CURVA "S"

OBRA OBRA:
UBICACIÓN: 0
UNIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE ARAPA RESIDENTE DE OBRA : ING. MAUROMOSCAIRO CHURA
FECHA 0.00 SUPERVISOR DE OBRA : ING NESTOR ELOY GONZALES SUCASAIRE

CURVAS "S"
GRAFICO DE CONTROL DE OBRA

Avance Programado Avance Ejecutado


Monto Porcentaje % Monto Porcentaje %
Mes del Informe S/. Programado Acumulado S/. Mes Ejecutado Acumulado
INICIO 0.00 0.00% 0.00% 0.00 0.00% 0.00%
FEBRERO 201918 al 28 79,941.29 1.56% 1.56% 235,890.19 4.61% 4.61%
MARZO 2019 1,500,253.31 29.32% 30.89% 0.00 0.00% 4.61%
ABRIL 2019 1,293,507.99 25.28% 56.17% 0.00 0.00% 4.61%
MAYO 2019 1,233,761.33 24.11% 80.28% 0.00 0.00% 4.61%
JUNIO 2019 348,801.11 6.82% 87.10% 0.00 0.00% 4.61%
JULIO 2019 167,719.73 3.28% 90.38% 0.00 0.00% 4.61%
AGOSTO 2019 210,077.51 4.11% 94.49% 0.00 0.00% 4.61%
SETIEMBRE 2019 222,890.34 4.36% 98.84% 0.00 0.00% 4.61%
TOTAL S/. 5,056,952.61 S/. 235,890.19 4.61%
PRESUPUESTO EXP.TECNICO S/. 5,116,163.41

Incidencia Avance/Programado Saldo Físico por Ejecutar

Monto S/. Porcentaje %


295.08% S/. 4,880,273.22 95.39%

CURVA "S" DEL AVANCE FISICO - PRESUPUESTO VIGENTE


40.00%

35.00% 36.66%

30.00%
% DE AVANCES ACUMULADOS

25.00% 24.25%

20.00%

15.00% 14.17%

10.00%

6.84%

5.00%
3.06%
1.56%
0.00%
0.00% 0.00% 4.61%
INICIO FEBRERO 2018 MARZO 2018 ABRIL 2018 JULIO 2018 AGOSTO 2018 SETIEMBRE 2018
Avance Programado 0.00% 0.79% 3.06% 6.84% 14.17% 24.25% 36.66%
Avance Ejecutado 0.00% 0.65%

Meses Valorizados

Avance Programado Avance Ejecutado

AVANCE FISICO MENSUAL EN S/.


AVANCE FISICO EN %
Series1

Series2 EJECUTADO SALDO


1,135,520.79

4.61%
1,200,000.00
922,205.65

1,000,000.00
671,116.37

800,000.00

600,000.00
345,871.69
207,515.08

400,000.00
79941.29

59,208.06

200,000.00

95.39%
0.00

0.00

0.00

0.00

0.00

0.00
FEBRERO 2018 MARZO 2018 ABRIL 2018 JULIO 2018 AGOSTO 2018 SETIEMBRE 2018