1) During a software project Earned Value Analysis is performed and gives the
following results: EV: 523,000; PV: 623,000; AC: 643,000. Which results are
correct?
2) All of the following statements concerning project stakeholders are true except
c. Project stakeholders may influence the course of the project and its results.
a. Top.
b. Bottom.
d. Center.
a. Contract Administration.
b. Staff Acquisition.
c. Contract Closeout.
d. Contract Negotiation
b. Unachievable deliverables.
c. Accomplished objectives.
d. Decisions made earlier which limit the options for decision making.
a. Try to find some productive work for these staff members in the project and
leave them on the team.
b. The best thing is to do nothing. The customer will not realize the problem
anyway.
c. Try to find a responsible person for the over-assignment who can be made
accountable.
d. Take the two people off the team immediately and arrange for the refund of the
excess charges to the customer.
a. Working staff.
b. Materials.
c. Equipment.
d. The ability to communicate using drawings and pictograms which are understood
all over the world
11) You are assigned as the project manager in a project with an aggressive
schedule. During a recent meeting your team complained about the high pressure
applied and the many hours of overwork time. What is the preferred solution to
handle the problem?
b. Improve team communication and availability of high quality data on risks. Use
this information to enable you to make well-founded decisions earlier.
c. The problem might be the customer disturbing project rhythm. Keep him on
distance from the team.
b. Quality should be tested and inspected into work results on a regular base.
c. The primary cost of meeting quality requirements is the expense associated with
project quality management activities.
d. The primary benefit of meeting quality requirements is less rework, which means
higher productivity, lower costs, and increased stakeholder satisfaction.
a. Activities in PDM which are not necessary and can be dropped if time is running
out.
c. Activities, which can be passed to the team members with the lowest IQ.
b. Resource over-allocation.
c. Resource pooling.
d. Program management
16) Which of the following should not be reason for rebaselining in a project?
a. Scope changes.
b. Cost variances.
d. New information indicating that the basis for the original project cost
estimates was incorrect
17) When a change control system‘s provision for changes without formal review in
case of emergency is being utilized
a. Changes can be simply applied without further managerial activities if they help
solving the problem.
b. Changes must still be documented and captured so that they do not cause problems
later in the project.
19) Regarding quality and grade all of the following statements are true except
b. Grade is a category or rank given to entities having the same functional use but
different requirements for quality.
20) Which of the following is the correct formula for calculating present value of
a business or organization? Note: R = Interest rate, n = time periods
a. Present Value = Future Value/(1+R)n
21) Your most recent project status report contains the following information: BCWP
= 3,000, ACWP = 3,500 and BCWS = 4,000. The schedule variance is:
a. + 1,000.
b. + 500.
c. – 500.
d. – 1,000.
a. Floating.
b. Leveling.
c. Restructuring.
d. Crashing.
23) The _________ is a time-phased budget that will be used to measure and monitor
cost performance in the project.
b. project schedule
c. cost baseline
d. cost budget
a. Estimate at completion.
b. Budget updates.
d. Cost baseline.
a. Decision trees.
c. Risk symptoms.
d. Potential risk events.
Answers:
1) D
2) D
3) C
4) A
5) C
6) D
7) D
8) D
9) B
10) B
11) A
12) B
13) B
14) B
15) C
16) B
17) B
18) A
19) D
20) A
21) D
22) B
23) C
24) D
25) A