Vous êtes sur la page 1sur 8

EFFICIENT APPLICATIONS OF BUS TRANSFER SCHEMES

Craig Wester Terrence Smith


Member, IEEE Member, IEEE
GE Digital Energy Multilin GE Digital Energy Multilin
20 Technology Pkwy, Ste 300 4650 Parker Loop Rd
Norcross, GA 30092 Birchwood, TN 37308
USA USA

Abstract - The application of bus transfer schemes in M-T-M bus transfer schemes. Thus, Main-Tie-Main bus
industrial and utility facilities, such as paper mills, transfer schemes can be:
petrochemical facilities, and utility power plants is ƒ Accomplished by reduced amount of devices/IEDs (i.e.
significant in both its number and criticality. This paper “lean” applications)
will review the basics of main-tie-main bus transfer ƒ Implemented using protective relay inputs and outputs
schemes, highlight the technical challenges associated ƒ Implemented using protective relay-to-relay control
with implementing such schemes, and examine how logic via IEC61850 GOOSE messaging
modern technology can provide solutions that enhance ƒ Simplified as a result of the protection and logic being
efficiency, engineering, and operations. programmed in modern microprocessor based
Among the issues to be discussed in this paper are: (a) protection & control IEDs, such as protection, transfer
enhancing panel design by reducing the number of logic, interlocking, timing and sequencing functions
devices necessary for implementation; (b) achieving The application of new technology is rooted in an
savings in wiring by utilizing IEC61850 peer-to-peer understanding of tried and true concepts. This paper will first
communication methods; (c) how modern technology discuss the common types of bus transfer schemes that have
enhances the ability to test and troubleshoot the scheme been deployed for many years in industrial and utility facilities.
and; (d) examination of the advantages and Secondly, this paper will discuss several efficient methods of
disadvantages of different types of bus transfer schemes. using protective relay IEDs to perform M-T-M bus transfer.

I. INTRODUCTION II. AUTOMATIC BUS TRANSFER SCHEMES


The implementation of bus transfer schemes in industrial In a typical Main-Tie-Main bus arrangement (Fig 1), the
and utility facilities has typically taken the form of discrete automatic bus transfer scheme is used to minimize the effect
electromechanical relays that provide the necessary level of of outages on one of the incoming supplies by opening the
system protection and control. The value of these legacy normally-closed incoming breaker connected to that supply,
relays is their proven performance and high level of reliability. and then re-energizing the decaying bus by closing the
The disadvantages of these legacy relays are their cost, normally open bus tie breaker after the voltage of the
extensive use of panel space and extensive device-to-device decaying bus voltage drops to a predetermined level.
wiring.
Main-Tie-Main (M-T-M) bus transfer and protection for
industrial and utility installations has often been accomplished
using discrete relays and logic devices. Discrete relays were
used for overcurrent, overvoltage, undervoltage protection
and synchrocheck control. Auxiliary relays, timers, and
programmable logic controllers (PLCs) have been used for
control logic functions.
The development of the microprocessor-based relay has
provided the industry with a new tool that can not only meet
the needs of bus transfer scheme implementation, but also
offers numerous additional benefits that can help the
organization attain higher levels of cost efficiency. The ability
to provide protection, control, and automation in a single
device has led to the use of the term “intelligent electronic
device” or “IED”.
Advanced microprocessor-based protective IEDs with
programmable logic capabilities can simplify and enhance the
Fig. 1. Typical Main-Tie-Main Bus Transfer Scheme

978-1-4244-5674-1/10/$26.00 ©2010 IEEE


In the above-mentioned application, on recovery of the lost regard to less critical motor loads. Among the disadvantages
source, the load is transferred back to the preferred source, of the slow transfer scheme is that it causes the complete loss
which is determined by a selector switch (either incoming of motor loads, so it is not for use on critical process
source S1 or incoming source S2). This transfer can be applications. Also, the possibility of motor damage from
accomplished automatically or manually and in a break-then- jogging exists if the bus is reenergized before the motor
make (open transition) or make-then-break (closed transition) coasts to an acceptable level.
mode. During an Open Transition mode of re-transfer, the tie
breaker is opened, then the now healthy incoming source B. Residual Voltage Transfer
breaker is closed. During a Closed Transition mode of re-
transfer, the now health incoming source is closed and then One of the most commonly used main-tie-main bus transfer
the tie breaker is opened. schemes is the residual voltage transfer scheme. In the event
Synchrocheck relays may be required to synchronize the of a loss of the incoming source, this scheme transfers the
motor bus with the incoming supply, such as when generators motor-bus to the alternate healthy incoming source after the
are located on the bus or critical motor load applications, and voltage level of the decaying bus drops to a predetermined
supervise the closing of the now healthy incoming source level. This protects the decelerating motors of the decaying
breaker or tie breaker by comparing the difference in voltage bus from damage when connecting them to an
and possibly the phase angle between the incoming line unsynchronized alternative healthy voltage.
voltage and bus voltage. Typical synchrocheck settings are a The permissible setting of the residual voltage to transfer
delta voltage of 5% of nominal, a delta phase angle of 10 the motor-bus can be calculated from the given maximum
degrees, and a maximum frequency difference of 0.5Hz. allowable voltage across the motors (machine data from the
The prime requirement of the automatic bus transfer manufacturer) and the stability of the power system as to how
scheme is quick and safe restoration of power. However, the many of these motors can be re-accelerated without
simplicity of the automatic bus transfer application is offset by significant voltage sags.
the fact that each motor's bus has a unique voltage decay and The residual voltage transfer scheme criterion is indicated
phase angle characteristic during a transfer. Also, the various by:
applications of the automatic bus transfer scheme typically
lack the design flexibility to deal with issues such as a Vresidual < VM – VN
closed/open transition; variations in system-grounding
methods; and different motor starting configurations. Issues VM is maximum allowable voltage across the motor and VN is
such as the criticality of the motor loads and the cost of alternative healthy incoming source's nominal voltage.
implementation will drive the selection of the bus transfer Based on the pre-load condition of the motor-bus, the
scheme to be employed. There are typically four types of bus residual voltage transfer scheme can take between 0.5 to 3.0
transfer schemes in practice seconds to complete. This scheme is slightly more
complicated as it requires voltage relays to detect
ƒ Slow transfer scheme undervoltage conditions on the incoming source; overvoltage
voltage relays on the bus; electrical interlocks to accomplish a
ƒ Residual Voltage Transfer Scheme safe bus transfer; and synchrocheck relays to synchronize the
system return of the lost incoming supply. This scheme is
ƒ In-Phase Transfer Scheme applicable where the motor loads are non critical and the
safety of the motors is the prime concern. Typical healthy bus
ƒ Fast Transfer Scheme conditions are determined by a voltage greater than 0.9 per
unit. Transfer and restore occur when the voltage passes this
threshold for a time delay, typically 5 seconds.
A. Slow Transfer Scheme The advantages of the residual voltage transfer scheme is
that it provides for safe motor-bus transfer, is cost effective,
The slow transfer scheme involves the detection of a loss of and less complicated to implement as compared with the two
the incoming source by monitoring incoming line voltage; then remaining schemes to be discussed. The main
opening the affected incoming source breaker; and finally disadvantages are that load shedding may be required to
energizing of the dead bus by closing the tie breaker after a successfully transfer from the lost source, and paralleling of
predetermined safe decay time. The slow transfer scheme incoming sources may be required for a time when returning
typically does not require the bus voltage to be monitored and back to normal operation.
is designed to wait for a predetermined time of normally
greater than 0.5 seconds (allowing the motors to coast down), C. In-Phase Transfer
before connecting the decaying bus voltage to the alternative
healthy incoming source by closing the tie breaker. The In the event of a loss of the incoming source, the in-phase
predetermined time day should be such that flux in the motor transfer scheme predicts and transfers the motor-bus to the
will not cause back EMF and motor damage. alternate healthy incoming source when the decaying bus
Since a bus monitoring voltage relay does not supervise residual voltage phase angle is in-phase with the phase angle
this scheme, it offers cost effectiveness and easy of the alternate healthy incoming source voltage and phase
implementation for less critical motor loads. angle difference is near zero. By doing this, the voltage
The advantages of the slow transfer scheme are that it is difference across the alternative healthy source breaker is
very cost effective; easy to implement; and is very safe with reduced to only the difference in the magnitude of the
alternative healthy source (VN) and the decaying bus voltage Similar to the in-phase transfer scheme, the fast bus
(VB). transfer scheme also requires advanced and accurate
The net result is minimization of the resultant V/Hz information of the tie-breaker closing time. The intent of the
difference between the decaying bus voltage and the alternate fast transfer scheme is primarily to maintain the uninterrupted
healthy incoming source; thereby minimizing the impact on power supply to the bus thereby supporting critical loads and
the running motors and loads on the decaying bus. critical motors in the system. However, accomplishing a high-
In addition to the requirements of the residual voltage speed motor transfer involves relatively expensive equipment
transfer scheme, the in-phase transfer scheme requires an and is generally complex to implement.
automatic synchronizer relay to connect the decaying bus The main advantage of the fast bus transfer scheme is that
voltage to the healthy source with near-zero phase angle the power supply is uninterrupted. The possibility of motor
difference. Advanced and accurate information of the tie damage does exist due to motor jogging and this scheme is
breaker closing time is required to make this scheme function the most complex and expensive to implement of those
properly. The in-phase transfer scheme also provides a fast discussed.
method for transferring the motor-bus in instances where the
two incoming supplies are not initially in sync.
The main advantage of the in-phase transfer scheme is that III. IMPLEMENTATION OF A TYPICAL RESIDUAL VOLTAGE
continuous power is provided to the motors and load. The DEPENDANT TRANSFER SCHEME USING THREE
disadvantages may include the remote possibility of motor MICROPROCESSOR BASED RELAYS
damage and the possible requirement of load shedding. Also,
this scheme is more expensive and complicated to implement The typical automatic main-tie-main bus transfer scheme
as compared to the other schemes discussed. minimizes the effect of outages during a transformer fault or
an undervoltage condition on one of the incoming supplies by
D. Fast Bus Transfer opening the incoming breaker (for example, SB1) connected
to that supply, then re-energizing the decaying bus by closing
In the event of a loss of the incoming source, this scheme the bus tie breaker (52-T). This transfers the decaying bus to
transfers the motor bus to the alternate healthy source as fast the other healthy incoming source (for example, SB2).
as possible by keeping the dead time to a minimum. A To protect motors connected to the decaying bus from
simultaneous / parallel fast transfer scheme simultaneously damage, the bus tie breaker (52-T) is not allowed to close
issues commands to open (trip) the normal incoming source after a transfer has been initiated until the decaying (residual)
breaker, close tie breaker and close the alternative healthy voltage on the bus has been reduced to a safe level.
incoming source breaker. By doing so, it limits the total In addition, the scheme also confirms the following before
transfer time from 1 to 2 cycles (power system frequency). issuing a close command:
Since this is a paralleling scheme it requires that the circuit 1. Both incoming breakers (SB1 and SB2) are racked-in
breakers interrupting and incomer transformers withstanding and closed with the tie breaker (52-T) also racked-in.
capabilities be rated for the parallel operation. The sequential 2. The incoming breaker is not carrying any fault
fast transfer scheme prevents the paralleling of the incomer current. This prevents a faulted bus from being
supplies while transferring the motor-bus by first tripping the transferred to the alternative healthy source.
normal source breaker of the lost incomer source, closing the 3. There is no undervoltage condition existing on the
tie breaker and then closing the alternative healthy source other incomer source and no voltage dipping,
breaker. However, the total transfer time is increased by the followed by a consecutive voltage restoration of both
normal source breaker tripping time plus the time required in the incomers due to a system disturbance.
acknowledging the breaker open status.
Both of the fast transfer schemes (simultaneous & Traditionally, the automatic bus transfer scheme was
sequential) require a fast synchrocheck relay to detect the implemented by using individual electromechanical relays,
change in relative phase angle between the and by developing the control systems of electrical interlocks
disconnected/decaying bus and the alternate source voltages separately. The relay panels would be rather large with space
before closing the alternative source to the decaying bus. This for discrete relays along with associated voltmeters, amp-
scheme is also referred as supervised fast transfer scheme. meters, and control & selector switches.
In addition to the above requirements, this scheme requires a Developments in relay technology led to the first generation
dynamic high-speed synchronizer relay to ensure that the of microprocessor-based relays. They offered simplicity in the
phase angle, frequency, and voltage magnitude difference implementation of the automatic bus transfer scheme by
between the motor bus voltage and the alternative source providing a built-in control system and protection elements as
voltage is within acceptable limits prior to issuing the closing shown in Figure 2, which uses three microprocessor based
command to the alternative healthy breaker. relays. This configuration has extensive wiring between the
contact inputs and contact outputs of the three
microprocessor based relays.
Fig. 2. Diagram of Three Microprocessor Based Relay Implementation of Main-Tie-Main Transfer Scheme

These first generation microprocessor-based relays were ƒ Similarly, the blown fuse of the measured voltage
superior in providing control and protection elements in inputs could cause the initiation of the bus transfer
comparison to their ancestral electromechanical relays. scheme and needs to be blocked.
However, they still lacked a custom built automatic bus ƒ While transferring the motor-bus to another healthy
transfer scheme, due to their limited hardware and software incoming source, there is need to select control
capabilities. Due to the various onsite practices, the mediums (based on the measured analog inputs) to
implementation of the residual voltage dependent bus transfer decide the completion of the transfer. For example,
scheme also varies from one site to another and requires a monitoring an overloading condition on the incoming
great flexibility in its implementation. Here are the few transformer and its required load shedding.
examples of onsite flexibility requirements. ƒ Need for more inputs and outputs from the relay to
ƒ On the return of the lost power supply, it is the practice implement electrical interlocks (such as picking up
of using various restoration methods such as: manual master trip relay 86 for a fault on the bus side) which
and automatic; close transition and open transition. also creates undervoltage condition on the incoming
ƒ Generally the line side Potential Transformer (PT) input feeder, and to avoid paralleling of the incoming
detecting undervoltage on the incomer supply is phase- sources.
phase or phase-ground. This arrangement cannot
detect a blown fuse condition on the unmonitored
phase-ground voltage of the primary side of the
incoming transformer.
IV. PEER-TO-PEER COMMUNICATIONS USING IEC61850 ƒ Interlocking (bus protection) with downstream relays
GOOSE MESSAGING can be accomplished with IEC61850 GOOSE
messaging
Technological advancements in relay hardware design and ƒ Scheme alarms when either protective relay is off-line
the development of high-speed peer-to-peer communication or not communicating.
protocols have resulted in a new generation of intelligent ƒ Reconfiguration of scheme without time and expense
electronics devices (IEDs). These protective and control of additional wiring.
relays have the capability to accept multiple levels of current .
and voltage inputs and to analyze these values at significantly
increased speeds. The main advantages of using these
numerical IEDs are simplification of the automatic bus transfer
system, component cost reduction, increased system
reliability, and the availability of events for transfer analysis.
An efficient way to apply these IEDs and obtain a custom-
built automatic bus transfer scheme is to use high-speed
peer-to-peer IEC61850 GOOSE messaging between two
protective relays. IEC61850 uses an Ethernet connection as
the medium of communication between the protective relays.
Logical I/O via Ethernet communications is used in place of
traditional hard wire to exchange the information between the
two protective relays. The information sent over the network
might include main and tie breaker status, voltage detector
status, current detector status and transfer scheme status.
Modern IEC61850 implementations are able to send
messages between relays at speeds of around 2-4 ms. Also,
IEC61850 has recently added the capability of exchanging Fig. 3. Data Exchanged Between Two Protective Relays with
analog data between relays so actual values of currents and IEC61850 Peer-to-Peer Communications
voltages are now also able to be sent over the high speed
network. Figure 3 illustrates some of the data that can be
exchanged between the two relays via the high-speed When applying main-tie-main automatic bus transfer using
network. two protective relays and IEC61850 GOOSE messaging,
When using IEC61850 GOOSE messaging, one can limit protective relay 1 will be the master and implement automatic
the wiring to the protective relay to the following: bus transfer logic and provide protection for Main 1 circuit
breaker. Protective relay 1 controls Main 1 circuit breaker and
ƒ 3 phase & ground currents Tie circuit breaker. Protective relay 1 provides overcurrent
ƒ 3 phase bus voltages protection for Main 1 circuit breaker. Protective Relay 2
ƒ 1-3 phase line voltages provides overcurrent protection and transfer control for Main 2
ƒ 52a contact circuit breaker. Figure 4 shows the typical configuration.
ƒ TOC contact (is breaker racked in?)
ƒ Trip output
ƒ Close output

Reduction in wiring is attractive to the switchgear builder


and allows them to limit the wiring across shipping splits.
The advantages of using two protective relays and
IEC61850 GOOSE communications are:
ƒ Significant reduction in hardwiring as compared to that
between traditional bus transfer schemes.
ƒ Transmitting and receiving digital status between two
protective relays high speed via Ethernet port.
ƒ The use of programmable logic controller functions
such as timers and control logic within the protective
relay provides for the flexibility to implement a custom
bus transfer scheme to best meet the needs of the
application.
ƒ Selector switch functions (select to trip, auto transfer
on/off) can be traditionally wired switches, or
implemented via protective relay faceplate
programmable pushbuttons, eliminating components
and installation costs.
Fig. 4. Transfer Scheme Solution Using Two Protective Relays with
IEC61850 Peer-to-Peer Communications
V. AUTOMATIC M-T-M BUS TRANSFER SCHEME USING
SINGLE IED
The final implementation we will discuss uses a single Source 1 Source 2 Tie Brkr
S1 Clsd. S2 Auto Dead
52a 52a 52a TOC 86LOR 43AM Spare
protective relay IED with the capability to accept the Contact Contact Contact Contacts
Pref. Trans Pref. Return Source

necessary number of current transformer (CT) and potential


transformer (PT) inputs required for the application.
B3b H7a H7c H8a H8c P7a P7c P8a P8c U7a U7c U8a U8c

B3a

S1 S1 TIE TIE S2 S2
+Power CLS TRIP CLS TRIP CLS TRIP
+ + + + + +

B5b H4c H1c H3c H6c H5c H2c


Power
Supply

B6a H4b H1b H3b H6b H5b H2b

S1 S1 TIE TIE S2 S2
-Power
CLOSE TRIP CLOSE TRIP CLOSE TRIP

Fig. 5. Automatic Bus Transfer with Single IED Fig. 6 Discrete Inputs and Outputs for a Single Protective
Relay Transfer Scheme
The protective relay performs the logic necessary for the
transfer scheme internally via programmable logic. Figure 5
shows this type of configuration. The relay used in a single IED transfer scheme must have
Using a single IED for automatic bus transfer has the expanded capabilities to perform the transfer function. First,
following: the relay must have three phase voltage inputs for both mains
ƒ Position and status indications for each circuit breaker. and if residual voltage transfer is desired a voltage input for
ƒ Phase and neutral/ground overcurrent protection for each bus. Three phase voltage inputs are necessary to
Main 1 and Main 2 circuit breakers. transfer on negative sequence overvoltage as well as loss of
ƒ Undervoltage supervision for Main 1, Main 2, and Tie source. This allows the bus to be transferred before
circuit breakers. equipment is damaged or motors are tripped on negative
ƒ Synchronism check for closing Main 1 & Main 2 circuit sequence voltage. The relay must also have sufficient
breakers undervoltage elements and negative sequence voltage
ƒ Transfer auto/manual selection via front pushbuttons or elements to implement the scheme. Lastly, the relay must
external control switch have sufficient logic capabilities to perform the transfer for all
ƒ Transfer scheme lockout and block via internal three breakers.
programmable logic A single protective relay IED that performs all of the transfer
ƒ Trip selector via front pushbuttons or external control needs of the switchgear simplifies design of the transfer
switch. scheme because information is no longer needed to be
ƒ Oscillography & sequence of events capture entire passed from one relay to another. As an additional benefit,
scheme operation and timing. with one relay, the programmable logic settings to provide the
ƒ Ability to custom the transfer scheme to any transfer functions can more easily be tested in simulation
application. conditions before the switchgear is installed reducing
commissioning time. This highlights an additional benefit of
single relay transfer schemes; the relay logic can be
configured such that, with limited modifications, one logic
setting can provide transfer for any bus architecture or
transfer option. The same logic settings can use pushbutton open/close breakers, rack in/out breakers, change
or discrete inputs to provide several options of transfer operating selector switch positions, etc.
including: ƒ If using IEC61850 peer-to-peer GOOSE messaging,
• Main-Tie-Main or Main-Main architectures by make sure all devices are on-line and communicating
treating the Main-Main as a Main-Tie-Main where with each other and that relevant breaker and transfer
the tie is always closed. status are being recognized across the network.
• Open or closed transition modes upon return from ƒ If the synchrocheck is being used, make sure that the
transfer. incoming breakers do not close when the phases are
• A preferred main bus arrangement, that swapped or are out of predetermined phase angle
determines which main is closed in main-main boundary.
architectures or which combination of two breakers ƒ Ensuring that all output contacts operate per the logic
are closed in main-tie-main architectures. and schemes; e.g., the close output contact is asserted
• Auto return or manual return when a signal to close is received from the control
switch, or perhaps via a serial or Ethernet
Discrete inputs, necessary to accomplish the options listed communications link.
above are shown in Figure 6. ƒ Ensuring that an open transition scheme does close
the tie breaker or alternate healthy breaker if the main
breaker fails to open.
VI. TESTING
ƒ Making sure that a transfer does not get initiated when
Unlike conventional transfer schemes using traditional control power is lost to any one of the protective relays
electromechanical relays, testing microprocessor-based and that the bus is experiencing a short circuit fault.
automatic transfer schemes requires additional steps and There are both advantages and disadvantages when testing
better understanding of the different logic used within the microprocessor-based relays and associated transfer scheme
protective relay(s). Knowledge regarding the software and logic.
firmware revision is required before programming these Among the disadvantages are that the programmable logic
microprocessor-based relays. Microprocessor-based relays is more complex and may require additional testing time and
generally have numerous pages of settings to be entered into software tools. Additional training may be required of both
the protective relay to ensure the proper functionality. engineers and technicians to properly program and test these
Moreover, it is necessary to determine which settings protective relays. Also, the programming and configuration of
specifically affect the transfer scheme. We also need to bear the protective relays is a complex process that not only
in mind that some manufacturers have factory default settings requires knowledge of the application but knowledge of how to
values already installed on these protective relays and only by integrate the relay into any possible automation systems via
understanding these values one can accomplish the desired Ethernet or serial communications.
functions. Here are the basic requirements for the on-site A key advantage is that a programming standard can be
starting and testing of the transfer scheme: developed and implemented at numerous locations with
ƒ Understanding the method for programming the decreasing engineering development costs after the standard
protective relay by downloading the settings using a is developed. Microprocessor-based relays also offer
personal computer via front port or Ethernet port. numerous tools in terms of event recording, oscillography, and
ƒ Verifying the firmware revisions on the protective the ability to send information to different places via serial or
relays and ensuring they are the most recent or at Ethernet communications networks. Software tools allow the
least the same on all protective relays. real-time graphical representation of the programmable logic
ƒ Ensuring the date and time synchronization (time and aid in the transfer scheme testing and troubleshooting.
stamping) on the protective relays is correct (in order The process of document control can also be streamlined as
to facilitate troubleshooting). settings can be stored in files apart from the actual protective
ƒ Understanding the different means by which the relay and any changes can be done off-line before sending to
protective relays communicate with each other; e.g. the protective relay.
contact inputs/outputs, serial port communications,
analog inputs, virtual inputs/outputs, Ethernet
networking, etc. VII. CONCLUSIONS
Once the protective relay has been properly programmed,
one can proceed in applying voltages and currents to the The bus transfer scheme in industrial and utility facilities is
protective relay (s). Applying an undervoltage on one of the a critical application that requires careful thought in how it is
sources and watching the source breaker trip (open) and the implemented. While electromechanical relays have provided
alternate source or tie breaker close does not complete the a reliable solution for a number of years, it is imperative that
true testing. On microprocessor-based protective relays, it is modern organizations seek to utilize new technology to
very important to work through all the different scenarios optimize resources and improve efficiency. Proven installed
applicable to the design and to ensure all criteria are met. solutions exist today using single IED or multiple IED
Some additional checks while testing an automatic transfer configurations and IEC61850 based peer-to-peer messaging.
scheme are: Engineers, designers, and technicians in the field need to be
ƒ Verifying that all contact and analog inputs are adequately trained on the full capabilities of the new
registered by the protective relay(s). For example, technology so that the different parts of the organization can
fully utilize the technology. From there, the organization can
reap the benefits of streamlined design and system operations
that maximize reliability and overall efficiency.

VIII. BIOGRAPHIES
Craig Wester is the southeast US regional sales manager
for GE Digital Energy Multilin in Norcross, Georgia. He was
born in Belgium, Wisconsin, and received a B.S. in Electrical
Engineering with a strong emphasis on power systems from
the University of Wisconsin-Madison in 1989. Craig joined
General Electric in 1989 as a utility transmission & distribution
application engineer. He is a member of the IEEE.

Terrence Smith has been an Application Engineer with GE


Digital Energy Multilin since 2008. Prior to joining GE,
Terrence has been with the Tennessee Valley Authority as a
Principal Engineer and MESA Associates as Program
Manager. He received his Bachelor of Science in Engineering
majoring in Electrical Engineering from the University of
Tennessee at Chattanooga and is a professional Engineer
registered in the state of Tennessee.

Vous aimerez peut-être aussi