Vous êtes sur la page 1sur 2

Asphalt Paving Speed

work tips pavement work tips — no. 31


INTRODUCTION Where:
November 2001

Key Summary
An important element in achieving smooth P = Paver forward
riding asphalt pavements is maintaining steady speed (metres/minute)
This issue provides
continuous paving. General guidance on smooth D = Delivery rate a guide to the
paver operation is provided in Work Tip No 3. (tonnes/hour)
calculation of paver
This Work Tip provides a guide to calculation w = width of spread forward speed for
of paver speed and roller capacity to enable (metres) smooth continuous
matching of: t = compacted paving and matching
• Asphalt plant production rates to average paver thickness (mm) roller capacity to
speed so that the paver can be kept moving d = compacted density ensure effective
steadily forward, averaging out minor of asphalt (t/m3). compaction.
variations in arrival of delivery trucks. Alternatively, the rate
• Paving speed to roller capacity so that the paver of delivery to match a particular paver forward
forward speed (and rate of supply) does not speed can be calculated from:
pavement

exceed the capacity of rollers to provide


effective compaction, or alternatively to P × w × t × d × 60
D=
determine the number of rollers required to 1000
achieve compaction for a given output. The above formulae can be used to develop
tables or charts for typical paving widths.
PAVER SPEED
Figure 1 illustrates paver forward speed for
The general formula for calculating paver various thicknesses of asphalt, a spread width of
forward speed for a given rate of delivery of 3.7 m, and a typical density of 2.40 t/m3. In the
asphalt is: example of roller capacity (over), an average
D × 1000 forward speed of the rollers of 4.7 m per minute,
P= and compacted thickness of 40 mm, can be
60 × w × t × d
matched to a spreading output, or average mix
delivery rate, of 100 t/h.
Figure 1 Paver Speed continued on reverse

400
m
0m
Mix Deliveries - tonnes per hour

300
10

m
m
75

m
m
200 50
mm
40 th
Dep
t ed
o mpac
m C
25 m
100

AUSTROADS Example
Note: Paver speed
based on spread 3.7 m
wide and a compacted
density of 2.40 tonnes
3 6 9 12 15
per cubic metre Paver Speed - m/min

pavement work tips is produced by AUSTROADS in conjunction with AAPA


For more
Asphalt Paving Speed page 2 information on any
of the construction
practices discussed
COMPACTION CAPACITY The total number of passes is the number of in "pavement work
roller laps multiplied by the number of passes per tips", please contact
Rollers have to travel a much greater distance either your local
roller lap, plus any makeup pass the roller takes to
than the paver within a given time frame. The AUSTROADS
travel over the compacted section in order to reach Pavement Reference
number of roller passes does not increase in
fresh pavement. Group
proportion to the thickness of layer but net
forward travel speed is dependent on the rolling For example a roller of 1.4 m width will require representative or
3 laps to cover a paving width of 2.4 to 3.7 m. AAPA —
speed and number of passes to cover the paving
One complete coverage (3 laps) with two passes tel (03) 9853 3595;
width. fax (03) 9853 3484;
per lap will require 6 passes. Two coverages of
The primary factors determining production e-mail:
the mat will require 6 laps (12 passes).
capacity of an asphalt roller are: info@aapa.asn.au
With an extra lap for the longitudinal joint, the A complete list of
• Drum width total number of passes becomes 14. A makeup "pavement work
• Number of passes pass brings the total to 15. tips" issues is
• Roller speed. In the above example, a roller travelling at 6 available on AAPA's
km/h (100 m/min) and an overall efficiency of web site:
Other conditions must also be met, including www.aapa.asn.au
the number of roller passes required to compact factor of 0.7 for non-productive time and travel,
will result in an average forward speed of: Issues may be
the asphalt and the amount of time that the freshly downloaded using
placed asphalt is exposed before it is compacted. 100 x 0.7 / 15 = 4.7 m/min. Adobe Acrobat
The allowable time for compaction will be reduced Reader. Copies may
when placing thin layers, low pavement surface Typical speeds for steel drum vibratory rollers also be obtained
temperature or when cool winds increase the rate commonly used for primary compaction of from AAPA.
of cooling of the mix. asphalt, are 3 to 6 km/h for thick layers and up to Material may be
Allowance must also be made for short breaks 10 km/h for thin layers. freely reproduced
providing the source
(filling with water, etc.), joint compaction, extra
Efficiency of vibratory rollers diminishes with is acknowledged.
distance travelled in changing lanes, and time taken
increased speed. Speeds greater than 7 km/h are This edition was
to change direction. Typically, a roller can be
not commonly used where high density is prepared by
expected to work for 50 minutes per hour, with a John Rebbechi in
required.
further 10 to 15% loss for non-productive work, consultation with
taking the overall efficiency to around 70 to 75%. Forward speed should also be linked to members of the
Longitudinal overlaps will vary according to how frequency of vibration. Around 33 beats per metre National Asphalt
the drum width suits the overall paving width and is considered an optimum relationship between Research
is generally a minimum of 150 mm. frequency and forward speed. Coordination
Group (NARC).
Figure 2 Typical Rolling Pattern

Width of roller Direction of paving

1
Width of lane being paved

2 LAP 1

3
7 4 LAP 2

5
6 LAP 3

Every pass of the roller should proceed straight into the uncompacted mix and return on the same path.
After the required passes are completed, the roller should move back across the lane (path 7) and repeat
the procedure.

Austroads and AAPA believe this publication to be correct at the time of printing and do not accept responsibility for any consequences arising from the use of the information
herein. Readers should rely on their own skill and judgement to apply information to particular issues.

Vous aimerez peut-être aussi