and clamping using proper clamp. No plastic Major
ties used. _
12 INSTALLATION ENGINEERING
OK
12.1 Installation documentation (IE-module available) Major
NA
12.2 Location, Floor, Antenna, Ladder, cabling, Earthing drawing available Major
NA
12.3 Future expansion is feasible ( No. of RBS cabinets can be added)
Remarks :