EPC Division - GMR Infrastructure

Ltd.

WORK METHOD STATEMENT FOR


WOODEN DOOR FRAME
INSPECTION, STORAGE, TESTING
& FIXING WORK

TATA HOUSING -KASAULI


WORK METHOD STATEMENT FOR CIVIL WORKS – TATA HOUSING-KASAULI REVISION NUMBER : 01
DATE OF ISSUE:19.12.2014 DATE OF REVISION: 19-12-14

INDEX

Sr.no. Description Page no.


1 Work method statement for wooden door frame for fixing 3-4
2 Checklist of wooden door frame 5

3 Inspection Report 6

4 Test Plan 7
WORK METHOD STATEMENT FOR CIVIL WORKS – TATA HOUSING-KASAULI REVISION NUMBER : 01
DATE OF ISSUE:19.12.2014 DATE OF REVISION: 19-12-14

9.0 Item of Fixing of wooden frame


Work
Purpose To Define the Work Methodology to be adopted for Carrying out fixing of wooden
door frame at the Project.
Scope Include D o o r f i x i n g to be Carried out during Construction at Project Site.
Applicable Contract Technical Specification
Standards/
1. IS: 4021: 1995 Timber Door specification
Codes/
2. IS: 287:1993 & IS 1734 Determination of density and moisture content
Ref. Docs.
3. IS: 1141-1993 seasoned process
4. IS: 3364-1976 measurement and evaluation of defects in timber.
5. IS 1708 Testing of small clear specimen for timber-(THDC)

Drawing./ Shop drawings.


Doc.
Approval
Activities 1. Approval of Make and Wooden section.
2. Approval of shop drawings.
3. Kiln seasoning and anti-termite treatment
4. Making of Wooden sections.
5. Fixing of frames.

Duration In line with the construction schedule of the project.


Tools Wood cutting & plaining machine, Drilling machine, Spirit level, Measurement
tape (metallic of 3m / 5 m),Chisel.
Trades men Skilled Masons, helpers.
Activity 1) This methodology approval are subject to sample approval in full including anchor
Description fastener , Hold fast, required coat of primer & Anti termite treatment on base.

2) The make and the section of the extruded Wooden sections shall be
approved by client from preferred manufacturers namely Red Marandi.
3) Seasoning process shall be done before being planned and shaped to the required
dimension.
4) The door Frame sections shall be fabricated and assembled as per approved
shop drawings.
5) Application of Anti-termite coating for the frame sides which are getting
abutting to the masonry/RCC face. Before starting of activity Name/Brand of
WORK METHOD STATEMENT FOR CIVIL WORKS – TATA HOUSING-KASAULI REVISION NUMBER : 01
DATE OF ISSUE:19.12.2014 DATE OF REVISION: 19-12-14

ATT & Name/Brand of primer shall be specified on checklist as per approved


by QA/QC.

6) All the section shall be inspected by GMR for any defect, crack, knots, holes
etc. after this stage pass primer application will be done.
7) Random testing as ITP done by GMR & witnessed by PIPL.
8) Application of colour less solignum paint to the face of frame in contact with
masonry.

9) Storage shall be done as per define in IS 4082. Door frame shall be stored in stacks
upon well treated so as to be above the ground level by at least 150mm at
respective building. Stack shall be protected from hot dry winds, direct sun or rain.
The frames shall not dragged or placed one over other.

10) Ensure proper alignment verticality before embedding hold fast and anchor
fastener.

11) Fixing of door frames shall be done as per the drawing by using MS hold fast for
masonry wall fixing and anchor fastener for RCC face. PIPL Approved Anchor
fastener as per Make & size shall be used, and same shall be mentioned in Checklist.

12) To fix the hold fast in masonry wall, the procedure fixed in mock up approval shall
be followed.

13) 3 hold fast of size 225x 25 xs6mm MS flat on each side embedded in M-15 concrete.
One at center point and other two at 30 cm from the top and bottom of the frames.

14) Remove temporary supports like thresh holds and corner parties’ final setting
of hold fast embedment and curing for 7 days.
15) Vertical members of the door frames shall be embedded in the floor for the
full thickness of the floor finish and shall be suitably strutted and wedged in
order to prevent warping during construction.
WORK METHOD STATEMENT FOR CIVIL WORKS – TATA HOUSING-KASAULI REVISION NUMBER : 01
DATE OF ISSUE:19.12.2014 DATE OF REVISION: 19-12-14

Responsibil1. 1) Execution Engineer shall be Responsible for the implementation of this


ity Matrix Methodology and Co-ordination with the Concerned Client.
2) Line Manager is responsible for maintaining all joint inspection
reports/records and approvals as per the requirements of Client/Their
Representatives.

3) Quality Assurance/Quality ControlEngineer will Randomly check the work in


line with the Specification.

Health & 1. Safety helmets, shoes, belts and gloves will be provided for masons and helpers.
Safety 2. Area lighting will be provided for night work. Good housekeeping will be
ensured.

3. Safety Supervisor shall ensure that Safety Precautions are taken and Safe Work
Environment is maintained..
TATA HOUSING DEVELOPMENT COMPANY LTD
Checklist for Door frame work
PROJECT: DATE:
Ref. Drawing No.: LOCATION: Sr.No:

YES No NA
1) Is approved Work Methodology is available.
2) Check for Approved material:
3) ATT name/brand as per approved by QA/QC.
4) Primer name/brand r as per approved by QA/QC
5) Anchor fastener Make / Size/ Spacing
6) Safety
a) Check for walkway Platform and access to workplace.
b) Check for safety of the Scaffold erected

c) Check for General PPE like safety helmets, safety shoes


d) Check for adequate task lighting during night time.
7) Check for Cleaning of work area. Is it Acceptable?
8) Is vertical members of the door frames embedded in the
floor for the full thickness of the floor finish

9) Check for workmanship:

a) Line
b) Level
c) Plumb
d) Right angles
e) Check for disposal of debris and house keeping

( )

Signature of Site Engineer

Corrective Action if any proposed: ___________________________________________________________


Inspected By: Reviewed by:
Signature: Signature:
Designation: Designation:
Date:
WORK METHOD STATEMENT FOR CIVIL WORKS – TATA HOUSING-KASAULI REVISION NUMBER : 01
DATE OF ISSUE:19.12.2014 DATE OF REVISION: 19-12-14

TATA HOUSING DEVELOPMENT COMPANY LTD


Inspection Test Plan for Door frame

Type of Parameter Specification Frequency Testing Responsibility Reference Record Remarks


Sl.no. Test requirement location document type

1 Identification Red Marandi


Third Third
Moisture Once in 75
2 <15 % party party test
Content nos. frames
Laboratory report
IS 12896-
3 Density
1990
As per As per
4 Dimension Randomly GMR QC in-
Drawing Drawing
charge
Cracks,
splits,
Physical shakes, Site
5 knots, sap IS 3364 Random
rots, pith
pockets,
wave