Vous êtes sur la page 1sur 1

TA 8027-ID Water Resources and Irrigation Sector Management Project-2 (WISMP-2)

Preparation for Modernization of the Management of the Jatiluhur Irrigation System


MONTHLY TIMESHEET
Name Month June 2017

Post Duty station Bandung

Date Calendar Day Work location Activities/remarks

1 Public Holiday

2
3 Weekend

4 Weekend

5
6
7
8
9
10 Weekend

11 Weekend

12
13
14
15
16
17 Weekend

18 Weekend

19
20
21
22
23
24 Cuti Bersama

25 Idul Fitri 1438 H

26 Idul Fitri 1438 H

27 Cuti Bersama

28 Cuti Bersama

29 Cuti Bersama

30 Cuti Bersama

Total At 1/30th month per one (1) day for periods Chargeable
0.00
cal.days less than one month input (months)

Total months worked


Previous total Signed Date
(Team Member)
This month

Total to date Countersigned Date


(Team Leader)

431232601.xlsx