Académique Documents
Professionnel Documents
Culture Documents
September 2015
Disclaimer: This Condition Based Maintenance Manual for Distribution Substation (PE) is a
document providing technicians, engineers, and managers of the Distribution Division of Tenaga
Nasional Berhad with an understanding of Condition Based Maintenance methodology. The
information in this document has been prepared in good faith and represents the Asset
Management Department’s intentions and opinions at the date of issue. The Asset Management
Department may change any information in this document at any time.
ii
Acknowledgement
We would like to express our deepest gratitude to the management of the
Distribution Division, for giving us the opportunity to develop the Condition
Based Maintenance Manual for Distribution Substation (PE).
Special thanks to Mr. Zahari bin Dollah, Mr. Roshimee Mustapha, Mr.
Mohammad Khuzairee b. Ibrahim, Ms. Komal Deep Kaur, Mdm. Noor Hanisa
bt Ali, Ms. Nursyahira Sharif, as well as the SL1M trainees, Ms. Sumaiyah bt
Mohamad Sani and Mr. Aizuddin b. Abd Rahim from Asset Management
Department, for their valuable contribution and assistance in developing this
manual.
The project team would also like to express our gratitude to Technical Experts
Mr. Young Zaidey B. Yang Ghazali and Mr. Sharizal B. Shamuri from Asset
Management Department and not forgetting Mr. Pairolani Bin Hj. Hashim
from ILSAS for their valuable input and guidance to develop this manual.
Our appreciation also goes to TNBR QATS staffs headed by Mr. Zulfadly Zardi
and team comprising Mdm. Nurul Farhana Yanti bt A.Ghani, Mr. Mohd
Fakhrurrazi bin Husain and Mr. Abu Sufian bin Abu Bakar for providing
information and data of equipments for maintenance testing.
Thank you.
Foreword
VP Distribution Division,
Datuk Ir. Baharin Din
Although various technical and engineering circulars and guidelines have been
issued from time to time, it is found that discrepancies in standard practices
of Condition Based Maintenance for switchgear and transformer among states
are still widespread, thus affecting the performance and lifespan of the
switchgear and transformer. In view of this, it is timely that such a practical
handbook on Condition Based Maintenance of Distribution Substation (PE) is
produced for easy reference throughout TNB Distribution Division.
Thank you.
iv
Contents
Chapter 1 Introduction ..........................................................
. 1
1.1 Overview .................................................................................................... 1
1.2 Objec ves .................................................................................................. 2
1.3 Scope of This Manual................................................................................. 3
1
Chapter 1 Introduction
1.1 Overview
Distribu on network assets are developed, operated and maintained to
provide distribu on of power to the consumers. In TNB Distribu on, these
assets that consist of various equipment are grouped as follows:-
Primary Systems
Secondary Systems (prote on relays and telecontrol equipment)
In line with industries pra ces in managing the asset and with the increasing
expecta on for maintenance to deliver improved performance, Distribu on
Division has prepared this Cond on Based Maintenance Manual for
Distribu on Substa on (PE).
2 Distribution Substation ( PE)
1.2 Objectives
1
The objec ves of this manual are as follows:-
Table 1-2 : Maintenance Interval for Switc hgear under in-Service Condition
1
Frequency
Diagnostic Techniques
OLU/HFU VCB RMU SF6
Tier 1
Tier 2
Insula on Resistance
18 months 24 months 36 months
(Bushing/Busbar)
- -
Circuit Breaker Timing 24 months
- -
Vacuum Checks 24 months
18 months -
Oil Dielectric -
Tier 3
Par al Discharge Locator & - Condi on Condi on
Monitoring Based Based
SF6 Gas Analysis (Gas Purity, - Condi on
-
Dewpoint & SO2) Based
- Condi on Condi on
Contact Resistance
Based Based
- Condi on Condi on
Power Frequency/ Pressure Test
Based Based
Dielectric Dissip on Factor (DDF) - Condi on
-
Tan δ Based
6 Distribution Substation (PE)
IMPORTANT:
Multiply test frequency dura on in Table 1-2 and Table 1-3 by the factor
in Table 1-1: Maintenance Frequency Matrix .
Chapter 1 Maintenance of Assets 7
Functional Acquire/Create
Policies, Utilize
Strategies,
Standards, Maintain
Process and
Procedures Renew/Dispose
While practicing time based maintenance for Civil and Mechanical Assets, TNB
has adopted and implemented a condition based maintenance strategy for all
electrical assets.
8 Distribution Substation (PE)
2.2 Methodology
The guidelines review and formulation was carried out based on
manufacturers’ recommendation, statutory requirement and TNB’s operation
and maintenance experience.
2 In general, the inspection and maintenance plan for the assets are categorized
based on Tiers that have been categorized as:-
1. Electrical Assets
2. Civil and Mechanical Assets
CONDITION BASED
MAINTENANCE
CONDITION BASED
MAINTENANCE
TIER 1
TIER 2 PLANNED
TIER 2
TIER 3 UNPLANNED
TIER 3
CONDITION BASED
MAINTENANCE
PREVENTIVE CORRECTIVE
MAINTENANCE MAINTENANCE
ROUTINE/
SCHEDULE IRREGULARITY EMERGENCY
Chapter 3 Switchgear
3.1 Preliminaries
Switchgear is key components in the power system and appropriate for
analysis under a risk assessment program. Switchgear failure can have
significant economic impact due to long lead mes in procurement,
manufacturing and installa on in add on to high equipment cost.
Determining the exis ng cond on of switchgear is an essen al step analyzing
the risk of failure.
3 Switchgear types available in the distribu on system are categorized as
follows:
In vacuum circuit breakers, the fixed and moving contacts are housed
permanently inside a sealed vacuumed ceramic bottle. The arc is quenched as
the contacts are separated in vacuum. In the MV switchgear range, vacuum is
the most predominant insulating medium for circuit breaking.
3
(3) (4)
(1) (2)
3 (5)
(12)
(6)
(7)
(8)
Voltage Level 11 kV
Voltage (kV) 12
Main Busbar Current (A) 2000
Rated Current 630 / 1250 / 2000
Rated Insulation Level 75 kV Peak / 28 kV Power
Frequency 3
Short Time Current 20 kA/25 kA @ 3 sec
Construction Metal Clad
Short Circuit Breaking 20 kA / 25 kA
Current (A)
Closing Operation Motor Charged Spring
Tripping System Shunt Trip
Tripping Control Source DC 30 V / 110 V
Opening Time < 50 msec
Making Time < 60 msec
Typical Dimension (mm) W – 600/800
D – 2200/2250
H – 2300
Relay & Control Switchgear
16 Distribution Substation (PE)
a) Economical
b) Ease of maintenance
c) Space saving
d) Suitable for indoor and outdoor use
3 protection of the RMU (Ingress Protection (IP) rating). IP42 is suitable for
indoor while outdoor applications require a minimum of IP54.
For the insulation, RMU can either use oil or Sulphur Hexafluoride (SF 6) gas.
The insulation is responsible to clear the arc during operation. Other than
that, the insulation will also assist in cooling the bus-bar and the blade inside
the same chamber. The typical ratings for the RMU are given in the following
table.
Chapter 3 Switchgear 17
Short- me Withstand
Load break switch 20kA 3 sec
Earthing switch 2.1kA 1 sec
Making capacity
Load break switch 50 kA peak
5.4 kA peak
Earthing switch
A typical ring main unit (RMU) comprises of two fault-make load-break ring
feeder/ earth switches and one or more tee-off transformer fused switch or
circuit breaker. All live parts, including switching components are housed
within the oil filled or SF6 gas filled enclosures. Gas filled enclosures are
considered sealed for life for normal opera ng cond ons.
Each ring switch is a fully fault making, load breaking device which can be
operated in three pos ons ‘On’, ‘Off’ and ‘Earth’. In some design, cable test
terminals are available with the earth removed by lowering the interlocked
earth bar a ached to the hinged box of the unit depending on the switchgear
model.
The Tee off feeder may be either a fused switch or a circuit breaker employing
rota ng arc device or vacuum interrupters as a means of interrup ng fault or
load currents. The fused switch is normally located outside the gas
compartments while the circuit breaker is housed in the gas filled chamber.
18 Distribution Substation (PE)
The integrity of the quenching medium is the main concern for these RMU
and careful monitoring will ensure its lifespan extension.
3.2.1 Overview
Switchgear maintenance testing can be performed in 3 stages or tiers as
described below.
NOTE: Tier 3 inspections are intended to confirm or refute the need for more
extensive maintenance, rehabilitation, or switchgear replacement.
Chapter 3 Switchgear 21
Insulation Resistance
Tier 2
3
18 months 24 months 36 months
(Bushing/Busbar)
Oil Dielectric Test 18 months - -
- -
Trip Test (On-line timing) 24 months
-
Circuit Breaker Timing (Off-line Test) 24 months -
- -
Vacuum Checks 24 months
Tier 3
Partial Discharge Locator & - Condition Condition
Monitoring Based Based
- Condition
SF6 Gas Leakage Emission -
Based
- Condition Condition
Power Frequency/ Pressure Test
Based Based
Dielectric Dissipation Factor (DDF) - Condition Condition
Tan δ Based Based
- Condition
Contact Resistance -
Based
3.2.3 Tier 1
Table 3-4 : Maintenanc e Testing of Switchgear in Tier 1
Maintenance Tools &
Function Team
Tests/Condition Equipment
1. Thermography To check if there is any FLUKE Ti 32 Vendor,
loose contact or any high Maintenance
resistance surface Team
between any electrical
contact
3.2.3.1 Thermography
1. Switch off all heaters at least 3 hours (if applicable) before any scanning
as the heat from the heaters can mask hot spots in the equipment
scanned.
2. Before scanning, record the loading in Amps and Voltage for each piece of
equipment scanned and status of breaker position (ON/OFF/ISOLATED).
Note: Any external light sources that may be reflected from the
surfaces scanned may cause wrong interpretation of data, for example,
reflection from light sources, sunlight, heat reflection, etc. Ensure there
are no cold drafts or winds blowing directly at then equipment scanned.
Chapter 3 Switchgear 25
Table 3-6 : Result & Condition for Thermography Test (Enclosed Metal Clad)
Result (∆T) Condition
0 °C Good
1 ~ 5 °C Fair
>5°C Poor
Note:
For any temperature difference, further inspe on and analysis is
required. Record and monitor load and ambient temperature.
26 Distribution Substation (PE)
Arcing produces a high frequency ultrasonic signal that is airborne, but when
it comes in contact with the metallic surface of the switchgear, a portion of
3 that signal is refracted through to the other side. Detecting that signal can be
done with an airborne sensor positioned in one of the openings at the panel
covers with the bolt removed or with a contact magnetic sensor directly
touching the panel body.
≥ 1 dB
2. For Ring Main Unit (RMU) and Air Insulated Switchgears (AIS), scan all
the compartments directly using flexible probe.
5. Listen for abnormal sound e.g. crackling, buzzing or frying sounds. Aim
the scanner at each spot for a while before moving on to another spot
so that intermittent discharges will also be captured.
6. Record results in decibel (dB) and store any abnormal sounds for
further analysis by software where necessary. The instrument will
capture both mechanical vibration noise and partial discharge.
≥ 1 dB Tracking,
Serious level, areas of the fault deemed to
Arcing
be serious nature. Shutdown and repair of
the equipment within 2 weeks would be
≥ 4 dB Corona required to avert fire or failure.
*Note:
If ultrasound characteristic (Arcing, Tracking) detected for less than 0
dB, it is considered as serious level. Shutdown and repair of the
equipment within 2 weeks would be required to avert fire or failure.
Chapter 3 Switchgear 29
The partial discharge creates current spikes in the conductor and also in the
earthed metal surrounding the conductor. TEVs are a very convenient
phenomenon for measuring and detecting Internal Partial Discharges as they
can be detected without making an electrical connection or removing any
panels.
10 ~ 50 Surface Tracking
> 50 Interference
TEV Sensor
External
On/Off Button Sensor Socket
Keypad
Headphone
Socket
7. Sensor Capacitive
10. Accuracy ±1 dB
< 20 dB
20 ~ 29 dB
> 29 dB
Chapter 3 Switchgear 31
4. Listen for abnormal sound e.g. crackling, buzzing or frying sounds. Aim
the scanner at each spot for a while before moving on to another spot so
that interm ent discharges will also be captured.
5. Record results in decibel (dB) and store any abnormal sounds for further
analysis by so ware where necessary. The instrument will capture both 3
mechanical vibra on noise and par al discharge.
6. During the course of scanning, eliminate external noise sources that may
interfere with the scanning.
Table 3-14 : Result and Action for Internal Partial Discharge Test (TEV)
Result (dB) Action
Note:
3. DC Power Supplies
Good b ery condi on
Ba ery output voltage (>28.5V when AC OFF )
5. Switchgear Accessories
Complete set of tools for breaker opera on
Complete set of tools for earth switch opera on
34 Distribution Substation (PE)
1. Switchgear Panel
• Standard Feeder Name
3
• Standard Breaker Number
• AMPs Meter
• MCB ‘ON’
• Heater ‘ON’, Amps Reading
• Abnormal Sound
• SF6 Gas Pressure (RMU) Oil Level (RMU)
• Panel Earthing
• Panel Door Tightly Closed
Normal
Green 130 ± 5 -
Operating
2. Cable
• Cable Earthing
• Cable Clamp
• Cable Entry to switchgear compartment properly sealed
3. Earthing
• Oxid on/Loose Connec on/Vandalised
Chapter 3 Switchgear 35
4. EFI
Note :
1. Check for an -vermin at various loca ons in the substa on.
2. Record visit in the Log Book available at the substa on
3. Abnormali es need to recorded in VI check list
36 Distribution Substation (PE)
3.2.4 Tier 2
Tools &
Maintenance Test Team
Function Equipment
3
2. Oil Dielectric To check the break down Oil Test Set Vendor,
voltage of the oil which is Maintenance
used as insulation Team
3. Trip Test (On- To test the breaker in the Trip Test Set Maintenance
Line Timing) energized state so that the Team
performance of the first trip
can be analyzed
4. Circuit Breaker To ignite movement which Timing Test Set Vendor,
Timing may smoothen harden Maintenance
moving parts. Also to check Team
the opening and closing
time of a circuit breaker and
to identify which is the
sluggish part through time
profiling
5. Vacuum Check the integrity of the Vacuum Vendor,
Checks vacuum bottle to ascertain Checker Maintenance
the ability of the breaking Team
chamber to inhibit
flashovers
Chapter 3 Switchgear 37
Insulation resistance (IR) checks are carried out to give an indication of the
relative quality of the insulation system of an equipment.
1. Ensure the correct test instrument is used for the object to be tested by
checking the test voltage. Refer for guidelines on the test voltages.
3 Table 3-20 : Minimum Rating Insulation R esistance Test For Switchgear
Rating of Equipment Test Voltage DC
12 kV 2.5 kV
3. Connect earth lead of the tester to earthing point of the object. Then
proceed with measuring lead of the instrument to the line terminal of
test instrument.
3
Figure 3-12: Insulation Resistance for Circuit Breaker Truck (Open Position)
Figure 3-13: Insulation Resistance for Circuit Breaker Truck (Close Position)
Chapter 3 Switchgear 41
3. Read the value of the insulation resistance and record in test format.
Result Condition
≥ 1 GΩ Good
< 1 GΩ Poor
Chapter 3 Switchgear 43
The obje ve of dielectric test is to check the break down voltage of the oil
which is used as insula on integrity. This breakdown voltage is ind ve of
the amount of contaminant in the oil and samples for tes ng should be
obtained from OLU/HFU er a heavy fault or series of faults and at regular
intervals. 3
Check colour, odour and dielectric strength of insula ng oil.
Check for oil leaks at the seals and gasket.
1. Clean the test instrument, the test chamber, test vessel/container and
the cover from dirt and oil. Rinse with part of the oil sample to be tested
if necessary. Exterior surfaces may be wiped with a clean cloth damped
with an alcohol based cleaning fluid or other cleaning fluids
recommended by the manufacturer.
2. Clean the electrodes and all parts that come in contact with the oil
sample until they are thoroughly clean. Rinse with part of the oil sample
if necessary.
3. Pour the oil sample into the container slowly up to the oil mark indicated
without spilling and without the formation of air bubbles. Be careful not
to introduce any contaminants into the oil sample.
Chapter 3 Switchgear 45
4. Set the gap between the electrodes according to the requirement of the
test undertaken. Confirm the gap has been set properly and lower
electrodes into the oil sample.
5. The oil sample is now ready for testing of its dielectric properties.
1. Ensure step 1 and 2 above are completed before conducting this test.
2. Power up the test instrument.
3. Select the desired test sequence and initiate test. After the initial stand
time for the oil and test set is complete, a high voltage will be applied
between the electrodes according to the test sequence selected. These
test sequences are based on National specifications. 3
Table 3-23: Oil Test Standards
Standard Test AS 1767 CEI 10-1 ASTM D1816 ASTM D877
Specification BS5874 TOCT 6581
Selected BS148 VDE 0370
BS 5730 STAS 286
IEC 156
IP 295
NFC 27
SABS 555
UNE 21
Electrode Shape
Electrode
2.5mm 2.0mm 2.5mm
Spacing
This test is performed to test the breaker in the energized state so that the
performance of the first trip can be analyzed. By performing this test, the
current profile allows diagnosis of potential defects in the trip coil mechanism
and also highlights problems within the main circuit breaker contacts. Each
Circuit Breaker type has a characteristic profile similar to that shown in
Figure 3-17.
Deviations from this profile can be easily detected by comparing profiles from
first trip operations with subsequent or previous trip coil profiles. The same
methodology can be applied to the close coil operation.
Table 3-25 : Equipment Speci cation for Trip Test (On -Line Timing)
Item Speci cation
1. Measurement Voltage 0 ~ 265 Vdc
Range Current 0.2 ~ 20 Adc
2. Measurement Resolution 0.03%
3. Basic Accuracy 0.5%
4. Dynamic Error Motion 1%
Speed 3%
5. Time Base Accuracy 0.02%
6. Measurement Interval 0 ~ 1000 ms
7. Able To Capture Online Test With - Main mechanis ming
Graphic - Trip latch ming
- Trip coil ming
3
- S on b ery and wiring
- Auxiliary switch contac ming
- Main contac ming
8. Operating Environment -10 ~ 50°C
9. Closing Closing Voltage At 100% rated voltage
Characteristic Closing Time ≤ 80 ms
Chatter Time 11 kV ≤ 8 ms, 36 kV ≤ 12 ms
10. Tripping Tripping Voltage At 100% rated voltage
Characteristic Tripping Time ≤ 50 ms
Di rent Contact ≤ 5 ms
Time
50 Distribution Substation (PE)
2. To capture a TRP operation, identify a dc current path where the trip coil
current will flow when a TRIP command is given.
4. Fit the DC current probe around this wire. The respective trip or closing
coil currents are captured using a Hall Effect clamp on probe.
5. For best results, fit the DC current probe around the negative return of
the DC circuit of the trip or close coil.
6. Connect the voltage monitoring leads at the positive and negative supply
of the trip coil to monitor voltage drop across the trip coil when it is
energized.
8. Keep a safe distance from the switchgear once the set-up is complete and
is ready to receive a breaker TRIP or CLOSE command.
IMPORTANT:
3
Making a Breaker TRIP/CLOSE Measurement
1. Give a TRIP/CLOSE command when the Central Control Centre for the
TNB region gives the green light. This opera on should be performed by
authorized TNB switching personnel.
2. The TRIP/CLOSE Command can be effected from any one of the following
loca ons :-
• The trip/neutral/close selector switch at the switchgear
• SCADA remote control
• Breaker control switch or pushbu on at the remote control panel
3. When the breaker is tripped/close, save the trip coil current profile and
other data for further analysis and for archiving the data to library for
breaker performance trending purposes.
52 Distribution Substation (PE)
Note: If closing and tripping time obtained is more that OEM declared
time, then servicing and lubrication of circuit breaker needs to be
performed.
Chapter 3 Switchgear 53
The circuit breaker is designed to clear a fault by quickly interrupting the fault
current, thus minimizing damage to the electrical circuit through which the
fault current flows. However, once put in service, the breaker may remain
idle for long periods of time i.e. the mechanical parts are not operated until it
is taken out for maintenance or until a fault occurs. Breaker tests to analyze
its performance can be carried out either with the breaker still online or off-
line.This test can be performed under both energized and de-energized
switchgear. The advantage of this analysis is to detect failure of the driving
shaft, gear assembly and spring.
3
3.2.4.4.1 Equipment Specification
2. If the breaker is withdrawable, trip the circuit breaker and rack the
breaker out to test or disconnected position.
1. Connect the breaker to the test set according to instructions given by the 3
manufacturer.
(i). Check if all there is any vacuum leak to ensure the integrity of the
vacuum interrupter.
(ii). Detect dirt on the poles of the vacuum bottle and on the exterior
surface which makes it unsafe during operation.
(iii). Check for sufficient distance between the two poles of the vacuum
bottle to see if frequent operations have caused misalignment to the
breaker mechanism.
Ripple Max 3%
Terminal.
6 Large Test Clip Provides for quicker connec on and more efficient
Connectors tes ng process
7 TEST Safety Both knobs must be turned simultaneously to apply high
Control Knobs voltage to the test object.
8 ACCEPTABLE Lights up when the breaking chamber test result is
Green Lamp posi ve
9 DEFECTIVE Lights up when the breaking chamber test result is
Red Lamp negative, when the flashover threshold voltage
1. Always comply with TNB safety regula ons when working with
equipment connected to high voltage mains.
2. Clean the surface of the vacuum bottle and the connected linkages
thoroughly. Use a dry lint free cloth or industrial paper travel. Avoid using
any cleaning solvents. Denatured alcohol may be used if required.
3. Check the insulation resistance of the vacuum bottle. If the value drops
below 1000 MΩ (corrected to 20°C), discontinue vacuum test and consult
the manufacturer for advises. If value is good, continue test set-up.
6. Connect the part negative DC clamp of the high voltage cable to the
control mechanism side of the breaking chamber.
7. Connect the positive DC clamp of the high voltage cable to the other
3
terminal on the breaking chamber.
1. Ensure step 1 and 2 above are completed before conducting this test.
Note: For guide on test voltage refer to IEC 694 and ANSI C37-06
standards.
3
5. Observe the indication lights. If the “defective” indication lights up or if
the test set trips, the breaking chamber is considered defective.
Note: If metallic discharge sounds are heard during the test but the
discharge is not sustained or bridges the gap between electrodes
permanently, the object under test is accepted as non-defective.
Note: A full time 10 second test is required after that. There must be a
pause of 2 minutes before starting the next test. This pause permits
proper resetting of the vacuum tester’s internal timer counter.
2. Remove the ground connection and connect it to the metallic part of the
high voltage cable before removing it from the circuit breaker.
Note:
When a DC test voltage is used, electrostatic charges can build up on:-
3.2.5 Tier 3
3.2.5.1 PD Locator
The PD Locator is used to identify and locate the early warning signs of PD
activity that signals the start of insulation degradation that could ultimately
lead to disruptive failures.
3. Listen for abnormal sound e.g. crackling, buzzing or frying sounds. Aim
the scanner at each spot for a while before moving on to another spot so
that intermittent discharges will also be captured.
3 4. Record results in decibel (dB) and store any abnormal sounds for further
analysis by software where necessary. The instrument will capture both
mechanical vibration noise and partial discharge.
5. During the course of scanning, eliminate external noise sources that may
interfere with the scanning.
TEV dB magnitude
Perform immediate shutdown and repair of the equipment.
> 29
3
Figure 3-28 : Identification of Transformer
Item Specification
1. Measuring Range Voltage 0 ~ 80 kVac (rms)
Secondary Current 0 ~ 60 mA (rms)
2. Current Current Rating 13 mA
Short-circuit Current Max. 50 mA (1 minute)
Chapter 3 Switchgear 67
3. If the test object is a withdrawable breaker, trip the breaker, then rack
the breaker out to ‘Test’ or ‘Disconnected’ position.
2. Ensure that the ground leads are connected and that the test object is
properly earthed.
3. Connect the test set to the Mains but do not power-up until the test set-
up is completed and is ready for testing.
1. Ensure step 1 and 2 above are completed before conducting any tests.
2. Turn the voltage control knob of the variable transformer to the zero
output voltage position.
3. Turn ON the power for the test equipment. Just before the application of
the test voltage, ensure that the earth connection at the test object is
disconnected.
4. Raise the test voltage until the desired value is reached then apply this
voltage for at 1 minute. For guidance on test voltage, refer to .
5. If the test set does not trip due to disruptive discharges and the “PASS”
indication is given, the test is complete and the object under test is
considered to be in good condition.
6. If the test instrument trips due to disruptive charges, the test object is
considered defective.
Note: Any discharge sounds that are heard during the test are of no
importance. The results shall solely be based on the “acceptable” or
“defective” indication.
7. Some test sets will give the value of the leakage current measured during
the test. Record this value if it is available.
8. When the test is completed, return the voltage control knob to the zero
voltage position.
5. Plug the high voltage cable into the HIGH VOLTAGE TO TEST OBJECT
socket.
7. Plug the line cord cable into the mains socket on the power supply.
5. Select the test voltage and adjust to the required level. Voltage applied is
up to 10 kV but not more than phase voltage.
8. Enter the temperature of the test object so that the tan delta & power
factor values displayed are automatically compensated for 20°C. If there
is no built in conversion feature, key in the compensation table values.
10. Turn on the high voltage to apply the test voltage to the object under
test.
2. Ensure the power supply to both sides of the breaker or isolator contact
or joints is turned OFF and that there is no feedback supply.
4. Do not disconnect current leads or open the device under test whilst the
micro-ohmmeter is still connected to it.
6. Connect the two current cables from the test set across the contacts or
joints so that the current generated by the micro-ohmmeter will flow
through the contacts to be measured.
7. Similarly, connect the two sensing cables (using the same polarities as
used for current cables) on two sides of the contacts or joints and as close
to the targeted object as possible.
IMPORTANT:
3. Turn on the test set to start current injec on. Check the Power “ON”
ind on to ensure the test set is powered up properly. The test
instrument is now ready for use.
4. Sta ng from zero, slowly turn the control knob to increase the current
output of the test set un it reaches the desired current value.
5. The micro-ohmmeter will measure the voltage drop across the breaker or
3 disconnector contacts and will automa cally calculate the actual
resistance in micro-ohms. Take the reading displayed on the screen, and
then turn the current down to zero again.
Note: High current must only flow for a short me interval. Never leave
the instrument una ended whilst it is on and in high-current mode.
1. Record test results for each phase of the contact, disconnector or joint in
the test sheet.
3
Note:
Compare obtained results with the acceptable range given by the
manufacturer. The varia on value should not more than 20% from
previous result or by comparison with similar conne ons (IEC
62271-1:2007 clause 6.4.1 – measurement of the resistance of
circuit/main circuit.
If re-occur, De-energized to
locate gas leak, perform tier 3
If less than specified limit
Insulation
Tier 2 > 1GΩ inspect & rectify. If required
Resistance
perform tier 3 test.
Replace oil or perform asset
Oil Dielectric Test Tier 2 > 30kV replacement. Refer circular
A15/2011
2. Breaker Compartment
3. Cable Compartment
2. Insulation Condition
No cracks, chips, dents or discoloura on
Insula on boots / jackets for busbar joints in good cond on
Chapter 3 Switchgear 83
3. Cable Compartment
4. Electrical Joints
Exposed joints properly insulated
Bolts correctly sized and mounted
Electrical joints torque checked
84 Distribution Substation (PE)
1. Breaker Checks
Correct ra ng
CONNECTED/DISCONNECTED s rs placed correctly
Secondary control plug can be inserted properly (where applicable)
Smooth rack-in/rack-out opera on
Breaker can be charged manually
3
Chapter 4 Transformer 87
Chapter 4 Transformer
4.1 Overview
Distribution Transformer is usually utilized in Distribution Substation (PE).
Distribution transformer is a transformer that provides the final voltage
transformation in the electric power distribution system, stepping down the
voltage in TNB distribution system. Normally ratings for distribution
transformer are from 1000 kVA and below.
4.4.1 Overview
Tier 3 4
Turn-ra o measurement (TTR)
Winding resistance measurement
(WR)
Cond on Type 2
Oil sampling:
Based
Moisture Content
Dissolved gas analysis (DGA)
92 Distribution Substation (PE)
Under normal condition, the maintenance diagnostic testing for Tier 1, 2 and 3
on distribution transformers shall be conducted according to the maintenance
intervals in , and respectively.
Body &
Substatio
Visual Inspection Accessory N/A
3 months n Team
Transformer
6 months Airborne
Cable Box Vendor/
Ultrasonic Scanning Ultrasonic
Transformer 12 Team
4 months
Test Set
(Based on
Body & ENGR-
Infrared 750-36 Thermo Vendor/
Accessory
Thermography QR02) Camera Team
Transformer
Insula on Resistance
(IR) & Polariza on Vendor/
Transformer IR Tester
Index (PI) Substa on
Winding 5kV
measurement for Team
18
main winding
Months
Insula on Resistance
(oil type) Vendor /
(IR) & PIDAR Transformer IR Tester
24 months Substa on
measurement for Tx Tail 5kV
(VCB) Team
tail
36 Months
Oil Sampling:
(RMU SF6) Vendor
Breakdown
Dieletric /
Voltage Oil Tank
Tester Substa on
(BDV)
Team 4
94 Distribution Substation (PE)
Turn-ratio Vendor/
Turn Ratio
measurement Tap Changer Substation
Test Set
(TTR) Team
4.4.3 Tier 1
6. Perform scanning
Note: Any external light sources that may be reflected from the
surfaces scanned that may cause wrong interpretation of data for
example, reflection from light sources, sunlight, heat reflection and etc.
Ensure there are no cold drafts or winds blowing directly at then
equipment scanned.
4
Chapter 4 Transformer 99
2. Resolu on 1 dB
3. Accuracy ±1 dB
Note: Also applies for cond on where the dB level below 0dB but
ultrasound characteris has been detected. Priority for corre ve
ac on is based on the following category:
Arcing =
Tracking = Serious
Corona = Intermediate
4.4.4 Tier 2
Under normal cond on, Tier 2 tests are carried out on all transformer
popula on based on the designated maintenance intervals. Tier 2 tests be
carried out in Offline Cond on Assessment.
Voltage 5 kVdc
1. Test Conne ons for High Voltage Winding Terminal to Ground Terminal
shown in Figure 4-7.
2. Test Conne ons for Low Voltage Winding Terminal to Ground Terminal
shown in .
3. Test Conne ons for High Voltage Winding Terminal to Low Voltage
Winding Terminals shown in Figure 4-9. 4
4. Wait for the measurement to stabilize according to table below :-
IR10 min
PI =
IR1min
IR60sec
DAR=
IR30sec
Table 4-13 : Result & Action for Insulation Res istance of Transformer
Windings
Condition
Result Action
Indicator
PI > 2.0
DAR ≥ 1.6 Good Normal to moderate
or IR ≥ 600 MΩ (Wdg)
conditions. Continue test
or IR ≥ 1500 MΩ (Tail)
as part of Tier 2 test at
1.5 ≤ PI < 2.0 normal intervals specified
1.1 < DAR < 1.5 Fair in Subchapter 4.4.2
or 400 MΩ ≤ IR < 600 MΩ (Wdg)
or 1500 MΩ ≤ IR < 1000 MΩ (Tail)
Note: Priority for action taken should be given to equipment with poor
and bad condition indicator.
4.4.4.3 Continuity Test
Test Voltage 500 Vdc 2.5 kVdc 5.0 kVdc 5.0k Vdc
Chapter 4 Transformer 109
Voltage 5 kVdc
4.4.4.3.3 Result
4.4.5 Tier 3
The transformer turns ratio (TTR) test detects shorts between turns or layers
of the same coil, which indicates insulation failure between the turns. These
tests are performed with the transformer de-energized and may show the
4 necessity for an internal inspection or removal from service.
2. Output current 1A
3. Make sure that zero voltage cond on exists. The bushing/ transformer
tail termina ons of high voltage and low voltage terminals must be
isolated from the conne on lines.
4
4. Ensure that the applica on of the diagnos voltage does not lead to
flashovers to other nearby items which are in service.
Winding resistance can detect broken conductor strands, loose conne ons,
and bad contacts in the tap changer. The resistance is measured on all taps of
a tapped winding to ensure that the on-load tap changer does not open circuit
during the tap changing opera on.
Voltage 36 Vdc
1.Maximum Value
Current 10 A
Note: Priority for action taken should be given to equipment with poor and
bad condition indicator.
Chapter 4 Transformer 115
Oil Quality Analysis used on transformer oil includes some physical tests such
as dieletric strength, moisture content and DGA. Therefore, they are not
ind ve of overall transformer cond on that would lead to replacement.
a) Safety Precautions
Ensure that the transformer body is properly earthed and inspect the external
cond on of the transformer for any leaks or cond ons that may become
hazardous to the personnel when oil sampling is conducted. Ensure that
working zone is not obstructed and adequate safe working clearance is
observed at all e.
Iden the correct sampling point or valve intended for oil sampling (either
sampling of oil from bo om of the Tank, or conservator). Know the type of
valve and the appropriate sampling tools and adaptors to be used. 4
b) Before Sampling
Check that the oil level in the conservator. Know the total quan ty of oil to be
taken and always ensure that the oil level does not drop to below 1/3 of the
oil level in the conservator a er sampling completed. shows the quan ty of
oil required for various tests. Do not take oil sample if the oil level is already
below the 1/3 level in the conservator. If so, oil sampling can only be
conducted on the transformer topping up of oil. This is applied for either
sampling of oil from Tank, or any conservator.
118 Distribution Substation (PE)
1. Moisture 50
Ensure the weather is conducive to carry out oil sampling. Do not carry out oil
sampling in rain, strong wind and at night e. Before oil sampling, ensure
the following steps are taken:
Clean the outside of the valve with a clean cloth to remove any loose
debris that may fall into the sample.
If drain plug is used, make sure the valve is closed before removing
the drain plug.
Prepare the area under the valve as to avoid oil spillage.
Slowly remove the drain plug.
Waste
Vessel
Figure 4-17 : Oil sampling using bottle from Transformer Drain Valve
Chapter 4 Transformer 119
Once the valve is totally prepared then sampling can commence. The oil
sampling procedure is in accordance to the combina on of standards IEC
60475 and IEC 60567. The la er standard is specific to oil sampling for DGA,
which is stringent and is thus applicable also to oil sampling for oil quality and
furan tests. The pra ce below provide detailed informa on concerning
taking the actual sample.
i) Flush the oil through the valve to clean sampling valve, adaptor and tube
as well as to remove debris and water from the oil prior to taking a
sample into waste vessel. Flushing and purging helps to remove any
debris and moisture, coats the plunger to create an adequate seal and
helps to remove air bubbles.
Figure 4-18 : Oil sampling valve showing water and debris accumulation
ii) Place tube into glass bo le, ensuring end of tube reaches the bo om or
touching the inner side of the bo le. Ensure the pressure inside the tank
is pos ve. Immediately close the valve is the pressure inside the
transformer tank is nega ve.
120 Distribution Substation (PE)
iii) Open sampling valve to about half fill the bottle then close valve. Rinse
the bottle 2 to 3 times to remove any debris remaining from the bottle.
iv) Steadily fill the bo le avoiding any splashing, aera on or bubbling which
likely to cause premature degassing of the oil. Take temperature of the oil
sample.
d) After Sampling
Cleanup is a necessary step of the sampling activity. The area should be left
cleaner than found so that possible hazards can be minimized for the next
sampling crew. Make sure that drain valves and sampling cocks are wiped
clean of oil and closed tightly. Remove all debris and tools from the area, and
cleanup any liquid spillage.
4
Figure 4-23 : Close the valve and cleaned
Inspect the level of oil in the conservator and carry out topping up is
necessary. All unused oil shall be scraped following the existing procedure.
Chapter 4 Transformer 123
Oil sampling form below shall also be filled and subm ed together with the
oil samples to TNBR.
124 Distribution Substation (PE)
Samples should not be stored longer than 3 days before shipping to the
laboratory for analysis. Store bottles containing the oil samples in the dark to
prevent from photo-degradation, and keep them away from temperature
extremes and humid environments. They shall also be stored up-right and in a
secure manner for shipping.
Figure 4.25 illustrates the corre ve ac ons required based on the results of
oil quality analysis and the cond on indicators. Details regarding the
ve ac ons namely oil recond oning, oil replacement/retrofi ng and
oil reclama on are further elaborated in Subchapter 4.4.6.1.
Extraction and analysis of gasses evolved from oil degradation due to thermal
and electrical faults.
The identity and relation of the individual gases are indicative of the types of
fault that occur in a transformer while the rate of gas generation can indicate
the severity of the fault. The characteristic patterns and the relative
proportion of the dissolved gases associated with the main fault types are
summarised in through .
60
50
40
30
13
20
0.2 0.2 0.5 0.1
10
0
H2 CO CH4 C2H4 C2H6 C2H2
Fault gases
Overheating of paper
100 92
80
% dist ribut io n
60
40
20 6.7
1.2 0.01 0.01 0.01
0
H2 CO CH4 C2H4 C2H6 C2H2
Fault gases
Figure 4-30 : Percentage proportion of gases indicating Overheating of Paper
4
Overheating of oil
70
63
60
% distribution
50
40
30
16 17
20
10 2 2
0.01
0
H2 CO CH4 C2H4 C2H6 C2H2
Fault gases
Arcing
70
60
60
50
% dist ribut io n
40
30
30
20
10 5 3 2
0.1
0
H2 CO CH4 C2H4 C2H6 C2H2
Fault gases
4
130 Distribution Substation (PE)
4 T1 Thermal Fault
t ≤ 300°C
Overloading of the transformer in emergency situations.
Block item restricting oil flow in windings.
Stray flux in damping beams of yokes.
Limits for the key gas concentra on refer to below where Cond on 1
indicates normal cond on whilst Cond on 4 indicates serious cond on.
Table 4-24 : Limits for gas concentrations based on IEEE Std 57.104:1991
for Tank
Status H2 C2H2 C2H4 C2H6 CH4 CO TDCG
Cond on
100 35 50 65 120 350 720
1
4
132 Distribution Substation (PE)
During oil replacement process, the transformer is drained of the oil, its
interior is flushed with hot Naphthenic oil to remove the accumula on of bulk
sludge and then refilled with new oil. The old oil should be scrapped in
accordance with TNB disposal policy of waste material.
Changing the oil does not remove all the deposited sludge, especially those in
the cooling fins, trapped in the solid insula on and in between the windings.
Refilling the transformer with new unused oil should include the oil
recond oning process men oned above.
134 Distribution Substation (PE)
4.4.6.2 Testing the Transformer with Turns Ratio and Insulation Resistance
Tests
1. After completion of the tap changer overhaul, proceed with Turns Ratio
and Insulation Resistance Tests according to the procedures stated in
Subchapter 0.
Minor
Gasket – accessories
Sealing Repair
POOR,
degraded/damaged –
BAD
with/without oil leaks Gasket – main & conservator Medium
tanks Repair
Minor
POOR, Repair
Low oil level Main conservator tanks
BAD
136 Distribution Substation (PE)
Condition
Condition Indicator
Indicator Components Action
Results
Ranking
POOR, Minor
Air flow blocked Cable box vents
BAD Repair
4 Malfunction
POOR,
BAD
Valves
Minor
Repair
POOR, Minor
Abnormal noise External components
BAD Repair
POOR, Minor
Dirty Gauges, indicators
BAD Repair
Presence of
POOR, Minor
encumbrance/weed/ Bay, compound
BAD Repair
animal nests
Chapter 4 Transformer 137
Diagnostic Condition
Component Action
Techniques Indicator
Body &
Visual Inspection Accessory Poor/Bad Minor/Medium Repair
Transformer
Infrared
Body &
terminations for loose
4
Accessory Poor/Bad
Thermography contacts as well as
Transformer radiators & Tank for
accidentally closed
valves or blocked oil
flow
Immediate shutdown
and repair of the
Cable Box terminal
Ultrasonic Scanning Poor/Bad
Transformer bushings/terminations/
cable box to avert fire
or failure.
138 Distribution Substation (PE)
TIER 1
Diagnostic Condition
Component Action
Techniques Indicator
Diagnostic Condition
Component Action
Techniques Indicator
4 Insulation resistance
Based on Turns Ratio,
and Polarization
Transformer Winding Resistance,
Index (PI) and
Winding & Poor/bad Insulation Resistance
Dieletric Absorbtion
Tail to locate the possible
Ratio (DAR)
fault location.
measurement
Breakdown Voltage
Tank Poor/Bad Replace Oil
(BDV )
Chapter 4 Transformer 139
Diagnostic Condition
Component Action
Techniques Indicator
Transformer
Turns-ratio Based on Turns Ratio,
Winding & Poor/bad
measurement (TTR) Winding Resistance,
OLTC
Insulation Resistance
Transformer
Winding resistance to locate the possible
Winding & Poor/bad
measurement (WR) fault location.
OLTC
4
140 Distribution Substation (PE)
Maintenance
Planning CBM DMMS
CBM Data DARAT
SG/ Tx/ (Risk)
Cable
Maintenance
Planning TBM TBM Data
ERMS-PM ERMS-FM
Maintenance Maintenance
Schedule Cost
ERMS Integrated
System
Diagnostic
CBM
Asset Value
Asset Detail
TBM
Maintenance Cost
Health Index
Life Cycle Cost
5
Maintenance Activity
All the data inspections repair and replacement works are properly recorded
and documented through:-
1) ERMS – PM
2) Maintenance Planning (QR – 02)
3) Distribution Maintenance Management System (DMMS) – applicable
for 33kV & 11kV Transformers and Medium Voltage Underground
Cable
5
Chapter 5 Maintenance Management System 143
Apart from that, these data and activities must also be updated to HQ
according to the respective Operasi Wilayah.
(i) Access server \\129.6.70.241 > home > (find the respective Operasi
Wilayah folder)
5.3.2 ERMS – PM
Note:
A – letter
N – number
X – combination of letter & number
Level 6 Equipment
Max 6-characters code to
The recommended codes are
as shown in Appendix 5-4.
5
iden equipment.
148 Distribution Substation (PE)
5 Users can refer to Manual Asset Inventory for Asset Plant and Machinery or
Panduan ERMS-PM as a guide to use IH01, IH06 and IH08. Panduan ERMS-PM
can be obtained from the server \\129.6.70.241>home>PANDUAN ERMS-PM.
Chapter 5 Maintenance Management System 149
5.4 Appendices
Appendix 5-1: List of TNBD’s Business Areas and Station Codes
Business 4-Letter
No. State Station Name Area Station Code
1 Johor PBN (Johor) 6303 JPBN
2 Johor PK Batu Pahat 6330 JBPT
3 Johor PC Pontian 6333 JPON
4 Johor PK Johor Bahru 6340 JJBU
5 Johor PC Kota Tinggi 6341 JKTG
6 Johor PK Kulai 6342 JKLY
7 Johor PK Pasir Gudang 6345 JPGD
8 Johor PC Johor Jaya 6346 JJJY
9 Johor PCK Bandar Penawar 6347 JBPN
10 Johor PK Muar 6350 JMUR
11 Johor PC Segamat 6352 JSEG
12 Johor PCK Tangkak 6353 JTGK
13 Johor PK Kluang 6360 JKLU
14 Johor PC Mersing 6361 JMSG
15 Johor PCK Yong Peng #N/A
16 Kedah PBN (Kedah) 6202 KPBN
17 Kedah PK Alor Setar 6240 KALS
18 Kedah PC Jitra 6242 KJIT
19
20
Kedah
Kedah
PC Langkawi
PC Guar Cempedak
6243
6244
KLGK
KGCM 5
21 Kedah PCK Kuala Nerang 6245 KKNG
22 Kedah PC Pendang 6246 KPDG
23 Kedah PK Sg. Petani 6290 KSGP
24 Kedah PC Baling 6292 KBLG
25 Kedah PCK Sik 6293 KSIK
26 Kedah PK Kulim 6294 KKLM
27 Kedah PCK Bandar Baru 6295 KBBU
28 Kedah PC Kuala Ketil 6296 KKTL
29 Kedah PCK Serdang 6297 KSDG
30 Kelantan PBN (Kelantan) 6403 DPBN
150 Distribution Substation (PE)
Business 4-Letter
No. State Station Name Area Station Code
31 Kelantan PK Kota Bharu 6410 DKBU
32 Kelantan PCK Gua Musang 6411 DKRI
33 Kelantan PC Pasir Mas 6412 DPMS
34 Kelantan PC Pasir Puteh 6413 DPPH
35 Kelantan PCK Gua Musang 6414 DGUA
36 Kelantan PC Tumpat 6415 DTUM
37 Kelantan PC Bachok 6416 DBAC
38 Kelantan PK Tanah Merah 6417 DMER
39 Kelantan PCK Machang 6419 DMAC
40 Kelantan PCK Jeli 6461 DJEL
41 Kelantan PCK Kuala Balah 6462 DKBL
42 Melaka PBN (Melaka) 6302 MPBN
43 Melaka PC Alor Gajah 6315 MALG
44 Melaka PC Jasin 6316 MJAS
45 Melaka PC Masjid Tanah 6317 MMAT
46 Melaka PCK Merlimau 6318 MMER
47 Melaka PC Melaka 6302 MMLK
48 N Sembilan PBN (Negeri Sembilan) 6301 NPBN
49 N Sembilan PK Seremban 6320 NSBN
50 N Sembilan PC Tampin 6321 NTAM
5 51
52
N Sembilan
N Sembilan
PCK Kuala Kelawang
PC Port Dickson
6322
6324
NKKG
NPDN
53 N Sembilan PC Rembau 6325 NREM
54 N Sembilan PC Nilai 6326 NNIL
55 N Sembilan PK Kuala Pilah 6327 NKLP
56 N Sembilan PC Bahau 6328 NJEM
57 N Sembilan PC Gemas 6329 NGEM
58 Pahang PBN (Pahang) 6401 CPBN
59 Pahang PK Kuantan 6420 CKTN
60 Pahang PC Pekan 6422 CPEK
61 Pahang PC Rompin 6424 CROM
62 Pahang PCK Bandar Muadzam 6425 CBMS
63 Pahang PC Raub 6430 CRAU
Chapter 5 Maintenance Management System 151
Business 4-Letter
No. State Station Name Area Station Code
64 Pahang PK Bentong 6431 CBTG
65 Pahang PC Kuala Lipis 6433 CKLS
66 Pahang PK Temerloh 6450 CTML
67 Pahang PCK Maran 6451 CMRN
68 Pahang PC Jengka 6452 CJEN
69 Pahang PC Jerantut 6453 CJRT
70 Pahang PC Triang 6454 CTRI
71 Pahang PCK Tioman 6455 CTIO
72 Pahang PC Gebeng 6426 CGBG
73 Perak PBN (Perak) 6204 APBN
74 Perak PK Ipoh 6210 AIPO
75 Perak PC Kampar 6211 AKAM
76 Perak PK Bidor 6212 ABID
77 Perak PC Behrang 6213 ABEH
78 Perak PCK Cameron Highlands 6215 ACHL
79 Perak PC Parit 6218 APRT
80 Perak PC Hulu Kinta 6219 ATGR
81 Perak PK Taiping 6220 ATPG
82 Perak PC Batu Gajah 6221 AGAJ
83 Perak PK Kuala Kangsar 6222 AKSR
84 Perak PC Grik 6223 AGRK
85
86
Perak
Perak
PC Bagan Serai
PC Sg. Siput
6224
6225
ASER
ASIP
5
87 Perak PK Sri Manjung 6227 ASIT
88 Perak PK Teluk Intan 6250 ATEL
89 Perak PC Hutan Melintang 6252 AHML
90 Perak PCK Kg. Gajah #N/A
91 Perlis PBN (Perlis) 6201 RPBN
92 Perlis PCK Padang Besar 6271 RPBR
93 Perlis PC Kangar 6201 RKAN
94 P Pinang PBN (Pulau Pinang) 6203 PPBN
95 P Pinang PK Seberang Perai 6231 PBUT &
PBMT
152 Distribution Substation (PE)
Business 4-Letter
No. State Station Name Area Station Code
96 P Pinang PC Nibong Tebal 6232 PNTL
97 P Pinang PK Pulau Pinang 6260 PPPG
98 P Pinang PC Bayan Baru 6261 PBYB
99 P Pinang PC Bertam 6230 PBTM
100 P Pinang PC Butterworth 6231 PBUT
101 P Pinang PC Bukit Mertajam 6231 PBMT
102 Selangor PBN (Selangor) 6102 BPBN
103 Selangor PK Petaling Jaya 6130 BPJY
104 Selangor PC Subang Jaya 6131 BSJY
105 Selangor PK Klang 6140 BKLG
106 Selangor PC Kuala Selangor 6141 BKSL
107 Selangor PK Banting 6142 BBAN
108 Selangor PC Port Klang 6143 BPKG
109 Selangor PC Sg. Besar 6144 BSBR
110 Selangor PC Sg Pelek 6145 BSPL
111 Selangor PCK Telok Panglima Garang 6146 BPGR
112 Selangor PCK Salak Tinggi 6147 BSTG
113 Selangor PK Rawang 6150 BRWG
114 Selangor PK Shah Alam 6160 BSAM
115 Selangor PK Bangi 6180 BBBB
5 116
117
Selangor
Terengganu
PC Cheras
PBN (Terengganu)
6153
6402
BCRS
TPBN
118 Terengganu PK Kuala Terengganu 6440 TKTR
119 Terengganu PK Kemaman 6441 TKEM
120 Terengganu PC Dungun 6442 TDUN
121 Terengganu PC Besut 6443 TBST
122 Terengganu PCK Setiu 6444 TSTU
123 Terengganu PCK Kerteh 6445 TKTE
124 Terengganu PCK Kuala Berang 6446 TKBG
125 Terengganu PCK AMBS 6447 TAMB
126 Terengganu PC Marang 6448 TMRG
127 Terengganu PCK Batu Rakit #N/A
128 WP KL PBN (WP KL) 6101 WPBN
Chapter 5 Maintenance Management System 153
Business 4-Letter
No. State Station Name Area Station Code
129 WP KL PK ( KL Barat ) 6121 WKLB
130 WP KL PK ( KL Timur ) 6122 WKLT
131 WP KL PK ( KL Pusat ) 6123 WKLC
132 WP KL PK ( KL Selatan ) 6124 WKLS
133 WP Putrajaya PBN (Putrajaya & Cyberjaya) 6103 VPBN
134 WP Putrajaya PC (Putrajaya) 6103 VPTJ
135 WP Putrajaya PC (Cyberjaya) 6103 VCBJ
5 ATEL/PCE/J00152/X
ATEL/PCE/J00152/XA
INFRASTRUCTURE
COMPOUND
ATEL/PCE/J00152/XB LIGHTING
ATEL/PCE/J00152/XD DRAINAGE
ATEL/PCE/J00152/XE SIGNBOARD
ATEL/PCE/J00152/Z BUILDING SYSTEM
ATEL/PCE/J00152/ZA BUILDING
ATEL/PCE/J00152/ZB FIRE FIGHTING SYSTEM
ATEL/PCE/J00152/ZD AC SUPPLY