Kalapatti Apartment (Work Flow)

S.No Activities Status Responsibility Remarks Date: 17.07.2019


J.V Ration Finalization with LMW - CFO for 75% &
1 25% Completed Mr. Bharathi Freezed the ratio as 75% & 25%

2 Architect - Floor plan Completed Mr. Bharathi Freezed the Floor plans with Buildup area of 22532 sq.f

3 Architect - Elevation and Structural Drawings 20.07.2019 Mr. Bharathi The Drawings for Apartment is in process.

4 Estimate & Construction Schedule 24.7.2019 Mr. Jaya Bharath Afer the receiving the structural Drawings final costing will be done

5 Marketing - sales flow Completed Mr. Vishnu Hari Already done with the current market study.

6 Cash Flow 25.7.2019 Mr. Sathish Will be ready afer receving the final costings

LMW Meeting & JV Finalization (Apartment name


7 selection) 27.7.2019 Mr. Bharathi Afer the cashflow statement the jv agreement will be processed

8 Contrator finaliztion Completed Mr. Bharathi Selected Contractors for Plumbing & Electrical

Mr. Bharathi / Mr. Documents collecting and Plan conformation is under progress With
9 LPA Approval Process & RERA Approval Intiated from 10.07.2019 Vishnu Hari an Agent Samy Kannan. Approval Process with take till Oct 2019

10 Opening Escrow Account in Bank Sep-19 Mr. Sathish A spearate account should be opened for this project

As the approval process takes for 2 months, the lanch is planned for
11 Planned for Launch Nov-19 Mr. Bharathi Sep-mid or Nov-1st week

Sale Agreement & Construction Agreement Mr. Bharathi / Mr.


12 Preparation Sep-19 Vishnu Hari Co-ordinating with legal Dept

13 Booking Form & Brouchure preparation Sep-19 Mr. Vishnu Hari Marketing activities will be carried out from Oct to Sep

Lauch preparation such as flex, newspapar ads & Infrastructure at site


14 Ads and Launch Preparation Sep-19 Mr. Vishnu Hari will be done
Kalapatti Individual house (Work Flow)
S.No Description Completion date Responsibility Remarks Date: 17.07.2019

1 Site Registration Completed Mr. Bharathi The Land registration id done by the client with LMW on 4th July 19

The Drawings is already done, Elevation to be designed with Client


2 Drawing Finalization 22.07.2019 Mr. Bharathi consultation.

3 Specifications and Brands Finalization 22.07.2019 Mr. Bharathi Material Specs and Brands to be finalized

Mr. Bharathi & Payment terms & Agreement to be duly signed by the customer &
4 Payment terms & Agreement 25.07.2019 Vishnu RVL