BUILT UP RATE FOR 1M3 REINFORCED IN-SITU CONCRETE WITH GRADE 35 (1:0.

5:1)

Concrete Mixtures 1 : 0.5 : 1 = 2.5 M3


Material Price: Cement per bag (50kg) - RM 18.93
Sand per m3 - RM 42.90
Aggegrate per m3 - RM 43.33
Rental Concrete Mixer size 5/3.5 per month - RM 420.00
Rental Mobile Crane per day - RM 1600.00
Rental Vibrator, genset, pump etc - RM 270.00
Diesel cost per litre - RM 2.18
Lubricrant oil cost per litre - RM 10.00
Wage for skilled labour per day - RM 107.00
Wage for general labour & Operator per day - RM 70.00
Overhead - 5%
Profit - 10%
a. Concrete Mixer
From Table 1 : Machinery output per hour - 1.25 m3
From Table 2 : Labour constant for transport, pour and compact per m3 1.31 hours
From Table 2 - : Diesel per hour 0.91 litres
: Lubricant oil per hour 0.045 litres
b Mobile Crane
Machinery output per day - 10.00 m3

ITEM DESCRIPTION SUB TOTAL TOTAL


(RM) (RM)
1.00 Material
a. Cement 1 m3 = 28.7 bag x RM 18.93 543.29
b. Sand 0.5 m3 = 0.5 m3 x RM 42.90 21.45
c. Aggregates 1 m3 = 1 m3 x RM 43.33 43.33
608.07
Assume shrinkage, compaction, wastage (50%) 50% x RM 608.07 304.04
Cost for 2.5 m3 912.11

Material cost per m3 = RM 912.11


2.5 m3 364.84 364.84

2.00 Machinery
a. Concrete Mixer
a. Rental per hour = RM 420.00 2.02
26 hari x 8 jam

b. Diesel cost = 0.91 ltrs x RM 2.18 1.98

c. Lubricant oil cost = 0.045 ltrs x RM 10.00 0.45


4.45
From table, machinery output = 1.25 m3 per hour

Machinery cost per m3 = 4.45 3.56 3.56


1.25

b. Mobile Crane = RM 1600.00 160.00


10.00 m3

c. Other machineries (Vibrator, genset, pump etc) = RM 270.00 27.00


10.00 m3

3.00 Labour
a. Labour for mixing ( 1 operator + 1 general labour)
* Wage operator per hour = RM 70.00 8.75
8 hrs

* Wage general labour per hour = RM 70.00 x 1 8.75


8 hrs 17.50

From table, machinery output = 1.25 m3 per hrs

Labour cost per m3 = 17.50 14.00 14.00


1.25

b. Labour for pouring and compacting (1 skilled + 1 general labour)


* Wage skilled labour per hour = RM 107.00 13.38
8 hrs

* Wage general labour per hour = RM 70.00 x 1 8.75


8 hrs 22.13

From table, labour constant = 1.31 hrs per m3

Labour cost per m3 = 22.13 x 1.31 28.98 28.98


598.39
4.00 Overhead ; assume 5% x 598.39 29.92
628.31
5.00 Profit ; assume 10% x 628.31 62.83

RATE PER M3 CONCRETE 691.14