Académique Documents
Professionnel Documents
Culture Documents
ABSTRACT
Conventionally it has been known two mining extraction variants: surface and
underground methods; However, due to the demands of the market, the mining industry
is faced with the challenge of extracting as much as possible from a mineral deposit;
what it means to look for other alternatives. This is where the idea of combining both
methods mentioned above arises. In this work the main factors to determine the
transition from an open pit to an underground exploitation have been developed; such
as the type of deposit, mining costs, geotechnical factors, optimal depth of the transition,
among others. Additionally, Chuquicamata Underground Mine project was analyzed in
order to show the main design parameters taken and the benefits present in this type of
exploitation.
1. INTRODUCTION
Mining industry, a risky business due to the changing prices of commodities, has the
challenge of maximizing the cash flow of every projects, which is achieved by reducing
costs and optimizing the extraction of mineral resources. For this reason is essential
choose an efficient mining method for the operation, deciding between the development
of an open-pit or underground mine. However, in many cases the combination of both
options is more profitable.
This paper will analyze the considerations necessary for the choice of a combined mining
method, showing the main benefits of developing a project of this type and the optimal
point of transition of the methods.
Additionally, a brief analysis of a project underway in Chile called the Chuquicamata
Underground Mine Project will be carried out; in which the largest open pit mine in the
world is building the necessary infrastructure to carry out the exploitation of its copper
deposit through the Block Caving method; prolonging the life of the mine for four more
decades and achieving to extract 60% more reserves than what has already been
extracted so far during the last one hundred years of exploitation.
Fig. 1. Open-pit economical block model Fig. 2. Underground economical block model
Source (Bakhtavar, Shahriar and Oraee.2009) Source (Bakhtavar, Shahriar and Oraee.2009)
Subsequently, the author makes the optimization for the surface extraction by using the
Korsakov algorithm, obtaining the final pit with a depth up to level 7 of the block model
(Figure 3) and for the case of the underground extraction they got the optimum
underground layout (Figure 4).
Then it is possible to determine the economic result of the exploitation in each level for
both extraction methods (Table 1).
Table 1. Economical results of the example. Source (Bakhtavar, Shahriar and Oraee.2009)
To complete the process, the author introduces the concept of maximization of the NPV,
considering additional factors such as the discount rate, in addition to using a support
pillar between both methods, with which a more realistic economic distribution of the
block model is obtained and also a graphic representation of the extraction limits for each
case (Table No. 2 and Figure No. 5). Proving that the maximum NPV of the project is
achieved with the combination of both mining methods that independently Bakhtavar, K.
Shahriar, and K. Oraee (2009).
Table 2. Economical results with the NPV of the example. Source (Bakhtavar, Shahriar and Oraee.2009)
Fig. 5. Optimal transition from open pit to underground
Source (Bakhtavar, Shahriar and Oraee.2009)
On the other hand, the choice of underground mining method is key to the development
of the operation, since it must meet a high quota of production at a low cost per tonne
extracted because the laws that are presented in this type of deposits are low. That is
why the main methods to be taken into account are those of massive mining such as
Caving. Taking the case of Chuquicamata as an example, the chosen method is block
caving, through the use of macro blocks. This method has cost advantages in terms of
production capacity and a good adaptation to geomechanical conditions; however, the
loss of selectivity must be accepted, as well as the high degree of investment in time and
money necessary, since Codelco plans to invest USD 4.2 billion and a construction time
of 9 years.
5. CONCLUSIONS
The main reason for using the combined method of exploitation is to increase the NPV
of the project, extracting the optimal amount of reserves at a lower cost per ton instead
to use a single method individually.
The depth at which the method transition must be made is decided by an economic
analysis, evaluating both options separately and then combining them in order to obtain
the highest profits, and also taking into account the geological characteristics of the
deposit.
The depth of an open-pit mining operation plays an important role as it goes deeper,
there are greater geotechnical risks (slope instability), greater stripping, greater transport
cycles, etc. That is why it is decided to migrate to an underground method. However, the
design and construction of the project is another big challenge because the operation is
already in huge depths and above is the open pit.
The tendency of the mining industry is to opt for underground operations with massive
mining methods, since production costs are reduced due to the movement of enormous
amounts of material and it can even be compared with a superficial method by the index
of production and associated costs.
The goal of future operations is to automate processes in order to reduce costs, provide
better working conditions and be friendlier to the environment.
The analysis of Chuquicamata Underground Mine case served as an example to indicate
the benefits that the use of this method brings, such as the fact that 1,700 million
additional copper reserves can now be extracted and that it will extend the mine for four
more decades; additionally to analyze the necessary infrastructure for the project and
the main parameters of the design.
6. REFERENCES
CODELCO (2009). CRITERIOS ESPECIFICOS DE DISEÑO
Available at:
https://www.codelco.com/prontus_codelco/site/artic/20110706/asocfile/2011070
6150616/criterios_espec__ficos_de_dise__o_rev_p.pdf
[Accessed 1 Feb. 2018].
CODELCO (2009). PRINCIPALES DECISIONES.
Available at:
https://www.codelco.com/prontus_codelco/site/artic/20110706/asocfile/2011070
6150616/informe_principales_decisiones_rev_p_25_03_2009.pdf
[Accessed 1 Feb. 2018].
SOLAR, J. (2010). MODELO DE PROGRAMACIÓN MATEMÁTICA PARA
SUSTENTAR LA TRANSICIÓN RAJO SUBTERRÁNEA. Santiago de Chile:
Universidad de Chile.
Available at:
http://repositorio.uchile.cl/handle/2250/102466
[Accessed 1 Feb. 2018].
BAKHTAVAR, E., SHAHRIAR, K., AND ORAEE, K. (2009). TRANSITION FROM
OPEN-PIT TO UNDERGROUND AS A NEW OPTIMIZATION CHALLENGE IN
MINING ENGINEERING
Available at:
https://link.springer.com/content/pdf/10.1007%2Fs10913-009-0060-
3.pdf
[Accessed 1 Feb. 2018].
Ordin, A. and Vasil’ev, I. (2009). OPTIMIZED DEPTH OF TRANSITION FROM OPEN
PIT TO UNDERGROUND COAL MINING
Available at:
https://link.springer.com/content/pdf/10.1134%2FS1062739114040103.pdf
[Accessed 1 Feb. 2018].