SL.NO. ITEM NO.

L B H Q UNIT

Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm
1 depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up
m, disposed earth to be levelled and neatly dressed.
All kinds of soi
LONG WALL
GRID 1,2,4 3 8.3 0.8 0.55 10.956
GRID 3 1 2.48 0.8 0.55 1.0912
SHORT WALL 0
GRID A,B,D 3 4.59 0.8 0.55 6.0588
GRID C 1 1.85 0.8 0.55 0.814
TOTAL QUANTITY 18.92 M3
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering
2 work up to plinth level:
1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
LONG WALL
GRID 1,2,4 3 8.3 0.8 0.1 1.992
GRID 3 1 2.48 0.8 0.1 0.1984
SHORT WALL 0
GRID A,B,D 3 4.59 0.8 0.1 1.1016
GRID C 1 1.85 0.8 0.1 0.148
TOTAL QUANTITY 3.44 M3

3 Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6
cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:
Cement mortar 1:6 (1 cement : 6 coarse sand
LONG WALL
1,2,4 3 8.1 0.6 0.45 6.561
GRID 3 1 2.28 0.6 0.45 0.6156
SHORT WALL 0
GRID A,B,D 3 4.79 0.6 0.45 3.8799
GRID C 1 2.05 0.6 0.45 0.5535
TOTAL QUANTITY 11.61 M3

Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6
4 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:
Cement mortar 1:6 (1 cement : 6 coarse sand
LONG WALL
1,2,4 3 7.95 0.45 0.35 3.756375
GRID 3 1 2.13 0.45 0.35 0.335475
SHORT WALL
GRID A,B,D 3 4.94 0.45 0.35 2.33415
GRID C 1 2.2 0.45 0.35 0.3465
TOTAL QUANTITY 6.7725 M3
Providing and laying in position specified grade of reinforced cement concrete in plinth,including the cost of cente
5 shuttering, all cost of materials and all labour charges etc, but excluding the cost of reinforcement.
1:1.5:3 ( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
LONG WALL
1,2,4 3 7.8 0.3 0.1 0.702
GRID 3 1 1.98 0.3 0.1 0.0594
SHORT WALL
GRID A,B,D 3 5.09 0.3 0.1 0.4581
GRID C 1 2.35 0.3 0.1 0.0705
TOTAL QUANTITY 1.29 M3
6 EARTH FILLING
BED 1 1 2.35 2.85 0.45 3.013875
BED 2 1 2.35 2.85 0.45 3.013875
KITCHEN 1 2.35 2.25 0.45 2.379375
TOILET 1 1.22 1.08 0.45 0.59292
HALL 1 2.35 3.96 0.45 4.1877
PASSAGE 1 0.55 1.38 0.45 0.34155
TOTAL QUANTITY 13.5293 M3

7 Solid masonry using pre cast solid blocks (factory made) of size 30x20x15cm or nearest available size confirming to
2185 part I of 1979 for super structure up to floor two level with thickness 15cm in : CM 1:6 ( 1 cement : 6 coarse s
etc complete
LONG WALL
1,2,4 3 7.65 0.15 2.85 9.811125
GRID 3 1 1.83 0.15 2.85 0.782325
SHORT WALL
GRID A,B,D 3 5.24 0.15 2.85 6.7203
GRID C 1 1.53 0.15 2.85 0.654075
STEP 4 1 0.25 0.15 0.15
PARAPET
LONG WALL 2 6.04 0.1 0.6 0.7248
SHORT WALL 2 7.75 0.1 0.6 0.93
TOTAL QUANTITY 19.77263
DEDUCTIONS
D1 2 1 0.15 2.1 0.63
D2 2 0.9 0.15 2.1 0.567
D3 1 0.75 0.15 2.1 0.23625
O1 1 0.9 0.15 2.1 0.2835
O2 1 1.53 0.15 0.75 0.172125
W2 4 1 0.15 1.5 0.9
W3 1 1.5 0.15 1.5 0.3375
KW 1 1 0.15 1 0.15
V 1 0.6 0.15 0.45 0.0405
DEDUCTED QUANTITY 3.316875
NET QUANTITY 16.45575 M3
8 Providing and laying in position specified grade of reinforced cement concrete in lintel,including the cost of center
shuttering, all cost of materials and all labour charges etc, but excluding the cost of reinforcement.
1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
LONG WALL
1,2,4 3 7.65 0.15 0.15 0.516375
GRID 3 1 1.83 0.15 0.15 0.041175
SHORT WALL
GRID A,B,D 3 5.24 0.15 0.15 0.3537
GRID C 1 1.53 0.15 0.15 0.034425
TOTAL QUANTITY 0.945675 M3
BERTH 1 2.4 0.5 0.06 0.072
KITCHEN SLAB 1 3.9 0.6 0.06 0.1404
TOTAL QUANTITY 0.2124 M3
Providing and laying in position specified grade of reinforced cement concrete in sunshade,including the cost of
9 centering , shuttering, all cost of materials and all labour charges etc, but excluding the cost of reinforcement.
1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
FRONT 1 5.54 0.6 0.1 0.3324
W2 4 1.6 0.6 0.1 0.384
W3 1 2.1 0.6 0.1 0.126
KW 1 1.6 0.6 0.1 0.096
V 1 1.2 0.6 0.1 0.072
KITCHEN SIDE 1 3.15 0.6 0.1 0.189
TOTAL QUANTITY 1.1994 M3

10 Providing and laying in position specified grade of reinforced cement concretein slab,including the cost of centerin
shuttering, all cost of materials and all labour charges etc, but excluding the cost of reinforcement.
1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
R.C.C SLAB 1 5.94 8.05 0.1 4.7817
TOTAL QUANTITY 4.7817 M3
11 Reinforcement for R.C.C including cutting, bending, laying in the correct position etc. complete
BELT 1.29M3 @ 40KG/M3 51.6
LINTEL 0.9468 @ 80KG/M3 75.744
SUNSHADE 1.1994 @ 80KG/M3 95.952
ROOF SLAB 4.7817 @ 90KG/M3 430.353
BERTH AND KITCHEN SLAB 0.2124 @ 40 KG/M3 8.496
TOTAL QUANTITY 662.145 KG

11 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering
work up to plinth level:
1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
BED 1 1 2.35 2.85 0.075 0.502313
BED 2 1 2.35 2.85 0.075 0.502313
HALL 1 2.35 2.25 0.075 0.396563
KITCHEN 1 1.22 1.08 0.075 0.09882
TOILET 1 2.35 3.96 0.075 0.69795
PASSAGE 1 0.55 1.38 0.075 0.056925
TOTAL QUANTITY 2.254883 M3
12 Plastering with 1:4, 12mm thick one coat including all cost of materials and all labour charges etc complete
INSIDE WALL
BED 1 1 11 3 33
BED 2 1 11 3 33
KITCHEN 1 9.8 3 29.4
TOILET 1 5.8 3 17.4
HALL 1 13.22 3 39.66
PASSAGE 1 5.06 3 15.18
167.64
DEDUCTIONS
D1 2 1 2.1 4.2
D2 4 0.9 2.1 7.56
D3 2 0.75 2.1 3.15
W2 4 1 1.5 6
W3 1 1.5 1.5 2.25
KW 1 1 1 1
V 1 0.6 0.45 0.27
O1 2 0.9 2.1 3.78
O2 2 1.53 0.75 2.295
DEDUCTED QUANTITY 30.505
INSIDE NET QUANTITY 137.135 M2
OUTSIDE WALL
OUTSIDE WALL 1 26.38 3.8 100.244
SUNSHADE 1 15.19 1.3 19.747
ROOF 1 7.85 5.74 45.059
STEP (TREAD) 4 1 0.25 1
STEP (RISE) 6 1 0.15 0.9
STEP (SIDE) 12 0.25 0.15 0.45
PARAPET
LONG WALL 2 8.05 1.3 20.93
SHORT WALL 2 5.54 1.3 14.404
202.734
DEDUCTIONS
D1 2 1 2.1 4.2
W2 4 1 1.5 6
W3 1 1.5 1.5 2.25
V 1 0.6 0.45 0.27
KW 1 1 1 1
DEDUCTED QUANTITY 13.72
OUTSIDE NET QUANTITY 189.014 M2
GRAND TOTAL 326.149 M2

12 Floor finishing with cement mortar of 1:4 with a neat floating cement coat mixed with red oxide and finishing smo
etc complete as per the directions of the Engineer in charge
BED 1 1 2.5 3 7.5
BED 2 1 2.5 3 7.5
HALL 1 2.5 4.11 10.275
KITCHEN 1 2.5 2.4 6
TOILET 1 1.37 1.53 2.0961
PASSAGE 1 1 1.53 1.53
TOTAL QUANTITY 34.9011 M2
KITCHEN SLAB PLASTERING 1 3.9 1.26 4.914
BERTH PLASTERING 1 2.4 1.06 2.544
42.3591 M2
13 Plastering with 1:3, 9mm thick one coat including all cost of materials and all labour charges etc complete
BED 1 1 2.5 3 7.5
BED 2 1 2.5 3 7.5
HALL 1 2.5 4.11 10.275
KITCHEN 1 2.5 2.4 6
TOILET 1 1.37 1.53 2.0961
PASSAGE 1 1 1.53 1.53
TOTAL QUANTITY 34.9011 M2
14 WHITE WASHING
TOTAL QUANTITY 361.0501
DEDUCTED QUANTITY 1 1.53 1.37 1.8 2.466
NET QUANTITY 358.5841 M2
15 Dad doing of with ceramic tiles including all cost of material and labour charges etc complete
BATHROOM FLOOR 1 1.53 1.37 2.0961
BATHROOM WALL 1 5.8 1.8 10.44
TOTAL QUANTITY 12.5361 M2
RATE AMOUNT

s over areas (exceeding 30 cm in


th, lead up to 50 m and lift up to 1.5

187.3 3543.716
st of centering and shuttering - All

6659.456 22908.52864

g up with cement concrete 1:6:12 (1


h level with:

5897.615 68471.31015

g up with cement concrete 1:6:12 (1


h level with:

5897.62 39941.63145
nth,including the cost of centering ,
reinforcement.

9442.961 12181.41969

est available size confirming to IS


CM 1:6 ( 1 cement : 6 coarse sand)

7625.254 125479.27351
tel,including the cost of centering ,
reinforcement.

9442.96 8929.971198

9442.96 2005.684704
nshade,including the cost of
the cost of reinforcement.

b,including the cost of centering ,


reinforcement.

. complete

st of centering and shuttering - All

6659.46 15016.299813
ur charges etc complete

th red oxide and finishing smooth


0
charges etc complete

complete
SL.NO. ITEM Q UNIT RATE AMOUNT

Earth work in excavation by mechanical means


(Hydraulic excavator)/manual means over areas
1 (exceeding 30 cm in depth, 1.5 m in width as well
as 10 sqm on plan) including disposal of
excavated earth, lead up to 50 m and lift up to 1.5
m, disposed earth to be levelled and neatly
dressed.
All kinds of soil 18.92 M3 187.3 3543.716

2 Providing and laying in position cement concrete


of specified grade excluding the cost of centering
and shuttering - All work up to plinth level:
1:4:8 (1 cement : 4 coarse sand : 8 graded stone
aggregate 40 nominal size) 5.6948825 M3 6659.46 37924.842

Random rubble masonry with hard stone in


3 foundation and plinth including levelling up with
cement concrete 1:6:12 (1 cement : 6 coarse
sand : 12 graded stone aggregate 20 mm nominal
size) up to plinth level with:
Cement mortar 1:6 (1 cement : 6 coarse sand 18.3825 M3 5897.2 108405.28

4 Filling available excavated earth (excluding rock)


in trenches, plinth, sides of foundations etc. in
layers not exceeding 20 cm in depth,
consolidating each deposited layer by ramming
and watering, lead up to 50 m and lift up to 1.5 m 13.529295 M3 187

Providing and laying in position specified grade of


5 reinforced cement concrete including the cost of
centering , shuttering, all cost of materials and all
labour charges etc, but excluding the cost of
reinforcement.
1:1.5:3 ( 1 cement : 1.5 coarse sand : 3 graded
stone aggregate 20 mm nominal size)
Belt 1.29 M3
Lintel 0.94568 M3
Sunshade 1.1994 M3
Roof slab 4.7817 M3
kitchen Slab 0.104 M3
Berth 0.072 M3
TOTAL 8.39278 M3 10167.13 85330.485
6 Reinforcement for R.C.C including cutting,
bending, laying in the correct position etc.
complete
BELT @ 40KG/M3 1.29 KG
LINTEL @ 80KG/M3 0.9468 KG
SUNSHADE @ 80KG/M3 1.1994 KG
ROOF SLAB @ 90KG/M3 4.7817 KG
BERTH AND KITCHEN SLAB @ 40 KG/M3 0.2124 KG
TOTAL QUANTITY 8.4303 KG

Solid masonry using pre cast solid blocks (factory


made) of size 30x20x15cm or nearest available
7 size confirming to IS 2185 part I of 1979 for super
structure up to floor two level with thickness
15cm in : CM 1:6 ( 1 cement : 6 coarse sand) etc
complete 16.45575 M3 7625.25

8 Plastering with 1:4, 12mm thick one coat


including all cost of materials and all labour
charges etc complete 326.149 M2

Plastering with 1:3, 9mm thick one coat including


9 all cost of materials and all labour charges etc
complete 34.9011 M2

10 Floor finishing with cement mortar of 1:4 with a


neat floating cement coat mixed with red oxide
and finishing smooth etc complete as per the
directions of the Engineer in charge 34.9011 M2
11 KITCHEN SLAB WITH RED 4.914 M2
12 BERTH PLASTERING 2.544 M2
13 WHITE WASHING 361.1281 M2

Dad doing of floor with ceramic tiles including all


4 cost of material and labour charges etc complete
(Bathroom only) 12.5361 M2
15 JOINERY DETAILS
SS