FORM 1(5)

(See Regulation 3)
ARCHITECT’S CERTIFICATE
[To be submitted at the time of Registration of Ongoing Project and for withdrawal of
Money from Designated Account]

Date: - 31/10/2018
To,
SHARNAM
Register Addresh: - SHARNAM, Opp. Splace Hospital, Nr. Sapphire Global School, Parivar Char
Rasta, Waghodia Road, Vadodara - 390019

Subject: - Certificate of Percentage of Completion of “SHARNAM” Construction Work of 62


Shop & 61 Offices & 152 Residency Flates of 7 - Tower of the Single Phase of the Project

[PR/GJ/VADODARA/VADODARA/Others/MAA03111/070718] situated on the Plot

bearing C.N. No. /CTS No. /Survey No.: - 815/1/2, Final Plot No: - 158/4/1, 158/4/2.

Demarcated by its boundaries (latitude and longitude of the end Points)

22.292655 & 73.243097 to the North 22.292119 & 73.243105 to the South 22.292405 &
73.243541 to the East 22.292414 & 73.242488 to the West of Division: - Vadodara, Village: -
Bapod, Taluka: - Vadodara, District: - Vadodara, PIN: - 390019, Admeasuring: - 6400.00
Sq.Mtrs. Area being Developed Sharnam.

Sir,
I/We have undertaken assignment as Architect of certifying Percentage of
Completion of Construction Work of 62 Shop & 61 Offices & 152 Residency Flates of 7 -

Tower of the Single Phase of the Project, situated on the Plot bearing C.N. No. /CTS No. /Survey
No.: - 815/1/2, Final Plot No: - 158/4/1, 158/4/2, of Division: - Vadodara, Village: - Bapod,

Taluka: - Vadodara, District: - Vadodara, PIN: - 390019, Admeasuring: - 6400.00 Sq.Mtrs.


Area being Developed Sharnam As per the Approved Plan.

1. Following technical professionals are appointed by Owner/Promoter: - (as applicable)


(i) M/s./Shri/Smt. Janki Creation as Engineer

(ii) M/s./Shri/Smt. Integral Design as Structural Consultant

(iii) M/s./Shri/Smt. Not Applicable as MEP Consultant

(iv) M/s./Shri/Smt. Vrajesh Rameshchandra Shah as Site Supervisor/Clerk of Work

Based on Site Inspection by Undersigned on 31/10/2018 Date and with Respect to each of the

Building/Wing or of the Plots as the case may be of the aforesaid Real Estate Project, I certify that as
on the date of this certificate, the Percentage of Work done for each of the building/Wing of the
Real Estate Project as registered Vide number
PR/GJ/VADODARA/VADODARA/Others/MAA03111/070718 under GujRERA is as
per table A herein below. The Percentage of the work Executed with respect to each of the activity of
the entire phase is detailed in Table A and B.
TABLE – A
TOWER - A
(To be prepared separately for each Building/Wing of the Real Estate Project)
Sr. Tasks/Activity Percentage of work done
No.
1 Excavation 100 %
2 Zero Number of Basement(s) and Plinth 100 %
3 Zero Number of Podiums 00 %
4 Stilt Floor 100 %
5 Seven Number of Slabs of Super Structure 100 %
6 Internal walls, Internal Plaster, Floorings within
Flats/Premises, Doors and Windows to each of 45 %
the Flat/Premises
7 Sanitary Fittings within the Flat/Premises 35 %
8 Staircases, Lifts Wells and Lobbies at each Floor
level connecting Staircases and Lifts, Overhead
30 %
and Underground Water Tanks
9 The external plumbing and external plaster,
Elevation, completion of terraces with 25 %
waterproofing of the Building/Wing.
10 Installation of lifts, water pumps, Fire Fighting
Fittings and Equipment as per CFO NOC,
Electrical fittings to Common Areas, electro,
40 %
mechanical equipment, compliance to
conditions of environment/CRZ NOC, Finishing
to entrance lobby/s, plinth protection, paving of
areas appurtenant to Building/Wing, Compound
Wall and all other requirements as may be
required to Obtain Occupation/Completion
Certificate
TABLE – A
TOWER - B
(To be prepared separately for each Building/Wing of the Real Estate Project)
Sr. Tasks/Activity Percentage of work done
No.
1 Excavation 100 %
2 Zero Number of Basement(s) and Plinth 100 %
3 Zero Number of Podiums 00 %
4 Stilt Floor 100 %
5 Seven Number of Slabs of Super Structure 100 %
6 Internal walls, Internal Plaster, Floorings within
Flats/Premises, Doors and Windows to each of 40 %
the Flat/Premises
7 Sanitary Fittings within the Flat/Premises 35 %
8 Staircases, Lifts Wells and Lobbies at each Floor
level connecting Staircases and Lifts, Overhead
30 %
and Underground Water Tanks
9 The external plumbing and external plaster,
Elevation, completion of terraces with 25 %
waterproofing of the Building/Wing.
10 Installation of lifts, water pumps, Fire Fighting
Fittings and Equipment as per CFO NOC,
Electrical fittings to Common Areas, electro,
40 %
mechanical equipment, compliance to
conditions of environment/CRZ NOC, Finishing
to entrance lobby/s, plinth protection, paving of
areas appurtenant to Building/Wing, Compound
Wall and all other requirements as may be
required to Obtain Occupation/Completion
Certificate
TABLE – A
TOWER - C
(To be prepared separately for each Building/Wing of the Real Estate Project)
Sr. Tasks/Activity Percentage of work done
No.
1 Excavation 100 %
2 Zero Number of Basement(s) and Plinth 100 %
3 Zero Number of Podiums 00 %
4 Stilt Floor 100 %
5 Seven Number of Slabs of Super Structure 100 %
6 Internal walls, Internal Plaster, Floorings within
Flats/Premises, Doors and Windows to each of 40 %
the Flat/Premises
7 Sanitary Fittings within the Flat/Premises 35 %
8 Staircases, Lifts Wells and Lobbies at each Floor
level connecting Staircases and Lifts, Overhead
30 %
and Underground Water Tanks
9 The external plumbing and external plaster,
Elevation, completion of terraces with 00 %
waterproofing of the Building/Wing.
10 Installation of lifts, water pumps, Fire Fighting
Fittings and Equipment as per CFO NOC,
Electrical fittings to Common Areas, electro,
40 %
mechanical equipment, compliance to
conditions of environment/CRZ NOC, Finishing
to entrance lobby/s, plinth protection, paving of
areas appurtenant to Building/Wing, Compound
Wall and all other requirements as may be
required to Obtain Occupation/Completion
Certificate
TABLE – A
TOWER - D
(To be prepared separately for each Building/Wing of the Real Estate Project)
Sr. Tasks/Activity Percentage of work done
No.
1 Excavation 100 %
2 Zero Number of Basement(s) and Plinth 100 %
3 Zero Number of Podiums 00 %
4 Stilt Floor 100 %
5 Seven Number of Slabs of Super Structure 100 %
6 Internal walls, Internal Plaster, Floorings within
Flats/Premises, Doors and Windows to each of 38 %
the Flat/Premises
7 Sanitary Fittings within the Flat/Premises 30 %
8 Staircases, Lifts Wells and Lobbies at each Floor
level connecting Staircases and Lifts, Overhead
28 %
and Underground Water Tanks
9 The external plumbing and external plaster,
Elevation, completion of terraces with 22 %
waterproofing of the Building/Wing.
10 Installation of lifts, water pumps, Fire Fighting
Fittings and Equipment as per CFO NOC,
Electrical fittings to Common Areas, electro,
15 %
mechanical equipment, compliance to
conditions of environment/CRZ NOC, Finishing
to entrance lobby/s, plinth protection, paving of
areas appurtenant to Building/Wing, Compound
Wall and all other requirements as may be
required to Obtain Occupation/Completion
Certificate
TABLE – A
TOWER - E
(To be prepared separately for each Building/Wing of the Real Estate Project)
Sr. Tasks/Activity Percentage of work done
No.
1 Excavation 100 %
2 Zero Number of Basement(s) and Plinth 100 %
3 Zero Number of Podiums 00 %
4 Stilt Floor 100 %
5 Seven Number of Slabs of Super Structure 100 %
6 Internal walls, Internal Plaster, Floorings within
Flats/Premises, Doors and Windows to each of 45 %
the Flat/Premises
7 Sanitary Fittings within the Flat/Premises 35 %
8 Staircases, Lifts Wells and Lobbies at each Floor
level connecting Staircases and Lifts, Overhead
30 %
and Underground Water Tanks
9 The external plumbing and external plaster,
Elevation, completion of terraces with 25 %
waterproofing of the Building/Wing.
10 Installation of lifts, water pumps, Fire Fighting
Fittings and Equipment as per CFO NOC,
Electrical fittings to Common Areas, electro,
40 %
mechanical equipment, compliance to
conditions of environment/CRZ NOC, Finishing
to entrance lobby/s, plinth protection, paving of
areas appurtenant to Building/Wing, Compound
Wall and all other requirements as may be
required to Obtain Occupation/Completion
Certificate
TABLE – A
TOWER - F
(To be prepared separately for each Building/Wing of the Real Estate Project)
Sr. Tasks/Activity Percentage of work done
No.
1 Excavation 100 %
2 Zero Number of Basement(s) and Plinth 100 %
3 Zero Number of Podiums 00 %
4 Stilt Floor 100 %
5 Seven Number of Slabs of Super Structure 100 %
6 Internal walls, Internal Plaster, Floorings within
Flats/Premises, Doors and Windows to each of 45 %
the Flat/Premises
7 Sanitary Fittings within the Flat/Premises 35 %
8 Staircases, Lifts Wells and Lobbies at each Floor
level connecting Staircases and Lifts, Overhead
30 %
and Underground Water Tanks
9 The external plumbing and external plaster,
Elevation, completion of terraces with 25 %
waterproofing of the Building/Wing.
10 Installation of lifts, water pumps, Fire Fighting
Fittings and Equipment as per CFO NOC,
Electrical fittings to Common Areas, electro,
40 %
mechanical equipment, compliance to
conditions of environment/CRZ NOC, Finishing
to entrance lobby/s, plinth protection, paving of
areas appurtenant to Building/Wing, Compound
Wall and all other requirements as may be
required to Obtain Occupation/Completion
Certificate
TABLE – A
TOWER - G
(To be prepared separately for each Building/Wing of the Real Estate Project)
Sr. Tasks/Activity Percentage of work done
No.
1 Excavation 100 %
2 Zero Number of Basement(s) and Plinth 100 %
3 Zero Number of Podiums 00 %
4 Stilt Floor 100 %
5 Seven Number of Slabs of Super Structure 100 %
6 Internal walls, Internal Plaster, Floorings within
Flats/Premises, Doors and Windows to each of 45 %
the Flat/Premises
7 Sanitary Fittings within the Flat/Premises 35 %
8 Staircases, Lifts Wells and Lobbies at each Floor
level connecting Staircases and Lifts, Overhead
32 %
and Underground Water Tanks
9 The external plumbing and external plaster,
Elevation, completion of terraces with 30 %
waterproofing of the Building/Wing.
10 Installation of lifts, water pumps, Fire Fighting
Fittings and Equipment as per CFO NOC,
Electrical fittings to Common Areas, electro,
40 %
mechanical equipment, compliance to
conditions of environment/CRZ NOC, Finishing
to entrance lobby/s, plinth protection, paving of
areas appurtenant to Building/Wing, Compound
Wall and all other requirements as may be
required to Obtain Occupation/Completion
Certificate
TABLE – B
Internal & External Development Works in Respect of the entire Registered
Phase
Sr. Common areas and Proposed Percentage Remarks
Facilities Amenities of Work
No. (Yes/No)
Done
1 Internal Roads & Footpaths YES 00 % Local Authority
2 Water Supply YES 00 % V.M.S.S. Water
Supply
3 Sewerage (chamber, lines, Septic YES 00 % Local Authority
Tank, STP)
4 Storm Water Drains N.A. N.A. Local Authority
5 Landscaping & Tree Planting YES 00 % Local Authority
6 Street Lighting YES 00 % Local Authority
7 Community Buildings YES 00 % CLUB HOUSE
8 Treatment and disposal of sewage N.A. N.A. N.A.
and sullage water /STP
9 Solid Waste Management & Disposal N.A. N.A. N.A.
10 Water Conservation, Rain Water N.A. N.A. N.A.
Harvesting , Percolating Well/Pit
11 Energy Management N.A. N.A. N.A.
12 Fire Protection and Fire Safety N.A. N.A. N.A.
Requirements
13 Electrical Meter Room, Sub-station, YES 00 % Substation &
Receiving Station Receiving Station
Provided By Local
Authority
14 Use of Renewable Energy N.A. N.A. N.A.
15 CCTV Camera YES 00 % Local Authority
16 Letter Box N.A. N.A. N.A.
17 Others (Option to Add more) - - -

Yours Faithfully,
Signature & Name (IN BLOCK LETTERS) with Stamp of Architect
Council of Architects (COA) Registration No. CA/ /
Council of Architects (COA) Registration valid till (Date) / /

Vous aimerez peut-être aussi