0.3 7.93
7.93 m3
4.76 m3
0.762 1.43
1.43 m2
0.3 7.93
7.93 m3
0.762 1.43
1.43 m3
Total 9.36 m3
Unit
Weight(Kg/ Quantity Unit Remarks
m)
3.00 1,737.12 kg
0.17 687.43 kg
2424.55 kg
2545.77 kg
2545.77 kg
Abstract of Cost Estimation
Client :NPL
Project : Boundary Wall
S.N Description Unit Quantity
1 Site preparation/ Protection
1.1 Protection work
1.1.1 Site preparation/ Protection LS 1.00
2 Civil works
2.1 Excavation work
2.1.1 Earthwork in excavation in ordinary to mixed/hard soil in foundation
including dressing of sides and proper compaction to trench bed, disposing
of excess soil and filling in trenches by proper compaction after construction cum 7.93
of structure all complete as per drawing, specification and instructions by
the Engineer.
Page 5 of 24
ct of Cost Estimation
20,000.00 20,000.00
538.95 4,274.55
373.75 1,778.58
13,473.76 106,863.76
17,185.21 24,618.84
921.61 1,320.26
226.14 575,701.32
Page 6 of 24
NPL
Bill of Qua
Project :- BOUNDARY WALL
Location:-
2 Civil works
2.1 Excavation work
2.1.1 Earthwork in excavation in ordinary to
mixed/hard soil in foundation including dressing 7.93 cum
of sides and proper compaction to trench bed,
2.2 Backfilling
disposing ofworks
excess soil and filling in trenches by
2.1.2 Backfilling works inafter
proper compaction 150construction
mm layer withof structure
compaction
all completeasasgiven in drawing,
per drawing, specification
specification and 4.76 Cum
and instruction by the Engineer
instructions by the Engineer.
Page 7 of 24
Project :- BOUNDARY WALL
2.5 Steel work
2.5.1 Supply, manufacture and installation of structural
steel works including two coats of Epoxy paints
over one coat of epoxy primer all complete as per 2545.77 Kg
drawing, specification and instruction by the
Engineer.
Total Rs
Discount %
Discount Amount
Phone
Adress
Date
Page 8 of 24
NPL
Bill of Quantity
In word
Page 9 of 24
-
Page 10 of 24
Total Amount
Page 11 of 24
-
Page 12 of 24
Client NPL
Project : Boundary Wall (Frontal Face)
Date:
Quantity Estimate
S.N. Description No L (m) B(m)
1 Site preparation/ Protection 1
0.3 1.73
1.73 m3
1.04 m3
0.762 0.31
0.31 m2
0.3 1.73
1.73 m3
0.762 0.31
0.31 m3
Total 2.04 m3
Unit
Weight(Kg/ Quantity Unit Remarks
m)
3.00 378.84 kg
0.17 150.01 kg
528.85 kg
555.30 kg
555.30 kg
Abstract of Cost Estimation
Client :NPL
Project : Boundary Wall (Frontal Face)
S.N Description Unit Quantity
1 Site preparation/ Protection
1.1 Protection work
1.1.1 Site preparation/ Protection LS 1.00
2 Civil works
2.1 Excavation work
2.1.1 Earthwork in excavation in ordinary to mixed/hard soil in foundation
including dressing of sides and proper compaction to trench bed, disposing
of excess soil and filling in trenches by proper compaction after construction cum 1.73
of structure all complete as per drawing, specification and instructions by
the Engineer.
Page 17 of 24
ct of Cost Estimation
10,000.00 10,000.00
538.95 932.22
373.75 387.88
13,473.76 23,305.39
17,185.21 35,094.05
921.61 287.93
226.14 125,574.60
Page 18 of 24
NPL
Bill of Qua
Project :- BOUNDARY WALL (Frontal Face)
Location:-
2 Civil works
2.1 Excavation work
2.1.1 Earthwork in excavation in ordinary to
mixed/hard soil in foundation including dressing 1.73 cum
of sides and proper compaction to trench bed,
2.2 Backfilling
disposing ofworks
excess soil and filling in trenches by
2.1.2 Backfilling works inafter
proper compaction 150construction
mm layer withof structure
compaction
all completeasasgiven in drawing,
per drawing, specification
specification and 1.04 Cum
and instruction by the Engineer
instructions by the Engineer.
Page 19 of 24
Project :- BOUNDARY WALL (Frontal Face)
2.5 Steel work
2.5.1 Supply, manufacture and installation of structural
steel works including two coats of Epoxy paints
over one coat of epoxy primer all complete as per 555.30 Kg
drawing, specification and instruction by the
Engineer.
Total Rs
Discount %
Discount Amount
Phone
Adress
Date
Page 20 of 24
NPL
Bill of Quantity
In word
Page 21 of 24
-
Page 22 of 24
Total Amount
Page 23 of 24
-
Page 24 of 24