Académique Documents
Professionnel Documents
Culture Documents
IV. Installation
a. Prior to installing plasterboard, a building should be thoroughly checked to ensure that the framing is plumb,
level and square other trades have finished their ‘rough-ins’.
b. The spacing of studs, joists or battens takes into account the spacing required by the linings given in the
Frame Spacing table. When the installation is completed, the plasterboard will comply with the required
level of finish.
c. Prior to installing plasterboard, a building should be thoroughly checked to ensure that the framing is plumb,
level and square other trades have finished their ‘rough-ins’.
d. The spacing of studs, joists or battens takes into account the spacing required by the linings given in the
Frame Spacing table. When the installation is completed, the plasterboard will comply with the required
level of finish.
e. Before fixing plasterboard to steel framing, check that the framing has been assembled and erected in
accordance with manufacturer’s instructions. All contact surfaces of the steel frame are dry, clean and free
from foreign materials such as oil, grease and dirt.
f. Steel furring channels are fixed at right angles to the underside of joists by means of clips or fasteners.
Anchor clips are used to fix steel furring to a concrete slab ceiling. Furring channels should be spaced
according to the sheet thickness given in the Frame Spacing.
g. Carefully plan the installation. Sheets should be set out to ensure best coverage and to minimize butt joints
and waste. Provide control joints in walls and ceilings at: – maximum 12m intervals in both directions – at
every change of material – over control joints in the substrate – at every change of substrate material.
Site Construction Methodology
Gypsum Board Installation to Ceiling
h. Plasterboard should be fixed to the substrate using one of the following systems: Combination adhesive and
fastener. Screw fixed only. Nail fixed only.
i. A variety of trims exist for finishing corners, edges and joints of plasterboard to create neat sharp lines,
minimize cracking and to offer a higher level of impact resistance. Trims may be fixed with nails, staples or
with cornice adhesive and then stopped and finished with the normal 3-coat system.
V. Supervision
Installation is carried out by the skilled and experienced installer who has expertise in board installation finishing.
They are assisted by unskilled laborers. Their work is in turn supervised by experienced Foremen. Site Engineer/
Architects will be available for co-ordination with other sub-contractors and Main Contractor and also to look
into the technical aspects.
a. Steel Framing, Wall angles, C-Channel, Carrying Rod, Connecting Clip, Blind Rivets to connect steel to steel
furring.
b. Black screw to connect gypsum board and steel framing.
c. Shadow Line by KUS, as the termination between wall and ceiling.
d. Gypsum Putty and Wire mesh tape for the control joint in each and every board laid.
Site Construction Methodology
Gypsum Board Installation to Ceiling
IX. General
a. The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site conditions.
Source: http://www.boral.com.au/brochures/ordering/PDF/04686_T_InstMan_Reprint_Oct09.pdf
Site Construction Methodology
Gypsum Board Installation to Wall (Drywall & Partitions)
IV. Installation
a. Prior to installing plasterboard, a building should be thoroughly checked to ensure that the framing is plumb,
level and square other trades have finished their ‘rough-ins’.
b. The spacing of studs, joists or battens takes into account the spacing required by the linings given in the
Frame Spacing table. When the installation is completed, the plasterboard will comply with the required
level of finish.
c. Prior to installing plasterboard, a building should be thoroughly checked to ensure that the framing is plumb,
level and square other trades have finished their ‘rough-ins’.
d. The spacing of studs, joists or battens takes into account the spacing required by the linings given in the
Frame Spacing table. When the installation is completed, the plasterboard will comply with the required
level of finish.
e. Before fixing plasterboard to steel framing, check that the framing has been assembled and erected in
accordance with manufacturer’s instructions. All contact surfaces of the steel frame are dry, clean and free
from foreign materials such as oil, grease and dirt.
f. Steel furring channels are fixed at right angles to the underside of joists by means of clips or fasteners.
Anchor clips are used to fix steel furring to a concrete slab ceiling. Furring channels should be spaced
according to the sheet thickness given in the Frame Spacing.
Carefully plan the installation. Sheets should be set out to ensure best coverage and to minimize butt joints
and waste. Plasterboard is generally applied horizontally in residential construction and is necessary if a
Level of Finish of 3, 4, or 5 is required. However, sheeting may be fixed vertically if it is to cover the whole
wall.
Site Construction Methodology
Gypsum Board Installation to Wall (Drywall & Partitions)
g. Provide control joints in walls and ceilings at: – maximum 12m intervals in both directions – at every change
of material – over control joints in the substrate – at every change of substrate material.
h. Plasterboard should be fixed to the substrate using one of the following systems: Combination adhesive and
fastener. Screw fixed only. Nail fixed only.
i. A variety of trims exist for finishing corners, edges and joints of plasterboard to create neat sharp lines,
minimize cracking and to offer a higher level of impact resistance. Trims may be fixed with nails, staples or
with cornice adhesive and then stopped and finished with the normal 3-coat system. A shadow line effect is
required such as: – plasterboard and masonry wall junctions – ceiling and wall junctions – door and window
jambs.
V. Supervision
Installation is carried out by the experienced and competent installer who has expertise in board installation.
They are assisted by unskilled laborers. Their work is in turn supervised by experienced Foremen. Site Engineer/
Architects will be available for co-ordination with other sub-contractors and Main Contractor and also to look
into the technical aspects.
VI. Machinery and Tools to be Used
a. Wall studs, Connecting Clip, Blind Rivets to connect steel to steel furring.
b. Black screw to connect gypsum board and steel framing.
c. Shadow Line, Corner bead, casing bead by KUS, as the termination between wall and ceiling.
d. Gypsum Putty and Wire mesh tape for the control joint in each and every board laid.
d. Screw Gun. (Makita or any other similar brand)
e. Iron Scissor Cutter for furring
f. Tool box containing spirit level, measuring tape, water level, right angle, plump. Etc.
Site Construction Methodology
Gypsum Board Installation to Wall (Drywall & Partitions)
VIII. General
b. The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site condition.
Source: http://www.boral.com.au/brochures/ordering/PDF/04686_T_InstMan_Reprint_Oct09.pdf
Source: https://www.bca.gov.sg/Professionals/IQUAS/..%5CIquas%5Cgpgs%5CCTiling%5CCChpt3.pdf
V. Grouting
a. Grouting Joints, using grouts manufactured with Portland cement.
b. Allow Tile Time to Dry. Be sure the tile adhesive has had ample time to dry before you begin grouting to
avoid problems.
c. Grout preparation. Carefully read and follow all instructions and precautions on the grout package. When
mixing your grout compound, it’s important to take into consideration timing, since grout will harden in the
mix bucket. Start making your mixture wet to dry, meaning dry grout mixture in your mixing bucket, and wet
agent in another appropriate receptacle. For un or non-sanded grout, gradually mix the two together until
you get a mixture about strong enough to sustain a trowel upright. For sanded grout, look for a mixture
about the consistency of cookie dough. Note that when selecting grout, style is not the only factor.
Actual Installation
IV. Installation
a. All stone will be clad to the structure of the building with metallic fasteners – ‘Z’ type angles described
separately with all necessary components to support the cladding in place, to the lines and dimensions set
by plumb and as shown in drawings.
b. Markings will be made on the wall by setting plumb to determine the exact locations.
c. Stone slabs will be segregated and arranged in the open space near cladding point to select stones of
matching sizes and veins.
d. Protective coating will be applied behind the stone as a damp proof.
e. Stone anchors shall be securely drilled in the wall and located as shown in drawings and shall be set plumb
and in true place.
f. Surface level will be ensured to maintain right angle as well as the plumb
g. Clean cladding surfaces that have become dirty or stained prior to setting, to remove soil, stains and other
foreign materials.
a. Clean stone by thoroughly scrubbing exposed surfaces with fiber brushed, followed by a thorough
drenching with clear water.
b. Mild cleaning compounds that do not contain caustic materials, harsh filters or abrasives.
h. Stone cladding shall be carried out by masons skilled in the procedures required for the Project.
i. Powered cutting machines are employed to cut stones and the exposed edges straight.
j. Anchors/angles, fasteners and other accessories are positioned in the wall for maintaining proper alignment
in horizontal and vertical direction and fitted as required to secure stones slabs in place.
Site Construction Methodology
Stone Installation to Wall Cladding
V. Supervision
Installation is carried out by the experienced and competent masons who have expertise in dry fix process.
They are assisted by unskilled laborers. Their work is in turn supervised by experienced Foremen. Site Engineer will
be available for co-ordination with other sub-contractors and Main Contractor and also to look into the
technical aspects. He will ensure that the overall work conforms to the shop Drawing.
a. Angles/anchor to be used:
'Z Type Angle 40 x 70 x 40 x 4mm. The sizes and the type of angle may vary depending upon the
space between stone and the wall and other factors. The angles to be used will be of stainless grade
304
Accessories include bolts, nuts, shield, ext arm, pins and washers all of stainless steel grade 304
b. Glue to be used: Italian Solid Cream glue ‘Marmolit’ mixed with hardener
c. Protective Coating: Sikagard 700S siloxane based water repellent.
Site Construction Methodology
Stone Installation to Wall Cladding
a. All standard Health, Safety & Environment norms will be adhered to strictly.
b. All the workmen will wear overalls, safety shoes, goggles, hand gloves and helmets. Adequate lighting and
ventilation will be ensured during installation.
c. It will be ensured that machinery and tools used are safe and always in good condition. Where applicable
only calibrated tools will be used
d. Markings will be made on the wall by setting plumb to determine the exact locations
Site Construction Methodology
Stone Installation to Wall Cladding
IX. Maintenance
The stone cladding will be under 1-year maintenance period. Any installation deficiencies that are noticed in
stones already fixed are attended to within this period
X. General
The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site condition
Site Construction Methodology
Painting Procedure to Gypsum Board (Latex)
a. Shall be delivered in sealed containers that plainly show the designated name, specifications.
b. Ensure good ventilation/exhaustion at the workplace.
c. Prevent formation of aerosols
d. It is recommended that it be sealed for damp areas where condensation might occur due to temperature.
e. Surface Preparation: Check the nail holes, nicks or cuts that might have been affect the smoothness of the
surface. Using drywall compounds such as boral premium powder and putty and gauge tape for the joints.
Make sure that the compound mixture applied is smoothly rubbed by the sandpaper.
f. Applying first Coat: Using roller, move until the whole surface is fully painted then brush all the sides that the
roller cannot reach.
g. Check the imperfections of the surface that may be seen by eye, and retouch using the drywall
compounds. Then lightly sand completed surface. Dust off the surfaces.
h. Applying Second Coat of Paint: The final coat of paint. Take a brush and cut in. As you finish brushing one
surface wall at a time roll immediately. Move to the next surface wall and repeat procedure until all
surfaces are completed.
Source: http://www.painterclick.com/new_drywall_painting.htm
V. Supervision
Painting procedures is carried out by the skilled and experienced painters who have expertise in painting works.
They are assisted by unskilled laborers. Their work is in turn supervised by experienced Foremen.
Site Engineer will be available for co-ordination with other sub-contractors and Main Contractor and also to
look into the technical aspects. He will ensure that the overall work conforms to the shop Drawing.
a. All standard Health, Safety & Environment norms will be adhered to strictly.
b. All the workmen will wear overalls, safety shoes, goggles, hand gloves and helmets. Adequate lighting and
ventilation will be ensured during installation.
c. It will be ensured that machinery and tools used are safe and always in good condition. Where applicable
only calibrated tools will be used
d. Markings will be made on the wall by setting plumb to determine the exact locations
IX. Maintenance
Painting works and finishes can easily stained by other materials that might damp into it. But simple retouches
and brushes can cover the dent.
X. General
The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site conditions.
Site Construction Methodology
Painting Procedure to Concrete Wall (Latex)
a. Shall be delivered in sealed containers that plainly show the designated name, specifications.
b. Ensure good ventilation/exhaustion at the workplace.
c. Prevent formation of aerosols
d. It is recommended that it be sealed for damp areas where condensation might occur due to temperature.
Site Construction Methodology
Painting Procedure to Concrete Wall (Latex)
IV. Procedure
a. Verify the color of paint to be applied, specified by the designer. In which, select paint that is appropriate
for the location, for exterior it should be resistive to moisture & sun exposure. While for indoor/interior acrylic
paint is recommended.
b. Clean the concrete wall. For exterior projects, use a power washer to rid the wall of all dirt and dust. If your
project is indoors, scrub the wall with soapy water and a scrub brush instead of using a power washer.
c. Apply masonry neutralizer to remove the acid content of the masonry and to avoid peel-off of paint. Rough
sand surface to remove efflorescence salts.
d. Repair any cracks or blemishes in your wall with concrete patch/boral mixtures. Follow the directions to mix
up the concrete patch mixture. Fill holes and use a trowel to smooth the patch to match the surface of the
wall.
e. Check the wall for moisture. Paint applied to a wall that is not properly sealed will not adhere properly. Tape
the plastic sheeting to the wall. Attempt to get the sheeting as air-tight as possible. Check the plastic after
24 hours. If moisture appears within the plastic, you will need to seal the wall. If no moisture is present, the
wall is already sealed.
f. Seal the concrete wall. Roll on 1 coat of concrete sealer and allow it to dry overnight. Concrete sealer is
available at most hardware or home improvement stores.
Site Construction Methodology
Painting Procedure to Concrete Wall (Latex)
g. Apply 1 coat of concrete primer. You can use rollers or brushes to apply the paint. Ensure the primer is
applied evenly, whichever technique you use. Let it dry for 24 hours. If you can see the wall through the
primer, apply 1 more coat.
h. Paint your wall with concrete paint. Paint should be applied in at least 3 thin layers. The paint may be
sprayed on, rolled on or painted on with a brush. The paint should not be streaky or show brush strokes.
Allow to dry for 24 hours.
i. Roll on concrete paint sealer. Cover with 2 coats, allowing it to dry between coats. Paint sealer helps the
paint to adhere to the wall and last longer.
Source: http://www.wikihow.com/Paint-a-Concrete-Wall
V. Supervision
Painting procedures is carried out by the skilled and experienced painters who have expertise in painting works.
They are assisted by unskilled laborers. Their work is in turn supervised by experienced Foremen.
Site Engineer will be available for co-ordination with other sub-contractors and Main Contractor and also to
look into the technical aspects. He will ensure that the overall work conforms to the shop Drawing.
Painting works and finishes can easily stained by other materials that might damp into it. But simple retouches
and brushes can cover the dent.
X. General
The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site conditions.
Site Construction Methodology
Wood Varnish Finish Procedure
Color Swatches Method
Preparation Application
a. Shall be delivered in sealed containers that plainly show the designated name, specifications.
b. Ensure good ventilation/exhaustion at the workplace.
c. Prevent formation of aerosols
d. It is recommended that it be sealed for damp areas where condensation might occur due to temperature.
e. Varnish is a mixture of oils and natural resins.
g. Apply the first coat of thinned varnish and let it dry. Use a flat paintbrush or foam applicator to apply the
varnish to the wood. Use long, even strokes, and work along the wood grain. Let this first coat dry for 24
hours.
h. Sand the first coat and wipe it with a damp cloth. After applying the initial coat of thinned varnish, smooth it
out. Do this by buffing the surface of the varnished wood with 280-grit sandpaper and then using a dry cloth
to wipe away any dust of debris
Make sure to wipe down the work space with a damp cloth to get rid of any dust caused by the
sanding
Make sure that the brush is clean with paint thinner (if using an oil-based varnish) or water (if using a
water-based varnish).
i. Apply the next coat of varnish and allow it to dry. Using a clean brush or a new foam applicator, apply the
varnish to the wooden piece. Once again, make sure that brushing along the wood grain. It doesn’t have
to thin this layer. Wait 24 hours for this layer to dry.
If using a spray on varnish, you can spray on another coat. Make sure to keep the can 6 to 8 inches
away from the surface, and spray on a single, light coat. Spray the varnish on too thickly, it may end
up with puddles, drips, and runs.
Let the varnish dry 24 hours before applying the next coat, and remember to clean the work space of any
dust or dirt caused by the sanding.
k. Continue applying more varnish and sanding between coats. Apply 2 to 3 more coats of varnish. Remember
to let the varnish dry between coats, and to sand and wipe the varnish clean before applying more varnish.
Always work along the grain when applying and sanding the varnish.
For optimal results, consider waiting 48 hours before applying the final coat.
l. Wait for the varnish to finish curing. Varnish will typically need some time to finish curing. To prevent ruining
the varnish, leave your wooden piece some place where it will not be disturbed.
Some varnishes finish curing with 24 or 48 hours, while others need as much as 5 or 7 days. Some varnishes
require 30 days to finish curing. Refer to the instructions on the can for more specific drying and curing times.
Source: http://www.wikihow.com/Varnish-Wood
b. Use proper ventilation. Many paint thinners and varnishes have strong fumes, which may cause light-
headedness or nausea.
c. Do not mix wood varnishes together. This could a cause negative and dangerous chemical reaction.
Source: http://www.wikihow.com/Varnish-Wood
IX. Maintenance
Varnish works and finishes can last longer but too much exposure to heat or to coolness might produce cracks.
But cracks can be easily retouch.
X. General
The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site conditions.
V. Supervision
Installation of wood door is carried out by the skilled and experienced carpenters who have expertise in
finishing carpentry works. They are assisted by inexperienced laborers. Their work is in turn supervised by
experienced Foremen. Site Engineer/Architect will be available for co-ordination with other sub-contractors
and Main Contractor and also to look into the technical aspects. He will ensure that the overall work conforms
to the shop Drawing.
b. When installing a solid core door, take a screw out of each of the 3 hinges and drive a long 2.5" screw in.
This will increase door stability. Shimming door jamb after bracket installation will also greatly increase the
strength
c. Make sure the screws are tightly installed so that the doors will function well.
Use screws to install one side of the head jamb so you can remove the door in the event of a problem.
X. General
The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site conditions.
Site Construction Methodology
Sliding Wood Door and Jamb Installation including Casing
Hardware Installation
Source: http://www.dummies.com/how-to/content/how-to-install-pocket-doors.html
Site Construction Methodology
Sliding Wood Door and Jamb Installation including Casing
V. Supervision
Installation of wood door is carried out by the skilled and experienced carpenters who have expertise in
finishing carpentry works. They are assisted by inexperienced laborers. Their work is in turn supervised by
experienced Foremen. Site Engineer/Architect will be available for co-ordination with other sub-contractors
and Main Contractor and also to look into the technical aspects. He will ensure that the overall work conforms
to the shop Drawing.
b. When installing a solid core door, take a screw out of each of the 3 hinges and drive a long 2.5" screw in.
This will increase door stability. Shimming door jamb after bracket installation will also greatly increase the
strength
c. Make sure the screws are tightly installed so that the doors will function well.
IX. Maintenance
Use screws to install one side of the head jamb so you can remove the door in the event of a problem.
X. General
The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site conditions.
Site Construction Methodology
Installation of Wood Veneer Wall Panels
Source: http://www.laminart.com/document/2687/Lamin-Art-install_Veneer_070115.pdf
IV. Installation
a. Edges and whole veneer panel must be sealed using a clear varnish or other suitable sealer to prevent
moisture penetration/absorption.
b. Drill a wood nuts/ baton on the concrete wall. It will serve as the counterpart of the tucker gun installed in
the veneer panel.
c. Apply rugby or any other wood glue that will bond the wall and the substrate of the veneer. Make sure that
the veneer will be fixed tightly.
d. Upon installation of veneer panel, make sure the hairline/ hasps are in one direction or stroke. Narrow panels
for wall applications, held rigidly in place by a securing system can have just a face side if the back side is
protected from excess humidity and covered with a suitable sealant such as paint, lacquer, or a vapor-
retarding varnish.
e. The termination of veneer panel to another veneer panel should be almost zero-to zero termination so that
when retouching the termination, there will be minimal works to be done.
f. Make sure that the veneer is closely flat to the wall to avoid the result of waviness.
g. To avoid warping of a panel assembly faced with Veneer-Art®, stresses resulting from thermal and
hygroscopic forces on both sides of the assembly must be balanced. The best results are obtained when a
backing sheet with characteristics comparable to the face sheet, is laminated to it.
h. After installing veneer panel, retouch all the minor damages of the panel.
Site Construction Methodology
Installation of Wood Veneer Wall Panels
V. Supervision
Installation of veneer panel is carried out by the skilled and experienced carpenters who have expertise in
finishing carpentry works. They are assisted by inexperienced laborers. Their work is in turn supervised by
experienced Foremen. Site Engineer/Architect will be available for co-ordination with other sub-contractors
and Main Contractor and also to look into the technical aspects. He will ensure that the overall work conforms
to the shop Drawing. And secure that there are no scratches, damaged panels, alignments, even and
straightness, the gap and termination, and the quality of the finish product.
c. Install veneer panel with proper care by two carpenters to avoid warping of the panel upon installation.
IX. Maintenance
Once veneer is installed, it is difficult to demolish and reinstall the same material. Veneer is quit sensitive type of
laminated wood. But damages can be retouch by varnish and still look the same as the veneer finish.
X. General
The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site conditions.
Site Construction Methodology
Installation of Frameless Shower Glass Enclosures
V. Supervision
Installation of glass enclosure is carried out by the skilled and experienced glass installers who have expertise in
glass and glazing installation works. They are assisted by inexperienced laborers. Their work is in turn supervised
by experienced Foremen.
Site Engineer/Architect will be available for co-ordination with other sub-contractors and Main Contractor and
also to look into the technical aspects. He will ensure that the overall work conforms to the shop Drawing. And
secure that the glass has no defects, breakage and scratches.
Site Construction Methodology
Installation of Frameless Shower Glass Enclosures
VI. Materials Used in Preparation
a. Silicon Sealant
b. U-Channel
c. Glass Door Hinges
d. Glass Door Handle
e. U-Channel
f. Plumb Tools
VII. Machinery and Tools to be Used
a. Glass Suction Cup
VIII. Safety Procedures
a. Consider using proper protection, such as safety glasses, gloves, and a mask.
b. Make sure the suction glass holder is tighten to hold the glass when installing.
X. General
The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site conditions.
Site Construction Methodology
Installation of Wallpaper on Concrete Wall
Wallpaper has the tendency of cutting and easily stained by some chemicals, but simple water with soap soak
using clean cloth can remove stains and dents.
X. General
The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site conditions.
Site Construction Methodology
Carpet Method of Installation
a. Carpets today have revolutionary carpet fiber systems that give supreme softness while being virtually stain
proof.
b. It is comfortable underfoot, easy to replace while being warmer, softer and quieter underfoot. Installation
flexibility allows carpet to go over a variety of substates.
c. Install tack less strip on the concrete floor. Leave a space of about 1/2" between the strips and the wall,
and be sure the pins or tacks face towards the wall. (They're called tackless strips even though they have
two or three rows or very sharp tacks, because using these "tackless strips" means you don't need to "tack"
carpet down.) At corners, make sure the tackless strips are butted tightly against each other.
d. Put the under pad down in strips that butt up to or reach the tackless strips. Butt the strips against each other
- don't overlap them - then staple the underlay down along the inside edge of the tack less strip.
Trim the excess underlay along the inside of the tackless strip and use duct tape to seal the seams. A small
bead of glue can be used on concrete floors to hold the pad in place.
e. To install carpet properly, you need to start with a piece that overlaps the edge of the floor by 4 to 6 inches
(10.2 to 15.2 cm). The overlay can then be trimmed so the carpet fits properly. To cut your first section,
measure the room at its longest point and add 6 inches (15.2 cm) to that measurement.
Mark the back of your carpet on both edges with that measurement and join the two marks with a chalk
line. Fold the carpet over on itself, and using a straight edge and a sharp utility knife, cut through the
backside of your carpet. Be sure to place a piece of scrap board underneath your cut line to protect the
underlying carpet.
Site Construction Methodology
Carpet Method of Installation
f. If the area is wide enough and need to get another piece of carpet, follow the same process with the
second piece - measure, mark and trim. Be sure the carpet pile is running the same way in both pieces, and
that the carpet piece is large enough to overlap the wall by 4 to 6 inches (10.2 to 15.2 cm), as well as
overlapping the first piece of carpet by 4 to 6 inches (10.2 to 15.2 cm). (Try to layout your carpet pieces so
the seams won't be in noticeable areas, but obviously sometimes that just isn't possible.)
g. Where the carpet pieces will join, overlap the two pieces, and then using a utility knife or a rented seam
cutter, cut through both pieces of carpet, ensuring the edges will match exactly. After cutting the carpet,
center a piece of seaming tape on the floor underneath where they join, adhesive side up.
Use the seaming iron to activate the adhesive (the iron goes on the tape, not on top of the carpet), and
then butt the edges together and seal the seam with a rolling pin or a carpet roller.
h. Use a knee kicker to attach the carpet along one edge. A knee kicker is a solid metal tool about 18" long
with "teeth" that will grip the carpet on one end, and a heavily padded "butt" on the other. Place the
toothed end of the kicker about 3" from the wall and drive your knee forcefully into the padded end of the
tool. This will stretch the carpet over the tackless strip where the tacks will grab it and hold it firmly in place.
Source: http://www.wikihow.com/Install-Carpet
V. Supervision
Installation of carpet roll is carried out by the skilled and experienced upholster who have expertise in fabric/
carpet upholstery works. They are assisted by inexperienced laborers. Their work is in turn supervised by
experienced Foremen.
Site Engineer/Architect will be available for co-ordination with other sub-contractors and Main Contractor and
also to look into the technical aspects. He will ensure that the overall work conforms to the shop Drawing. And
secure that the carpet termination are clean.
IX. Maintenance
Carpets need to be vacuumed once a week and more often in areas of heavy traffic. Frequent vacuuming
prolongs the life of your carpet by preventing a buildup of gritty particles that can cut carpet fibers.
Source: http://home.howstuffworks.com/home-improvement/household-hints-tips/cleaning-organizing/carpet-cleaning-
tips.htm
X. General
The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site conditions.
IX. Maintenance
Site Construction Methodology
Padded Panel need to be vacuumed once a week and more often in areas of heavy traffic. Frequent
vacuuming prolongs the life of your fabric by preventing a buildup of gritty particles that can cut fabric fibers.
X. General
The Sub-Contractor reserves the right to amend the method from time to time in consultation with the Main
Contractor, depending upon the specific site conditions.