Académique Documents
Professionnel Documents
Culture Documents
Piping
General Piping Inspection Procedure
Revision Authorization
Rev. Changed Changed
Date Endorsed Endorsed Approved
No. Section By
1.0 12 Mar14 All SS PVR RJR
Distribution List
Introduction
The Distribution List shows current users of this practice. Users will be provided with the data
link for this document. To receive an electronic copy, contact the Head of Documents /
Standards.
Manual Distribution
Original Signed Copy with
Documents and Standards
Controlled Electronic Copy Posted in
RGDMS
File name:
1.0 SCOPE
2.0 INTRODUCTION
2.1 Purpose
2.2 Objectives
3.0 REFERENCES
4.0 INSPECTION PROGRAM.
4.1 Purpose of Inspection
4.2 Inspection Frequency
4.3 Data Compilation
4.4 Inspection Plan
4.5 Inspection scheduling
4.6 External Visual Inspection (GVI)
4.6.1 Inspection for CUI
4.7 Inspection for Internal Corrosion
4.8 Inspection of Non-metallic Piping
4.8.1 Glass reinforced plastic (GRP) piping
5.0 REPAIRS AND QA/QC
6.0 COMPETENCY ASSURANCE
7.0 DOCUMENTATION AND REVIEW
7.1 Activity Results Analysis
7.2 Corrosion rate calculations
7.3 Remaining Life Assessment
7.4 Fitness for service evaluation (FFS)
7.5 Assessing the probability of failure due to corrosion
8.0 VERIFICATION AND MEASUREMENT
9.0 EXCEPTION REPORTING
10.0 APPENDICES
10.1 Appendix A- Piping retirement thickness
1.0 SCOPE
The requirements of this General Piping Inspection Procedure apply mainly to all criticality
“A” and “B” piping, as defined in Equipment Criticality Assessment. Requirements will also
be applied to selected criticality “C” and “D” piping at RasGas’s option (refer Table 1-1).
For the purpose of this document, any piping located between the nozzle of a pressure
vessel, tank, or heat exchanger and the first isolation valve upstream or downstream of that
equipment, is considered to be part of the equipment. This procedure includes the
equipment degradation monitoring, inspection, and welding activities required to assure
the integrity of piping designed to ASME B-31.3 (or similar piping code) for the following
facilities:
2.0 INTRODUCTION
2.1 Purpose
The purpose of this procedure is to provide a framework document that identifies:
2.2 Objectives
This procedure seeks to conduct and manage Piping Inspections, to achieve the following
objectives:
Comply with applicable regulatory requirements.
Comply with RasGas piping ES requirements and thereby meeting FIMS (RGEE6-6)
requirements.
Maintain standards of mechanical integrity and reliability required to meet business
objectives established by the OLT, TLT and Asset team.
Minimize significant failures over the design life of piping and facilities.
Help to achieve optimum life-cycle maintenance costs.
3.0 REFERENCES
The industrial and international standards and references contained in this section are
provided strictly for reference and are not represented as requirements except if specified
within this document and design basis for the facilities. References are as follows:
Design references:
ASME B31.1 Power Piping
ASME B31.3 Process Piping
ASME B31.8 Gas Transmission and Distribution Piping
Welding references:
Inspection references:
Other references:
Piping inspections, i.e. both on stream and off stream inspections, are carried out to
detect, measure and monitor various deterioration mechanisms that may be active
depending on its internal / external environment. The purposes of these inspections are
to ensure that deterioration in piping condition is detected before its integrity is at risk.
Accurate compilation of data on piping segments at the facility is the first step. If a
piping line list does not exist, one is created from the piping and instrumentation
diagrams (P&IDs) and piping isometric. The line list contains all the line segments for the
facility with information regarding service, size, temperature and pressure rating,
material, pipe class or specification, description of origin and exit, and whether it is
insulated.
Piping inspection program consists of planned piping circuit (Corrosion loop, CL) to be
inspected, inspection locations (CMLs or TMLs) on a given CL, and the type and method
of inspection at the identified location. Given the large number of piping segments in an
operating facility, the setting up and maintenance of the piping program can be time
consuming and requires adequate planning, preparation, resource allocation, and
budgeting. For effective and manageable inspection program, piping circuits (corrosion
loops, CL) are used, that group pipe segments exposed to similar modes of internal and
external degradation (considered as a best practice).
All the above requirements are captured in a work pack (IE WP) which describes the
lines included in a CL, damage mechanisms expected (driver for inspection), type of
inspections, time required for each inspection, logistics required to complete each
inspection, inspection locations, marked up P&IDs & ISOs and some relevant tables
which summarizes inspection activities; and is developed for each CL. Documentation of
the inspection findings in Meridium, review the inspection findings and approving
recommendation are part of this program. This is required to determine fitness for
service of the piping segment, with a clear and timely set of recommendations to ensure
safe and reliable operations.
Once circuits are defined, inspection intervals are defined, CMLs & TML’s are identified,
and entered into the inspection database; the final step is to schedule the inspection.
The dates for the inspection should be scheduled by CMMS team (computerized
maintenance management system) in SAP as per frequency set by RBI program and
inspection reports will entered in Meridium.
Corrosion loops (CL) are inspected externally to determine the condition of the outside
of piping, insulation, painting and coating systems, associated supports and hardware. It
also helps to check for leaks, misalignments, vibration, corrosion at supports, etc. Where
possible, inspections take place while the line is in-service to enhance the detectability
of the above items. External visual inspection also serves to uncover any field
modifications or temporary repairs not previously recorded on the piping drawings or
records (or both).
Insulated piping which operates in –4°C to 150°C GIP4.2.1 temperature range is susceptible
to external corrosion if water is able to penetrate the insulation weather jacketing.
Sources of water include rain, deluge, and condensation (particularly on cold lines).
Corrosion under insulation (CUI) can occur anywhere the jacket is breached, including
improperly caulked jacket seams, cutouts for pipe supports and connections, damaged
jackets, and termination points (especially for vertical lines).
For complete guidance on the details required for a CUI inspection program, refer to CUI
Manual and XOM MPM TMEE-062, GIP 4.2.1.
Internal visual inspections are not normally performed on piping, except in some
refractory lined piping of SRU. When possible and practical (for large diameter pipe or
when flanges are disconnected), the same can be undertaken and is similar to vessel
internal inspection and should be conducted with the same methods and procedures
used of vessel internal inspection. Remote visual inspection techniques (Boroscope,
Rover camera, etc.) can be helpful for both small and large diameter pipes.
This section of the procedure outlines the inspection practices adopted by RasGas to
verify and maintain mechanical integrity of its nonmetallic piping systems during
operation.
The scope of this section is limited to in-service inspection of GRP systems to assure
adequate levels of safety during operation. During visual inspections GRP piping systems
are checked for evidence of impact damage and breakdown of the outer surface due to
weld splatter, abrasion, chalking (ultraviolet [UV] degradation) or aging. An illumination
source is used to maximize the extent and accuracy of the visual inspection. Flanges are
examined closely for evidence of cracking and leaks, and earthing cables are checked for
signs of corrosion. Checks are made to verify that the GRP piping is adequately
supported, especially near valves and heavy equipment items installed on the system.
Design or fabrication concerns identified during external visual inspections are noted for
follow-up action.
See PIM section No: T13-X01-009_0061 for detailed procedure for repairs and modifications.
This part describes how Piping Inspection results are analyzed for the evaluation of
individual piping/components fitness-for-service determinations.
Where:
tI = thickness of wall recorded in baseline survey (mm or inches)
tL = last recorded thickness of wall (mm or inches)
tP = thickness of wall recorded in previous survey (mm or inches)
6) Consider a one time reinspection recommendation before next due inspection per
the current Equipment Strategy.
7) Inspection frequency is increased (that is, inspection interval is reduced) to closely
monitor deterioration prior to failure. Re-inspection frequency is estimated by
using one-half of the calculated remaining life. Conduct RBI analysis and adjust the
inspection frequency.
Plan repair / replacement as required.
The affected pipework is re-rated to a lower pressure.
Note: Inspection does not mitigate risk; it better defines the probability of failure.
9.0 APPENDICES
10.1 Appendix A- Piping retirement thickness
Piping requires sufficient thickness for pressure containment and for structural
requirements/mechanical integrity. Piping thickness data for FFS determination is to be
collected as per Piping Thickness Monitoring Procedure (T13-X01-0043). The retirement
thickness is taken to be the greater of the value shown below (to assure that sufficient
mechanical strength remains in the pipe after the specified corrosion allowance has
been expended)API-574.
For piping >24” and/or calculated wall thickness piping (versus nominal schedule piping): (A)
calculate the minimum require thickness for pressure per the calculation below; (B) calculate
the required thickness per vacuum design requirements and (C) calculate t = D*0.169 where D
is the Nominal Pipe Size in inches and the resulting t is in mm (for NPS>24). Take the higher of
the three as the “minimum thickness” required before retirement.
For all other piping, unless subject to unusually large loads (many valves, etc), use the following:
Nominal Pipe Size (NPS) Retirement Thickness (mm)
3 through 18 3.4
20 through 22 3.8
24 4.2
The above is to be used as a first pass flag thickness for input to Meridium as the “minimum
thickness” requirement for determining remaining life. If we have readings at or below the
retirement thickness, FFS should be performed.
WARNING: When selecting a t-min (required thickness) or running the t-min calculator in
Meridium for piping >=24” (or for any other piping with calculated wall thickness vs nominal
wall thicknesses), check the calculated required thickness considering vacuum and pressure
thickness requirements as applicable before using the Nominal t-min which is based on
0.169*D.
10.2 Appendix B- Piping Inspection Checklist