Académique Documents
Professionnel Documents
Culture Documents
(234) 062-887482;
08028451593; 08054143288; E-mail: pauma1 @ paumaengineering.Com
SERVICE
BROCHURE
E-mail: paumaengineering@yahoo.com
(234) – 062-887482, 08028451593,
08054143288, 08068702323, 08023637599
VISIT OUR WEBSITE AT: 0 P.O.Box 4921, Kaduna, Kaduna State
w www.paumaengineering.com NIGERIA.
CONTENTS
PAGE
1.0 INTRODUCTION……………………..……………………………2
3.0 ACTIVITIES............................................................................3
3.1 Consultancy..........………………………………………………. 3
CERTIFICATES........................................ …………......................54
1
1.0 INTRODUCTION
We have a crop of highly qualified and experienced personnel whose experiences span over
three decades in highly reputable companies and parastatals like NEPA(PHCN), NNPC,
SPDC (SHELL), ITCC, DIZENGOFF, SIEMENS etc. Added to this is the fact that our
Engineering Personnel are highly rated by COREN and Nigerian Society of Engineers. They
are also members of reputable international engineering bodies such as IEE (UK) and IEEE
(USA). Our personnel stock also include seasoned professionals in the field of quantity
surveying, cost consultancy and project management.
2.0 REGISTRATION
We are duly registered with the Corporate Affairs Commission under the Companies and
Allied Matters act of 1990, with registration certificate No. 857523 of 1992. copies of this are
as indicated in section 4.0. We are also duly registered with Federal Ministry of Mines Power
and Steel on category 1 status to execute jobs on all voltage levels as required by law under
section 4 (P) of Electricity Ordinance Act CAP 57 (now CAP 106).
Our practice is strictly guided by the Code of Practice of the Council of Registered Engineers
of Nigeria (COREN) and Electricity Ordinance Act (CAP 57) of 1958.
3.0 SERVICES
Services offered by us include, but not limited to the followings:-
3.1 CONSULTANCY
Engineering System Studies and Analysis: which is computer based with more indept
evaluation of operational integrity and system reliability. Reliable computer programs has been
developed for reliability studies, fault studies Load-flow analysis, system forecast, protection
system analysis etc.
Electrical Power System Planning and Design: involving all voltage levels and all areas of
the Power System including Generation, Transmission and Distribution.
Power System Protection and Control: with specific reference to system configuration and
equipment design. Our specific computer analysis puts emphasis on load flow in radial and
2
interconnected systems, system fault simulation/analysis with a view to evolving reliable
system fault levels for dependable relay coordination, load forecast to cater for future
requirements and reliability prediction and analysis to adequately cater for future trouble
spots.
Energy Management Systems: which include system development for strategic energy
utilisation.
Process Control System Analysis and Design: including computer based evaluation of
process control systems.
A number of System Designs and Developments have been embarked on for both LV and
HV networks as follows:
➢ Complete 132/33/11/0.415KV System Planning and Design for New Kaduna Millenium
City.
3.2 CONSTRUCTION/INSTALLATION
A number of System Installations have been embarked on for both LV and HV networks
through the short span of our practice. These include:
3
➢ Design Construction and Installation of MV Panels IBBI, Kaduna; Chida
International Hotel, Abuja; AIT Corporate Headquarters, Abuja;
➢ Rehabilitation and Maintenance of 11KV Equipment at ABU Main Campus, Zaria; Bank
of the North Headquarters, Kano; NNPC (KRPC) Kaduna Power Plant.
➢ Reactivation of Vandalised U/G 11KV Armoured Aluminium Conductor for Julius Berger
at Ajaokuta Steel Plant.
4
➢ Reactivation of Tripping Units at NEPA (PHCN) Abuja Zone.
➢ Reactivation of damaged Underground cable for 90KW, 3.3KV electric motor at LAB,
KRPC Kaduna.
Apart from the above listed services, we are also engaged in procurement and supply of
HV/LV Electrical equipment as follows:
➢ Supply of 110/30V Tripping Units for Lilleker at ABUTH Shika and Kaduna State Water-
works, Kaduna; NEPA (PHCN) Zonal Headquarters, Abuja; ASAA Pyramid Holtel,
Kaduna; PHCN Zonal Headquarters, Port-Harcourt; Lower Usman Dam Abuja e.t.c.
➢ Supply of 5No ABB 11KV Switchgear Control Panels for Lilleker Brothers at Summit
Hills Calabar.
Apart from the above listed areas of operation, we are also engaged in training of technical
staff of companies and government parastatals such as NNPC, NEPA, UNIPETROL, BANK
OF THE NORTH etc in the following areas:
6
4.0 EXPERIENCE PROFILE
16. Protection System Study and System Study NEPA February, 2002
Analysis of Kano 33/11KV Kano
network.
17. Design and Installation of 7.5MVA System IBBI, Kaduna June, 2003
33/11KV Injection Substation at Installation
IBBI Plant, Kaduna.
18. Design and Installation of 2000A System Chida Hotel August, 2003
MV panels complete with Installation Abuja
Automatic Transfer Switch at
Chida International Hotel, Abuja.
48 Test & Commissioning of 150MVA, Substation Test Taleveras/TCN July 2017- 2018
330/132kV Power Transformer at &
Afam Power Station, Port-Harcourt, Commissioning
Nigeria.
11
TOOLS AND EQUIPMENT
12
Plot 7, Kachia Road(Dogara Ga Allah House), By Command Junction; P.O.Box 4921
Kaduna.-062/513404,08028451593. E-mail: pauma @ myway.com; Fax –
062/515795
1. SITE EQUIPMENT
13
- Mobile Vice (1 No)
- Table Vice (1 No)
14
2. WORKSHOP EQUIPMENT
- Heavy-duty, 3-phase fixed drilling Machine
- Heavy-duty fixed motorised cutting saw
- Heavy-duty fixed table filing machine*
- All-purpose fixed table vice
3. OFFICE EQUIPMENT
15
PERSONNEL
RESOURCES
16
5.0 PERSONNEL RESOURCE
Listed below is a brief profile on the key Resource personnel for the company:
1 Engr. Paul I. Audu: Holds a bachelor of engineering degree from Ahmadu Bello University
Zaria, 1980. Throughout his twenty-four years post-graduation field experience, he has
worked in many outstanding and reputable companies and parastatals in Nigeria. These
include successful career breakthrough in NNPC, NEPA, SHELL PETROLEUM DEV. CO. and
private consultancy. He successfully redesigned a number of injection substations in NEPA
Kaduna, Kano, Abuja and Kontagora. He also effectively conducted Power System analysis
and project supervision in SHELL, Warri. He is COREN registered engineer and also holds
some professional credentials like MNSE, MIEEE, AMIEE. He holds Mines and Power
Professional License Category 1. He has also acquired competence and tremendous
experience in the preparation of cost estimates, tender documents and project management.
He is the coordinating Group Project Manager for all projects and will be saddled with the
responsibility of ensuring that the assignment is conducted and implemented in accordance
with the Terms of Reference.
2. Meszticzky Istvan holds Electrical Wiring Installation Licence Category One RC-1244B
(200), Master of Trade (1985), Qualified Electrical Production Engineer (1985), Technician
Certificate (1980), Technical Secondary School (1974).
Mr. Steven started his career in Hungary in 1974 with DIGEP HUNGARY FACTORY, on
base 220/35/20/10/0.380KV Power Station Maintenance (HUNGARY). He moved to Nigeria
1993 as a Consultant to ITCC and participated in Rural and Urban electrification
projects in Kaduna, Bauchi, Katsina and Jigawa states. Position as: Site Supervisor, Project
Supervisor, Project Manager, Chief Engineer of Electrification, Technical Advisor,
and Project Consultant (NIGERIA).
Between 1999 and 2002 he was a Technical Adviser for Hungarian Embassy in Nigeria,
Surporting Technical Services for Nigerian Business Partners (Training, Maintenance,
Spare Parts Supply etc.)
3. Dam Lazarus Ahmadu: Engr. L.A. Dams holds a B. Eng. Degree in Electrical Engineering
from Ahmadu Bello University Zaria, Nigeria (1983). His professional career started at the
National Grains production Company (N.G.P.C) Limited – a grains producing and processing
firm in Kaduna, Nigeria where he was initially on the National Youth Service Corp (1983) and
later employed as a factory Engineer (1984). He was responsible for the operations and
maintenance of the Electrical/Mechanical Machines & Equipment. He spent four years at the
N.G.P.C Ltd during which he acquired enormous experience in Grain processing Technology
and Machinery.
17
He has been involved in the design and construction supervision of the electrical services of
domestic commercial and industrial buildings. He has also acquired competence in the
preparation of cost estimates, tender documents and project management.
He is registered with COREN and Nigerian Society of Engineers (NSE). He shall be Sub-
Group Manager in charge of planning and design.
5. Mrs. Maria C. Audu (B.A. Hons., LLB. A.B.U) is the Administrative Manager of PAUMA
Engineering consultants. She is a graduate of Ahmadu Bello University (June 1983) and holds
Bachelor of Arts degree in English Literature as well as LLB from the same institution (2006).
She had been involved in post-primary educational development in both Kaduna State and
Federal levels since 1984. She is presently pursuing a post graduate degree course in English
Literature at Ahmadu Bello University, Zaria. She is a principal partner and coordinates the
Administrative activities of the company.
She shall co-ordinate the sub-group activities for Project Administration.
6. Engr. Dikko M.A. Abubakar (B. Eng MNSE) is an Electrical engineer with twenty-three years
field experience on consultancy and construction services. He is a graduate of Ahmadu Bello
University (1980) and has been involved in numerous projects like electrification of 39 towns
and villages in Kwara State, integrated engineering services in Katsina and Kaduna as well as
design and installation of government house protects in Kaduna and Katsina State. Details are
in the Curriculum Vitae.
He is the Sub-group Manager in charge of System Evaluation.
7. IRO, CHIDI SUNDAY Holds B.E.N.G (Hons) in Electrical Engineering from University of Ilorin
and has had several work experiences in the field with PAUMA ENGINEERING
CONSULTANTS since graduation. Details are in the attached C.V.
He is responsible for System Data Coordination.
8. Olorunleke, Samuel Holds B.ED (TECHNICAL) and is our field supervisor in Control
System Installation, with special bias on SCADA Communication and control. He is our Field
Coordinator (Installations).
9. Elijah Adewumi Raji holds London C&G F.TECH. and PGD(Electrical Power) from BUK
Kano. He has worked for several years with NEPA/ PHCN as a transmission substation
Operator (TSO), Power System Protection Engineer (Distribution), Manager Distribution, Zaria
before retirement. He is the Protection and Control System Supervisor.
10. Godwin Ajodoh is the company’s Construction and Installation Coordinator. He has acquired
tremendous experience as an electrical supervisor in Arewa Textile Kaduna and several other
reputable companies before joining PAUMA Engineering in 2006. He has coordinated several
Installation and construction works in the company. These include: installation of distribution
SCADA pilot scheme at Abuja, installation of SCADA for Siemens in TCN 550/132/33KV
network nationwide, Maintenance and overhauling of all Electric Motors in KRPC, Kaduna,
construction and installation of 2000A LV Panel for AIT Headquarters, Abuja, Installation of
HV Capacitor Banks at Kaduna Waterworks, Bauchi waterworks and NTA headquarters,
Abuja,e.t.c.
18
11. Ologun Olusegun Emmanuel is a graduate of Abubakar Tafawa Balewa University (ATBU),
Bauchi and holds a B. Eng. Honours degree with Second Class Upper. He has been with
PAUMA ENGINEERING since 2006. Emmanuel has made significant contribution to the
company since joining fully as a Graduate Engineer. He is an invaluable material in System
Control and Software development. He is a team Leader.
12. Abdul Salami Onimisi holds a B. Eng. Degree with Second Class Upper from Federal
University of Technology, Minna. He has been with the company since 2006 and has worked
with us on Distribution SCADA installation in Abuja, Installation of SCADA for Siemen on
Transmission Network Nationwide and a host of Power system installations.
13. Cyprian Ifeanyi Okolo is a graduate of ATBU and has been with PAUMA Engineering since
2009. He holds a B. Eng. Degree in Electrical Engineering and has participated in several
design and installation jobs for the company, including reactivation of Control System for
KRPC Power Plant and Raw water intake, Construction of Auto-changeover Panel, Auto-fire
Panel for NALADO office complex.
14. Kingsley Uwalaka is a graduate of Anambra State University, Awka and has been with
PAUMA Engineering since 2009. He holds a B. Eng. Degree in Electrical Engineering and has
participated in several design and installation jobs for the company.
15. Daniel Azubuike holds London C&G Course “B” certificate in electrical engineering and has
worked with Power Construction and Engineering Co. Enugu, Eurafic Electric Co. Ltd., Lagos,
ITT Nig. Ltd, The Democrat & Reporter Newspapers as installation and Maintenance
technologist between 1974 and 1993. He was also specially trained on Cummings Generating
Set Operation & Maintenance in 1983.
19
ORGANISATIONAL CHART
20
SERVICES
21
1. INSTALLATION OF SCADA EQUIPMENT IN
ABUJA DISTRIBUTION PILOT PROJECT
The project involved the construction of the marshalling panel, wiring of the control panels in
the substations to the RTUs for command and indication link-up, interconnection of the control
and indication terminals to the 32DI and 16CO modules in the RTU, programming and
commissioning of the system. The overall layout of the substation infrastructures is shown
below.
The control center comprises a central computer with its related peripherals and communic ations equipment.
The system is capable of communicating over Radio channel using a protocol specifically adapted for this
type of communication.
The control system enables extensive control and monitoring of the remote sites via the Radio network.
The System is based on the MOSCAD equipment family. .
The system comprises of:
-20 Remote Stations.
-3 Control Centers
22
The screen shown below is the first screen that appears just after running SCAD A Application from the
desktop.The first screen is a Map of Abuja area where the RT Us are installed.
23
Clicking the site names will open the “Single Line” diagram of each site. RTU name will show red when under
communication failure while green when communication is OK.
Clicking “Garki Unit” from the “Function Key” will bring up the screen shown below:
Clicking on one of the sites in the right side of the screen(every screen) will bring up a single line diagram of
that substation. The structure of the whole substation is shown in the diagram below.
24
2. SIEMENS SCADA/EMS PROJECT IMPLEMENTATION
Not less than twenty-eight (28No) 330/132/33KV Transmission Substations were attended to
nationwide, including Akangba 330/132/33KV, Ikeja-west 132/33KV, Ogba 132/33KV, Ejigbo
132/33KV, e.t.c.
The job involved RTU Adaptation with existing substation control panels and outdoor
equipment as indicated in the block diagram below. In some cases at 330KV substations (like
Akangba) where the old type of SCADA exists with the marshalling kiosks, it is disconnected
and rewired.
COMM.
DATA LINK
COMMUNICATION
PANEL
The main components consists of RTU made up of the CPU, Digital Indication interface
(32DI), Command interface (32CO), Analogue interface (32AI) and Communication interface
connected as shown above.
Command Module (CO)
All CBs and tap-changer controls are connected to CO32 modules
Analogue Interface Module
All voltage and current transducers (active and reactive power measurements) are connected
to the AI32 modules
27
28
3. PARAMETERISATION & STATION ACCEPTANCE
TEST (SAT) FOR SIEMENS SUBSTATION
AUTOMATION SYSTEM AT WUYE DISTRICT, ABUJA
The purpose of this site.reception (SAT) was to test all the hardware and software solution
provided in accordance with specifications. This test procedure has all the steps leading to the
verification and control of the functioning of the system provided.
29
Due to a large number of Bays, test was processed by sampling. A test will be done on
switchgear per type and per voltage level. Every modification on the switchgear tested should be
reported to all other switchgears of the same type.
3. Fields;Applications
The main purpose was the commissioning of the DCS STATIONS "A" and "B" 33/11KV for ARAB
CONTRACTOR projects.
Scope of Works for Installation/Commissioning – Air force Base News Engineering Project
include:
1. Erection of Panels
2. Charging of Panels
3. Signal testing
4. Communication testing with relays
5. HMI testing
6. Alarm & event testing and
7. Final SAT as per document
The proposed Substation Automation System (SAS) for NDPHC, NIGERIA SAS system
consists of installation of OWS/EWS, Data Concentrators in control room.
The Data Concentrator configured from SIEMENS products range, SICAM 1703 ACP. The
SICAM 1703 ACP products is designed to cater to the specific requirements of power sector
/Rallway/Metfo links.
System Configuration
The Proposed system is as per the configuration below. Proposed SAS System consists of
OWS/EWS, Data Concentrator in Control room. Switchyard control room shall have one OWS
(Operator Work Station) and One Engineering workstation, One Data Concentrator with
hardwired and communication port to communicate with numerical relays on IEC61850
30
protocol. One GPS clock is provided for SAS system clock synchronization. Three links on
MODBUS RTU from Data Concentrator shall be provided to communicate with SEL Relays,
on 11KV panels and MFM. One link on IEC -101 will be provided to communicate with
gateway.
31
5. DEVELOPMENT OF KADUNA MILLENIUM CITY
ELECTRICAL INFRASTRUCTURES
Apart from installation and commissioning, we are also involved in system specification and
design as was the case with Kaduna Millenium City Electrical Infrastructures. We were
involved in the design of bulk power supply from Primary feeder supply down to end users, as
well as Station Automation Specification. The Design Summary and specifications are
illustrated in the diagrams below:
2x
15MVA,33/11K
V
33KV CABLE
33KV O/H LINE
33KV INCOMING
LINE
33/11KV INJECTION
2x
SUBSTATION
7.5MVA,33/11K H / ANGLE POLES
2x V
15MVA,33/11K
V 2x
15MVA,33/11K
V
PROPOSED 33KV
PRIMARY ROUTE INTER-
CONNECTIONS USING
U/G CABLES OR
OVERHEAD LINES
32
M
P13 M M P13
9 9 LEGEND
OPERAT
CIRCUIT BREAKER
OR’S EVENT M M 33KV, 3-, 50HZ DOUBLE BUS M M
M MOTORISED
TERMINA PRINT
ISOLATOR
CPU L ER EARTH SWITCH
Pictur VOLTAGE
eM
M
TRANSFORMER
M M M M M M M
OPTICAL CURRENT TRF.
SYSTEM showi POWER/DIST.
TRANSFORMER
BUS
M
ng M M M
BAY COMPUTER
groun
d floor TR 1
of the P13
9
P139
M
left- P13 M M SINGLE-LINE DIAGRAM FOR
33/11KV INJECTION
wing 9 SUBSTATION TYPE 1
M M M M (7 OUTGOING RING FDRS)
of the
11KV, 3-, 50HZ DOUBLE BUS
seven-
M M M M M M M M M Mfloor M M M M M M M M M M M M M M M M M
M M
buildi
M M M M M ng
M M
P2
32
M M M M M M M
P1 P1 P1 P1 P1 P1 P1 BUS P1 P1 P1 P1 P1 P1
39 39 39 39 39 39 39 COUPLER
STN. CONT.. 39 39 39 39 39 39
RING 1A RING 2A RING 3A RING 4A RING 5A RING 6A RING 7A UNIT RING 7B RING 6B RING 5B RING 4B RING 3B RING 2B RING 1B
RING A RING B
Bulk Power Source
R Sub-transmission
T
U
Circuits
Distribution
Substations
H
A C
R
D
C
O
P
Y
LOOP NO L-X-0Y
I
-
Distribution
Substations
33
6. EXPERIENCE & TRACK RECORD ON INTELLIGENT CONTROL PANELS
We have successfully specified, built and installed a number of intelligent power control units in
several places as indicated below.
34
DIGITAL MODULES CONNECTION DIAGRAM
PANEL PC
Power Supply
+24V D.C.
35
System operation
The PC has a touch screen facility, so there is no need for keyboard. On the main
screen is shown a vertical cross section of the building under control. Two alarm
conditions are being monitored per each floor, the fire alarm and the flow alarm.
Each of these has different alarm indication on the screen, and is reacted to differently
by the system. When a fire alarm condition is detected for example, the green
rectangle indicator will turn to red with flashing “Alarm” written on the face instead on
the usual none flashing “Safe” written on it. A less audible alarm siren will sound at this
juncture. But if the flow detector alarm is detected, then in addition to the flashing
indicator, will be shown a symbol of a flame .
The alarm siren will sound in two stages, the second stage much louder than the first.
This arrangement was predicated on the fact the fire alarm, being smoke detection
based could easily be triggered by a smoke coming from sources other than fire. In
such a case, the alarm condition will not initiate the fire control mechanism. If however
both fire and flow alarm conditions are detected simultaneously, then fire control
mechanism will initiate a chain of actions geared towards an effective combat of the
fire.
36
On the initiation of the second stage alarm, Fire Control Mechanisms will be activated
with the starting of the fire pump to pump water to the Fire Sprinkler Nozzles on the
particular floor in question. This is followed by starting of the Bore-hole pump to
replenish the water in the underground tank.
Other crucial conditions automatically activated by the Panel PC are as follows:
- Shutdown of the air-conditioning system
37
It is operated automatically from RGK60 AMF module that senses the normal supply
voltage and/or frequency, comparing it with a set value and decides whether the power
supply quality is adequate or not for a required operation. If otherwise an instruction is
transmitted to generator control unit and the engine is automatically started for an
alternate supply from the standby generator.
Safety of operation is guaranteed by a set of electrically interlocked contactors, relays
and timers properly coordinated in the AMF module to ensure full isolation in the
event of failures.
The AC Distribution Panel is an intelligent unit built around the versatile multipurpose
industrial grade control module called MIAC (Matrix Industrial Automotive
Controller) usually employed in controlling a wide range of different electronic
systems.
The aim is to be able to integrate the control panel into a universal state-of-the-art
Building Management System ( BMS ), which is a computer-based control system
installed in buildings that controls and monitors the building’s mechanical and electrical
equipment such as ventilation, lighting, power systems, fire systems, and security
systems; consisting of software and hardware, with the software program, usually
configured in a hierarchical manner.
38
THE MIAC
The Matrix Industrial Automatic Controller (MIAC) is an industrial grade control unit
which can be used to control a wide range of different electronic systems. It is
designed to operate off 12V or 24V. It has 8 analogue and 8 digital inputs, four (4) high
current relay outputs and four (4) motor outputs. The unit is programmed directly from
a PC’s VSB port and is compatible with flow code graphical programming language.
The plant generators are automatically selected in the event of outage on the basis
of available operational regime.
OPERATIONAL CRITERIA
In order to effectively harness the advantages of modern technology in enhancing
uninterrupted production with reliable power supply, we intend to utilize a full-fledged
control system that operates on three functional regimes using Programmable Logic
Controllers with precise control capabilities built around Micro-controllers.
These include:
1. Running the entire plant power system on full automated operation using
available plant characteristics to establish uninterrupted power transfer when there
is a change in source supply.
39
3. Inhibiting all automated systems and allowing manual system switching.
To achieve the above listed criteria, selection shall be done in two stages –
FUNCTION selection and MODE selection stages. Function selection is determined
by plant operational regimes while Mode selection is based purely on power system
configuration.
FUNCTION SELECTION
(a) STAGE 1- Full Auto:
This stage is selected to implement a fully automated power transfer system
depending on plant operational exigency.
When this function is selected, the system controller searches for applicable
MODE of transfer relevant to available operational regime and automatically
implements the necessary power system transfer.
40
41
42
6.5 AUTOMATED DUAL POWER TRANSFER CONFIGURATION FOR
PRIORITIZING GENERATOR ASSIGNMENT AT NALADO HEAD
OFFICE, CENTRAL BUSINESS DISTRICT - ABUJA.
This design was made, built and integrated with 1.2 above. It was intended
to prioritize operation of two generators in the premise (750KVA and
150KVA) when the mains power goes off, such that duty is assigned to one
generator at a time, depending on available load at the time of power
transfer. It was designed and programmed in such a way that the 750KVA
generator does not come on stream as long as the load is below 150KVA.
Whenever the available load exceeds 150KVA, G1 (750KVA) is started
automatically and the load transferred from G2 (150KVA) to G1. The
unused set is also switched off automatically as soon as load is transferred
successfully.
The operation is built around Deep Sea ATS Module DSE 705 and Matrix
Industrial Automatic Controller (MIAC). The MIAC module is programmed
to do the Load Monitoring and Duty Assignment while the DSE 705 does
the Power Transfer.
43
Indication on MIAC with MAINS 'OFF'
and Power Generator 2 'On Duty'
44
45
SUBSTATION PROJECTS
46
33/11KV ITC/TDN PROJECTS
INTERNAL LAYOUT OF THE ACTIVE SIEMENS’ RTU INTERNAL WIRING OF THE SIEMENS’ COMMUNICATION
IN 330KV CONTROL ROOM 49 PANEL IN 330KV CONTROL ROOM
INSTALLATION OF 33KV TRANSF. BREAKER/VTs NEWLY INSTALLED 11KV SCHNEIDER SF6 SWITCHGEARS
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79