Vous êtes sur la page 1sur 6

Estimate of the 11 KV Trqnsmission Line on 9 MTR PCC Pole

RATE PER
S.NO. PARTICULARS OF MATERIAL UNIT Qty AMOUNTS
UNIT
1 Lattice tower 42' Long with cross arm Nos. 27700

2 PCC Pole 9 Meter Long (200 KG) Nos. 18 2700.00 48600.00

11 KV Cross Arm Set with top hamper &


3 Set. 18 695.00 12510.00
clamps
4 11 KV PIN Insulator Nos. 60 45.00 2700.00
5 11 KV G.I. PIN Nos. 60 65.00 3900.00

6 11 KV Disc lnsulator 45KN (T&C) Nos. 12 254.00 3048.00

7 Hardware SetFor(T&C) Nos. 12 120.00 1440.00


8 G.I. Stay Set 16 X 1800 mm Set. 10 490.00 4900.00

9 G.I. Stay Wire 7/10 S.W.G (7 / 3.15 mm) Kg 80 70.00 5600.00

10 11KV Stay Insulator Nos. 10 25.00 250.00


11 ACSR WEASEL Conductor KM 3.9 25000.00 97500.00
12 11 KV Line DP Set Set. 2 5800.00 11600.00
14 11 KV Cut point Channel Nos. 4 350.00 1400.00
15 M.S.Nut bolts kg 20 80.00 1600.00

16 Earthing Set Nos. 2 700.00 1400.00

17 G.I.Earth Wire 8 SWG kg 50 75.00 3750.00


Misc LS 105.50
Total Rs. 200303.50
Over Head Charges @ 35 % Rs. 70106.23
Grand Total Rs. 270409.73
e

Remarks

Rate Only

Alternate pole consider

Only consider with DP set


lABOUR CHARGES FOR ERECTION OF 1 KM 11KV LINE

CLRC LABOUR
PARTICULARS UNIT QTY
NO RATE

1 Conducting route survey as per approved route map


and pegging of route with tee off point section point Km. 300.00 1.000
& double pole locations.
2 Trimming of tree branches/plants and preparing Per
route approchases for proposed line. tree/ 40.00 0
plant
3 Excavation of pit in ordinary rock which does not
require blasting to erect various supports and stay
sets including stacking of excavated muck from the Pit 290.00 22
edge of excavation/pit. 9 Mtr/1,2mx0.6mx1.50 m
deep
4 Erection of PCC poles in excavated pit with fixing of
brackets,cross arms & top hampers as required in
alignment after checking the same with plumb line.
The support is to be back filled with soil with proper Nos. 425.00 18
ramming.PCC Poles 9 Mtr. Long(200Kg.)

6 Fixing and assembly of disc.point channel pair with


pilot plates top hampers & clamps on erected single Nos. 70.00 2
pole structure as per design.
7 Fixing of 11kv B&S/T&C type disc insulator of 11kv
lines (each unit consiting of 1nos.disc.& 1set of
H/W ) on terminal point including fixing of Nos. 30.00 6
hardware and strips.
8 Fixing of 11 KV pin insulator with pins. Nos. 15.00 60
12 Excavation of pit in ordinary rock which does not
require blasting to erect various supports and stay
sets including stacking of excavated muck from the Pit 250.00 10
edge of excavation/pit
Stay set/Depth of pit :- 6'x 5/8" -0.75x0.5x1.35 m
13 Erection & fixing of G.I.Stay sets with anchor plates
in excavated pit in required position and back filling
with soil with proper ramming.The work includes
fixing of stay clamps.Stay insulator with stay wire at Nos. 300.00 20
both ends with proper tension.Size of stay set/stay
wire,6"x5/8" with 7/10 SWG stay wire
14 Erection &assembly of 2 Pole structures of steel
(11KV Line DP) supports or PCC poles in excavated
pit in alignment after checking the same with plumb
line.lncluding fixing of top bracing of M.S.Channels
with pilot plates and clamps.The support is to be
back filled with soil with proper ramming.The nuts Nos. 1400 2
&bolts are to be provided by the contractor as per
Nigams specfication for which the payment will be
made at the prevailing Discom store issue rates.

15 ACSR WEASEL-Laying ,jointing , stringing,


tensioning and clamping of conductor with proper
sag as directed , using bolted type hardware
including binding on pin insulators,jumpering on
section points with binding wire / km/co 1500.00 3.900
P.G.clamps.Aluminium jointing sleeves will be used nd.
for jointing the conductor.The line must stand at
proper voltage on charging.

Total
NE

AMOUNTS

300.00

0.00

6380.00

7650.00

140.00

180.00

900.00

2500.00

6000.00
2800.00

5850.00

32700.00

Vous aimerez peut-être aussi