Académique Documents
Professionnel Documents
Culture Documents
This paper was prepared for presentation at the PSIG Annual Meeting held in San Antonio
Texas, 7 November – 9 November 2005.
This paper was selected for presentation by the PSIG Board of Directors following review of
information contained in an abstract submitted by the author(s). The material, as presented,
does not necessarily reflect any position of the Pipeline Simulation Interest Group, its officers,
or members. Papers presented at PSIG meetings are subject to publication review by Editorial
Committees of the Pipeline Simulation Interest Group. Electronic reproduction, distribution, or
storage of any part of this paper for commercial purposes without the written consent of PSIG
is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300
words; illustrations may not be copied. The abstract must contain conspicuous
acknowledgment of where and by whom the paper was presented. Write Librarian, Pipeline
Simulation Interest Group, P.O. Box 22625, Houston, TX 77227, U.S.A., fax 01-713-586-5955.
ABSTRACT
Natural gas transmission networks tend to be dynamic in
nature and the majority in Europe do not normally operate on
a simple steady-state basis. Loads ramp up and down in
response to changing demands, driven to some extent by the
new emerging European market.
TRANSIENT THEORY OVERVIEW Transient simulators all use the same fundemental equations to
solve the problems of transient flow. The equations of
The majority of problems analysed by engineers involve some transient flow are the equations for the conservation of mass,
form of transient phenomena. Transient solutions to problems, momentum and energy. Together with an equation of state
whilst often attempted, are not always fully utilised or these form a complete system which can be solved. Other
understood. The reasons for this may include: variables may be computed from the results.
• Steady-state analysis provides an adequate The equations which are solved in transient simulators are:
approximation
• Transient analysis is complicated • Mass Conservation
• Transient analysis is time consuming
( Aρ )t + ( Aρv )x =0
Whilst the point that steady-state analysis provides an
adequate approximation may be argued, with modern software Where
and personal computing power available the points regarding 0≤ x ≤ L&t ≥ 0
the complexity of transient analysis and the time consuming
nature of transient analysis may be disregarded. • Momentum Conservation
The question may then be asked : “Why use a transient
simulation?” Px f
vt + vv x + + ghx + vv = 0
ρ 2D
Transient simulations of a pipeline support a more detailed
understanding and appreciation how a pipeline will behave • Energy Conservation
under operational conditions.
δP f 4U w
ρcv (Tt + vTx ) = −T
3
For example, a gas transmission system which supplies power vx + ρ v − (T − Tg )
facilities for a region: Because of the likely large swing in load δT ρ 2D D
requirements on a diurnal delivery schedule, such a pipeline
should be analysed to ensure that the swing can be maintained • Equation of state
by the existing capacity of the pipeline without the need for
storage, and that the gas can be transported along the pipeline
quickly enough to replenish the depleted parts of the network PV = ZRT
when required.
C o ld D a y H o u r ly L o a d P r o f ile
800
700
Steady-state Capacity
Demand (mmscfd)
600
500
4 0 0shown in Chart 1 shows that, although it could
The example
be argued3 that
0 0 over a sufficiently long time period a pipeline
behaves in
2 0a 0steady-state fashion, over the time scales of
operation1(hours
0 0 or days) transient analysis is needed to
understand the0
implications of load variations within the
pipeline system
11
13
15
17
19
21
23
1
T i m e (H o u r s)
Chart 1: Chart illustrating how a load may change at a demand on a cold day
PSIG 0504 A case study of how transient analysis facilitates asset optimisation 3
Where:
THE NETWORK UNDER CONSIDERATION
A Cross sectional pipe P Pressure The network under examination was the Dublin area
area Transmission System. It is a complex interconnected network
ρ Fluid Density U Heat Transfer Coefficient with more than 10 separate transmission pipelines and over 50
v Fluid Velocity Cv Heat capacity of gas offtake stations. To appreciate the analysis undertaken, it is
x Position along the Tg Ground Temperature important to have an understanding of the main features of this
pipe network.
t Time Z Compressibility
L Length of Pipe R Gas Constant
f Moody Friction D Internal Pipe Diameter Dublin consists of the following principle pipelines:
Factor
g Acceleration due to h Elevation of pipe Pipeline Ø in P psig Year
gravity ( mm) (barg) Built
NETWORK OVERVIEW
Transco
Figure 1 : BGE Network
SNIP
Corrib
South PTL Ireland’s natural gas network currently has two
North sources of supply. The majority of gas comes
Mayo Pipeline
Galway Under from the UK, where the BGE system ties into
Pipeline Construction IC2 the Transco network. Kinsale is a mature
Under
Construction
IC1
indigenous field with the ability for storage.
Storage is also available on the Interconnector
Dublin subsea pipelines. A 2nd indigenous field off the
west coast, Corrib, is due to come on stream in
2007 and there are two major pipelines
currently under construction : the Mayo-
Galway pipeline & the South-North pipeline.
There is an independent Transporter connected
to the BGE Scottish system. This the Scotland
Kinsale Northern Ireland Pipeline (SNIP) which is
Kinsale operated by Premier Transmission Ltd (PTL).
40 Barg CCGT
Swords AGI 19 Barg
Eastwall
Pipeline
70 Barg Ringmain
CCGTs
Poolbeg
19 Barg Canal
Feeder AGI
Sandyford AGI
Dublin
Brownsbarn Distribution
40 Barg Southern Feeder AGI
DEVELOPING THE MODEL and running them in the model. Model pressures were then
compared with the relevant SCADA pressures and the
Up to the time of the request for additional capacity, all delivered volumes in the model were comparing with actual
modelling of the Dublin network was done using steady-state flow data.
analysis.
Considerable time was spent data cleansing. Dublin is a
In the first instance, the steady-state model was run, with each complex integrated network and it was important to ensure
offtake flow rate set to the relevant maximum peak hourly that the SCADA data under consideration was correctly
rate. This preliminary analysis indicated that the additional interpreted. It was therefore necessary to fully understand the
capacity could not be accommodated, as the additional make-up of all the numbers being used and so considerable
demand resulted in an unacceptably high increase in flow effort was spent ensuring that the historic information was
through Poolbeg Feeder AGI. processed appropriately.
Given that the network had in the preceding years been The calibration work proved successful. Figure 3 shows
significantly reinforced, there was an underlying feeling that pressures at Guinness AGI, which is in the center of Dublin 19
the additional capacity could be made available. However the Barg network.
steady-state model indicated that there would be difficulty in
doing this. Rather than carry on with the steady-state analysis
on a trial and error basis, it was deemed appropriate to develop Figure 3 Guinness AGI Pressures
a transient model of the system, in order to get a better Modelled Pressure Actual Pressure
The actual flow data used for calibration was equivalent to A report was prepared which described in detail the work
64% of the estimated peak day demand for the coming winter, undertaken and included a recommendation that the network
so load trends for the relevant offtakes were turned up, to be modified .Transmission Operations subsequently reset the
produce appropriate peak hour demands. The load profiles discharge pressure at the relevant regulator stations in
associated with the calibrated data were utilised without accordance with the findings of the transient analysis. With
modification. There was considerable debate over whether or the system suitably biased it was possible to offer the
not changes should be made to certain profiles, to allow for additional capacity to the Power Generator.
possible behavior patterns that may only exists on and around
a 1 in 50 type day. In Dublin, snow on the ground for It’s not unreasonable to suggest that the solution could have
approximately 5 days could be considered representative of been produced by using steady-state analysis. However such
peak type conditions. Future work planned on this model work would have involved an indefinite amount of “trial &
includes the non-linear adjustment of the profiled loads to take error”, which would undoubtedly have taken considerably
account of the nature of the peak day in a more appropriate longer to do. In fact it could be argued that using the transient
manner model, forced BGE to address the key issues such as station
throughputs & system biasing. In addition, the calibrated
There are three regulating stations in the center of Dublin that transient model provided a level of confidence in the results
act as 290 psig pressure injection points at the center of the that would not otherwise have been present. Put simply,
system. Swords Road AGI is on the CCGT Pipeline. steady-state analysis was not the right tool for the job. Steady
Sandyford & Poolbeg Feeder AGIS are on the Southern state studies are very useful in certain instances such as initial
Feeder pipeline. In the model, these AGIs were initially set to line sizing but such an approach was not entirely suitable in
discharge an outlet pressure of 290 psig, as they were this case study.
configured in the field.
With this arrangement the transient model reflected the FURTHER OPTIMISATION STUDIES
findings of the preliminary steady-state model. Once again the
volumetric flow through the Poolbeg Feeder AGI exceeded
the station’s capacity. However it was also observed that the The development of a transient model of Dublin City was a
flows through Swords Road and Sandyford were less than the result of a specific request from a customer. The model has
maximum allowable. subsequently proved to be of considerable value in relation to
other areas of the business. The accurate and robust nature of
By adjusting the outlet pressures at these sites it was possible this particular software tool has enabled BGE to model
to control the quantity of gas passing through these Stations. numerous pipeline reroutes which have been carried out in
Turning down the outlet pressure setting at the Feeder Station, Dublin since the time of the original work. At various
transferred demand to Swords Road and Sandyford. locations in Dublin, relatively short sections of the existing
transmission mains have had to be moved. Modelling such
A series of model runs were carried out with various works in advance of construction has meant that several
permutations of station outlet pressures until the load through schemes were carried out within having to use temporary by-
each of the AGIs were less than the station volumetric limit passes. Appropriate models developed from the original
maximum capacity model, demonstrated the feasibility of simply shutting the
particular section and thus leaving out a live by-passes. Not
As a result of this work it was possible to identify an operating only does this reduce the cost of construction but it also
arrangement which allowed the additional capacity to be improves the level of construction safety, by eliminating the
accommodated without exceeding volumetric limit at any of need to have a temporary high pressure by-pass line within the
the three central regulating stations. construction wayleave.