Académique Documents
Professionnel Documents
Culture Documents
The passage of the Electric Power Industry Reform Act (EPIRA) of 2001
was occasioned by unabated increases in electricity prices, heavy indebtedness
of public electric utilities, and perennial threat of supply problems which the
government had difficulty addressing. It became clear that a centrally managed
electricity system, mainly owned and run by the State, was no longer tenable.
This prompted the restructuring and liberalization of the market.
Generation Companies
Distribution Utilities
ANECO BATELEC 2
BENECO CASURECO 1
CASURECO 2 CENECO
COTELCO DASURECO
FIBECO FLECO
MERALCO NEECO 2-Area I
NEECO 2-Area II NONECO
NORECO 1 NORECO 1
PELCO 1 PELCO 2
SIARELCO SIASELCO
SOCOTECO 1 SORECO 2
TARELCO 1 TARELCO 2
Generation
- WESM: Market
- NPC: Return on Rate Base Methodology
- IPPs: Individual review of bilateral contracts or PSA
Transmission
- Previously, Return on Rate Base Methodology
- Currently, Performance-Based Regulation
Distribution
- Private Distribution Utilities
o Previously, Return on Rate Base Methodology
o Currently Performance-Based Regulation
- Electric Cooperatives
o Previously Cash Flow Methodology
o Currently Benchmarking Methodology
ERC originally applied the Rate Base Methodology in setting rates. Now,
ERC used the Performance Rate Base (“PBR”) Methodology in accordance
Section 43 (f) of the EPIRA.
Under the PBR, Regulated Entities are entitled to earn a return on the
value of their rolled-forward RAB, as part of the annual allowed revenue
requirement. The value of the RAB therefore has a direct bearing on the price
consumers pay for electricity distribution.5
Section 4.8 of the RDWR describes the approach to the opening valuation
of the RAB, an Optimized Depreciated Replacement Cost (ODRC) valuation
method is adopted. This method is to ensure that only those assets that are
required to provide efficient distribution services and allows efficient planning
and investment in distribution assets are included in the RAB.6
4 Paragraph 4.15.1 Final Determination ERC Case No. 2010-069RC dated 06 June 2011
5 Paragraph 4.15.3 Final Determination ERC Case No. 2010-069RC dated 06 June 2011
6 Paragraph 4.16.1 Final Determination ERC Case No. 2010-069RC dated 06 June 2011
b) A Regulatory Reset Expert/s retained by ERC pursuant to Article
XIV of the RDWR for purposes of undertaking the valuation (and
preparing the Valuation Report).7
For power transformers, AACI did not use actual values in the market
to determine their replacement costs but merely based or benchmarked
these on replacement costs of similar National Grid Corporation of the
Philippines (“NGCP”) large power transformers and compared the values to
graphs of observed international market prices for equipment. Hence, AACI
stated:
7 Paragraph 4.15.2 Final Determination ERC Case No. 2010-069RC dated 06 June 2011
8 Paragraph 4.16.4 Final Determination ERC Case No. 2010-069RC dated 06 June 2011
“In the case of power transformers, these were given
individual replacement costs and added to the replacement costs
of standard modules covering transformer take-off assets, etc.
This was necessary as the transformation voltages vary, with
corresponding variation in MVA capacity. The replacement costs
were determined based on observed international market prices
for equipment. Figure 1 shows the cost per capacity for large
power transformers based on March 31, 2010 replacement costs
of NGCP large power transformers with the same voltage
transformation ratio and capacity.
Figure 1
[Emphasis Supplied]
xxx"
[Emphasis Supplied]
2. NCL did not agree with the new age profiles submitted by
MERALCO and recommended that further action be undertaken to
arrive at a more reasonable and efficient asset ages for Poles,
Overhead Conductors (including Pole Tops) and Customer Service
Connections;
9 Page 57 paragraph 4.17.3 of the ERC Final Determination in ERC Case No. 2010-069RC
10 Page 58 paragraph 4.17.4 of the ERC Final Determination in ERC Case No. 2010-069RC
11 Paragraph 4.17.4 Final Determination ERC Case No. 2010-069RC dated 06 June 2011
That is to say, NCL was of the view that revaluation of MERALCO’s fixed
assets, to reflect just and reasonable costs, must be undertaken in order for
ERC to have a sound basis in coming up with its final determination.
However, not only did ERC fail to take further action for MERALCO to
come up with an actual and correct revaluation of its assets, ERC merely relied
on a simulated value for opening RAB, particularly, a rolled-forward calculation
of the RAB amounting to One Hundred Twenty Four Billion One Hundred
Ninety Million One Hundred Thousand Pesos (Php124,193,100,000.00)12,
submitted by MERALCO, and which was later on adopted by ERC for the Final
Determination subject to the true up during the Fourth Regulatory Period.
On the other hand MERALCO’s overstatement in its CAPEX for the Third
Regulatory Period was laid bare when the replacement cost values for 33 MVA,
83 MVA and 150 MVA transformers as compared to the values of the
transformers used by ACCI was much higher.
However, despite the fact that MERALCO grossly overpriced its existing
fixed assets and capital expenditures and, further, notwithstanding that ERC’s
own Regulatory Reset Expert conclusively confirmed the overstatement of
figures, ERC allowed the apparent fraud.
As can be seen above, all of the data and information came from
MERALCO, which was in turn reviewed by AACI, with respect to the fixed
assets, and SKM for its CAPEX for the Third Regulatory Period.
13 Page 21 of the Asset Valuation Subject to Performance Based Regulation of Manila Electric
Company (MERALCO) dated 31 March 2010 prepared by Asian Appraisal Company Inc.
14 http://freecurrencyrates.com/en/exchange-rate-history/USD-PHP/2014/yahoo
15 Date of Application filed by MERALCO
“MERALCO uses a system to come up with the cost-estimate
based on the project’s scope of work, wherein the significant
factors affecting the cost are the prices of equipment and
materials involved, as well as the associated labor costs. The
major drivers of costs for MERALCO substation equipment are
the equipment costs itself and the needed labor for its installation
and commissioning. Furthermore, the cost estimate for materials
are based on the moving average price of the particular
equipment to be used in the project.”
However, MERALCO did not submit any proof or receipts of the previous
purchases, as basis on how they arrived at the said moving average price.
16 Distribution Utility
17 Power Plant Generating Company
18 Par. 29.1 of the Joint Application [ERC Case No. 2013-049RC]