Devendra Pakhare
Production (operations)
Pluga Pumps & Motors (P) Ltd.
Manjusar GIDC,Dist. Vadodara, INDIA
Cell : +91 8850676781
Scope of work
Design, develop, install & commissioning of coil forming machine, as per Pluga FE Line specifications
The machine will produce winding coils 133/ shift in 8 hour shift. The supplier is responsible to ensure
required output levels with optimum resources.
Lead Time: Approved machine at vendor end from Pluga FE technical team must be despatched from
Supplier premises within 60 days of ordering
Packing & Forwarding: Full machine to be packed properly and despatch from supplier end with robust
packaging. Supplier is responsible for any transit damage. Transit insurance to be done by Pluga FE. Supplier
to inform before dispatch
GUARANTEE OF QUALITY
The Seller guarantees that the commodity here of is made of the best materials with first class
workmanship, brand new and unused, and complies in all respects with the quality and
specification stipulated in this Contract. The Guarantee period shall be 12 months Operations from
the date on which the final acceptance protocol is signed by representatives of both parties at Pluga
FE
Payment Terms:
10 % advance (BG to be provided?), 20% after design approval, 50% after successful testing at
supplier’s end, balance to be paid within one month of successful commissioning.
Design review will be done in detail. Supplier to provide drawings to Pluga FE and visit for detail
design review (complete layout, station arrangement, trolley design, material handling, tackles,
fixtures etc.). Once the approval is done then only manufacturing will start
Acceptance Criteria
1. Look / Aesthetics of line must be world class – welding , painting, machining and other
mechanical work and processes must have very good finish and of required material
properties . All fixtures must be black iodized with excellent surface finish
2. All ranges should in the scope must be qualified in the system – Changeover less than one
minute from part to part
3. All fixtures and job contact areas shouldn’t damage and scratch paint / parts of Pumps
4. Any deviation from approved design need to be approved from technical team
5. Electrical , hydraulic , pneumatic & water lines are routed neatly to ensure safe operation
6. Cycle time shouldn’t’ exceed against our requirement of capacity mentioned above
7. Offset setting should be easily changeable
8. V4 to v6 changeover setting should be with ease and minimum changeover time
RFQ Coil Forming Machine 21/03/2018
Winding wire is poly wrap Coil total length fig. 1 with range is from 180 mm to 600 mm
Coil will be made for single phase and three phase
Also this machine should be capable for copper enamel and PVC wire. This is for gaining flexibility
while higher demand Variation
Process
Set coil forming machine (ferma) as per require model. (Set length with winding wire) . Also set coil
turn on counter as per model.
Check winding wire diameter with micrometre and start coil forming with help of machine.
After completion of require turn stop machine, cut end wire and insert sleeve ( as per colour code )
and tie coil with help of wire .
Remove ferma and unload coil from ferma and put it on rack.
In case of auto machine (three wire) ensure that three spool are available set Ferma, check machine
speed, close door properly and then start machine . (Before starting machine check program of coil
Model with actual requirement.
Service support