PAVEMENT DESIGN FOR STRENGTHENING

(Based on IRC 37/2012 and IRC 81/1997)

Step 1 Enter the values in "INPUT "sheet

Step 2 This program allows only five reaches.

Step 3 Print the 'abstract' sheet

Step 4 Select the life period as per your requirements

Based on the selected life period get the print of " years " sheet. For 5 years
Step 5 print "5 years" etc

To repeat or for new calculations, close the program and open again and enter
Step 6 from "INPUT" sheet to avoid error.

Send your suggetions to zoorace@yahoo.com or by calling suresh ade in 94441 57725 to improve th
program further.
NING
97)

heet. For 5 years

en again and enter

e in 94441 57725 to improve the


Strengthening to Trichy - Ramanathapuram road km 0/0 - 3/2 of NH 210 including construction of Centre median at
Name of the Road Km 0/0 - 3/2.
Reach 0/0 -1/0 1/0 - 2/0 2/0 - 3/0 3/0 - 3/2
Rolling / Plain Rolling / Plain Rolling / Plain Rolling / Plain
Road terrain Terrain Terrain Terrain Terrain
Dual carriageway Dual carriageway Dual carriageway Dual carriageway
Carriageway lanes two lane road two lane road two lane road two lane road

Design life in years 10 10 10 10 5


Construction period 1 1 1 1
Year of Traffic Census Taken 2017 2017 2017 2017
Current year 2017 2017 2017 2017
Annual growth rate of CV 5 5 5 5
Initial Traffic Volume CV 6723 6723 6723 6723
Direction of traffic census taken BOTH direction BOTH direction BOTH direction BOTH direction
Characteristic Deflection 1.594 1.592 1.595 1.599
BM CEILING in mm 55
Traffic Volume after completion 3530 3530 3530 3530 0
Vehicle Damaging Factor, VDF 4.50 4.50 4.50 4.50 0.50
Lane Distribution Factor LDF 0.75 0.75 0.75 0.75 0.45
DESIGN TRAFFIC IN MSA
Reach 0/0 -1/0 1/0 - 2/0 2/0 - 3/0 3/0 - 3/2
For 10 Years 54.70 54.70 54.70 54.70 #DIV/0!
For 6 Years 59.15 59.15 59.15 59.15 #DIV/0!
For 7 Years 70.81 70.81 70.81 70.81 #DIV/0!
For 8 Years 83.04 83.04 83.04 83.04 #DIV/0!
For 9 Years 95.89 95.89 95.89 95.89 #DIV/0!
For 10 Years 54.70 54.70 54.70 54.70 #DIV/0!

suresh ade 94441 57725


Pavement Composition (Strengthening) zoorace@yahoo.com

Name of work :
Strengthening to Trichy - Ramanathapuram road km 0/0 - 3/2 of NH 210 including
construction of Centre median at Km 0/0 - 3/2.

140705V

5 Years 6 Years 7 Years 8 Years 9 Years 10 Years

Reach BM DBM BC DBM DBM DBM BM DBM BC BM DBM BC BM DBM BC BM DBM BC

0/0 -1/0 0 85 40

1/0 - 2/0 0 85 40

2/0 - 3/0 0 85 40

3/0 - 3/2 0 85 40

suresh ade 94441 57725


zoorace@yahoo.com

Strengthening to Trichy - Ramanathapuram road km 0/0 - 3/2 of


Name of Work : NH 210 including construction of Centre median at Km 0/0 - 3/2.

Reach 0/0 -1/0


Terrain ---------- Rolling / Plain Terrain
Dual carriageway two lane
Carriageway lanes --------
road
Constuction period in Years ---------- 1
Year of Traffic Census Taken ---------- 2017
Current year ---------- 2017
Annual growth rate of CV ---------- 5

Initial Traffic Volume CV BOTH direction ---------- 6723


Characteristic Deflection ---------- 1.594

Initial Traffic Volume after completion


1
3362x ( 1+0.05) ---------- 3530 cv/day
Vehicle Damaging Factor, VDF ---------- 4.50
Lane Distribution Factor, LDF ---------- 0.75

Design Traffic N = 365 * ( (1+r)^n - 1) * A * D * F )/ r

For 15 Years
15
= 365 x ( ( 1+0.05 ) -1) x 3530 x 4.5 x 0.75
0.05
= 93.83 MSa

For 10 Years
10
= 365 x ( ( 1+0.05 ) -1) x 3530 x 4.5 x 0.75
0.05
= 54.70 MSa

For 5 Years
5
= 365 x ( ( 1+0.05 ) -1) x 3530 x 4.5 x 0.75
0.05
= 54.70 MSa

suresh ade 94441 57725


Pavement Composition (Strengthening) Design Life 10 years

Strengthening to Trichy - Ramanathapuram road km 0/0 - 3/2 of NH 210 including construction of Centre median at
Km 0/0 - 3/2.

Proposed
Required
BM
Reach Deflection Msa BM Overlay BM DBM BC Remarks
thickness in
Thickness
mm

0/0 -1/0 1.594 54.70 176 0 85 40 179

1/0 - 2/0 1.592 54.70 176 0 85 40 179

2/0 - 3/0 1.595 54.70 176 0 85 40 179

3/0 - 3/2 1.599 54.70 176 0 85 40 179

suresh ade 94441 57725