Owner :
Main Contractor :
Sub Contractor :
Consultant :
Project Title :
TRUCK MOUNTED GAS TURBINE POWER PLANT
PAYA PASIR – MEDAN 75 MW
DOCUMENT NO. :
TMGT-PPM-C1-WS-001
PURPOSE :
PAGE : 2 of 12
DISTRIBUTION LIST
PP GE
PAGE : 3 of 12
TABLE OF CONTENTS
1 GENERAL ......................................................................................................................................... 4
2 STORAGE AND HANDLING ............................................................................................................. 4
3 SETTING OUT .................................................................................................................................. 4
4 JACK-IN OF PILES ........................................................................................................................... 5
4.1 Jack-In of Piles .......................................................................................................................... 5
4.2 Installations ................................................................................................................................ 5
4.3 Welding of Pile Joints ................................................................................................................ 6
4.4 Inspection .................................................................................................................................. 7
4.5 Jack-in Record........................................................................................................................... 7
4.6 Pile Loading Test: ...................................................................................................................... 7
4.7 Tolerance................................................................................................................................... 7
5 ATTACHMENTS................................................................................................................................ 7
JOB NO : 16-12401
PAGE : 4 of 12
1 GENERAL
1.1 Scope
This specification covers the requirements for piling work to be provided for Paya Pasir Truck
Mounted Gas Turbine Power Plant Project owned by PT PLN BATAM with total net capacity 75 MW
and is located in Medan Marelan District, Medan City, North Sumatera province.
1.2 References
This material shall be in accordance with the latest issue of the following codes and standard :
ANSI/AWS D1-1 Structural Welding Code
JIS A 5335 Pre-tensioned Spun Concrete Piles
1.3 Materials
Piles are Pre-stressed Concrete Spun Piles with minimum compressive strength fc=500 Mpa at 28
days (cylinder test), cement type II and shall conform to JIS A 5335 or equivalent. Type of shoe shall
be mamira or pencil type.
The Subcontractor shall submit a detailed description of driving machines and a detailed
construction procedure for Contractor approval. The construction procedure shall include, but not
limited to the following :
3 SETTING OUT
(1) Underground facilities, if any, shall be provided with sufficient protections and shall be checked to
confirm that they are not adversely affected.
(2) If necessary, Subcontractor shall demolish existing concrete pavement.
(3) The Subcontractor shall properly set out the centre of each pile position and shall establish position
and level marks by means of triangular and return leveling. Setting out and markings shall be
adequately protected until the works have been completed. Refer to tolerances of locations stated
in section 4.7 in this specification.
(4) Setting out shall be carried out from the control points. Immediately before installation of the pile,
the pile position shall be marked with suitable identifiable pins or markers.
JOB NO : 16-12401
PAGE : 5 of 12
4 JACK-IN OF PILES
This work shall comprise installation of the precast prestressed piles, inclusive of pitching and jacking,
pile splicing and cutting, all in accordance with this specification and to the details shown on the
drawings.
4.2 Installations
The Equipment shall have the capacity to jack-in the piles to the certain depth and / or reach
ultimate bearing capacity as described below :
- Diameter and Depth of Pile refer to DWG No. TMGT-TRL-C1-DW-001 Piling Plan.
- Capacity of Pile refer to Soil Investigation and Analysis Report.
Jacking equipment, its accessories, and related equipment shall be subject to inspection and
approval by PT PLN BATAM prior to execution.
Piles shall be pitched accurately in the positions as shown on the drawings. At all stages
during installation and until the pile has set, all exposed piles shall be cut off to the ground
level by means of diamond cutter. All cutting of pile to the cut off level shall be prevented from
damage and deviated out of position. For all piles to specified lengths, pile head cut off shall
be avoided by using suitable combination of pile lengths.
- Each pile shall be hydraulically injected continuously until the specified pressure gauge
reading and/or depth has been reached. A follower (long dolly) is not permitted unless
approval has been obtained from Contractor Engineer. The Subcontractor shall inform
Contractor Engineer without delay if an unexpected change in driving characteristic is
encountered.
- A detailed record of the jacking resistance over the full length of each pile shall be kept.
The log shall record loading resistance for every 300 mm of pile penetration.
- The pile other than frictional pile will be considered SET when the pile has ceased to settle
at the recorded pressure which gives a resultant load of 2 times the design load, unless
otherwise agreed by Contractor Engineer.
- Unless otherwise specified in the Drawing, all friction piles shall be jacked to the specified
depth.
JOB NO : 16-12401
PAGE : 6 of 12
When the following criteria are satisfied, the pile jacking shall be terminated with the prior
approval of Contractor Engineer.
- The in-ground pile length indicated on the design drawing is mostly satisfied
- The termination criterion is to jack the pile to 2 times of the design load for a minimum of
two cycles or other safety factor as instructed by Contractor Engineer. The corresponding
pressure has to be held for minimum 30 seconds without settlement or unless otherwise
specified by Contractor Engineer. The process shall be repeated if instructed by Contractor
Engineer.
- In case where it is difficult to jack piles to the required depth, instructions given by
Contractor shall be followed immediately at the time and not allowed to delay the pile
jacking within 12 hours.
(1) Pile shall be spliced in accordance with PC Pile manufacturer and/or as described in
attachment -1
(2) Pile joints shall be welded in accordance with AWS D1.1 or equivalent.
(3) Shielded metal arc welding equipment with sufficient capacity shall be used. Welding rod
shall refer to AWS or equal.
(4) Parts to be welded shall be cleaned of rust, mud and all other foreign matter by wire
brushing.
(5) After the upper pile in secured in position, the pile axes shall be aligned and offsets and root
gaps shall be corrected.
(6) Tack welding prior to full welding shall be done, for the purpose of holding piles firm in place,
if necessary.
(7) Prior to welding, the welding current, voltage, speed, and manipulation shall be confirmed.
Welding shall be done so that no defect may be caused.
(8) No welding shall be done during rain or when a strong wind is blowing.
Even under such weather conditions, welding may be done if the following conditions are
satisfied:
- The welder and the parts to be welded are properly protected.
- Approval is obtained from Contractor.
- Proper measures are provided for the base metal.
(9) The welder shall passes procedural qualification specified in AWS.D.1.1 or equivalent under
the local code and a copy of the certificate shall be submitted to the Contractor.
(10) After the welding work is completed, the welded point will be visually checked by Contractor.
(11) After welding finished, inspected and tested all steel joint surface shall be coated by coal tar
epoxy coating or similar.
JOB NO : 16-12401
PAGE : 7 of 12
4.4 Inspection
(1) All weld shall be visually inspected in accordance with the acceptance standards and
requirement of ANSI / AWS D1.1 section 8.6 " Quality " and section 5.24 " Weld Profile "
Also the weld shall not have any cracks, undercut exceeded 0.8 mm depth, exposed surface
porosity, and slag inclusion.
(2) LPT (Liquid Penetrant Test) shall be performed at the rate of 10% minimum for random
location, but subject to change depending on welding production performance. Record and
Inspection forms are attached as an example. (See ATTACHMENT - 5).
An original and complete Jack-in record of each pile shall be submitted to Contractor daily. The
complete record in a tabular form for each Jack-in pile shall include:
- material size and length of piles
- the pile identification number,
- batter or vertical designation,
- location of each pile with coordinates, time and date driven,
- actual penetration depth and length of piles,
- details of equipment,
- size length of Pile hoisting and weight of lift weight used,
- ground elevation, and tip elevation,
- pile cut elevation
- and any abnormality, if any.
Format of jack-in record are attached as an example. (See ATTACHMENT 2).
During the works, maximum 10% of the total number of working piles should be load tested up to
1.5 times working load by PDA Test Method and Pile Integrity Test (PIT) to demonstrate that
meets the design criteria including adequate bearing capacity and immediate settlement
characteristics and that the level of workmanship given in the construction proposals can be
achieved. Full recording and monitoring shall be carried out during piling as relevant to the pile
type.
4.7 Tolerance
5 ATTACHMENTS
ATTACHMENT – 1 Pile Splicing
ATTACHMENT – 2 Quality Control Daily Pile Quality Control Record
ATTACHMENT – 3 Daily Piling Record
ATTACHMENT – 4 Piling Site Report
ATTACHMENT – 5 Welding Inspection
JOB NO : 16-12401
PAGE : 8 of 12
ATTACHMENT – 1
PILE SPLICING
Welding Specification:
Joint Details
Dia. a Lo
300 8.0 4.2
350 8.5 4.2
400 9.5 4.2
450 10.0 4.4
600 12.0 4.4
JOB NO : 16-12401
PAGE : 9 of 12
ATTACHMENT – 2
QUALITY CONTROL
DAILY PILE QUALITY RECORD
TRUCK MOUNTED GAS TURBINE POWER PLANT
Prepared by
SUB/CON. INSP_____________________
PAGE : 10 of 12
ATTACHMENT – 3
PAGE : 11 of 12
ATTACHMENT – 4
PAGE : 12 of 12
ATTACHMENT – 5
WELDING INSPECTION
Project :
Location :
Area :
Date :
Weather :
PILE
JOINT WELDING
DWG NO. REF. WELDER INSPECTION RESULT TIME
NO. ELECTRODE
NO.
Inspection Method:
V : Visual
LPT : Liquid Penetrant
PR : Radiographic Test
Inspection by Witness by
CONTRACTOR PT PLN BATAM
_______________________ ___________________