FORMULA :
EAC = ACTUAL COSTS (AC) + ESTIMATE TO COMPLETE (ETC)
ETC = ESTIMATE AT COMPLETION (EAC) – ACTUAL COSTS (AC)
CPI = EV/AC
UPPER CONTROL LIMIT = +2(SD)
Dave is managing a new project to create a radio-operated model plane. The project budget is
set at $200,000 and the project must be completed within six months of the starting date. The
initial document authorizing this project and giving Dave the authority to apply organizational
resources to the project activities is called
a. Project charter
Since the levels of both cost and risk vary throughout the project life cycle, which of the
following statements is true?
In a phased project, phase end meetings are used to sign-off on the deliverables associated
with that phase. These phase end points typically provide a good opportunity to evaluate the
progress and performance in that phase. Which of the following terms is synonymous for
phase end?
c. Meet with manufacturing employees and tell them their jobs are safe
b. Stakeholder analysis
Which of the following are inputs to the Develop Project Management Plan process?
d. Both a and b
On a project schedule network diagram, leads and lags are used to define the relationships
between activities. These leads and lags indicate either acceleration or delay, respectively, of
the successor activity. If a team member on your project indicates FF+3 on the network
diagram, what does that notation indicate?
Which of the following are inputs to the Manage Stakeholder Engagement process?
b. Horizontal communication
Earned value analysis can be used for measuring the project
performance. Project managers use this analysis to plan for risks based
on the actual cost, schedule and progress of the work. During the
executing phase, if a project has negative values for the cost variance
and the schedule variance, which of the following would most accurately
represent the project's status?
d. Forming
During project execution, the planned value, earned value and the actual
cost all have identical values. In this scenario, which of the following
statements best describes the status of the project?
If one standard deviation is equal to 0.02, what is the upper control limit in a control chart if the
upper control limit is set at +2 Sigma?
b. 0.04
Ryan Systems is in the 3rd week of a 5-week project to consolidate all of its data servers to a
central location in its new data center. The amount of money spent on this project to date is
approximately $80,000. The planned value for the move as of the 3rd week is $50,000. What is
the status of the project at this time? Over budget
b. Behind schedule
John has just finished the requirements documentation including the deliverable acceptance
criteria to determine the success of the project in terms of the deliverables produced. A series
of tasks are included in the criteria. Both John and the customer must perform this series of
tasks in order to complete the acceptance and sign-off the final deliverables. Which of the
following project processes would use these criteria to provide formal acceptance of the
deliverables?
d. Validated scope
Which of the following processes describes the collection, measurement and distribution of
performance information, and measuring the health of the project to identify project areas that
require corrective or preventive actions?
Wilma is examining the data on her control chart. It shows four consecutive points above +3
sigma and three subsequent points below -3 sigma. If the lower and upper control limits are
set at +-3 sigma, what should Wilma report as the status of the process?