Vous êtes sur la page 1sur 10

790 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 27, NO.

2, MAY 2012

Distribution Power Flow Management Utilizing


an Online Optimal Power Flow Technique
Michael J. Dolan, Member, IEEE, Euan M. Davidson, Member, IEEE, Ivana Kockar, Member, IEEE,
Graham W. Ault, Member, IEEE, and Stephen D. J. McArthur, Senior Member, IEEE

Abstract—This paper describes the current connection regime DNOs in terms of power flow directions and magnitudes. This
for distributed generation (DG) in the U.K. and presents a novel ap- uncertainty is currently addressed by relatively conservative
plication of the optimal power flow (OPF) technique for automatic planning rules that mitigate these risks and ensure security of
power flow management (PFM) to manage thermal constraints in
distribution networks. OPF formulations have been used, in an of- supply. DNOs are looking towards active network manage-
fline mode, as a power system planning tool for several years. The ment (ANM) schemes [1] based on monitoring and control of
novel implementation of OPF for “corrective” PFM in an online the distribution network and connected users to increase DG
operational mode, for MV distribution networks, is presented and connection while minimizing, deferring, or even avoiding any
tested in this paper. The authors demonstrate, through simulations capacity upgrades associated with DG connection. ANM can
conducted on a commercially available substation computer, that
such an application of OPF can represent first on, last off gener- thus support renewable generation connections and, therefore,
ator connection agreements that reflect the current principles of help to meet renewable targets through incentives such as the
access in the U.K. Two case study networks, a 33 kV and an 11 kV, renewable obligation certificate (ROC) scheme in the U.K. [2].
provide the basis for assessment of the OPF-based PFM algorithm A prominent approach to delivering ANM schemes is the de-
in terms of computation time to arrive at a solution in the event of velopmental Autonomous Regional Active Network Manage-
a network thermal excursion and the level of DG curtailment nec-
essary to meet network thermal limits. Assessments are made and ment System (AuRA-NMS) developed in a major research, de-
fully discussed of the suitability for an OPF-based approach for velopment, and demonstration industry oriented activity. The
distribution network management within an online network con- core functionality of AuRA-NMS, categorized by industry re-
trol scheme including discussion of the important consideration of quirements, is to perform automatic restoration, voltage con-
control robustness. trol and power flow management (PFM). This differs from ex-
Index Terms—Active network management, distributed control, isting ANM solutions due to the package of functionalities of-
distributed generation, optimal power flow. fered. Thus, AuRA-NMS is a move away from bespoke ANM
solutions to a generic one with multiple functions being hosted
on an open, flexible, extensible platform [3], [4]. Flexibility is
I. INTRODUCTION
required to allow for deployment on topologically diverse net-
works and by being easily re-configurable within any network

I N the U.K., increasing numbers of distributed generation


(DG) connections are being made in the distribution net-
works at all voltage levels due to the proximity of new and re-
on which it is deployed (e.g., topology or plant rating changes,
addition or removal of DG, installation or removal of monitoring
equipment or changes to the existing control strategy). The ex-
newable energy resources to distribution circuits. Presently, the tensible, i.e., modular, characteristic allows for new or updated
U.K. distribution network operators (DNOs) are obliged to offer versions of the functionality to be integrated within the archi-
a connection to renewable generators based on the available net- tecture or for redundant functionality to be removed without
work capacity and any associated network reinforcement costs. having to re-write existing software. In addition to the above re-
This cost burden is incurred by the prospective DG developer quirements, the scheme must also operate in a robust, safe and
and recovered by the DG operator/owner. The generation con- secure way and should therefore exhibit graceful degradation
nections may or may not be economically feasible due to these under communication failures and erroneous data inputs. The
reinforcement costs and there is a resulting need to explore more development stage of AuRA-NMS brought about the investiga-
economic methods of generation connection. tion of three approaches to the PFM problem: current tracing,
The stochastic nature of the power output of most forms of constraint programming, and optimal power flow.
renewable energy sources brings operational uncertainty to the The work reported here is an extension of the work carried
out under the AuRA-NMS project [5]–[7]. The focus and con-
Manuscript received February 17, 2011; revised June 18, 2011 and October tent of this paper is on the novel application and real-time testing
04, 2011; accepted November 16, 2011. Date of publication January 16, 2012; of the OPF technique to the distribution PFM problem with em-
date of current version April 18, 2012. This work was supported in part by the
UK’s Engineering and Physical Science Research Council (EPSRC), SP Energy
phasis on deploying PFM software with a commercially avail-
Networks, EDF Energy, and ABB. Paper no. TPWRS-00139-2011. able OPF engine in a real-time control application. The paper
The authors are with the Institute for Energy and Environment, University of demonstrates the ability of such an approach to conform to the
Strathclyde, Glasgow G1 1XW, U.K. (e-mail: michael.dolan@eee.strath.ac.uk; current DG connection philosophy in the U.K. and other ter-
edavidson@eee.strath.ac.uk; ivana.kockar@eee.strath.ac.uk; g.ault@eee.
strath.ac.uk; s.mcarthur@eee.strath.ac.uk). ritories: “last-in, first-off” (LIFO). Applying a “pseudo” style
Digital Object Identifier 10.1109/TPWRS.2011.2177673 generator cost approach to define the preferential curtailment of
0885-8950/$26.00 © 2012 IEEE
DOLAN et al.: DISTRIBUTION POWER FLOW MANAGEMENT UTILIZING AN ONLINE OPTIMAL POWER FLOW TECHNIQUE 791

different generating technologies has been previously reported The AuRA-NMS solution addresses the complexity issues
and applied in [8] and [9]. of constraint management schemes by hosting generic and dis-
In this paper, the impact of DG on distribution network power tributed functionality that is capable of offering responsive mod-
flows as well as a suitable OPF formulation to address DG ac- ular control actions for any thermal violation, voltage excursion
cess rights is discussed initially. Then, the practical applica- and post-fault restoration. Taking an active approach to man-
bility and the ability of the OPF to operate within a real-time aging power flows ensures that the thermal limitations placed
and closed loop control environment to deliver PFM is demon- upon the network are met while maximizing DG access under
strated. As discussed in the following sections, this practical im- all operating conditions.
plementation was carried out by connecting outputs of the Pow-
erWorld tool with a dedicated PC acting as the real-time sim- B. DG Connection Principles
ulator and ABB’s COM6xx series substation automation com- The connection principle, for “non-firm” generation, prac-
puting hardware. The results of tests on two different networks ticed in the U.K. today is a last-in, first-off (LIFO) disconnec-
are presented and conclusions on the applicability of OPF in this tion order. This requires the most recent connected DG unit to
application are drawn. reduce its output first during a network constraint situation to re-
solve the constraint and return the network to a normal operating
state. Where this action is not sufficient to resolve the problem
II. IMPACT OF DG ON DISTRIBUTION NETWORK POWER the next most recent connected DG units would be called upon
FLOWS AND THE REQUIREMENT FOR ANM SYSTEMS to resolve the constraint, in succession, until the disconnection
list is exhausted. Conventional system planning rules would en-
A. Constraint and Power Flow Management of DG sure that, with no DG operational, the network limits would not
Connections be violated under normal operating conditions.
With an increase in the number and capacity of connected
Network power flows are influenced by the characteristics DG units, the LIFO access approach may hinder some invest-
of power injection and consumption, as well as the impedance ments in DG as newly connected DG units may face poor access
of the connecting circuits. By introducing DG units into dis- through more frequent disconnections. It is important to note
tribution networks, there is a move away from the traditional that LIFO arrangements had an important and positive role in
unidirectional power flow that distribution networks were origi- the initial stage of DG investments (clarity over network access
nally designed for. The resultant bidirectional power flows bring rights and protection of prior network connection contracts) but
added uncertainty to the direction and magnitude of flows in a with a growing need to increase the proportion of electricity gen-
distribution network and may pose significant risk to network erated by renewable low carbon technologies, in order to fulfil
security. obligations from the EU 20-20-20 target [12], the authors ac-
Traditionally network connections for DG have been assessed knowledge that DG connection principles must evolve. Other
against the available network thermal capacity as well as voltage connection principles are being investigated and showing im-
and fault current constraints. For example, an interconnected proved network access and subsequent energy yields [13].
network that has the capability to export excess DG may have The objective of this paper is to explore the role that an OPF
connection agreements that are approved as either “firm” or solution can play in active management of DG within the cur-
“non-firm”. These DG units with “firm” and “non-firm” rights rent commercial framework. The purpose of this is to better
can deliver power to load and export power to the adjacent net- utilize network assets and increase renewable DG output while
works uninhibited under normal network conditions. A “firm” recognizing the future potential and extensibility of an OPF so-
connection would be calculated on the n-1 maximum export ca- lution to deliver alternative principles of network access (e.g.,
pacity (for the highest rated interconnecting line being out of minimize DG set point change or delivering DG access bidding
service) plus the network minimum demand. This generation or sharing). This exploration of the potential of OPF to deliver
can therefore remain connected during an n-1 event and at any ANM is in line with the European Smart Grid Technology Plat-
load demand level hence the “firm” connection designation. form’s [14] interest in building up a “toolbox of proven tech-
“Non-firm” connections are calculated using the maximum niques that can be quickly and economically deployed”.
export capability (the sum of all interconnecting circuits) plus The analysis presented here is based on an OPF formulation
minimum load minus the connected “firm” generation. In the in which the cost of each DG unit reflects its connection order
event that one of the interconnecting lines is out of service with the highest cost of generation associated to the last DG
(during fault or maintenance), the “non-firm” generation would unit connected. Hence, similarly to the LIFO arrangement, this
need to be removed from the network, via a signal sent by the OPF-LIFO approach will first seek to constrain the last con-
DNO. The use of minimum load ensures that connections are nected DG units. In the case where a network is heavily con-
based upon a worst case scenario [10]. gested this OPF based method will have sufficient flexibility
The above discussion indicates that there is a need to develop to change the order of disconnection and, regardless of their
new ANM schemes to enable enhanced DG network access in an LIFO order, leave online the DG units whose contribution to
economically attractive manner. The assessment of one ANM the congestion is very weak and thus the curtailment of their
scheme [11] shows that the lost revenue from carefully con- outputs will not help in relieving congestion. The formulation
trolled curtailment is less costly than the expense of network re- of this described OPF-LIFO approach is derived by modifying
inforcement. The extent of this benefit depends on the network cost curves in the traditional OPF problem, as outlined in the
characteristics and the level of DG connection being considered. next section.
792 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 27, NO. 2, MAY 2012

III. APPLICATION OF OPTIMAL POWER FLOW within the OPF formulation however, due to the distributed con-
FOR POWER FLOW MANAGEMENT trol architecture of this ANM scheme voltages would be man-
aged by separate voltage control functions and coordinated ap-
A. Standard OPF Formulation propriately within the control architecture.
Optimal power flow [15]–[17] is a well established technique
used for power system operation and planning problems that B. OPF-LIFO Formulation for Power Flow Management of
can be formulated as an optimization problem. Typically, the Distribution Networks
goal is to minimize system operation costs or maximize social The OPF formulation defined by (1)–(6) is typically used for
welfare, subject to system operating constraints such as power operation of high voltage transmission systems with larger gen-
balance, generation loading limits and network capacity con- erating units. This is a complex problem with a large number of
straints. There are, however, various modifications of the ob- decision variables. The system operator has a set of well estab-
jective function formulation such as minimization of original lished rules and ancillary service arrangements to help maintain
control schedule deviation or bilateral contact curtailments [18]. secure system operation. These rules are reflected in the above
In addition, OPF has been investigated for evaluating the max- OPF formulation.
imum connection capacity of renewable DG units [19] and as As discussed in Section II, power flows at distribution levels
a real-time strategy for minimizing load curtailment to remove are evolving from being one-directional to bi-directional. Since
thermal congestion [20]. However, those previous applications the distribution networks were not designed for such an opera-
of OPF do not consider its use in a real-time generator con- tion, this can lead towards a more uncertain and congested sit-
trol situation, as is the focus of the application described in this uation than previously. This, therefore, requires novel network
paper. management solutions to facilitate increased DG connection. As
Typically, the OPF problem seeks to minimize system oper- such, DG developments at distribution levels are relatively re-
ation costs. In vertically integrated system operation, costs re- cent and thus the role of the DG in distribution network opera-
flect true costs of operating a unit, while in systems where elec- tions is less defined than it is for the generating units in the trans-
tricity markets are introduced, minimization is based on gener- mission system. As a result, effect of DGs on network calls for
ating unit offers submitted to a centralized market. operation techniques that will better reflect these uncertainties
The OPF formulation used within this paper is as follows: and bi-directional flows.
The aim of the OPF-LIFO approach proposed in this paper
(1) is to offer a solution that will support better operation of such
distribution networks. Since LIFO arrangements are currently
subject to applied by the U.K. DNO operators, the proposed method seeks
• Power balance equations to closely follow this LIFO access principle for the majority of
operating conditions. However, it will deviate from LIFO only
to avoid disconnecting or curtailing an unnecessary level of gen-
(2)
erator output. In that way application of OPF-LIFO will allow
for better utilization of DG resources and network infrastruc-
ture.
(3) The proposed OPF-LIFO method is based on the above OPF
formulation (1)–(6), with the only change being in the defini-
tion and formulation of the individual generation cost terms,
• Generation limits
, in the objective function (1). While in the general
(4) OPF formulation these terms reflect either true costs associated
with the electricity production, or the offer curves that genera-
(5)
tors submit when selling energy on the market, in the OPF-LIFO
• Thermal limits formulation terms reflect the order of the generators’
connections. Thus, each generator is assigned a constant cost
(6) function defined as
In the objective function (1), is the cost or offer (7)
function of a generator at bus , and are active and re-
active generation outputs while and are active and re- where is a constant allocated to each generating unit to re-
active demand at bus , , , and are the flect its connection order. This means that in order to priori-
upper and lower active and reactive generating unit limits. tize the utilization of generators that were connected first, they
and are the active and reactive power flows in the line be- will be assigned the lower value of , while those connected
tween and and is the apparent power thermal limit for last will be assigned the highest values. Note that the constant
the circuit (including transformers) between buses and . Note in (7) does not reflect actual generation costs (or offers),
that the power flow limitations (6) are verified for both the re- but, as mentioned above, is rather used to indicate a connection
ceiving and the sending end of lines. Traditionally the upper order which would be considered for resolving any network con-
and lower voltage magnitude limits at node can be included straint.
DOLAN et al.: DISTRIBUTION POWER FLOW MANAGEMENT UTILIZING AN ONLINE OPTIMAL POWER FLOW TECHNIQUE 793

Such modification of generation costs means that the solu-


tion of the above defined OPF will seek to maintain LIFO ar-
rangements as long as such an approach is curtailing generators
that can relieve the congestion. However, if the curtailment of
the particular generator does not address line overloads, the pro-
posed OPF LIFO will leave the output of this generator unmodi-
fied. Thus, by curtailing outputs of only generators that actually
affect the congestion, the OPF LIFO approach can help in in-
creasing the level of renewable generation outputs while seeking
to maintain LIFO rights.
In the case when deviation from the LIFO rule gives a solu-
tion that enforces less overall DG curtailment, the OPF-LIFO Fig. 1. Computation and issue of control signal.
formulation will automatically yield the improved generation
dispatch. This means that the developed OPF-LIFO formula-
tion may help DNOs automatically decide in which situations it achieved by conventional, larger scale generators. The inter-
would be beneficial for the overall system performance to for- mittent nature of renewable DG units introduces problems in
feit LIFO arrangements. defining and allocating power output set-points. In a congested
Furthermore, as in the case of other ANM schemes, in the network it is straightforward to calculate a curtailment level for
proposed mechanism a specific area of the distribution system a generating unit assuming that generator output measurements
is controlled with one or more interface points to the rest of the would be available.
network. This means that when the generation output from all Under congested operation the proposed constraint de-
of the DGs is greater than the demand in the given area, the sur- tection algorithm identifies any congested circuits violating
plus power is exported into the rest of the network through the the condition . The generator cost models
interfacing nodes. Similarly, if the DG output does not suffice are then sent to the OPF engine which returns generator
to supply the area demand, power balance will be maintained outputs based upon the solved OPF.
by importing necessary power through the interfacing nodes. In together with the actual generator real power
order to account for both cases, any such nodes are modelled as a output are passed to the algorithm to calculate the gener-
generator bus that can have both a positive and negative genera- ator control signals . These curtailment factors are sent
tion output. Furthermore, each of these outputs will have its sep- to the corresponding generator units, pictured in Fig. 1, as a
arate values of parameter , however the value assigned to the proportion of its actual output:
latter would be lower in order to maximize DG outputs and en-
courage export into the other part of the network. This cost allo- (8)
cation is representative of the negative generation bus being the
first historically connected generator and maintains the LIFO Restoring the permissible generation output defined by the
regime of the connected DG units. In fact, one of the aims of the current network limits and after the curtailment signal has been
DG installation is to reduce energy input from the grid, and here sent is, however, more problematic. This is due to the fact that
proposed OPF-LIFO is seeking to minimize this import or max- potential unconstrained outputs, defined by availability of the
imize the export. This is in the interest of all of the DG units in primary renewable resources (e.g., the wind), is unlikely to be
that area, but financial gains could allocate to cover the possible known by the control scheme. The difficulty is in how to rec-
losses of some generators. These additional financial arrange- ognize when a constraint has passed and the curtailment of the
ments, however, are not the subject of this paper because they DG unit can be relaxed. This is because it cannot be known what
will not affect the results of this real-time application of OPF. level of output the DG unit will achieve once curtailment is re-
The formulation of the OPF-LIFO presented in this section is leased. If the primary renewable resource is not known then DG
general. However, due to the modular nature of the AuRA-NMS units can only output what is available and not what the OPF
that, as discussed above, was influenced by the practical aspects solution requests or permits.
of the DNOs’ operation strategies, OPF-LIFO application was To overcome this issue the authors formulated a condition
intended only for relieving congestion due to thermal line limits. that identified whether an output curtailment could be relaxed
Therefore, the formulation omits voltage constraints as they will or removed from the constrained generators. Without knowing
be managed through another module specifically designed for the potential output of the renewable DG units the value of
the voltage control [21], [22]. This enables the application of the curtailed generator’s maximum rated output must
the commercially available PowerWorld tool which is included be used to obtain the level of relaxation with the variation in
into the real-time test platform, as discussed in the subsequent network loading. An updated control signal can be sent
sections. to the corresponding generators as defined in (8). In reality, this
level of output may not be attainable by a renewable DG unit
IV. PRACTICAL CONSIDERATIONS FOR IMPLEMENTING since the achievable output might be less than ,
OPF AS AN ACTIVE PFM SCHEME as discussed above. However, in order to maintain the system
Traditionally, OPF has been used for generation dispatch within thermal limits the generator output cannot exceed
where a calculated operating point can be allocated and , i.e., generation output is capped. In the case
794 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 27, NO. 2, MAY 2012

where , the control signal (equal to 1)


informs the DG unit that it can run unconstrained at whatever
level of generation resources permit as defined by (8).

V. TEST ENVIRONMENT
A closed loop test environment was established to evaluate
the performance of incorporating OPF into an online PFM al-
gorithm and comprises the following elements: Substation com-
puter, real-time simulator (dedicated PC), PFM and OPF soft-
ware and the case study network models. Each element of the
test environment is introduced in the following sections.
Fig. 2. 11-kV radial system.
A. Hardware Test Platform
The substation computing hardware used for the development
and testing was ABB’s COM6xx series substation automation
product. The COM6xx is a Windows XP Embedded industrial
computer that offers a powerful substation computing platform
onto which ANM and other control functionality can be de-
ployed.
The COM6xx acts as a gateway for mapping, monitoring,
control and protection signals from remote devices (generators,
transformers, protection relays) into the substation as long as the
protocol is supported by the COM6xx. A full description of the
ABB COM6xx series hardware can be found at [23].

B. Real-Time Simulator
A means of emulating the data transfer from network intelli-
gent electronic devices (IEDs) to the PFM algorithms was de-
veloped. The real-time simulator software runs on a dedicated
PC and calls upon data files that hold load and generation pro-
files. These profiles are used to represent the system conditions
Fig. 3. 33-kV interconnected system.
over time. The network model embedded within the COM6xx
is set to update once each second.
Within the real-time simulator are embedded controller
D. Case Study Network models
functions that simulate network control responses and include:
tap-changers; circuit breakers; real power set-point control Network case studies were used to represent two different real
responses; and power factor set-point control responses. For distribution systems in the U.K. The first case study network is a
the purpose of this investigation only real power set-point section of 11-kV radial distribution network with two DG units
control (that includes DG unit power output ramp rates) for DG (Fig. 2). Common planning practice for 11-kV networks entails
trim/trip controls were utilized. tapered capacity feeders that meet the feeder loading, voltage
drop and post-fault reconfiguration requirements with strategi-
C. PFM and OPF Software cally placed open points to achieve necessary levels of network
security. This tapering limits the prospective DG connection ca-
To achieve network management with the OPF-LIFO pacity on the 11-kV circuits.
approach, a new algorithm was developed. The algorithm iden- The second case study network is the 33-kV interconnected
tifies thermal constraint violations, updates DG cost models and network depicted in Fig. 3. This network is supplied via two
calls upon the OPF engine to solve the congestion constraint 132-kV circuits from “Sub X”. These terminate into two
while following connection and operating constraints. The 132/33-kV transformers at “Sub A” and “Sub B”. These two
outputs of running the OPF-LIFO algorithm are control signals substations operate as an interconnected group at 33 kV via
to the corresponding generating units with updated set points. three circuits. A further two 33-kV circuits radiate to supply
The PowerWorld power systems analysis software package loads and generation and these circuits have normally open
provided the functionality to solve the OPF problem defined points midway along their lengths at “Sub E” and “Sub G”.
above. Additional developed software provides the algorithms Combining the COM6xx platform with the real-time sim-
for congestion detection, cost models representing LIFO and ulator, the OPF-LIFO software and the case study network
the control signal processing. models enabled the authors to perform a number of studies
DOLAN et al.: DISTRIBUTION POWER FLOW MANAGEMENT UTILIZING AN ONLINE OPTIMAL POWER FLOW TECHNIQUE 795

TABLE I
EXAMPLE OF BREAKPOINT AND COSTS FOR CONNECTED DG
UNITS. DG A IS DEEMED TO BE THE FIRST CONNECTED UNIT

Fig. 4. Hardware and software interface and function interactions.

to assess the “closed-loop” performance of the OPF-LIFO


approach on the two different test distribution networks.
Fig. 4 shows the hardware connection interface and the soft- Fig. 5. 11-kV network with DG B last on.
ware interactions of the real-time simulation environment and
the substation computer. A dedicated PC emulated the data re-
trieval from the power system’s IEDs in the field by passing the is correct. The real-time simulator was interfaced with the
data to the substation computer via OPC. This data is then mon- substation computer using OPC. This enables the data “value”,
itored by the thermal detection algorithm and used within the “quality of value”, and “timestamp” to be evaluated. In the
OPF solver when a thermal excursion is identified. event of “bad” data it would be envisaged that such a scheme’s
functionality would be postponed until all data is deemed to be
E. Case Study Profiles “good”. The means of data acquisition and management with
the evolution of smart meters and distribution state estimation
Analysis of the two case studies was carried out for selected brings about uncertainty in ascertaining the quality of “future”
load and generation profiles utilizing the hardware and soft- data. An extension of this research is aimed at evaluating these
ware functions described above. The load and generation pro- issues and the performance of ANM functions under these
files were selected to ensure that one or more circuits was sub- circumstances. Therefore, the assessment criteria of interest
jected to a thermal constraint violation. are the levels of curtailment of DG and the time to compute
1) Case Study 1: 11-kV Radial Network: For the purpose of a solution rather than robustness against data or model error.
this test generating unit DG A (Fig. 2) was assumed to have a Control signals and computation times are the focus of this
constant output value of 1.6 MW with generating unit DG B assessment. In the practical implementation described, the load
varying its output to represent a small wind farm. The combina- and generation profiles are updated at each simulation “time
tion of varying DG B together with the varying load at “Bus 5” step” and monitored, for thermal excursions, at every third
changed circuit flows and caused congestion in either “Line 1” “time step”.
or “Line 2”.
2) Case Study 2: 33-kV Interconnected Network: In the A. Case Study 1: 11-kV Radial Network
second case study (Fig. 3), the profiles developed for the inter-
connected system held all generation at a constant level equal The LIFO connection principle can be represented by ap-
to the maximum rated DG outputs, , with the exception of plying a higher cost in the OPF formulation to the last histor-
generating unit DG 5. An increase of load at “Sub A” and the ically connected DG unit, in (8), and a lower value to the first
varying output of DG 5 contributed to overloads on “Line 1”. historically connected unit. The primary vertical axis in Fig. 5
In order to reflect the LIFO connection agreements within the displays the generating unit control signal value in per unit of
case study simulations the costs are applied to DG units as per generating unit capacity while the secondary vertical axis shows
the example in Table I. the MW line loading with and without curtailment of DG with
line limits shown for reference.
In Fig. 5 it can be observed that DG B was curtailed to alle-
VI. RESULTS AND DISCUSSION
viate the thermal constraint that occurred on “Line 1” as per the
Note that for the purpose of this lab-based closed-loop cost models assignment (i.e., DG B was the most recent to con-
demonstration it is assumed that all input measurement data nect so had the lower cost of curtailment). Initially, the detected
796 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 27, NO. 2, MAY 2012

TABLE II
GENERATOR CONNECTION PRIORITY

Fig. 6. 11-kV network with DG A last on.

Fig. 8. Case A—Interconnected network—DG 5 last on.


Fig. 7. 11-kV “Line 2” thermal constraint.

constraint conditions require a deeper curtailment, which corre-


spond to the dip at approximately time step 41 in Fig. 5. How-
ever, as network conditions change a further calculation offers
the DG greater access. As Fig. 5 indicates, even a small change
in loading, which occurred only 3 time steps after the initial cur-
tailment signal, results in the reduction of the thermal overload.
This then allows for the partial relaxation of the control signal.
The computation time for each of the seven generator unit set
point control signals under this system event range from 38 to
65 ms. Fig. 5 illustrates that the seventh signal, calculated at step
125, allows DG B to run unconstrained, i.e., control signal equal Fig. 9. Case B—Interconnected network—DG 3 last on.
to 1.
In a second case the DG cost models are reversed and DG A
is deemed to have been the last connected generator and there- cases (unchanged at 1.0 per unit output). Under this congestion
fore called upon first to resolve the thermal constraint on “Line situation and regardless of the connection priority, DG B is the
1” (Fig. 6). The MW line loading with and without DG cur- only DG unit that feeds into the congested line and can therefore
tailment is depicted on Fig. 6. During this scenario there are a be the only unit that can technically resolve the congestion. The
total of four control signals sent with the last signal allowing discrepancy between the two DG B control signals, in Fig. 7, is
DG A to output unconstrained. The computation time, for OPF due to the precise time of thermal overload detection (the algo-
solutions, ranges from 31 to 58 ms until the DG is returned to rithm cycles in a 3 “time step” loop) and illustrates the impact of
unconstrained operation. measurement and scan time on generation control in a dynamic
In order to illustrate the result that the OPF-LIFO approach environment.
has on generating units that do not have any direct effect on the
congested line, the thermal rating of “Line 2” (Fig. 2) is reduced. B. Case Study 2: 33-kV Interconnected Network
Fig. 7 illustrates the control actions for this case. For the second case study network (Fig. 3), increased load at
The dashed trace in Fig. 7 shows the set point control signal “Sub A” ensured a thermal constraint on “Line 1”. In Table II the
sent to DG B when its cost model is set to make it the last con- generating unit identification numbers are listed along with their
nected generating unit. The solid trace shows the DG B set point connection priorities. This situation produces the results illus-
control signal when DG A is set as the last connected generator. trated in Fig. 8, 9, and 11. Three different cases are explored (A,
The constant trace is the DG A set point control signal for both B, and C) with the purpose demonstrating the varying levels of
DOLAN et al.: DISTRIBUTION POWER FLOW MANAGEMENT UTILIZING AN ONLINE OPTIMAL POWER FLOW TECHNIQUE 797

Fig. 10. Case A and B—interconnected network—line loading.


Fig. 12. Interconnected network case C— “line 1” switched out.

on Fig. 9. This occurs as a result of the rise in load which in-


creases the thermal constraint on “Line 1”. A number of revised
initial set point control signals are calculated to compensate for
this increasing congestion (between time-step 37 and 42). As
the thermal constraint is alleviated (from time step 65 onwards),
new set point control signals are calculated, with computation
times ranging from 60 to 97 ms, and sent to the DG unit until it
can run unconstrained at full rated output.
The line loading for the scenarios run in Figs. 8 and 9 is shown
as the solid trace on Fig. 10. The other two traces show the
resultant line loading levels when DG 5 and DG 3 are curtailed.
Fig. 11. Case C—interconnected network (increased constraint). With the same connection priority maintained, as in Case B
above, the load at “Sub A” is doubled to increase the magni-
tude of the thermal constraint. The DG units’ connection order
curtailment under the same thermal constraint location for dif- list now has to be used more extensively by the OPF-LIFO al-
fering DG connection orders and severity of thermal constraint. gorithm to manage the congestion (Fig. 11). DG units 3, 4, and
In Fig. 8, DG 5 had the largest costs in its OPF cost model 5, prioritized as 10th, 9th, and 8th, respectively, are curtailed in
to represent being the last connected generating unit, and hence the appropriate order to keep the network within thermal limits.
was the first unit curtailed when “Line 1” experiences a thermal As system loading changes, these generating units are brought
constraint. The primary vertical axis in Fig. 8 shows the MW back on in the reverse order. With DG 3 offline and DG unit 5
level of curtailed and potential generation, while the secondary operating at maximum rated output the DG unit 4 control signals
vertical axis depicts the set point control signal sent to the DG fluctuates against the network conditions to ensure that thermal
unit. The horizontal axis shows the simulation time steps. limits are adhered to. In this case loading is such that DG unit 3
It can be observed that the set point control signal commu- must remain offline.
nicates four changes in output for DG 5, each taking between In a further test case the original “case study 2” load profiles
48 and 83 ms to compute the solution. The initial control signal were used while maintaining the connection priority set in Case
(at time-step 36) requires DG 5 to ramp down to approximately C. Fig. 12 illustrates the calculated DG unit set point control
90% of its output. When allowing generator unit DG 5 to ramp signals when “Line 1” is switched out. The result of this line
up towards its potential output, as the thermal constraint reduces outage is a step change in network states which creates over-
through load decrease, three further control signals are sent to loads on “Line 2” and “Line 3” (Fig. 3). Under this system event
the DG unit until it operates unconstrained. It is worth noting the order of curtailment is DG units DG 4, DG 3, DG 5, and
that at time-step 73 the generating unit DG 5 would be allowed Hydro B. These units are prioritized as 9th, 10th, 8th, and 2nd,
to operate at rated power, however, as the primary wind resource respectively. This breaks the cost modelled LIFO connection
is not present (i.e., insufficient wind speed) the actual generating order due to the severity of the situation however the result is
unit output level is lower to reflect the unavailability of the wind. less curtailment than enforcing LIFO under this event. Fig. 12
In order to test the effect that the order of priority has on cur- shows the DG unit control signals. At time-step 14, “Line 1” is
tailment results the connection order of unit DG 3 was changed. switched out and at time-step 41 the line is returned into service.
This is shown in column 2 of Table II where the cost for DG 3 Hydro B station is the first to be allowed back on, followed by
was changed to set it as the last connected DG unit. In Fig. 9, units 4 and 5, simultaneously, and then as load levels drop DG 3
the axes display the same information as that of Fig. 8 previ- is signalled to run unconstrained. This relaxation of DG curtail-
ously. In Case B there are a number of signals sent to curtail unit ment follows the LIFO connection agreement, i.e., generators
DG 3—noticeable from the number of control signals logged with the lowest priority are brought back online first.
798 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 27, NO. 2, MAY 2012

VII. CONCLUSION capability to calculate voltage settings and other network con-
trols to meet DNO objectives. The coordination of different ob-
The closed loop simulation results presented above demon-
jectives within an OPF formulation of ANM requires further
strates that the novel application of OPF combined with pro-
thought.
totype PFM algorithms, running on a commercially available
substation computer platform, has the potential to operate in
an online and real-time environment. OPF-LIFO solution com- REFERENCES
putation time is in the tens of milliseconds range for moder- [1] D. Roberts, Network Management Systems for Active Distribution
Networks—A Feasibility Study, DTI Distributed Generation Pro-
ately sized distribution network areas. Continuous monitoring gramme (Contractor: SP PowerSystems LTD) Contract Number:
and control leads to progressive DG set point control signals K/EL/00310/00/00, URN Number: 04/1361, 2004.
allowing for the LIFO representation to be maintained and for [2] Department of Trade and Industry, in Energy White Paper: Our Energy
Future—Creating a Low Carbon Economy, 2003 & Meeting the Energy
good resolution DG set points to be calculated in contrast to Challenge, 2007.
the DG unit capacity blocks proposed in other PFM scheme de- [3] E. M. Davidson, S. D. J. McArthur, J. R. McDonald, and P. C. Taylor,
signs. Under network outage conditions and other more onerous “An architecture for flexible and autonomous network management
systems,” in Proc. CIRED 2009, Jun. 2009.
operation conditions a solution to the circuit congestion is found [4] E. M. Davidson, S. D. J. McArthur, C. Yuen, and M. Larsson,
through DG unit constraint control but the LIFO connection “AuRA-NMS: Towards the delivery of smarter distribution networks
agreements are not honoured. The outcome in this case allows through the application of multi-agent systems technology,” in Proc.
IEEE Power and Energy Society General Meeting—Conversion and
greater energy yields across the DG units than that of conven- Delivery of Electrical Energy the 21st Century, 2008, Jul. 20–24, 2008.
tional methods, i.e., inter-tripping of all “non-firm” DG units. [5] E. M. Davidson, S. D. J. McArthur, M. J. Dolan, and J. R. McDonald,
This non-conformity of the LIFO principle of access demon- “Exploiting intelligent systems techniques with an autonomous re-
gional active network management system,” in Proc. IEEE Power and
strates the potential for OPF to be used under different connec- Energy Society General Meeting 2009.
tion principles such as DG bids for access to distribution net- [6] M. J. Dolan, E. M. Davidson, G. W. Ault, and J. R. McDonald, “Tech-
work capacity or some form of access sharing to enhance DG niques for managing power flows active distribution networks with
thermal constraints,” in Proc. CIRED 2009, Jun. 2009.
access. In summary, the novel OPF-LIFO approach has been [7] E. M. Davidson, M. J. Dolan, S. D. J. McArthur, and G. W. Ault,
found, through implementation and testing, to be viable in terms “The use of constraint programming for the autonomous management
of robustness (find a practical solution under all test cases), of power flows,” in Proc. 15th Int. Conf. Intelligent Systems Applica-
tions to Power Systems, Nov. 2009.
speed of computation and the ability to represent existing (i.e., [8] M. J. Dolan, E. M. Davidson, G. W. Ault, J. R. McDonald, F. Coffele,
LIFO) and alternative principles of access to distribution net- and I. Kockar, “Using optimal power flow for management of power
work capacity. Future work would be required to address impor- flows active distribution networks with thermal constraints,” in Proc.
44th Int. Universities’ Power Engineering Conf., Glasgow, U.K., 2009.
tant practical issues ahead of field test of the OPF based PFM [9] T. Boehme, G. P. Harrison, and A. R. Wallace, “Assessment of distribu-
method but the results presented in this paper show the potential tion network limits for non-firm connection of renewable generation,”
of the approach. IET Renew. Power Gen., vol. 4, no. 1, pp. 64–74, 2010.
[10] A. Collinson, F. Dai, A. Beddoes, and J. Crabtree, Solutions for
the Connection and Operation of Distributed Generation, DTI
VIII. FUTURE WORK Distributed Generation Programme (Contractor: EA Technology)
K/EL/00303/00/01/REP, 2003.
The analysis in this paper indicates that the performance, [11] R. A. F. Currie, G. W. Ault, C. E. T. Foote, and J. R. McDonald, “Active
power-flow management utilising operating margins for the increased
based upon reliable data, is robust since no non-convergence connection of distributed generation,” IET Gen., Transm., Distrib., vol.
situations arose. However, performance testing would require 1, no. 1, pp. 197–202, Jan. 2007.
modelling and simulating erroneous data from sensors and lack [12] European Commission, Combating Climate Change: The EU Leads
the Way. [Online]. Available: http://ec.europa.eu/publications/book-
of measurements as these would have a direct implication on the lets/move/70/index_en.htm.
network model. Misrepresentation of the actual system states [13] S. C. E. Jupe and P. C. Taylor, “Strategies for the control of multiple
would lead to erroneous control signals being sent to genera- distributed generation schemes,” in Proc. CIRED 2009, Prague, Czech
Republic, Jun. 2009.
tors and increase the probability of load flow divergence. Re- [14] European Commission, European SmartGrids Technology Plat-
cently, these issues have been discussed [24] in the context of form—Vision and Strategy for Europe’s Electricity Networks of the
voltage control and an approach to dealing with the loss of com- Future, 2006.
[15] J. Carpentier, “Optimal power flow,” Int. J. Elect. Power Energy Syst.,
munications to controllable devices presented. It is envisaged, vol. 1, pp. 3–15, 1979.
for this paper’s approach, that under these severe cases (e.g., [16] J. Carpentier, “Contribution a l’etude du dispatching economique,”
loss of or uncertain measurements or loss of controllable de- Bull. Soc. Franc. Elect., vol. 8, no. 3, pp. 431–447, 1962.
[17] H. Dommel and W. F. Tinney, “Optimal power flow solutions,” IEEE
vices attained via error checks or the communications standard) Trans. Power App. Syst., vol. PAS-87, pp. 1866–1876, 1968.
that the DNO would have to revert to traditional approaches, [18] I. Kockar and F. D. Galiana, “Combined pool/bilateral dispatch—Part
either trip all DG units or wait for protection systems to op- 2: Curtailment of firm and non-firm contracts,” IEEE Trans. Power
Syst., vol. 17, no. 4, pp. 1184–1190, Nov. 2002.
erate. This is undesirable but on the basis that active power flow [19] L. F. Ochoa, C. J. Dent, and G. P. Harrison, “Distribution network
management approaches yield higher levels of DG penetration capacity assessment: Variable DG and active networks,” IEEE Trans.
[11], [13], [25] than conventional inter-tripping schemes then Power Syst., vol. 25, no. 1, pp. 87–95, Feb. 2010.
[20] F. Capitanescu and L. Wehenkel, “Optimal power flow computations
this approach may be deemed suitable for extreme cases of error. with a limited number of controls allowed to move,” IEEE Trans. Power
In addition, further investigation of the capability of the OPF Syst., vol. 25, no. 1, pp. 586–587, Feb. 2010.
technique to represent alternative principles of DG access than [21] P. C. Taylor, T. Xu, S. McArthur, G. Ault, E. Davidson, M. Dolan, C.
Yuen, M. Larsson, D. Botting, D. Roberts, and P. Lang, “Integrating
LIFO is required to determine the technique’s feasibility and voltage control and power flow management AuRA-NMS,” in Proc.
flexibility for future connection arrangements. OPF also has the CIRED Smart Grids 2008.
DOLAN et al.: DISTRIBUTION POWER FLOW MANAGEMENT UTILIZING AN ONLINE OPTIMAL POWER FLOW TECHNIQUE 799

[22] P. C. Taylor, T. Xu, N. S. Wade, M. Prodanovic, R. Silversides, T. Ivana Kockar (S’99–M’04) received the Dipl.Ing.
Green, E. M. Davidson, and S. D. J. McArthur, “Distributed voltage (M.Sc.) degree from the University of Belgrade, Bel-
control AuRA-NMS,” in Proc. IEEE Power Engineering Society Gen- grade, Yugoslavia, and the M.Eng. and Ph.D. in 2004
eral Meeting, Jul. 2010, pp. 1–7. from McGill University, Montreal, QC, Canada.
[23] ABB. [Online]. Available: http://www.abb.com/Product/ She is a Lecturer within the Institute for Energy
seitp328/3cc7d0b2a99f2f40c1257188002facd2.aspx?product- and Environment at the University of Strathclyde,
Language=us&country=00. Glasgow, U.K. Her research interests include power
[24] M. Glavic, M. Hajian, W. Rosehart, and T. Van Cutsem, “Re- system operation planning and economics of energy
ceding-horizon multi-step optimization to correct nonviable or systems.
unstable transmission voltages,” IEEE Trans. Power Syst., vol. 26, no. Dr. Kockar chairs the IEEE PES Computing and
3, pp. 1641–1650, Aug. 2011. Analytical Methods Subcommittee (CAMS) and
[25] G. W. Ault, R. A. F. Currie, and J. R. McDonald, “Active power flow co-chairs the IEEE PES Task Force on Agent-Based Modeling of Smart Grid
management solutions for maximising DG connection capacity,” in Market Operation.
Proc. IEEE Power Engineering Society General Meeting, Jul. 2006,
pp. 1–5.

Michael J. Dolan (M’09) received the B.Eng (Hons) Graham W. Ault (M’98) received the B.Eng. degree
degree in electronic and electrical engineering from in electrical and mechanical engineering and the
the University of Strathclyde, Glasgow, U.K., in Ph.D. degree in electrical power systems from the
2006. University of Strathclyde, Glasgow, U.K., in 1993
He is currently a Research Fellow at the Institute and 2000, respectively.
for Energy and Environment at the University of Since 1996, has been researching power system
Strathclyde. His research interests include: active planning and operations issues relating to distributed
network management and sustainable energy sys- energy resources in distribution systems. He is cur-
tems for developing countries. His recent work has rently a Professor in the Institute for Energy and En-
focused on techniques and tools for real-time control vironment at the University of Strathclyde.
and operation of future energy networks.

Euan M. Davidson (M’06) received the M.Eng. Stephen D. J. McArthur (M’93–SM’07) received
degree from the University of Strathclyde, Glasgow, the B.Eng. (Hons.) and Ph.D. degrees from the Uni-
U.K., in 2000. versity of Strathclyde, Glasgow, U.K., in 1992 and
He is a Senior Research Fellow at the Institute for 1996, respectively.
Energy and Environment at the University of Strath- He is Director of the Institute for Energy and Envi-
clyde. His research interests include: multi-agent ronment and Director of the British Energy Advanced
systems; model-based reasoning; and the application Diagnostics Centre at the University of Strathclyde.
of intelligent system techniques to diagnostic, power
system control, operation, and management prob-
lems. His recent work has focused on active network
management and tools, techniques, and architectures
for intelligent or smart networks

Vous aimerez peut-être aussi