Concrete:
Slab Volume 92.4
Length 21 Cement in Bag 1108.8
Width 40 Sand 46.2
Thickness 0.11 Gravel 92.4
4 L. ; 1 Discont. 4 L. ; No Discont.
Discont. Bar 1.67 Discont. Bar 0
Cont. Bar 13.157 Cont. Bar 13.157
Midspan 5 Midspan 10
Num. of Tributary 8 Num. of Tributary 32
Length Bar 4 Length Bar 4
Total # of Bars 634.464 Total # of Bars 2964.096
Using 6m Length Bar 6
3 L. ; 1 Discont. 3 L. ; No Discont.
Discont. Bar 1.25 Discont. Bar 0
Cont. Bar 13.157 Cont. Bar 13.157
Midspan 3.75 Midspan 7.5
Num. of Tributary 2 Num. of Tributary 8
Length Bar 3 Length Bar 3
Total # of Bars 108.942 Total # of Bars 495.768
Using 6m Length Bar 6
Scaffolding Scaffolding
Columns Using 2" x 3"
No. of columns 66 Vert. Supp. Bd. Ft. 6098.4
Length 13.2 Hori. Supp. Bd. Ft. 27590.9
Vert. Multiplier 7 Brace Supp. Bd. Ft. 15246
Hori. Multiplier 31.67
Brace Multiplier 17.5
Beam Using 2" x 3"
Total Length 1413 Vert. Supp. Bd. Ft. 8478
Vert. Multiplier 6 Hori. Supp. Bd. Ft. 9891
Hori. Multiplier 7
Slab Using 2" x 3"
Area 840 Flooring Supp Bd. Ft 22932
2nd to 4th Floor 3
Flooring Multiplier 9.1
Paintworks Smooth
Area 5182.98
Amounnt of paint primer 129.5745
Amounnt of paint coat 129.5745
Tileworks
area 2520
Atile 0.04
# of pcs 63000
filler 1260
cement mortar 216.72
Tileworks
area 2520
Atile 0.04
# of pcs 63000
filler 1260
cement mortar 216.72
Inside the green rectangle means you can change the values UwU
Column
Cement in Bag 1951.488 bags
Sand 81.312 m3
Gravel 162.624 m3
Combined Footing
Cement in Bag 725.868 bags
Sand 30.2445 m3
Gravel 60.489 m3
Strap Footing
Cement in Bag 1295.448 bags
Sand 53.977 m3
Gravel 107.954 m3
:Using 10cmx20cmx40cm
Slab Reinforcement
CHB mortar
Formworks
Total Sheets
120cm x 240cm 2279.81
Scaffolding
Total Bd.Ft.
2" x 3" Lumber 90236.3
Columns
2" x 3" Lumber 48935.3
Wire 1102.444
Beam
2" x 3" Lumber 18369
Wire 413.8281
Slab
2" x 3" Lumber 22932
Wire 516.6261
Paintworks
129.5745
129.5745
244.8958
BILL OF MATERIALS AND ESTIMATES
I. MOBILIZATION
b) Columns
1951 bags Portland Cement 580 1131863
81 cu.m River Sand 2000 162624
163 cu.m Crushed Stone 2200 357772.8
c) Beams
2199 bags Portland Cement 580 1275311
92 cu.m River Sand 2000 183234.4
518 cu.m Crushed Stone 2200 1139280
d) Slabs
4435 bags Portland Cement 580 2572416
185 cu.m River Sand 2000 369600
370 cu.m Crushed Stone 2200 813120
e) Walls
4499 bags Portland Cement 580 2609165
187 cu.m River Sand 2000 374880
375 cu.m Crushed Stone 2200 824736
f) Concrete Stairs
bags Portland Cement 580 0
cu.m River Sand 2000 0
cu.m Crushed Stone 2200 0
Equipment Rentals
V. REBAR WORKS
a) Footing
price total price
454 pcs 25mm dia. X 6m RSB 1050 476399
15 kgs Tie Wire 30cm 90 1322.491
b) Columns
904 pcs 25mm dia. X 6m RSB 1050 949410
1089 kgs Tie Wire 30cm 90 97974
c) Beams
1963 pcs 25mm dia. X 6m RSB 1050 2060625
368 kgs Tie Wire 30cm 90 33164.15
d) Slabs
4202 pcs 10mm dia. X 6m RSB 165 693385.3
321 kgs Tie Wire 30cm 90 28878.79
e) CHB walls
1290 pcs 10mm dia. X 6m RSB 165 212877.7
63 kgs Tie Wire 30cm 90 5645.376
f) Stirrups
2273 pcs 10mm dia. X 6m RSB 165 375100
g) Lateral Ties
1888 pcs 10mm dia. X 6m RSB 165 311454
days = 70
b) Beams
494 shts. 120cm x240cm ordinary plywood 330 163031.2
18369 bd.f. 2" x 3" coco lumber 30 551070
414 kg Assorted Common Wire 120 49659.37
c) Slab
1166 shts. 120cm x240cm ordinary plywood 330 384753.6
22932 bd.f. 2" x 3" coco lumber 30 687960
517 kg Assorted Common Wire 120 61995.13
total cost 3678392
30 % of labor cost 1103518
I. Direct Cost 4781909
II. Indirect Cost
30 % of Direct Cost 1434573
Total Cost 6216482
VII. MASONRY WORKS
a) CHB Walling
17927.25 pcs 10cm x 20cm x40cm CHB 13 233054.3
2168.87056 bags Portland Cement 580 1257945
120.217084 m3 River Sand 2000 240434.2
total cost 18946307
30 % of labor cost 5683892
I. Direct Cost 24630199
II. Indirect Cost
30 % of Direct Cost 7389060
Total Cost 32019258
X. Paintworks
XII. DEMOBILIZATION
30 day progress total 0 1.13156 3.644953 3.644953 3.582385 5.317235 10.10036 9.714782 16.17242 36.20902 10.28358 0.198756
Cumulative progess 0 1.13156 4.776513 8.421466 12.00385 17.32109 27.42145 37.13623 53.30865 89.51767 99.80124 100
0 1179623 4979397 8779170 12513718 18056805 28586183 38713603 55572948 93319957 1.04E+08 1.04E+08
Cash Flow and S-Curve
MOBILIZATION 100
0 30 60 90 120 150 180 210 240 270 300
STAKEOUT
EXCAVATION AND FILLING
REBAR WORKS
FRAME WORKS AND SCAFFOLDING
STRUCTURAL CONCRETE WORKS 75
PLUMBING LINE WORKS
WATER PROOFING
PLUMBING FIXTURES
DRAINAGE ACT. DAYS
WATERWORKS 50 Column B
TILEWORKS
FIREPROTECTION
CONCRETE FLOOR(dummy)
MASONRY WORKS
PAINTING 25
ELECTRICAL WORKS
DOORS AND WINDOWS
SIGNAGE
DEMOBILIZATION
0
day 0 day 30 day 60 day 90 day 120 day 150 day 180 day 210 day 240 day 270 day 300 day 307
30 day progress total 0 1.13156 3.644953 3.644953 3.582385 5.317235 10.10036 9.714782 16.17242 36.2090207 10.28357659 0.1987557
Cumulative progess 0 1.13156 4.776513 8.421466 12.00385 17.32109 27.42145 37.13623 53.30865 89.5176677 99.80124429 100
% cash flow 0 1179623 4979397 8779170 12513718 18056805 28586183 38713603 55572948 93319957 104040332 104247530
EQUIPMENT day 30 day 60 day 90 day 120 day 150 day 180 day 210 day 240 day 270 day 300 day 307
shovel 10 5 5
wheel barrow 5 2 2
backhoe 1
grinder 2 2
steel cutter 2 2 2
welding tool 2 2 2
hose level 2 2 2 1 1
hack saw 3 3 3
plumb bob 1 1 2 2
portalif 1 1 1 2 2 2 2 2 2
mixer 2 2 2 2
vibrator 2 2 2 2
wrench key 2 2 1
threader 2 2 1
paint brush 3 3
roller 3 3
cutters 3 3 3
pliers 3 3 3
Manpower day 30 day 60 day 90 day 120 day 150 day 180 day 210 day 240 day 270 day 300 day 320
Foreman 1 2 2 2 2 2 2 2 2 2 2
Skilled 2 6 6 6 6 6 6 6 6 6 4
Unskilled 20 16 16 16 16 16 16 16 16 16 12
First activity is mobilization then a survey is conducted to find the area of the lot then begins a stakeout.
Afer the stakeout an excavation is conducted for soil investigation then filling is done afer the investigation.
Rebar works is next forming the beams, column, slab, and footing then frameworks and scaffolding and then concrete works.
Afer the concrete dries there begin activities water proofing, masonry works and water works.
Afer water proofing to prevent water from entering then begins plumbing fixtures adding the toilet, sink, etc. afer that the activity drainage is performed.
When the activity water works is done tile works can now begin then the fire protection.
Afer the CHB wall is done drying painting can now begin then electrical works then the installation of doors and windows.
Afer installing the doors and windows the signage can begin then the last activity which is demobilization.
nage is performed.