Académique Documents
Professionnel Documents
Culture Documents
DETAILED ESTIMATE
Mandal : #REF!
Sub-Division : Maheswaram
2
DETAILED DATAS S S R - 2010-11
1 2 3 4 5
BLD-CSTN-2-1 1 Earthwork in excavation for structures as per drawing
and technical specifications Clause 305.1 including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious material and
disposal upto a lead of 50 m, dressing of sides and
bottom and backfilling in trenches with excavated
suitable material as per Technical Specification 305
MORD / 304 MORTH
Unit : 1 cum
Taking output : 10 cum
a) Labour
Mazdoor ( Unskilled) No 3.64 #REF!
Add 75% for foundations Cum 0.75 #REF!
Seigniorage charges Cum 10.00 22.00
Cost for 10 cum
Add 14% overhead charges, Contractor profit #REF! #REF!
Rate per 1 cum
Rate per 1cum Rs
BLD-CSTN-2-4 1 Ordinory Rock not requireing blasting ManualMeans
Upto 3.00 mdept
Unit : 1 cum
Taking output : 10 cum
a) Labour
Mazdoor ( Unskilled) No 5.20 #REF!
Add 75% for foundations Cum 0.75 #REF!
Seigniorage charges Cum 10.00 22.00
Cost for 10 cum
Add 14% overhead charges, Contractor profit #REF! #REF!
Rate per 1 cum
Rate per 1cum Rs
BLD-CSTN-2-4 1 Ordinory Rock not requireing blasting Mechanical
Means Upto 3.00 mdept
Unit : 1 cum
Taking output : 180 cum
a) Labour
Mazdoor ( Unskilled) No 6.24 #REF!
b) Machinory
Hydraulic Excavator Hr 6.00 1808.50
Add 75% for foundations Cum 0.75 #REF!
Seigniorage charges Cum 10.00 22.00
Cost for 10 cum
Add 14% overhead charges, Contractor profit #REF! #REF!
Rate per 180 cum
Rate per 1cum Rs
Page 2 of 92
3
PSSR 24 A)Cutting road surface including stacking of excavated 10.00 1.00 372.00
materials for pipe line trench work.
Add 14% overhead charges, Contractor profit 372.00 #REF!
Rate per 10 Sqm
Rate per 1 Sqm Rs
PSSR 24 B) Cutting open C.C. road surface 1.00 1.00 1035.00
Add 14% overhead charges, Contractor profit 1035.00 #REF!
Rate per 1 cum
BLD-CSTN-2-8 2 Supplying and filling sand in trenches ,sides of the
foundations and basement with initial lead in layers
not exceeding 15 cm thick consolidatiing each
depposited layer by watering and rampping including
cost and conveyance of water to work site and all
operational incidental ,labour charges hire charges and
T & O Complete for finished item APSS 309 &310)
Unit : 1 cum
Taking output : 1 cum
a) Labour
Mazdoor ( Unskilled) No 0.31 #REF!
Sand for filling Cum 1.00 3018.84
Unit : 1 cum
Taking output : 6 cum
a) Labour
Mazdoor ( Unskilled) No 3.12 #REF!
Gravel for filling Cum 6.00 238.65
Page 3 of 92
4
Unit= 1 rmt
vi 250 mm dia
a) Labour
Mason 1st class day 1.620 #REF!
Mason 2 class
nd day 3.780 #REF!
b) Material
Rubber rings conforming BIS 5382/1985 each 50.000 59.00
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 100.000 0.00
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials
needed for testing (as per Sub Analysis 2 A)
Page 4 of 92
5
Page 5 of 92
6
BMW-A.-32
Supply of SWG SP-3 pipe conforming to ISI 651 1 1.00 306.00
- 6" dia (152.4mm)
Page 6 of 92
7
Page 7 of 92
8
Page 8 of 92
9
Page 9 of 92
10
(d) Add for water charges @ 1% on Labour & Testing #REF! 0.01
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit #REF! #REF!
(g) Cost for 30 m (e+f)
Rate per metre = g/30
vi 300 mm dia
(a) Labour
Mason 1st class day 1.500 #REF!
Mason 2nd class day 3.500 #REF!
Man mazdoor day 6.000 #REF!
Woman mazdoor (Water carrier) day 1.500 #REF!
b) Material
300 mm dia SW pipe 60cm long each 50.000 0.00
Cement for 50 joints =0.045 cum t 0.194 4816.45
Sand = 0.045 cum cum 0.136 3359.35
Spun yarn = 0.09x50=4.50 kgs 18.000 90.00
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing #REF! 0.01
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit #REF! #REF!
(g) Cost for 30 m (e+f)
Rate per metre = g/30
vii 350 mm dia
(a) Labour
Mason 1st class day 1.650 #REF!
Mason 2nd class day 3.850 #REF!
Man mazdoor day 7.000 #REF!
Woman mazdoor (Water carrier) day 1.750 #REF!
b) Material
350 mm dia SW pipe 60cm long each 50.000 0.00
Cement for 50 joints =0.045 cum t 0.225 4816.45
Sand = 0.045 cum cum 0.159 3359.35
Spun yarn = 0.09x50=4.50 kgs 21.000 90.00
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing #REF! 0.01
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit #REF! #REF!
(g) Cost for 30 m (e+f)
Rate per metre = g/30
viii 400 mm dia
(a) Labour
Mason 1st class day 1.800 #REF!
Mason 2 class
nd day 4.200 #REF!
Man mazdoor day 8.000 #REF!
Woman mazdoor (Water carrier) day 1.750 #REF!
b) Material
400 mm dia SW pipe 60cm long each 50.000 0.00
Cement for 50 joints =0.045 cum t 0.256 4816.45
Sand = 0.045 cum cum 0.181 3359.35
Spun yarn = 0.09x50=4.50 kgs 24.000 90.00
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing #REF! 0.01
Charges
(e) Total = c+d
Page 10 of 92
11
Page 11 of 92
12
C. LABOUR:
Page 12 of 92
13
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 #REF!
Grand Total Rs
BLD-CSTN-1-8 9 Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement kg. 180.00 4816.45
Sand (including 5% wastage) cum 1.05 3359.35
Seigniorage charges for sand cum 1.05
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 #REF!
Grand Total Rs
BLD-CSTN-3-5 11 Plain Cement concrete (1:4:8) using 40 mm metal with
concrete mixture. All work upto plinth level.
Unit = 1cum
A. MATERIALS:
Cement kg 162.00 4816.45
Coarse aggregate 40 mm cum 0.90 3287.52
Fine aggregate (Sand) cum 0.45 3359.35
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 304.50
C. LABOUR:
Mason 1st class day 0.10 #REF!
Mazdoor (unskilled) day 1.39 #REF!
Page 13 of 92
14
Grand Total
Ground Floor
Unit = 1 cum
A. MATERIALS:
BMT- No of blocks required for one cum of Masonry Nos 110.000 12286.93
A.07
Amount Rs.
#REF!
#REF!
220.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
220.00
#REF!
#REF!
#REF!
#REF!
#REF!
10851.00
#REF!
220.00
#REF!
#REF!
#REF!
#REF!
Page 15 of 92
16
Amount Rs.
372.00
#REF!
#REF!
#REF!
1035.00
#REF!
#REF!
#REF!
3018.84
#REF!
#REF!
#REF!
#REF!
1431.90
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Page 16 of 92
17
Amount Rs.
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
2950
0.00
#REF!
0
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
3040
0.00
Page 17 of 92
18
Amount Rs.
#REF!
0
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
4000
0.00
#REF!
0
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
4920
0.00
#REF!
0
#REF!
#REF!
#REF!
#REF!
210.00
#REF!
#REF!
Page 18 of 92
19
Amount Rs.
306.00
#REF!
#REF!
542.00
#REF!
#REF!
823.00
#REF!
#REF!
1150.00
#REF!
#REF!
1461.00
#REF!
#REF!
1682.00
#REF!
#REF!
782.67
369.53
4950.00
2741.20
0.00
8843.40
290.14
Page 19 of 92
20
Amount Rs.
#REF!
#REF!
602.06
272.11
3937.50
2741.20
0.00
7552.87
247.80
#REF!
#REF!
481.65
218.36
3150.00
2741.20
0.00
6591.21
216.25
#REF!
#REF!
361.23
162.53
1575.00
2741.20
0.00
4839.96
Page 20 of 92
21
Amount Rs.
158.79
#REF!
#REF!
240.82
109.18
1125.00
2741.20
0.00
4216.20
138.33
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
0.00
313.07
151.17
405.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
0.00
467.20
228.44
Page 21 of 92
22
Amount Rs.
810.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
0.00
626.14
305.70
1080.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
0.00
703.20
342.65
1215.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
0.00
780.26
379.61
1350.00
#REF!
Page 22 of 92
23
Amount Rs.
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
0.00
934.39
456.87
1620.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
0.00
1083.70
534.14
1890.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
0.00
1233.01
608.04
2160.00
#REF!
#REF!
#REF!
Page 23 of 92
24
Amount Rs.
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
0.00
#REF!
#REF!
2430.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Page 24 of 92
25
Amount Rs.
1405.06
206.32
210.55
371.58
2311.90
3527.32
Page 25 of 92
26
Amount Rs.
#REF!
#REF!
1733.92
3527.32
#REF!
#REF!
1155.95
3527.32
#REF!
#REF!
866.96
3527.32
#REF!
#REF!
780.26
2958.77
1511.71
304.50
#REF!
#REF!
Page 26 of 92
27
Amount Rs.
#REF!
#REF!
#REF!
#REF!
1324.52
1612.49
1775.26
1010.82
312.98
0.84
#REF!
#REF!
#REF!
1351.56
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Page 27 of 92
Laying of Under Ground Sewerage Pipe Line at Indrareddy Nagar of GP Bandlaguda MP Rajendranagar
Initial Cost Initial Cost Initial UP to 5 Km Lead Rate beyond Diffe cost of Cement Diffe cost of Total Cost Over Head
Sno Description of Pipes Lead for Pipe Lead Charges Initial Cost
of Cement of Steel Lead Charges 5Km @0.59% Steel @1% of Pipe/RM Charges@ 14%
1 300 mm dia SS Pipes Np3 Class 4400.00 #REF! 5.00 45.00 31.80 1.00 71.80 976.00 40.31 #REF! #REF!
2 450 mm dia SS Pipes NP3 Class #REF! #REF! 5.00 45.00 46.50 2.20 134.50 1508.00 #REF! #REF! #REF!
3 600mm dia SS Pipes NP3 Class #REF! #REF! 5.00 45.00 69.40 3.30 201.40 2412.00 #REF! #REF! #REF!
SWG Pipes
Asst.Exe.Engineer Dy .Executive.Engineer
PRI Shamshabad PRI SD Rajendranagar
Laying of Under Ground Sewerage Pipe Line at Indrareddy Nagar of GP
Bandlaguda MP Rajendranagar
Supply of SWG SP-1 pipe conforming to ISI 651 -of Different dias including Lowering and laying in ready made trench
true to alignment and gradient, jointing, and testing of stone ware pipes including cost of jointing material such as
cement mortar (1:1) proportion and hemp yarn but excluding cost and conveyance of pipe. (Reference to
specifications BIS No. 6530/72) as per techinical specification of revised data PHE-LJSW-13
Rate / 30M 150mm Dia 200 mm Dia 250 mm Dia 300 mm Dia
Cost of sand
Laboue Charges
Extra on Labour
Component
Asst.Exe.Engineer
PRI Shamshabad
31
DETAILED DATA FOR MAN H OLES WITH FLY ASH B R IC K S
SSR 2014-15
Index-code S No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6
1 Constructon of 0.75 M Circular Sewer Man hole of
0.75 mts x 0.55 m of 0.75 M depths with Fly Ash
bricks in cm 1:6 prop and corbelling too including cc
bed ( 1: 4 : 8 ) prop using 40 mm gauge HG Metal 0.10
mt thick and CC (1:2:4) Prop benching /
chanelling,internal plastreng with 20 mm thick cm 1:4
and External Plasterng with 12mm thick CM (1:4)
with fine rendering including cost and fixing of CI
steps and fixing FC/ CI cover and frame but excluding
the cost of cover and frame, including the cost and
conveyance of all materials at site complete and curing
for 21 days complete all taxes seignarage charges as
per specification etc complete.
Page 31 of 92
32
Index-code S No Description Unit Quantity Rate Rs. Amount Rs.
For Metal Cum 0.219 75.00 16.40
For Sand Cum 0.277 90.00 24.89
Rate per Each Man hole Rs 8196.58
Additional manhole 0.10 mt depth constructon of
0.75 circular sewer man hole of 0.75 mts depth with
2nd Class modulor bricks in CM(1:6) Prop as per
specification etc complete. benching /
chanelling,internal plastreng with 20 mm thick cm 1:4
and External Plasterng with 12mm thick CM (1:4)
with fine rendering including cost and fixing of CI
steps and fixing FC/ CI cover and frame but excluding
the cost of cover and frame, including the cost and
conveyance of all materials at site complete and curing
for 21 days complete all taxes seignarage charges as
per specification etc complete.
Page 32 of 92
33
Index-code S No Description Unit Quantity Rate Rs. Amount Rs.
Total Cost Each Rs 13740.87
2 Constructon of 0.90 M Circular Sewer Man hole of
0.90 mts x 0.55 m of 1.0 M depths with Fly Ash bricks
in cm 1:6 prop and corbelling too including cc bed ( 1:
4 : 8 ) prop using 40 mm gauge HG Metal 0.10 mt
thick and CC (1:2:4) Prop benching /
chanelling,internal plastreng with 20 mm thick cm 1:4
and External Plasterng with 12mm thick CM (1:4)
with fine rendering including cost and fixing of CI
steps and fixing FC/ CI cover and frame but excluding
the cost of cover and frame, including the cost and
conveyance of all materials at site complete and curing
for 21 days complete all taxes seignarage charges as
per specification etc complete.
Page 33 of 92
34
Index-code S No Description Unit Quantity Rate Rs. Amount Rs.
Additional manhole 0.10 M depth constructon of 0.90
circular sewer man hole of 0.90 mts depth with Fly
Ash bricks in CM(1:6) Prop as per specification etc
complete. benching / chanelling,internal plastreng
with 20 mm thick cm 1:4 and External Plasterng with
12mm thick CM (1:4) with fine rendering including
cost and fixing of CI steps and fixing FC/ CI cover and
frame but excluding the cost of cover and frame,
including the cost and conveyance of all materials at
site complete and curing for 21 days complete all taxes
seignarage charges as per specification etc complete.
Page 34 of 92
35
Index-code S No Description Unit Quantity Rate Rs. Amount Rs.
Add Over Heads @14% 12936.91 0.00 0.00
Total Cost Each Rs 12936.91
Man hole Up to 1.60 M Depth 12936.91 1075.86 14012.77
Add Over Heads @14% 14012.77 0.00 0.00
Total Cost Each Rs 14012.77
Man hole Up to 1.70 M Depth 14012.77 1075.86 15088.63
Add Over Heads @14% 15088.63 0.00 0.00
Total Cost Each Rs 15088.63
Man hole Up to 1.80 M Depth 15088.63 1075.86 16164.49
Add Over Heads @14% 16164.49 0.00 0.00
Total Cost Each Rs 16164.49
3 Constructon of 1.20 M Circular Sewer Man hole
of 1.20 mts x 0.55 m of 1.0 M depths with Fly ash
bricks in cm 1:6 prop and corbelling too including cc
bed ( 1:4:8 ) prop using 40 mm gauge HG Metal 0.10
mt thick and CC (1:2:4) Prop benching /
chanelling,internal plastreng with 20 mm thick cm 1:4
and External Plasterng with 12mm thick CM (1:4)
with fine rendering including cost and fixing of CI
steps and fixing FC/ CI cover and frame but excluding
the cost of cover and frame, including the cost and
conveyance of all materials at site complete and curing
for 21 days complete all taxes seignarage charges as
per specification etc complete.
Page 35 of 92
36
Index-code S No Description Unit Quantity Rate Rs. Amount Rs.
Rate per Each Man hole Rs 14721.84
Additional manhole 0.10 mt depth constructon of
1.20 circular sewer man hole of 1.0 mts depth with Fly
Ash bricks in CM(1:6) Prop as per specification etc
complete. benching / chanelling,internal plastreng
with 20 mm thick cm 1:4 and External Plasterng with
12mm thick CM (1:4) with fine rendering including
cost and fixing of CI steps and fixing FC/ CI cover and
frame but excluding the cost of cover and frame,
including the cost and conveyance of all materials at
site complete and curing for 21 days complete all taxes
seignarage charges as per specification etc complete.
Page 36 of 92
37
Index-code S No Description Unit Quantity Rate Rs. Amount Rs.
Add Over Heads @14% 26830.47 0.00 0.00
Total Cost Each Rs 26830.47
Man hole Up to 2.0 M Depth 26830.47 1353.68 28184.15
Add Over Heads @14% 28184.15 0.00 0.00
Total Cost Each Rs 28184.15
Asst.Engineer Dy .Executive.Engineer
PR SD Ibrahimptanam PR SD Ibrahimpatanam
Executive.Engineer
PR Div Hyderabad
Page 37 of 92
38
Index-code S No Description Unit Quantity Rate Rs. Amount Rs.
Page 38 of 92
Page
D E T39
AILED DATAS
SSR 2018-19
Index-code S No Description Unit Quantity Rate Rs.
1 2 3 4 5
BLD-CSTN-2-1 1 Earthwork in excavation for structures as per
drawing and technical specifications Clause 305.1
including setting out, construction of shoring and
bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50 m, dressing of
sides and bottom and backfilling in trenches with
excavated suitable material as per Technical
Specification 305 MORD / 304 MORTH
Unit : 1 cum
Taking output : 10 cum
a) Labour
Mazdoor ( Unskilled) No 3.64 425.00
Add 75% for foundations Cum 0.75 1547.00
Add Mucipal Limits 0.40 2707.25
Cost for 10 cum
Add 13.615% Over heads Charges , Contractor 3790.15 0.00000
profit
Rate per 10 cum
Rate per 1cum Rs
BLD-CSTN-2-4 1 Ordinory Rock not requireing blasting
ManualMeans Upto 3.00 mdept
Unit : 1 cum
Taking output : 10 cum
a) Labour
Mazdoor ( Unskilled) No 5.20 425.00
Add 75% for foundations Cum 0.75 2210.00
Add Mucipal Limits 0.40 3867.50
Cost for 10 cum
Add 13.615% Over heads Charges , Contractor 5414.50 0.00000
profit
Rate Per 10Cum
Rate per 1cum Rs
PHE EXRW -33 1 Earthwork in excavation in Hard rock (blasting
prohibited) with rock breakersin hard rock
including breaking rock, loading , in tippers and
disposal with all lifts and lead up to 1000m as per
technical specifications 302.3.5
Unit : 1 cum
Unit : 1 cum
Taking output : 1 cum
a) Labour
Mazdoor ( Unskilled) day 1.10 425.00
chisellers day 1.50 470.00
black smith day 0.06 470.00
Add Mucipal Limits 0.40 1200.70
a)Mechinory
54 I&CAD Tipper 5.50 Cum capacity 1 trips per Hour day 0.18 1004.40
101 credit for excavated rock found unsuitable for use @ day 0.50 252.00
50%of excavated quantity
Add Mucipal Limits 0.00 1200.70
Cost for 10 cum
Unit = cum
Taking output = 180 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 3.220 425.00
Driller day 2.00 540.00
Blaster day 0.25 540.00
Add Mucipal Limits 0.40 2583.50
b) Machinery
2 R&B Dozer D-50 @ 30 cum per hour hour 6.00 1758.40
2 I&CAD Air compressor, 210 cfm hour 6.00 588.40
39 I&CAD 2 jack hammers hour 12.00 390.40
5 R&B Front end loader 1 cum bucket capacity @ 30 cum / hour hour 6.00 1843.52
54 I&CAD Tipper 5.5 cum capacity, 2 trips per hour hour 16.00 1004.40
c) Materials
Gelatin 80% per cent kg 70.00 73.00
Electric Detonators @ 1 detonator for 2 gelatine sticks of each 252.00 10.00
285 gm each
Credit for excavated rock found suitable for use @ 50 per cum 90.00 -194.00
cent quantity blasted
d&e) Overheads & Contractors Profit 0.0000% 39684.02
Cost for 180 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/180
BLD-CSTN-2-4 1 Ordinory Rock not requireing blasting Mechanical
Means Upto 3.00 mdept
Unit : 1 cum
Taking output : 180 cum
a) Labour
Mazdoor ( Unskilled) No 6.24 425.00
Add Mucipal Limits 0.40 2652.00
b) Machinory
52 I&CAD Hydraulic Excavator Hr 6.00 2967.90
Add 75% for foundations Cum 0.75 2652.00
Cost for 10 cum
Add 13.615% Over heads Charges , Contractor 23509.20 0.00000
profit
Rate per 180 cum
Rate per 1cum Rs
PHE CSHR -32 1 Cutting sheet rock including stockng of excavated
materials (Observed Rates )
Unit : 1 cum
quantiy of sheet roak as per stock measurement
36.53cum
a) Labour
Mazdoor ( Unskilled) day 60.00 425.00
Add Mucipal Limits 0.40 25500.00
PSSR 25 (a) A Cutting open B.T. road surface (as well as asphalt 10.00 1.00 1042.00
concrete upto 75 mm thick) including water bound
macadam
Add 13.615% Over heads Charges , Contractor 1042.00 0.00
profit
Rate per 10 Sqm
Rate per 1 Sqm Rs
PSSR 24 B) Cutting open C.C. road surface 1.00 1.00 2169.00
Add 13.615% Over heads Charges , Contractor 2169.00 0.00000
profit
Rate per 1 cum Rs
BLD-CSTN-2-8 3 Supplying and filling sand in trenches ,sides of the
foundations and basement with initial lead in layers
not exceeding 15 cm thick consolidatiing each
depposited layer by watering and rampping including
cost and conveyance of water to work site and all
operational incidental ,labour charges hire charges
and T & O Complete for finished item APSS 309
&310)
Unit : 1 cum
Taking output : 6 cum
a) Labour
Mazdoor ( Unskilled) No 0.31 425.00
Add Mucipal Limits 0.40 131.75
Sand for filling Cum 6.00 3018.84
Unit : 1 cum
m Taking output : 6 cum
a) Labour
Mazdoor ( Unskilled) No 0.31 425.00
Add Mucipal Limits 0.40 131.75
Unit = 1cum
A. MATERIALS:
Cement kg 162.00 4816.45
Coarse aggregate 40 mm cum 0.90 3287.52
Sand for concrete cum 0.45 3018.84
Water for Curing Kl 1.20 98.00
18 I&CAD Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 534.30
Unit = 1cum
A. MATERIALS:
Cement kg 129.60 4816.45
Coarse aggregate 40 mm cum 0.90 3287.52
Sand for concrete cum 0.45 3018.84
Water lncluding curing Kl 1.20 98.00
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 0.00
C. LABOUR:
Mason 1st class day 0.10 470.00
Mazdoor (unskilled) day 2.36 425.00
Add Mucipal Limits 0.40 1050.00
Grand Total
Add 13.615% Over heads Charges , Contractor 6529.06 0.00000
profit
Rate per 1 cum Rs
11 PCC Grade M15 - Nominal mix 1:2.5:5 (Hand
BLD-CSTN-2-3 mixing)
Unit = 1cum
A) Material
Cement kg 275.00 4816.45
Sand for concrete cum 0.48 3018.84
40 mm aggregate cum 0.54 3287.52
20 mm aggregate cum 0.27 3743.77
10 mm aggregate cum 0.09 3477.52
Water kl 1.20 98.00
B) Labour
Mason (1st Class) day 0.10 470.00
Mazdoor (Unskilled) day 2.36 425.00
Add Mucipal Limits 0.40 1050.00
Grand Total Rs
12 Masonry work in CM (1:6) prop with Flyash Cement
solid blocks of size 225 x 100 x 60 mm for
manufacturing of flyash solid blocks using flyash of 80
kgs, cement of 15 kgs. Gypsum of 5 kgs. and stone dust
including cost and conveyance of all materials, labour
charges, seiniorage charges, scaffolding and curing
BLD-CSTN-6-18 etc., cpomplete with a compresive streangth not
lessthan 50 kg/sqm for walls for Superstructure Walls.
Ground Floor
Unit = 1 cum
A. MATERIALS:
BMT-A.07 fly ash bricks required for one cum of Masonry Nos 672.00 12286.93
Cost of Cement Mortar (1:6) cum 0.10 4802.27
B. LABOUR
Mason 1st class day 0.42 470.00
Mason 2nd class day 0.92 450.00
Man Mazdoor day 0.70 425.00
Woman Mazdoor day 2.10 425.00
Rate per M Rs
Initial Socket Spigot NP2 Pipes 600 mm Dia 1 1.00 1429.00
Add difference cost of Cement ((6200-6300)/100)*0.59%*1404 4750.00
Unit= 1 rmt
vi 250 mm dia
a) Labour
Mason 1st class day 1.62 470.00
Mason 2nd class day 3.78 450.00
Man mazdoor day 10.50 425.00
Woman mazdoor(water carrier) day 2.30 425.00
Add Mucipal Limits 0.40 7902.40
b) Material
Rubber rings conforming BIS 5382/1985 each 50.00 91.00
c) Testing
Testing of Pipelines with required pressure as per rm 100.00 10.00
relevant IS Specification including filling with water
with a water lead upto 500 M, including hire charges
of testing equipment, labour and Materials needed for
testing (as per Sub Analysis 2 A)
Asst.Engineer Dy .Executive.Engineer
PR SD Ibrahimptanam PR SD Ibrahimpatanam
Executive.Engineer
PR Div Hyderabad
SSR 2018-19
Amount Rs.
6
1547.00
1160.25
1082.90
3790.15
0.00
3790.15
379.02
2210.00
1657.50
1547.00
5414.50
0.00
5414.50
541.45
467.50
705.00
28.20
480.28
180.79
-126.00
0.00
1735.77
1735.77
1368.50
1080.00
135.00
1033.40
10550.40
3530.40
4684.80
11061.12
16070.40
5110.00
2520.00
-17460.00
0.00
39684.02
220.47
2652.00
1060.80
17807.40
1989.00
23509.20
0.00
23509.20
130.61
25500.00
10200.00
16758.00
2250.00
750.00
55458.00
0.00
55458.00
308.10
1042.00
0.00
1042.00
104.20
2169.00
0.00
2169.00
131.75
52.70
18113.04
18297.49
0.00
540.00
18837.49
3139.58
131.75
52.70
1616.35
0.00
1616.35
269.39
2311.90
3527.32
85.00
34.00
5958.22
1733.92
3527.32
85.00
34.00
5380.24
1155.95
3527.32
85.00
34.00
4802.27
866.96
3527.32
85.00
34.00
4513.28
780.26
2958.77
1358.48
117.60
534.30
47.00
590.75
255.10
6642.26
624.21
2958.77
1358.48
117.60
0.00
47.00
1003.00
420.00
6529.06
0.00
6529.06
1324.52
1449.04
1775.26
1010.82
312.98
117.60
47.00
1003.00
420.00
7460.22
8256.82
480.23
197.40
414.00
297.50
892.50
231.19
5113.31
671.87
112.80
252.00
803.25
467.22
7651.64
807.04
282.00
408.00
276.00
1773.04
1129.85
423.00
680.00
441.20
2674.05
1872.00
-5.09
37.44
1904.35
0.00
1904.35
1429.00
-130.68
28.58
1326.90
0.00
761.40
1701.00
4462.50
977.50
3160.96
4550.00
15613.360
0
15613.36
0.00
15613.36
156.13
822.50
1863.00
4930.00
977.50
3437.20
4440.00
16470.200
0
16470.20
0.00
16470.20
164.70
893.00
2025.00
6840
19909.700
0
19909.70
0.00
19909.70
199.10
987
2205
5907.5
1232.5
7760
0.00
18092.000
0
18092.00
0.00
18092.00
180.92
1057.50
2362.50
6375.00
1402.50
4479.00
8840
24516.500
0.00
24516.50
245.17
1142.1
2551.5
6885
1402.5
8440
0.00
20421.100
0
20421.10
0.00
20421.10
204.21
1292.50
2902.50
6927.50
1402.50
5010.00
14720
32255.000
0
32255.00
0.00
32255.00
322.55
188.00
0.00
188.00
326.00
0.00
326.00
504.00
0.00
504.00
922.00
922.00
1330.00
0.00
1330.00
1810.00
0.00
1810.00
282.00
630.00
1275.00
425.00
1044.80
0.00
313.07
151.17
567.00
4688.04
4688.04
0.00
4688.04
156.27
423.00
945.00
1700.00
425.00
1397.20
0.00
467.20
228.44
1134.00
6719.84
0.00
6719.84
0.00
6719.84
223.99
493.50
1102.50
1912.50
531.25
1615.90
0.00
626.14
305.70
1512.00
8099.49
8099.49
0.00
8099.49
269.98
564.00
1260.00
2125.00
637.50
1834.60
0.00
703.20
342.65
1701.00
9167.95
9167.95
0.00
9167.95
305.60
634.50
1417.50
2337.50
637.50
2010.80
27660.00
780.26
379.61
1890.00
37747.67
37747.67
0.00
37747.67
1258.26
934.39
456.87
2268.00
11313.76
11313.76
0.00
11313.76
377.13
775.50
1732.50
2975.00
743.75
2490.70
0.00
1083.70
534.14
2646.00
12981.29
12981.29
0.00
12981.29
432.71
846.00
1890.00
3400.00
743.75
2751.90
0.00
1233.01
608.04
3024.00
14496.70
144.97
14641.67
0.00
14641.67
488.06
987.00
0.00
1411.22
685.31
3402.00
17107.33
171.07
17278.40
0.00
17278.40
575.95
933.66
1186.00
2356.71
457.44
443.89
746.02
140.00
6263.72
16.40
24.80
9.13
6314.05
543.27
67.38
63.11
2.24
1.39
677.39
3604.49
0.00
3604.49
4281.88
0.00
4281.88
4959.27
0.00
4959.27
5636.66
0.00
5636.66
6314.05
0.00
6314.05
6991.44
0.00
6991.44
7668.83
0.00
7668.83
8346.22
0.00
8346.22
9023.61
0.00
9023.61
9701.00
0.00
9701.00
10378.39
0.00
10378.39
1397.22
2263.06
5438.10
654.96
643.38
962.37
0.00
140.00
11499.09
23.15
35.74
11557.98
923.24
75.71
75.68
1074.63
2.59
1.62
1078.84
5084.94
0.00
5084.94
6163.78
0.00
6163.78
7242.62
0.00
7242.62
8321.46
0.00
8321.46
9400.30
0.00
9400.30
10479.14
0.00
10479.14
11557.98
0.00
11557.98
12636.82
0.00
12636.82
13715.66
0.00
13715.66
14794.50
0.00
14794.50
15873.34
0.00
15873.34
16952.18
0.00
16952.18
18031.02
0.00
18031.02
19109.86
0.00
19109.86
20188.70
0.00
20188.70
1979.39
3051.19
6079.87
764.18
828.96
1566.65
195.00
140.00
14605.24
14605.24
34.29
40.20
14679.73
1159.68
92.20
100.81
1352.69
9268.97
0.00
9268.97
10621.66
0.00
10621.66
11974.35
0.00
11974.35
13327.04
0.00
13327.04
14679.73
16032.42
0.00
16032.42
17385.11
0.00
17385.11
18737.80
0.00
18737.80
20090.49
0.00
20090.49
21443.18
0.00
21443.18
22795.87
0.00
22795.87
24148.56
0.00
24148.56
25501.25
0.00
25501.25
26853.94
0.00
1782.00
0.00
1782.00
1802.00
0.00
1802.00
2297.00
0.00
2297.00
2464.00
0.00
2464.00
Executive.Engineer
PRI Div Hyderabad
Initial
S.No. Unit Convey-ance Charges
Cost
Item no un loading
Sl. No. Description Quarry Page no Lead in KM Loading charges
charges
Total
(1) (2) (2) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16)
3 Sand for Mortar 28 Cum Krishna River 28 20 & CAD 250.00 2941.80 352.53 2589.27 760.00 90.00 10.08 3359.35
4 Sand for Concrete 27 Cum Local 27 20 & CAD 235.00 2770.80 332.04 2438.76 570.00 90.00 10.08 3018.84
5 Modulor Bricks of 23x11x7 1 1000 Nos Sanga Reddy 17 250.00 4744.80 568.59 4176.21 5700.00 38.50 55.36 55.36 9986.93
TBSC-A.I-01
6 Fly ash Bricks 225x100x60 75 Kgs/SqCm 7 1000 Nos Sanga Reddy 17 250.00 4744.80 568.59 4176.21 8000.00 55.36 55.36 12286.93
TBSC-A.II-05
40mm HBG metal SS5,
7 118 Cum Mekal gandi 30-F 12 250.00 2941.80 352.53 2589.27 505.00 126.25 67.00 75.00 3287.52
machine crushed
8 20mm HBG SS5 M/c chips 116 Cum Mekal gandi 28-D 12 250.00 2941.80 352.53 2589.27 870.00 217.50 67.00 75.00 3743.77
9 10 mm HBG SS5 M/c chips Cum Mekal gandi 26-b 12 250.00 2941.80 352.53 2589.27 657.00 164.25 67.00 3477.52
Executive.Engineer
PR Div Hyderabad
LEAD C H A R G E S - 2018-19
Metal Gravel & Shabad Bricks
Sand Stone
lead Rate lead Rate lead Rate lead Rate
1 33.00 1 34.20 1 48.60 1 55.10
2 46.20 2 47.90 2 68.00 2 77.10
3 63.90 3 63.90 3 94.00 3 102.80
4 77.60 4 77.60 4 114.10 4 124.80
5 91.30 5 91.30 5 134.30 5 146.80
6 105.00 6 105.00 6 154.40 6 168.80
7 118.70 7 118.70 7 174.50 7 190.80
8 132.40 8 132.40 8 194.60 8 212.80
9 146.10 9 146.10 9 214.70 9 234.80
10 159.80 10 159.80 10 234.80 10 256.80
11 173.50 11 173.50 11 254.90 11 278.80
12 187.20 12 187.20 12 275.00 12 300.80
13 200.90 13 200.90 13 295.10 13 322.80
14 214.60 14 214.60 14 315.20 14 344.80
15 228.30 15 228.30 15 335.30 15 366.80
16 242.00 16 242.00 16 355.40 16 388.80
17 255.70 17 255.70 17 375.50 17 410.80
18 269.40 18 269.40 18 395.60 18 432.80
19 283.10 19 283.10 19 415.70 19 454.80
20 296.80 20 296.80 20 435.80 20 476.80
21 310.50 21 310.50 21 455.90 21 498.80
22 324.20 22 324.20 22 476.00 22 520.80
23 337.90 23 337.90 23 496.10 23 542.80
24 351.60 24 351.60 24 516.20 24 564.80
25 365.30 25 365.30 25 536.30 25 586.80
26 379.00 26 379.00 26 556.40 26 608.80
27 392.70 27 392.70 27 576.50 27 630.80
28 406.40 28 406.40 28 596.60 28 652.80
29 420.10 29 420.10 29 616.70 29 674.80
30 433.80 30 433.80 30 636.80 30 696.80
31 445.20 31 445.20 31 653.60 31 715.20
32 456.60 32 456.60 32 670.40 32 733.60
33 468.00 33 468.00 33 687.20 33 752.00
34 479.40 34 479.40 34 704.00 34 770.40
35 490.80 35 490.80 35 720.80 35 788.80
36 502.20 36 502.20 36 737.60 36 807.20
37 513.60 37 513.60 37 754.40 37 825.60
38 525.00 38 525.00 38 771.20 38 844.00
39 536.40 39 536.40 39 788.00 39 862.40
40 547.80 40 547.80 40 804.80 40 880.80
41 559.20 41 559.20 41 821.60 41 899.20
42 570.60 42 570.60 42 838.40 42 917.60
43 582.00 43 582.00 43 855.20 43 936.00
44 593.40 44 593.40 44 872.00 44 954.40
45 604.80 45 604.80 45 888.80 45 972.80
46 616.20 46 616.20 46 905.60 46 991.20
47 627.60 47 627.60 47 922.40 47 1009.60
48 639.00 48 639.00 48 939.20 48 1028.00
49 650.40 49 650.40 49 956.00 49 1046.40
50 661.80 50 661.80 50 972.80 50 1064.80
51 673.20 51 673.20 51 989.60 51 1083.20
52 684.60 52 684.60 52 1006.40 52 1101.60
53 696.00 53 696.00 53 1023.20 53 1120.00
54 707.40 54 707.40 54 1040.00 54 1138.40
55 718.80 55 718.80 55 1056.80 55 1156.80
56 730.20 56 730.20 56 1073.60 56 1175.20
57 741.60 57 741.60 57 1090.40 57 1193.60
58 753.00 58 753.00 58 1107.20 58 1212.00
59 764.40 59 764.40 59 1124.00 59 1230.40
60 775.80 60 775.80 60 1140.80 60 1248.80
61 787.20 61 787.20 61 1157.60 61 1267.20
62 798.60 62 798.60 62 1174.40 62 1285.60
63 810.00 63 810.00 63 1191.20 63 1304.00
64 821.40 64 821.40 64 1208.00 64 1322.40
65 832.80 65 832.80 65 1224.80 65 1340.80
66 844.20 66 844.20 66 1241.60 66 1359.20
67 855.60 67 855.60 67 1258.40 67 1377.60
68 867.00 68 867.00 68 1275.20 68 1396.00
69 878.40 69 878.40 69 1292.00 69 1414.40
70 889.80 70 889.80 70 1308.80 70 1432.80
71 901.20 71 901.20 71 1325.60 71 1451.20
72 912.60 72 912.60 72 1342.40 72 1469.60
73 924.00 73 924.00 73 1359.20 73 1488.00
74 935.40 74 935.40 74 1376.00 74 1506.40
75 946.80 75 946.80 75 1392.80 75 1524.80
76 958.20 76 958.20 76 1409.60 76 1543.20
77 969.60 77 969.60 77 1426.40 77 1561.60
78 981.00 78 981.00 78 1443.20 78 1580.00
79 992.40 79 992.40 79 1460.00 79 1598.40
80 1003.80 80 1003.80 80 1476.80 80 1616.80
81 1015.20 81 1015.20 81 1493.60 81 1635.20
82 1026.60 82 1026.60 82 1510.40 82 1653.60
83 1038.00 83 1038.00 83 1527.20 83 1672.00
84 1049.40 84 1049.40 84 1544.00 84 1690.40
85 1060.80 85 1060.80 85 1560.80 85 1708.80
86 1072.20 86 1072.20 86 1577.60 86 1727.20
87 1083.60 87 1083.60 87 1594.40 87 1745.60
88 1095.00 88 1095.00 88 1611.20 88 1764.00
89 1106.40 89 1106.40 89 1628.00 89 1782.40
90 1117.80 90 1117.80 90 1644.80 90 1800.80
91 1129.20 91 1129.20 91 1661.60 91 1819.20
92 1140.60 92 1140.60 92 1678.40 92 1837.60
93 1152.00 93 1152.00 93 1695.20 93 1856.00
94 1163.40 94 1163.40 94 1712.00 94 1874.40
95 1174.80 95 1174.80 95 1728.80 95 1892.80
96 1186.20 96 1186.20 96 1745.60 96 1911.20
97 1197.60 97 1197.60 97 1762.40 97 1929.60
98 1209.00 98 1209.00 98 1779.20 98 1948.00
99 1220.40 99 1220.40 99 1796.00 99 1966.40
100 1231.80 100 1231.80 100 1812.80 100 1984.80
101 1243.20 101 1243.20 101 1829.60 101 2003.20
102 1254.60 102 1254.60 102 1846.40 102 2021.60
103 1266.00 103 1266.00 103 1863.20 103 2040.00
104 1277.40 104 1277.40 104 1880.00 104 2058.40
105 1288.80 105 1288.80 105 1896.80 105 2076.80
106 1300.20 106 1300.20 106 1913.60 106 2095.20
107 1311.60 107 1311.60 107 1930.40 107 2113.60
108 1323.00 108 1323.00 108 1947.20 108 2132.00
109 1334.40 109 1334.40 109 1964.00 109 2150.40
110 1345.80 110 1345.80 110 1980.80 110 2168.80
111 1357.20 111 1357.20 111 1997.60 111 2187.20
112 1368.60 112 1368.60 112 2014.40 112 2205.60
113 1380.00 113 1380.00 113 2031.20 113 2224.00
114 1391.40 114 1391.40 114 2048.00 114 2242.40
115 1402.80 115 1402.80 115 2064.80 115 2260.80
116 1414.20 116 1414.20 116 2081.60 116 2279.20
117 1425.60 117 1425.60 117 2098.40 117 2297.60
118 1437.00 118 1437.00 118 2115.20 118 2316.00
119 1448.40 119 1448.40 119 2132.00 119 2334.40
120 1459.80 120 1459.80 120 2148.80 120 2352.80
121 1471.20 121 1471.20 121 2165.60 121 2371.20
122 1482.60 122 1482.60 122 2182.40 122 2389.60
123 1494.00 123 1494.00 123 2199.20 123 2408.00
124 1505.40 124 1505.40 124 2216.00 124 2426.40
125 1516.80 125 1516.80 125 2232.80 125 2444.80
126 1528.20 126 1528.20 126 2249.60 126 2463.20
127 1539.60 127 1539.60 127 2266.40 127 2481.60
128 1551.00 128 1551.00 128 2283.20 128 2500.00
129 1562.40 129 1562.40 129 2300.00 129 2518.40
130 1573.80 130 1573.80 130 2316.80 130 2536.80
131 1585.20 131 1585.20 131 2333.60 131 2555.20
132 1596.60 132 1596.60 132 2350.40 132 2573.60
133 1608.00 133 1608.00 133 2367.20 133 2592.00
134 1619.40 134 1619.40 134 2384.00 134 2610.40
135 1630.80 135 1630.80 135 2400.80 135 2628.80
136 1642.20 136 1642.20 136 2417.60 136 2647.20
137 1653.60 137 1653.60 137 2434.40 137 2665.60
138 1665.00 138 1665.00 138 2451.20 138 2684.00
139 1676.40 139 1676.40 139 2468.00 139 2702.40
140 1687.80 140 1687.80 140 2484.80 140 2720.80
141 1699.20 141 1699.20 141 2501.60 141 2739.20
142 1710.60 142 1710.60 142 2518.40 142 2757.60
143 1722.00 143 1722.00 143 2535.20 143 2776.00
144 1733.40 144 1733.40 144 2552.00 144 2794.40
145 1744.80 145 1744.80 145 2568.80 145 2812.80
146 1756.20 146 1756.20 146 2585.60 146 2831.20
147 1767.60 147 1767.60 147 2602.40 147 2849.60
148 1779.00 148 1779.00 148 2619.20 148 2868.00
149 1790.40 149 1790.40 149 2636.00 149 2886.40
150 1801.80 150 1801.80 150 2652.80 150 2904.80
151 1813.20 151 1813.20 151 2669.60 151 2923.20
152 1824.60 152 1824.60 152 2686.40 152 2941.60
153 1836.00 153 1836.00 153 2703.20 153 2960.00
154 1847.40 154 1847.40 154 2720.00 154 2978.40
155 1858.80 155 1858.80 155 2736.80 155 2996.80
156 1870.20 156 1870.20 156 2753.60 156 3015.20
157 1881.60 157 1881.60 157 2770.40 157 3033.60
158 1893.00 158 1893.00 158 2787.20 158 3052.00
159 1904.40 159 1904.40 159 2804.00 159 3070.40
160 1915.80 160 1915.80 160 2820.80 160 3088.80
161 1927.20 161 1927.20 161 2837.60 161 3107.20
162 1938.60 162 1938.60 162 2854.40 162 3125.60
163 1950.00 163 1950.00 163 2871.20 163 3144.00
164 1961.40 164 1961.40 164 2888.00 164 3162.40
165 1972.80 165 1972.80 165 2904.80 165 3180.80
166 1984.20 166 1984.20 166 2921.60 166 3199.20
167 1995.60 167 1995.60 167 2938.40 167 3217.60
168 2007.00 168 2007.00 168 2955.20 168 3236.00
169 2018.40 169 2018.40 169 2972.00 169 3254.40
170 2029.80 170 2029.80 170 2988.80 170 3272.80
171 2041.20 171 2041.20 171 3005.60 171 3291.20
172 2052.60 172 2052.60 172 3022.40 172 3309.60
173 2064.00 173 2064.00 173 3039.20 173 3328.00
174 2075.40 174 2075.40 174 3056.00 174 3346.40
175 2086.80 175 2086.80 175 3072.80 175 3364.80
176 2098.20 176 2098.20 176 3089.60 176 3383.20
177 2109.60 177 2109.60 177 3106.40 177 3401.60
178 2121.00 178 2121.00 178 3123.20 178 3420.00
179 2132.40 179 2132.40 179 3140.00 179 3438.40
180 2143.80 180 2143.80 180 3156.80 180 3456.80
181 2155.20 181 2155.20 181 3173.60 181 3475.20
182 2166.60 182 2166.60 182 3190.40 182 3493.60
183 2178.00 183 2178.00 183 3207.20 183 3512.00
184 2189.40 184 2189.40 184 3224.00 184 3530.40
185 2200.80 185 2200.80 185 3240.80 185 3548.80
186 2212.20 186 2212.20 186 3257.60 186 3567.20
187 2223.60 187 2223.60 187 3274.40 187 3585.60
188 2235.00 188 2235.00 188 3291.20 188 3604.00
189 2246.40 189 2246.40 189 3308.00 189 3622.40
190 2257.80 190 2257.80 190 3324.80 190 3640.80
191 2269.20 191 2269.20 191 3341.60 191 3659.20
192 2280.60 192 2280.60 192 3358.40 192 3677.60
193 2292.00 193 2292.00 193 3375.20 193 3696.00
194 2303.40 194 2303.40 194 3392.00 194 3714.40
195 2314.80 195 2314.80 195 3408.80 195 3732.80
196 2326.20 196 2326.20 196 3425.60 196 3751.20
197 2337.60 197 2337.60 197 3442.40 197 3769.60
198 2349.00 198 2349.00 198 3459.20 198 3788.00
199 2360.40 199 2360.40 199 3476.00 199 3806.40
200 2371.80 200 2371.80 200 3492.80 200 3824.80
201 2383.20 201 2383.20 201 3509.60 201 3843.20
202 2394.60 202 2394.60 202 3526.40 202 3861.60
203 2406.00 203 2406.00 203 3543.20 203 3880.00
204 2417.40 204 2417.40 204 3560.00 204 3898.40
205 2428.80 205 2428.80 205 3576.80 205 3916.80
206 2440.20 206 2440.20 206 3593.60 206 3935.20
207 2451.60 207 2451.60 207 3610.40 207 3953.60
208 2463.00 208 2463.00 208 3627.20 208 3972.00
209 2474.40 209 2474.40 209 3644.00 209 3990.40
210 2485.80 210 2485.80 210 3660.80 210 4008.80
211 2497.20 211 2497.20 211 3677.60 211 4027.20
212 2508.60 212 2508.60 212 3694.40 212 4045.60
213 2520.00 213 2520.00 213 3711.20 213 4064.00
214 2531.40 214 2531.40 214 3728.00 214 4082.40
215 2542.80 215 2542.80 215 3744.80 215 4100.80
216 2554.20 216 2554.20 216 3761.60 216 4119.20
217 2565.60 217 2565.60 217 3778.40 217 4137.60
218 2577.00 218 2577.00 218 3795.20 218 4156.00
219 2588.40 219 2588.40 219 3812.00 219 4174.40
220 2599.80 220 2599.80 220 3828.80 220 4192.80
221 2611.20 221 2611.20 221 3845.60 221 4211.20
222 2622.60 222 2622.60 222 3862.40 222 4229.60
223 2634.00 223 2634.00 223 3879.20 223 4248.00
224 2645.40 224 2645.40 224 3896.00 224 4266.40
225 2656.80 225 2656.80 225 3912.80 225 4284.80
226 2668.20 226 2668.20 226 3929.60 226 4303.20
227 2679.60 227 2679.60 227 3946.40 227 4321.60
228 2691.00 228 2691.00 228 3963.20 228 4340.00
229 2702.40 229 2702.40 229 3980.00 229 4358.40
230 2713.80 230 2713.80 230 3996.80 230 4376.80
231 2725.20 231 2725.20 231 4013.60 231 4395.20
232 2736.60 232 2736.60 232 4030.40 232 4413.60
233 2748.00 233 2748.00 233 4047.20 233 4432.00
234 2759.40 234 2759.40 234 4064.00 234 4450.40
235 2770.80 235 2770.80 235 4080.80 235 4468.80
236 2782.20 236 2782.20 236 4097.60 236 4487.20
237 2793.60 237 2793.60 237 4114.40 237 4505.60
238 2805.00 238 2805.00 238 4131.20 238 4524.00
239 2816.40 239 2816.40 239 4148.00 239 4542.40
240 2827.80 240 2827.80 240 4164.80 240 4560.80
241 2839.20 241 2839.20 241 4181.60 241 4579.20
242 2850.60 242 2850.60 242 4198.40 242 4597.60
243 2862.00 243 2862.00 243 4215.20 243 4616.00
244 2873.40 244 2873.40 244 4232.00 244 4634.40
245 2884.80 245 2884.80 245 4248.80 245 4652.80
246 2896.20 246 2896.20 246 4265.60 246 4671.20
247 2907.60 247 2907.60 247 4282.40 247 4689.60
248 2919.00 248 2919.00 248 4299.20 248 4708.00
249 2930.40 249 2930.40 249 4316.00 249 4726.40
250 2941.80 250 2941.80 250 4332.80 250 4744.80
251 2953.20 251 2953.20 251 4349.60 251 4763.20
252 2964.60 252 2964.60 252 4366.40 252 4781.60
253 2976.00 253 2976.00 253 4383.20 253 4800.00
254 2987.40 254 2987.40 254 4400.00 254 4818.40
255 2998.80 255 2998.80 255 4416.80 255 4836.80
256 3010.20 256 3010.20 256 4433.60 256 4855.20
257 3021.60 257 3021.60 257 4450.40 257 4873.60
258 3033.00 258 3033.00 258 4467.20 258 4892.00
259 3044.40 259 3044.40 259 4484.00 259 4910.40
260 3055.80 260 3055.80 260 4500.80 260 4928.80
261 3067.20 261 3067.20 261 4517.60 261 4947.20
262 3078.60 262 3078.60 262 4534.40 262 4965.60
263 3090.00 263 3090.00 263 4551.20 263 4984.00
264 3101.40 264 3101.40 264 4568.00 264 5002.40
265 3112.80 265 3112.80 265 4584.80 265 5020.80
266 3124.20 266 3124.20 266 4601.60 266 5039.20
267 3135.60 267 3135.60 267 4618.40 267 5057.60
268 3147.00 268 3147.00 268 4635.20 268 5076.00
269 3158.40 269 3158.40 269 4652.00 269 5094.40
270 3169.80 270 3169.80 270 4668.80 270 5112.80
271 3181.20 271 3181.20 271 4685.60 271 5131.20
272 3192.60 272 3192.60 272 4702.40 272 5149.60
273 3204.00 273 3204.00 273 4719.20 273 5168.00
274 3215.40 274 3215.40 274 4736.00 274 5186.40
275 3226.80 275 3226.80 275 4752.80 275 5204.80
276 3238.20 276 3238.20 276 4769.60 276 5223.20
277 3249.60 277 3249.60 277 4786.40 277 5241.60
278 3261.00 278 3261.00 278 4803.20 278 5260.00
279 3272.40 279 3272.40 279 4820.00 279 5278.40
280 3283.80 280 3283.80 280 4836.80 280 5296.80
281 3295.20 281 3295.20 281 4853.60 281 5315.20
282 3306.60 282 3306.60 282 4870.40 282 5333.60
283 3318.00 283 3318.00 283 4887.20 283 5352.00
284 3329.40 284 3329.40 284 4904.00 284 5370.40
285 3340.80 285 3340.80 285 4920.80 285 5388.80
286 3352.20 286 3352.20 286 4937.60 286 5407.20
287 3363.60 287 3363.60 287 4954.40 287 5425.60
288 3375.00 288 3375.00 288 4971.20 288 5444.00
289 3386.40 289 3386.40 289 4988.00 289 5462.40
290 3397.80 290 3397.80 290 5004.80 290 5480.80
291 3409.20 291 3409.20 291 5021.60 291 5499.20
292 3420.60 292 3420.60 292 5038.40 292 5517.60
293 3432.00 293 3432.00 293 5055.20 293 5536.00
294 3443.40 294 3443.40 294 5072.00 294 5554.40
295 3454.80 295 3454.80 295 5088.80 295 5572.80
296 3466.20 296 3466.20 296 5105.60 296 5591.20
297 3477.60 297 3477.60 297 5122.40 297 5609.60
298 3489.00 298 3489.00 298 5139.20 298 5628.00
299 3500.40 299 3500.40 299 5156.00 299 5646.40
300 3511.80 300 3511.80 300 5172.80 300 5664.80
SPECIFICATION REPORT
#REF!
The above administratively sanctioned for Rs 2.00 lakhs vide Procdg No GP Resulation of GP _________________
under GP Grant . Accordingly the detailed estimate is prepared for laying of Under ground pipe line of 600 mm dia suitable popualtion of
_____ as per the census 2001 and designed for period of 20 years period
1 Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 2m in Loamy and Clayey Soils like B.C. Soils, red earth
& Ordinary Gravel (SS 20-B) including shoring, strutting, sheeting, planking and dewatering including cost of hire charges of T & P, labour
charges etc., complete for finished item of work for Foundation of Building.(APSS No. 308)
2 MANUFACTURE, SUPPLY AND DELIVERY OF R.C.C. SOCKET AND SPIGOT PIPESOF 600 MM DIA CONFORMING TO B.I.S. 458/2003 AT EX-FACTORY
(RATE PER METER OF EFFECTIVE LENGTH) EXCLUDING TRANSPORTATION, TAXES & DUTIES. Of Non Pressure pipes
3 Lowering the RCC S/S pipes carefully into the trenches laying them true to alignment and gradient, jointing with rubber rings and testing
including filling with water with a water lead upto 500 meters including cost of rubber rings as per BIS No. 783/1985
4 Filling excavated trenches ,with excavated soils in layers 15 cm thick consolidatiing each depposited layer by watering and rampping including
cost and conveyance of water to work site and all operational incidental ,labour charges hire charges and T & O Complete for finished item
5 Constructon of 1.0 M Circular Sewer Man hole of 1.20 mts x 0.55 m of 1.0 M depths with Fly ash cement sloid bricks in cm 1:6 prop and
corbelling too including cc bed ( 1: 4 : 8 ) prop using 40 mm gauge HG Metal 0.10 mt thick and CC (1:2:4) Prop benching / chanelling,internal
plastreng with 20 mm thick cm 1:4 and External Plasterng with 12mm thick CM (1:4) with fine rendering including cost and fixing of CI steps
and fixing FC/ CI cover and frame but excluding the cost of cover and frame, including the cost and conveyance of all materials at site
complete and curing for 21 days complete all taxes seignarage charges as per specification etc complete. 0.70 m, 0.80m ,0.90m 1.0m ,1..50
m ,1.70m ,2.0m depths
6 Manufacture as per BIS:12592 (Part 1&2) Supply & Delivery of manhole covers and frames with ISI marking anywhere in A.P., F.O.R. destination
including, loading, un-loading & stacking at site but excluding central excise duty, sales tax, octroi and other Govt levies etc., as applicable.
I.S.I Mark
9 Provision for VAT @4%
The estimate is prepared with SSR 2010-11 and submitted for according technical sanction.
Asst.Engineer Dy .Executive.Engineer
PR SD Ibrahimptanam PR SD Ibrahimpatanam
DETAILED AND ABSTRACT ESTIMATE
Measurements
Sno Description of item Nos. Qty Rate/Per Total Amount
L B D
1 2 3 4 5 6 7 8 9
1 Earthwork in excavation for Pipe Line trench Cutting as per drawing and technical specifications
Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in
trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH
including contractor profit
Main Line (Trunk Line)
For 300 Dia 1 x 1 43.00 0.90 1.00 30.39
For Man Holes PI/4 x 4 1.35 1.35 1.20 6.87
37.26 379.02 14122.00
Cum. 1 cum
2 MANUFACTURE, SUPPLY AND DELIVERY OF R.C.C. SOCKET AND SPIGOT PIPES CONFORMING TO B.I.S.
458/2003 AT EX-FACTORY (RATE PER METER OF EFFECTIVE LENGTH) EXCLUDING TRANSPORTATION, TAXES
& DUTIES. Of Non Pressure pipes
For 300 mm SS Dia Line For Main Line 1 x 1 43.00 43.00 1330.00 57190.00
Rm per Rm
3 Lowering the RCC S/S pipes carefully into the trenches laying them true to alignment and gradient,
jointing with rubber rings and testing including filling with water with a water lead upto 500 meters
including cost of rubber rings as per BIS No. 783/1985
For 300 mm SS Dia Line For Main Line 1 x 1 43.00 43.00 377.13 16217.00
Rm per Rm
7 Constructon of 0.90 M Circular Sewer Man hole of 0.90 mts x 0.55 m of 1.0 M depths with 2 nd Class
bricks in cm 1:6 prop and corbelling too including cc bed ( 1: 4 : 8 ) prop using 40 mm gauge HG Metal
0.10 mt thick and CC (1:2:4) Prop benching / chanelling,internal plastreng with 20 mm thick cm 1:4 and
External Plasterng with 12mm thick CM (1:4) with fine rendering including cost and fixing of CI steps and
fixing FC/ CI cover and frame but excluding the cost of cover and frame, including the cost and `
conveyance of all materials at site complete and curing for 21 days complete all taxes seignarage charges
as per specification etc complete.
150,000.00
Page 92 of 92