Project Details Checklist Date

Client Name Checklist Filled by


Contractor Name System Integrator
Analogue System IP System Video Analytics
Installation Details Total no. of Cameras Indoor Cameras Outdoor Cameras
Total no. of DVRs/NVRs HDD Capacity Recording Duration

No Description Check
A Camera Installation Overview
1 The system installed is in strict accordance with the agreed specification
2 Cable has been checked for continuity and is terminated correctly using proper connector
3 The resistance of the single loop cable has been tested according to the standard industry practices
4 The termination of the single loop cable has been tested according to the standard industry practices
5 The Cable length doesn’t exceed the maximum capable distance for that particular cable type
6 Baluns used in the installation are working as required
7 Cabling is at least 5" from power lines of 2 kVA or less
8 Cabling is at least 12" from fluorescent lighting & power lines between 2 & 5 kVA
9 Cabling is at least 40" from transformers and motors
10 No Ground Loop issues are found / Proper isolators are used to eliminate ground loop issues
11 Adequate Power is provided to power the camera. (Check power cable at camera end to confirm)
12 Camera lens used has the correct focal length and provides the required field of view
13 Cameras do not face directly into the sun when installed outdoors or any lighting when installed indoors
14 In locations that are directly facing a source of light (entrances and exits), WDR cameras have been used
15 The camera view is in focus all the time under changing lighting conditions
16 For Cameras that do not function in low light areas, to improve visibility supplementary lighting is provided
17 All installed cameras field of view covers the designated areas as per the local laws and regulation
18 Alarms interfaces are tested and are triggering correctly
19 If UPS is installed the system continues to operate correctly to specification when there is power outage
20 Night recording has been tested for the IR Cameras installed
21 For PTZ Camera Pan, Tilt, Zoom, features has been tested
22 All cameras have been tested for proper video quality using a monitor before connecting to the DVR
B DVR Installation Overview (Analogue System)
1 All cameras in the installation has been connected to the DVR
2 All cameras have been given a unique camera id and this has been documented
3 Accuracy of recording verified, based on the timestamp and the actual time
4 Operations such as monitoring, playback, remote monitoring, backup, switching and multiplexing are satisfactory
5 Based on the recording duration, the right capacity of hard disks have been installed
6 DVR and Router has been configured for remote monitoring

Infinique CCTV Systems Installation Checklist


1
DS-VS-IOM-201412V01
Project Details Checklist Date
Client Name Checklist Filled by
Contractor Name System Integrator
Analogue System IP System Video Analytics
Installation Details Total no. of Cameras Indoor Cameras Outdoor Cameras
Total no. of DVRs/NVRs HDD Capacity Recording Duration

No Description Check
7 Main Monitor and Spot Out monitor are configured properly
8 Alarms interfaces are tested and are triggered as configured
9 Central Monitoring Software is installed in a PC and is properly configured
C NVR Installation Overview (IP System)
1 All the IP cameras in the installation have been configured and detected by the NVR
2 All cameras have been given a unique camera id and this has been documented
3 If RAID5/6 is installed, check if the RAID has been configured correctly
4 All the hard disks (Fixed/Hot Swappable) have been installed and are working
5 Accuracy of recording verified
6 Operations such as monitoring, playback, remote monitoring, backup, switching and multiplexing are satisfactory
7 Alarms interfaces are tested and are triggered as configured
8 The Redundant power supply is tested (If applicable)
9 NVR and Router has been configured for remote monitoring
10 Main Monitor and Spot Out monitor are configured as working as required
11 Central Monitoring Software is installed in a PC and is properly configured
D Video Analytics Overview (IP System)
1 The Video Analytics license is activated in all the cameras which require that feature
2 Video Analytics features are configured as per the requirements
3 Video Analytics features are working satisfactorily as desired

Infinique CCTV Systems Installation Checklist


2
DS-VS-IOM-201412V01
Project Details
20

19

18

17

16

15

14

13

12

11

10

1
DS-VS-IOM-201412V01

Infinique CCTV Systems Installation Checklist

No.
Camera ID
Location
Camera Fixed

Cable Termination (Camera

Checklist Date
Side)
Cable Termination (DVR Side)

Cable Continuity / Resistance /


Termination Check
Power Supply Test

Focus Adjustment

Alignment and Fine Tuning

Night Test for IR Cameras

PTZ Control Cable Check &


Functionality
Operational Test