All these documents are the part of AIM (Oracle Application Implementation
Methodology) but not all companies are using the same AIM instead they are using their
own giving different names but the formats of all the documents are more or less same.
Hope this will clear all the doubts, if any question you can revert here or shoot me a mail to
good_looking_bad_character_glbc@yahoo.com (its just an id :P )
hi
MD50,MD70,MD60,MD20 are the documents prepared by the functional and technical
persons while they are going to implement and after implementation.
functional cons take the specifications from the client and they will prepare the document
to tech people as thier requirements is tat..
Hi Jamal,
You need to know and understand what is exactly the meaning of the BR & MD documents
are for.
You can say these are As Is process. So BR 100 is the To Be Process after you gather all
sorts of info from the Biz and map in the Oracle Systems.
These MD's are of basically discussed any customization needs or any special behaviaour
oracle system should work which is not the Standard Oracle Funtionality. These also
discussed about the tables and the Interface Tables or forms which are going to be used in
the particular modules. Thses also discussed about the High Level Designs like Flows of
the Business and all.
These MD's are basically made after you all Functional Design and if there is no work
around Oracle System provides for a particular Test Scenario and there is no other way
other than to go for the Customization.
Now I suppose you can understand what is the basic difference between these two.
Now as a Funtional Consultant you need to always go for the BR - 100, that is set up doc.
and in your scenario ( as you said that you have created in GL - COA / CAL / CVR etc)
you have to document all these into BR 100.
The first version of the BR100 will probably be used to build the TEST environment. Any
changes required as a result of problems encountered will be incorporated into the next
version of the BR100, which will then be used to build (say) the UAT environment. In
parallel with these environments, there will probably be a DEVELOPMENT environment
and it may be that there will be changes required to the BR100 because of issues
encountered there. The "Final" version of the BR100 will probably then be used to build
both the PRODUCTION and TRAINING environments.
Regards
Srinu,
In Development cycle, there are many documents required for various requirements.
MD.50 is Desgin Document(Functional resource will design), which explore all design
methods like its road-map, which includes all design setups.
MD.70 is technical Document(Technical resource will design), which show all Technical
Details like Coding, Maping and Logics.
1.Implementation
2.Customization
3.Conversions
2. Business Requirement Definition [RD] - This phase explains about the initial
baseline questionnaire and gathering of requirements.
RD.010 Identify Current Financial and Operating Structure RD.020 Conduct
Current Business Baseline RD.030 Establish Process and Mapping Summary
RD.040 Gather Business Volumes and Metrics RD.050 Gather Business
Requirements RD.060 Determine Audit and Control Requirements RD.070 Identify
Business Availability Requirements RD.080 Identify Reporting and Information
Access Requirements
3. Business Requirement Mapping [BR] - In this phase the requirements of business
are matched with the standard functionality of the oracle applications.
BR.010 Analyze High-Level GapsBR.020 Prepare mapping environment
BR.030 Map Business requirements
BR.040 Map Business Data
BR.050 Conduct Integration Fit Analysis
BR.060 Create Information Model
BR.070 Create Reporting Fit Analysis
BR.080 Test Business Solutions
BR.090 Confirm Integrated Business Solutions
BR.100 Define Applications Setup
BR.110 Define security Profiles
5. Build and Module Design [MD] - This phase emphasizes the development of
new functionality (customization) required by the client. It mainly details how to
design the required forms, database and reports.
MD.010 Define Application Extension StrategyMD.020 Define and estimate
application extensions
MD.030 Define design standards
MD.040 Define Build Standards
MD.050 Create Application extensions functional design
MD.060 Design Database extensions
MD.070 Create Application extensions technical design
MD.080 Review functional and Technical designs
MD.090 Prepare Development environment
MD.100 Create Database extensions
MD.110 Create Application extension modules
MD.120 Create Installation routines
10. Adoption and Learning [AP] - This phase explains the removal of the legacy
system and oracle application roll out enterprise wide.
AP.010 - Define Executive Project StrategyAP.020 - Conduct Initial Project Team
Orientation
AP.030 - Develop Project Team Learning Plan
AP.040 - Prepare Project Team Learning Environment
AP.050 - Conduct Project Team Learning Events
AP.060 - Develop Business Unit Managers’ Readiness Plan
AP.070 - Develop Project Readiness Roadmap
AP.080 - Develop and Execute Communication Campaign
AP.090 - Develop Managers’ Readiness Plan
AP.100 - Identify Business Process Impact on Organization
AP.110 - Align Human Performance Support Systems
AP.120 - Align Information Technology Groups
AP.130 - Conduct User Learning Needs Analysis
AP.140 - Develop User Learning Plan
AP.150 - Develop User Learning ware
AP.160 - Prepare User Learning Environment
AP.170 - Conduct User Learning Events
AP.180 - Conduct Effectiveness Assessment
11. Production Migration [PM] - The process of “decommissioning” of legacy
system and the usage(adoption) of oracle application system.
PM.010 - Define Transition Strategy
PM.020 - Design Production Support Infrastructure
PM.030 - Develop Transition and Contingency Plan
PM.040 - Prepare Production Environment
PM.050 - Set Up Applications
PM.060 - Implement Production Support Infrastructure
PM.070 - Verify Production Readiness
PM.080 - Begin Production
PM.090 - Measure System Performance
PM.100 - Maintain System
PM.110 - Refine Production System
PM.120 - Decommission Former Systems
PM.130 - Propose Future Business Direction
PM.140 - Propose Future Technical Direction
------------------------------------------------------------------------------------------------
Re: If any person ask what you know about AIM? How briefly we can explain b'coz we
cont expalin AIM in short time. Answer
#1
AIM methodology consists of 6 phases
Definition
Operation Analysis
Solution Design
Build
Transition, And
Production ...u can explain all of this phases if to
be
answered in a short span of time
Re: If any person ask what you know about AIM? How briefly we can explain b'coz we
cont expalin AIM in short time. Answer
#3
AIM is an Application Implementation Methodology
which is
being followed for Oracle Apps Implementation
project(ERP).
It consists different phases and processes. They are
Phases :
Definition
Operation Analysis
Solution Design
Build
Transition, And
Production
Processes :
Project Management
Business Process Mapping
APplication and Technical Architecture
Module Design and Build
Data Conversion
Documentation
Business System Testing
performance Testing
Adoption and Learning
Production Migration