Vous êtes sur la page 1sur 50

Contents

1. INTRODUCTION ................................................................................................................................... 3
2. TOTAL SCOPE OF WORK ...................................................................................................................... 4
3. PROJECT OBJECTIVES & ORGANIZATION ............................................................................................ 4
3.1 Statistics of key management personnel configuration of the project ........................................ 5
4. GENERAL SITE LAYOUT ........................................................................................................................ 6
5. MOBILIZATION PLAN ........................................................................................................................... 6
5.1 Main camp .................................................................................................................................... 6
5.2 Temporary Roads .......................................................................................................................... 7
5.3 Temporary Jetty ............................................................................................................................ 7
5.4 Water ............................................................................................................................................ 7
5.5 Electricity....................................................................................................................................... 7
5.6 Equipment parking and maintenance yard................................................................................... 7
5.7 Material storage facility ................................................................................................................ 8
5.8 Laboratory ..................................................................................................................................... 8
5.9 Medical and Health Facilities ........................................................................................................ 8
6. SUBSTRUCTURE WORK (LAND VILLAS) ............................................................................................... 9
6.1 Excavation ..................................................................................................................................... 9
6.2 Foundation footing ..................................................................................................................... 10
7. SUBSTRUCTURE WORK (OVER WATER VILLAS)................................................................................. 13
8. SUPERSTRUCTURE WORK ................................................................................................................. 17
8.1 COLUMN...................................................................................................................................... 17
8.2 BLOCK WORK .............................................................................................................................. 19
8.3 PLASTERING ................................................................................................................................ 23
8.4 TILLING ........................................................................................................................................ 26
8.5 WATER PROOFING ...................................................................................................................... 33
9. AC AND VENTILATION WORK ............................................................................................................ 38
9.1 Fan Coil Installation ..................................................................................................................... 38
9.2 Air-Conditioning Unit Installation ............................................................................................... 38
10. PLUMBING AND WATER SUPPLY WORK ......................................................................................... 38
10.1 Sanitary Ware Installation......................................................................................................... 39
11. POWER SUPPLY WORK .................................................................................................................... 39
11.1. General flow of Power supply construction ............................................................................ 39
11.2. Reserved and embedded stage................................................................................................ 39
11.3. Conduit laying .......................................................................................................................... 39

1
11.4. Cable tray laying....................................................................................................................... 40
11.5. Wiring ....................................................................................................................................... 41
11.6. Cable laying .............................................................................................................................. 41
11.7. Panel and cabinet installation .................................................................................................. 41
11.8. Light fixture installation ........................................................................................................... 42
12. INSTALLATION OF DUCTS (CONDUIT) ............................................................................................. 43
12.1. Installation techniques and procedures .................................................................................. 43
12.2. Duct materials .......................................................................................................................... 43
12.3. Size of ducts ............................................................................................................................. 43
12.4. Installation of ducts without concrete encasement ................................................................ 43
12.5. Installation of ducts encased in concrete ................................................................................ 43
12.6. Ducts and flexible tubing ......................................................................................................... 44
12.7 Grounding bushings .................................................................................................................. 44
12.8 Arrangement of duct banks ...................................................................................................... 44
12.9 Drainage .................................................................................................................................... 44
12.10 Pull wire .................................................................................................................................. 45
12.11 Spare capacity ......................................................................................................................... 45
13. MANHOLES AND HANDHOLDS........................................................................................................ 45
13.1. Selection................................................................................................................................... 45
13.2. Location.................................................................................................................................... 45
13.3. Hardware ................................................................................................................................. 45
14. INSTALLATION OF UNDERGROUND CABLES ................................................................................... 45
14.1. Preparation of ducts ................................................................................................................ 45
14.2. Method of pulling .................................................................................................................... 46
14.3. Length of pull ........................................................................................................................... 46
14.4. Cable racks ............................................................................................................................... 47
14.5. Cable terminations ................................................................................................................... 47
14.6. Cable grounding ....................................................................................................................... 47
15. SAFETY PLAN ................................................................................................................................... 48
15.1. Safety assurance ...................................................................................................................... 48
15.2. Security plan............................................................................................................................. 48
15.3. Electrical Safety ........................................................................................................................ 49
15.4. Fire safety................................................................................................................................. 50

2
1. INTRODUCTION
Proposed Avani Fares Maldives Resort located on Fares Island North West to Male capital and 100km
away in the Maldives Baa Atoll, renowned for its vibrant biodiversity from land to sea. The untouched
private island has 12.4 hectares of total land area. Avani Fares Maldives resort secluded northern
location is 45 minutes journey from sea plane from Male and 30 minutes by speed boat from Baa Atoll
domestic airport

Map-1

3
Map-2

2. TOTAL SCOPE OF WORK


This project has two phases. Phase one for developing land buildings which has 9 different types of
land villas, and phase two proposed for developing over water villas

Project scope includes substructure works for land building and over water structures, construction of
wall and internal partition, floor and wall finishes, supply and fixing of doors and windows, roof
construction and Mechanical, electrical and plumbing (MEP) works.

The schedule of building given below

Phase -1

Phase-2

All the excavation shall be mechanically carried out and foundation shall be column footing. As
contractor we propose hollow block for external wall and internal partitions for land and over water
villas. Normal plaster and paint wall finish shall be adopted. For openings wooden and glass panels
and frames shall be used. Timber roofing shall be used to construct roof of all king kind of buildings.

3. PROJECT OBJECTIVES & ORGANIZATION


Q/C Objective: In compliance with specification and relevant codes provided to Client.
Progress Managerial Objective: Within 12 months since commencement.
HSE Managerial Objective: Conform to CCCC/THEC’s Project HSE Management Guiding Plan, and also
take account of actual project characteristics.

Cost Control Objective: Fulfill every obligation under the contract within the contract value.

Safety Managerial Objective: No significant safety accidents, no fatalities, and maintain the minor
injury occurrence rate lower than 3/1000.

Allow for above Project objectives, Contractor will assign one project manager, two deputy project
managers and one chief engineer, as leading group, to conduct management over Project

4
management department which consists of construction department, QC department, HSE
department, logistics department, business & QS department, finance department, general
administrative office, which is demonstrated as the following chart:

3.1 Statistics of key management personnel configuration of the project


management personnel include
S/N foreman

Position QTY

1 Project manager 1

2 Deputy manager 1

3 Chief engineer 1

4 Chief economist 1

5 chief accountant 1

5
6 Construction Department 15

7 QHSE Department 2

Logistic including material


8 5
Department

9 Finance department 2

Business Management
10 2
Department

13 Subtotal 31

4. GENERAL SITE LAYOUT

5. MOBILIZATION PLAN
Through the inspection after island and permanent building location combined with the characteristics
of the road construction, water, electricity, materials and other resources distribution, and consider
the on-site construction management, material storage. According to the above reasons, the
construction of the resident arrangement is as follows:

5.1 Main camp


 The main camp is located between main jetty and water villa jetty on beach, 10m land side to
high tide line with area of around 3200 square meters.

6
 The main camp includes staff accommodation, labors accommodation and project office area.
 The areas proposed 500m2, 2500m2, 200m2 respectively for accommodation, labors
accommodation and project office
 All the temporary buildings shall be constructed using aluminum panel boards
 The office and labor camp shall be two storied buildings
 Staff labor camp shall have 10 single bed room for managers and 20 double bed room for rest
of staff. Wash room will be attached to living room and all basic fixtures shall be provided
 For labour 50 bed dorms 6 numbers shall be constructed, with public toilet facilities.

5.2 Temporary Roads


 The construction access road is convenient for the transportation of materials. 1350m access
road along on permanent road line at width of 5m.
 The access road and the construction access road are leveled by a bulldozer or a grader, and
the road surface is made of mud and gravel. In order to prevent dust, the pavement is used in
the field.

5.3 Temporary Jetty


 The temporary jetty shall be constructed during initial phase of mobilization
 Proposed jetty shall be located near material storage area and it will extended up to deep sea
where medium sized vessel can be reached
 It will be made from using sheet piles, sand bags and expected length shall be around 50
meters

5.4 Water
 According to the on-site inspection, the water for living and construction purpose shall be
produced from recycling the sea water using RO plants.
 Expected fresh water consumption per day approximately 200m3 for living and construction
purpose.
 To produce required water quantity 5 no of RO plants shall be stationed and each capacity
shall be 45 cubic meters per day.
 For drinking purpose treated water shall be tested in every two days.

5.5 Electricity
 Electricity for construction and living shall be produced from diesel generators
 Total electricity consumption at peak time for construction and living purpose approximately
200kwh.
 To meet site requirement it planned to arrange 7 numbers of 20kwh mobile generator and 6
numbers of 10kwh mobile generators
 All generators shall be feed to one main panel and from main panel it shall be distributed to
10 sub panels which located in 10 different places

5.6 Equipment parking and maintenance yard


 Construction of equipment parking lots and maintenance yard shall be located next material
storage area. For parking and maintenance 100m2 of land shall be allocated.

7
 Simple oil depot and tanker parking space are set within a certain distance. It is equipped with
the necessary fire protection facilities.

5.7 Material storage facility


 Material storage facility shall be constructed near temporary jetty to unload and storing
materials rapidly.
 Storage area shall be 1200m2, it will include open storage for sand, aggregates and block. And
temporary yard shall be fabricated using aluminum sheet to store cement, putty, paint and
other materials which will affect due to exposing to open environment.

5.8 Laboratory
 A site laboratory room shall be set up in the project operation area with area of 30m2.
 It will consist compression machine, scales, compaction tester, soil moisture checking
instruments and all other necessary testing equipment required for construction..

5.9 Medical and Health Facilities


 A sickroom shall be set up at project operation area with area of 15m2.

 An experienced nurse shall be employed to give first aid.

8
METHODOLOGY OF CIVIL WORKS

6. SUBSTRUCTURE WORK (LAND VILLAS)


6.1 Excavation
1. Scope

This describes a proper work procedure shall be carried out during the excavation stage as per
specification and contract drawings

2. Work Procedure

I. Excavation

 The area to be excavated shall be properly marked and clear before starting the works.
 The depth of excavation shall be periodically checked by a surveyor to avoid over
excavation. the bank of excavated area shall be sloped 30 degrees and shall be
maintained to avoid a collapse of the bank into the excavated area.
 All excavated material shall be kept a minimum of 1.0 meter from the edge of excavation
or shall be stockpiled to the area designated by the Engineer.
 For all excavation activities, adequate safety barriers, sign boards, advance warning signs
would be used.
 For foundation, as soon as the excavation reaches the required depth/elevation the
surface shall be leveled and shall be compacted to 95 % of maximum dry density or MDD.
 Before the compaction starts, it shall make sure that the excavated level is free from
standing water or excessive moisture content.
 Inspection would be conducted during compaction for checking and approval of the
Engineer.
 The compaction test report shall be submitted to the Engineer for approval prior to
proceed succeeding work.
 Anti-termite treatment would be conducted prior to start blinding works but make sure
the anti-termite material is approved by the Engineer.

II. Back filling

9
 After completion of the compaction under blinding, tie beams and ground slab.
Backfilling shall commence using similar excavated material. Care shall be taken to
remove bolder, vegetation and any other deleterious materials.
 But prior to backfilling, the compacted surface shall be accepted by the Engineer.
 The thickness of the back fill shall not be greater than 300mm.
 The sub-grade once approved, the excavated materials or any material source approved
by the Engineer shall be placed in layers not more than 300 mm thick followed by
compaction test when the surface level is ready.
 In-situ dry density test (compaction test) shall be performed at the rate indicated in the
specification.
 Back filling followed with compaction shall continue till final level is achieved.

3. Equipment and Tools

 Excavator
 Pay Loader
 JCB
 Six Wheel Truck
 Bob cat
 Shovel
 Total Station
 Meter tape

6.2 Foundation footing


1. Scope

The purpose of this Method Statement is to describe the measures and ways of completing concrete
pour work for footings on this project. The works shall be carried out in compliance with the drawings
and project specification.

2. Work Procedure

I. Reinforcement

10
 Some footings are composed of top and bottom reinforcement, the bottom bars shall be
supported with concrete block or spacer of correct thickness.
 Inspection Request (IR) would be submitted for steel reinforcement for checking and
approval of the Engineer prior to concrete casting.
II. Casting
 Make sure that the area within the shutter to be poured with concrete is cleaned.
Remove all rubbish, dirt, and any other deleterious material via air compressor.
 Inspection Request can be submitted to the Engineer or Consultant for approval of fixed
steel reinforcement and installed forms, if casting shall not take place on the same day.

 Readymade concrete shall be provided from batching plant approved by the Engineer.
The rate of concrete supply shall be 30 to 50 Cubic Meter per hour.
 The required number of concrete pumps will be available on site; extra pump will be on
standby ready for any incident circumstances.
 Concrete vibrators shall be ready to use at time of receiving concrete. Number of
vibrators shall be depending on concreted area to improve well compaction for concrete
pump.
 Computerized delivery ticket shall be checked for conformity as per the approved design
mix.
 Slump and temperature shall be carried out from each concrete truck mixer.
 Slump shall not more than 150mm and not less than 100mm as per Engineers instruction
and approval. Temperature of fresh concrete shall not more than 30 deg. Celsius as per
BS Standard.

11
 All data required for daily concrete schedule sheet will be recorded in the daily concrete
pour card.
 Concrete at truck mixer shall not exceed more than 90 minutes from leaving batching
plant.
 On acceptance, mix shall be directly unloaded in the concrete pumps. Care shall be taken
to make sure that concrete mix is not dropping from more than a height of 2 meter.
 Concrete when introduced to the footing at first level of 400mm shall then be vibrated,
the same shall be done for the succeeding layer of concrete until footing top level is
reached.

 When concrete reach proposed level; hand trowelling should carry out to get a smooth
surface according to the top footing level.
 When the concrete is cured it shall then be applied with water proofing system in
accordance to the specification.
 For approval: Inspection request would be submitted to the Engineer or Consultant for
the concrete pouring approval.
3. Equipment and Tools

 Concrete pump
 Truck Mixer
 Boom loader
 Bobcat
 Concrete Vibrators
 Wheel borrow
 Surveying instrument

12
 Metal tape
 Slump cone
 Slump tray
 Trowel
 Cubes
 Shovel

7. SUBSTRUCTURE WORK (OVER WATER VILLAS)


1. Scope

This describes a proper work procedure shall be carried out for foundation work for over water villas.
Here we supposed to use spun piles as column footing with diameter of 300mm.

2. Work Procedure

I. Pile stocking and transporting

 For the stock pile, in advance, make ground stable and evenly level and then chock out with
timber as below. Maximum stock shall be 3 story’s height.

 The pile section to be driven shall be lifted at the specified point meant for such purpose.
Any damage occurring to a pile section during this shall be the responsibility of the
Contractor.
 Lifting pile shall be at the triangular sign, space should not too far away from the crane and
area shall be free from other surrounding disturbances

13
II. Pile Driving

 Just before driving, each pile shall be checked for straightness, cracks and other defects.
 The pile location shall be as per approved drawing & shall be set out by contractor and
checked by the Client Surveyor. The Contractor shall be responsible for clearing the site of
any temporary obstructions to move the driving equipment to a suitable position from which
the pile can be driven.

 Pre boring shall be done just before Piling with depth that is checked and approved by the
Engineer after confirmation by Civil Design.

 In principle, pile driving shall be executed in the presence of representatives.

 It is preferable to drive piles from the center of site to it’s perimeter to avoid refusal. Due to
the compaction effect by the previously driven piles.

 Piles shall be moved from its storage area to the pilling machine with special care to avoid
damage to the pile.

 Piles shall be hung properly to avoid causing damages to them.


 The pile section to be driven shall be held true to the position in which it has to be driven.
The Engineer may check verticality, at his discretion & shall instruct the contractor about the
rectification if needed.

14
 Piles shall be driven plumb or to the designed angle, and shall not be excessively pulled into
line after driving.

 Proper cushion, preferably pine, shall be used to protect the pile head, and to transmit the
blow of hammer uniformly to the pile head. The cushion shall be changed at proper intervals.

 If the following matter happens, the Sub-contractor shall immediately inform Engineer. All
deviations shall be reported by the Engineer to Civil Design and their opinion on the matter
shall be sought, regarding the rectification including driving an additional pile if necessary.
In such case the cost of the pile driven in wrong location, including the material,shall be
recovered from the Contractor.
 Piles shall be driven to a specified 'set' (final set is less than 5 cm per 3 x 10 blows), total
blows per 0.5 m’ not exceed 500, total blows for total length not exceed 1800 or to a length
as specified on the design drawings provided by Client / Engineer. The pile should be driven
up to the pile driving elevation as specified on the drawings. All such levels shall be checked
and approved by the Engineer.

15
 If a pile is cracked, broken, or otherwise damaged or driven out of plumb or designed angel,
extra pile(s) shall be driven as directed by the Client representatives at the Sub-contractor’s
own expense.

 Welding of pile joint shall be inspected and rectified by Engineer before epoxy and driving
into appropriate depth or ‘set’.
 After a pile group is driven the contractor shall clear all his equipment, material, wood
scantlings or any other debris from the pile group location.
 The contractor shall carry out a pile load test either static or dynamic 3 % from total pile
driven.
3. Equipment and Tools

 Driving Rig
 Hammer JWDD 8.0 or Equivalen
 Cap and Wooden Cushion.
 Theodolite or Total Station.
 Auto Level
 Measuring Tape.
 Marking Stick / Paint / Color Pen.
 Service Crane.
 Trailer Truck.
 Wheel loader
 Excavator

16
8. SUPERSTRUCTURE WORK
8.1 COLUMN
1. Scope

This procedure provides a method of control of construction of rcc column in order to achieve
compliance with the contract specification and drawings.

2. Work Procedure

 Starters shall be made of 100 mm x 50 mm channel section.

 Concreting of starter will proceed after checking of layout with necessary clearance from
clients.
 Column wall Shutters/boxes will be 12mm thick film coated ply with backing angles at the
edges and flat at the center about 300C/C both ways. The lift for columns will be of 2.4 m
height in general but however this may vary depending on requirement.
 Vertical reinforcement bars and Stirrups shall be provided as per Drawings & BBS Checked by
clients and suitably tied with binding wire.
 The reinforcement bars shall be held in position rigidly from sway by suitable scaffolding
arrangement.
 Proper cover to the reinforcement shall be ensured by providing adequate numbers of
concrete cover blocks.

17
 Column shutters shall be erected true to line and plumb and adequate supports shall be
provided to keep the same in position during & after concreting.
 Proper staged platform will be provided for concreting.
 Concrete pour card as per approved format shall be made and maintained for each pour duly
signed by client & Simplex.
 Columns shall be poured in layers of 300 mm thick and each layer shall be vibrated properly.
 Adequate numbers of manpower in terms of skilled and unskilled shall be made available to
receive the concrete.
 Proper lighting arrangements shall be made for night works.
 Construction and expansion joints shall be provided and treated as per
instructions/specifications.
 Any loose deposited concrete afterwards shall be removed & disposed off.
 Hessian cloth shall be wrapped around the column/wall for keeping the element wet for
minimum of 14 days.

18
 De-shuttering shall be done after 12 hours/24 hours after casting of individual pours as per
Technical requirements and codal provisions.

8.2 BLOCK WORK


1. Scope

This procedure provides a method of control of construction of block masonry work in order to achieve
compliance with the contract specification and drawings.

2. Work Procedure

 Before work begins ensure that dimensional setting, levels alignments of all openings are
properly check, coordinated with MEP and responsible for the true and proper setting out work
as per indicated design drawing and reference grid lines.
 Block should not be damp at the time of starting masonry, when much water is present on the
block then mortar will become watery leading to a weak masonry. The blocks should be semi
dry or skin wet.
 First layer will be solid.
 Carry out one row of block work with “Dry bond” (i.e without mortar, lay the blocks in position),
the wall to establish proper spacing of blocks.
 Lay mortar for full bed width and for a length of three blocks at a time, and to 10mm thickness.

19
 Maintain a clear gap at head of each wall or partition as specified for head restrains to
accommodate slab deflection
 Excess mortar coming out on the edge (while pressing block in position in bed mortar) to be
taken by trowel and buttered to the cross directional joint or head joint surface of the next
block being laid.
 Mixing plant, tools and banker boards shall be kept clean at all times and accurate
volume/mixes proportions shall be followed, ingredients shall be mixed thoroughly to a
consistency suitable for the work and free from lumps. Mortars containing air-entraining
admixtures shall be mixed by machine, but not over mixed. Ratio shall be 1:5 (1-part cement
and 5 parts of sand)
 The thickness of courses shall be uniform with courses horizontal. Use straight edge and spirit
levels on top of the blocks laid and set the top level. Make sure that the spirit is in working
condition and read the bubble carefully
 Allow stiffener columns when area of blocks exceeding 12m, except instruction by client.
 Allowing approved shrinkage compensating material on the top surface of block which directly
touches the beam bottom and slab.
 No part of wall during construction shall raise more than one and half meter above the general
construction level
 50mm lean concrete shall be casted on all window sills. External window opening sills are
sloped outside to prevent water coming inside
 Construction sequence for villas shall follow according to below picture

1.
 200mm RCC kicker shall be casted on slab

20
 Lower part of block layer shall be laid
 Mid beam and lower part of column shall be casted
 Higher part of block layer which touches slab or beam bottom shall be laid including lintels
 Finally, slab shall be casted including higher part of column

3. Mid Beam & Lintel

Mid beams are casted on block work when they reached half height of the wall. It will give more
strength and stability to wall.

Lintels horizontal structure, shall be casted or placed on openings in order carry weight of
above walls.

21
Applicable for door width between 600-900mm Eg: entry door, toilet door, etc.

Cast-in-situ RCC lintel

Applicable for doors that precast lintel is not possible to install.

22
Cast-in-situ RCC lintel

Applicable for large span (>1.8m) doors and windows or other situation that precast lintel is not
possible, Eg: balcony window, double-leaf door, etc.

4. Equipment and Tools

 Hollow masonry block


 Cement
 Sand
 Masonry equipment
 Scaffolding with platform
 Plumb bob
 Mobile mechanical mixer
 Measurement box
 Sprit level
 Water level
 Survey instruments
 Measuring tape
 Trowel and hand tools

8.3 PLASTERING
1. Scope

The scope of this Method Statement covers the works in plastering of masonry and concrete structure
wall both for interior and exterior in order to achieve compliance with the contract specification and
drawings.

2. Work Procedure

I. Surface preparation and installation of plaster accessories

23
 All surface to be plastered shall be cleaned and sprayed with water, which shall be allowed
to dry out before rush coat is applied.
 Masonry work applied with scratch coat prior to plastering.
 Concrete surfaces where plaster to be cleaned.
 All undercoat shall be scratched to form an adequate key for the next coat.
 Level guides shall be provided up to required thickness.
 All junction between masonry block and concrete structure shall be covered with fiber
mesh, which shall be nailed or stapled as required.

 Plastering accessories such as plaster stops shall be used where plastering terminates and
is not covered by other finish at wall, ceiling, door, window frame junction and to all wall
openings and corners.

II. Mixing and application

 Mixing plant, tools and banker boards shall be kept clean at all times and accurate
volume/mixes proportions shall be followed, ingredients shall be mixed thoroughly to a
consistency suitable for the work and free from lumps. Plaster mixture contains approved
bonding agents, crack control agents and admixtures shall be mixed by machine, but not
over mixed. Ratio shall be 1:3 (1-part cement and 3 parts of sand) for all interior and
exterior walls.
 The walls shall be prepared as above and rendered with a mortar of cement and fine sand
in specified proportions. At suitable intervals, 15cmx15cm mortar squares to full thickness
of base coat shall be first laid to serve as a guide to ensure a plane, undercoat layer of
plaster over the entire surface of the wall.

 Apply plaster mixture over masonry block and concrete surfaces by two coats (under coat
and final finishing coat).
 The mortar shall be dashed against the surface to be plastered with considerable forced,
and shall be thoroughly worked into all joints and other surface depressions, to ensure a
permanent bond.

24
 The plaster shall be applied to required thickness of 15mm in internal, external walls and
adequate drying time shall be allowed for each under coat prior to the application of final
coat

 Internal walls finish shall be made as smooth and external wall finish shall be made as
semi rough
 Final coat should be made in a true plane using an aluminum straight edge.

25
 All wall faces finish shall be made plane and true to line in all directions and that all angles
are straight, true and plumb.
 Extra care shall be taken for plastering to be made neatly good up to wood frames, skirting
and around pipes or fittings.
 During the application, existing work will be protected against spillage, staining and other
damages.
 On walls plaster work shall be terminated at 100mm above false ceiling elevation.
 Ceiling surface shall be plastered with 10-12mm thick.
 Plaster shall only be stopped at corner beads or plaster stops at an induced groove.
 Where plaster abuts any metal item which is set in the plaster and is flush with the finished
plaster surface, provide raked “vee” joint at junction or as directed by the consultant.
 Point up and finish surfaces around fixtures, outlet boxes, pipping, fittings, tile and other
work flush with adjacent plaster.
 Each coat of all plaster work is to be maintained in a moist condition for at least 3 days
after the plaster.
 Finished work will be protected during progress of plastering work.
 Defective work shall be removed and replaced with new.

3. Equipment and Tools

 Cement
 Sand
 Approved admixtures
 Fiber glass mesh
 PVC Corner beads
 Masonry equipment
 Scaffolding with platform
 Plumb bob
 Mobile mechanical mixer
 Measurement box
 Survey instruments
 Trowel and hand tools
 Wood float
 Aluminum section

8.4 TILLING
1. Scope

This procedure provides a method of tiling work has to be carried out to achieve compliance with the
contract specification and drawings.

2. Work Procedure

I. Surface preparation

26
 All surface must be structurally sound, clean, and free from dust, oil and any trace of
foreign materials that may affect the adhesion of the tile adhesive on the substrate.
 Tilling shall be start after block and cement walls/floors well cured.
 1:3 (one-part cement three-part sand) cement sand bedding shall be laid on the surface
of the floor and finished semi rough. Thickness of bedding shall be 20mm-25mm and it
shall be maintained as necessary to obtain finish floor levels indicated on approved
drawings and tile manufacture details.
 Wall surface shall be 1:3 cement sand 15mm thick plaster initially finished rough.
 Painted surface shall be scrapped to expose to original substrate for direct tile fixing.
 Surface shall be thoroughly dampened with water and allow access to drain water.

II. Floor tiling


 Tile bed surface tiling shall be rough and level such that when thin set mortar to accept
tile is applied, no voids under tiles occur. Grind off high spots and fill-in low spots as
necessary to ensure no voids occur.
 Tile bed curing period shall be completed before starting of tilling work.
 Tiles of specified and approved sizes shall be fixed to floor surface by cement mortar.
 Apply floated coat of cement mortar to dry background in area of approximately 1m2 and
comb the surface with the solid bed trowel. Apply thin even coat of mortar to back of the
dry tiles. Press tiles into bedding with twisting/sliding action to give finished bed thickness
of not more than 3mm.

 Tiles shall be placed according to level shown in drawing and shall be placed firmly with
the help of rubber mallet.
 Tamp the tile with rubber mallet to obtain required adhesion and level.

27
 Tiles shall be laid with required spacing and spacers shall be used to align tiles

 Excessive mortar shall be removed with cloth before the material has set.
 Tiles shall be laid level or enough falls in wet areas as may be required.

 Particular care shall be taken in wet areas to prevent low spot and pooling of water.

28
 The tiles shall be neatly cut, grind rough on exposed edges around pipes and other
obstructions.
 Make provision of floor drains as per approved drawings.
 Ensure that joints are 6mm (or the depth of tile if less), and free from dust and debris.
 Approved grout shall be applied to the spaces between the tiles using sponge or small
piece of soft cloth.
 Force grout and fill joints completely to entire depth, clean off surface and leave free from
blemishes.
 Rub floor tiling with a dry cloth when joints are hard.
 Approved silicon rubber sealant shall be inserted between tile and sanitary fittings.
 Keep expansion/contraction and control joints free of mortar or grout.
 100mm height skirting shall be laid on floor tiles.

Dry floor tilling cross section

29
Wet floor tiling cross section

III. Wall tiling


 Block walls and concrete walls to be finished with tile, apply and levelling coat of plaster 15mm
thick, sufficient to cover the unevenness of the substrate and to make walls true vertical.
 Plaster curing period shall be completed before start of tiling work.
 To ensure rows of tiles are truly horizontal, a level line shall be established to position the
starting course.

 Tiles of specified and approved sizes shall be fixed to wall surface by approved adhesive.
 Mixing of adhesive shall be strictly followed in accordance with manufacture
recommendation.
 Apply floated coat of adhesive to dry background in area of approximately 1m2 and comb the
surface with the solid bed trowel. Apply thin even coat of adhesive to back of the dry tiles.
Press tiles into bedding with twisting/sliding action to give finished bed thickness of not more
than 3mm.

30
 Tamp the tile with rubber mallet to obtain required adhesion and level.

 Tiles shall be laid with required spacing and spacers shall be used to align horizontal vertical
joints.

31
 Lay tile to pattern in accordance with drawings. Verify pattern in uninterrupted through
openings.
 Establish lines of borders where applicable.
 Excessive adhesive shall be removed with a dry cloth before the material has set.
 The verticality of wall finish maintained with checking by plumb bob .

 Joints in glazed wall tiles and fittings, after edges of tiles have been thoroughly wet (after 48
hours later) it shall be grouted with approved grout.
 Ensure that joints are 6mm (or the depth of tile if less), and free from dust and debris.
 Grout shall be applied to the spaces between the tiles using sponge or small piece of soft cloth.
 Force grout and fill joints completely to entire depth, clean off surface and leave free from
blemishes.
 Rub wall tilling with a dry cloth when joints are hard.
 Keep expansion/contraction and control joints free of mortar or grout.

Dry wall tiling cross section

32
Wet wall tilling cross section

3. Equipment and Tools

 Cement
 Approved adhesive
 Mechanical tile cutter
 Grinder
 Trowel
 Mixer
 Rubber mallet
 Masonry square
 Plumb bob
 Sprit level
 Aluminum box bar
 Spacer

8.5 WATER PROOFING


1. Scope

The scope of this covers the works in water proofing roof, wet areas and pool base and wall, to achieve
compliance with the contract specification and drawings.

2. Work Procedure

I. Surface preparation

33
 Surface preparation is the most important before application
 The concrete surface shall be clean and free from contamination such as dust, oil, grease,
organic growth and release agents etc.
 All loosely adhering particles such as rust, mortar and cement laitance shall be removed.
 The surface shall be cleaned by wire/stiff brushing and finally soft brushing or composed air
 The surface shall be free from standing water.
 Pipes, sleeves, conduits, drains or any other penetrations shall be in place and protected with
cement sand mortar, prior to application.
 All cracks and joints shall be sealed as per client recommendation, at least two days before
application.
 The surface shall be prepared in a such a way to achieve a maximum adhesion of the coating
of the substrate.
 Application of the water proofing shall be done by experienced personals and as per
manufacture recommendation.

II. Wet areas (toilet, shower, pool, tanks, etc.)

 Make sure mix is homogenous and free from lumps, while mixing trying to avoid too must air
entering to the mix.
 Two coats of mix shall be applied over the surface by trowel or rollers within 60 minutes of it
being mixed.
 The first coat of cementitious mortar mix shall be applied with roller or trowel in a continuous
uniform coating.

 The theoretical first coat thickness shall be maintained 1-2mm but it will be vary with
manufactures recommendation.
 While the first coat is still fresh , polypropylene fabric carefully laid on the surface and it
pressed firmly using flat bladed trowel to make sure its perfectly wetted.

34
 Adjacent sheets of fabric shall be overlapped by 50mm at both the longitudinal and transverse
junction points.
 The second coat shall be applied at right angle to the first coat and completely cover the
reinforce fabric, successive coat must only applied after previous coat is dry ( after 4 to 5
hours) .

 Water proofing shall be extended up vertical surfaces, in toilets its extended up to 300mm
and 2100mm in shower areas. Pool walls and base entire area shall be covered with same
procedure.
 After applying surface shall be protected from rain and water spillage for 24 hours.
 Water shall be provided for flood test for minimum 24 hours for all water proofed areas.
 Protective layer of cement sand mortar shall be applied on water proofed area after final
inspection.
 Ponding tests shall be carried out twice to test for water tightness once after water proofing
completed and second time after completion of finishing work.
 3mm thickness, Q235 steel made water bar shall be laid on pool/tank bases and concrete
joints to prevent leakages. Detailed sketches given below,

Q235 steel made water bar

35
Connecting pool base and wall using steel water bar

Connecting in between beams and pool/tank walls using steel water bar.

36
Form work tightening arrangements for pool/tank walls

37
METHODOLOGY OF MEP WORKS

9. AC AND VENTILATION WORK


9.1 Fan Coil Installation
 The fan coil shall be equipped with independent support and hanger, the installation position,
height and slope shall be correct, fixation shall be reliable, and disassembly and maintenance
shall be convenient;
 The drainage slope shall be correct, the condensate water shall flow to the designated position
smoothly, the supply & return valve and filter shall be installed near the fan coil;
 When the fan coil operates, in order to prevent vibration being transmitted outwards, the
position where four hanger rods of fan coil is fixed with the fan coil shall be respectively
provided with one nut at the top and bottom and the nuts shall be tightened.
 In order to meet energy-saving requirement, the water-way of fan coil shall be provided with
an electrical two-way valve, the three-speed switch and summer-winter changeover switch
shall be provided indoors.

9.2 Air-Conditioning Unit Installation


 The ventilation and air-conditioning equipment shall be provided with the attached files such
as packing list, equipment specification, product quality certificate and product performance
test report, the imported equipment shall be also provided with the documentation of
qualified product inspection.
 Before equipment installation, unpacking inspection shall be performed, and form the
acceptance written record. The participants include the representatives of builder, supervisor,
constructor and manufacturer.
 The foundation shall be accepted before the equipment is installed, and the equipment can
be only used after it's qualified.
 The bottom of air conditioning cabinet shall be provided with rubber vibration isolating pad.
The distance of vibration isolating pad shall be same and thickness shall be uniform.
a). The height of condensate water trap seal can't be lower than 5cm.
b). The joint of air-conditioner supply & return pipe and air conditioning cabinet shall be
provided with rubber flexible joint.

10. PLUMBING AND WATER SUPPLY WORK


The indoor and outdoor plumbing work primarily includes domestic water supply, sewage, waste
water, chilled water, condensate water, hydrant and fire-fighting spraying. The domestic water supply
and return adopts PVC pipe, the seamless steel pipe with welded connection is adopted for over
100mm chilled water, the UPVC pipe will be adopted for below 100mm, the galvanized steel pipe is
adopted for condensate water, and hydrant pipe adopts galvanized steel pipe. The pipe insulation
adopts rubber and plastic sponge product.

38
10.1 Sanitary Ware Installation
 Get the samples of sanitary wares and submit to the client to make approval.
 The installation of sanitary wares shall adopt embedded bolt or expansion bolt.
 The installation of draw-off valve and floor drain shall be straight, even and reliable, lower
than the drainage face and there is no leakage on the circle. The floor drain water seal height
can't be less than 50mm.
 The lined bath tub shall be provided with an access door to the bath tub drainage outlet.
 The support and bracket of sanitary wares must have fine anti-corrosion and reliable
installation, and the support and bracket shall be contact with the sanitary ware tightly and
stably.

11. POWER SUPPLY WORK


11.1. General flow of Power supply construction
In the electrical construction principle of underground first and then ground; indoor first and then
outdoor, embedding first and then installation, gradually develop various works to be completed
according to construction period and position combining the civil work construction schedule, and
ensure project is completed finely.

11.2. Reserved and embedded stage


 Under the pre-condition of ensuring construction schedule and excellent project, perform the
work synchronously with the civil work and perform the reserved and embedded work well.
 The staff of electrical discipline must perform the embedding work well according to the civil
work construction progress. When the main body of construction and secondary wall is built,
hidden tubing will be performed synchronously with the civil work construction according to
the design requirement. Enhance inspection and don't omit, when the concrete is poured,
special staff shall be arranged to watch. If the fastening steel casing is adopted, the earth wire
welding process can be omitted.
 Reservation of hole and trench: when the hole is reserved on the cast-in-place concrete floor
slab, prepare the wooden box in advance, and fix the wooden box on the formwork reliably
according to the specification and position specified by the drawing before steel bar is bound.
During the construction, the staff of electrical discipline must make reservation at the
positions such as cable trench, bridge frame wire casing, panel and box embedded type
mounting position according to the drawing combining the civil work construction progress,
enhance inspection and don't omit, when the concrete is poured, special staff shall be
arranged to watch.

11.3. Conduit laying


Construction requirement: the tubing bending radius shall not be less than 6 times of outside diameter
of tubing. If there is one turn, the bending radius shall not be less than 4 times of the outside diameter
of tubing. When the brick wall, concrete wall and hollow brick wall cooperate with the walling vertical
pipe, this pipe shall be placed at the center of wall; if the pipe orifice is upward, it shall be plugged.

39
11.4. Cable tray laying

installation
Cable tray
Hole reservation

support and hanger


Fixation of bolt

Installation of protective earth wire


Embed hanger rod and
hanger
positioning
Snap line for

Installation of metal
expansion bolt

Lift cable tray


Embedded iron

support and hanger


Fixation of welding
Steel structure

Ground wire casing

Cable Tray Laying Flow Chart

The cable tray bending radius of cable is the 10 times of the cable with maximum outer diameter. The
bolt of cable tray and wire casing connecting plate shall be fastened, the nut shall be at the outer side
of cable tray and wire casing; the neutral metal case shall be integrated reliably and grounded well to
ensure the total wire is a fine electrical circuit. If the wire casing is laid vertically, it shall be fixed every
other 3m. When the cable tray crosses the fire wall and fire-proof floor slab, the fire prevention
measures shall be adopted, to prevent the fire burning along the line.

防火枕

钢板

线槽

Schematic Diagram of Wire casing Crossing Fire wall


线槽穿过防火墙节点图

40
11.5. Wiring

Select wire Insert strip- Clean Release line Binding of wire and strip-
line pipe and broken line line

Provide flare Insert Wire Connector Wire inspection and


wire connector binding measure insulation via
tramegger

Flow of Inserting Wire in the Pipe

For the pipe adopting hidden laying in the advanced poured concrete, the pipe shall be cleaned when
the formwork is disassembled; for the brick concrete structure wall, the pipe shall be cleaned before
plastering, the cleaned pipe shall be inserted with strip-line timely. When the line is inserted, two
workers shall cooperate mutually, and the wire shall be reserved with proper length for the next one
process. After the line is inserted, the 1000Vtramegger shall be used to measure the insulation
resistance value isn't less than 0.5MΩ, and make record.

11.6. Cable laying


Cable is laid along Horiz
the cable tray ontal
wire casing laying
Preparati Label
on work plate
Cable is laid along Vertical
the cable trench laying

Cable Laying Flow

Firstly, check whether the cable model, specification conform to the design value. Measure the
insulation with tram egger or perform withstand voltage test before cable laying, the insulation
resistance between lines and grounding shall not be less than 10MΩ. When the cable is laid along the
bridge frame or tray, it shall be laid with single layer and arranged in tidy, and the cable can't be
crossed, and the turn shall be based on the allowable bending radius of peak cross-section cable. Lay
the cable along the bridge frame wire casing, the sign board shall be hung at both ends, turn and cross,
and sign board shall be increased properly at the straight section.

11.7. Panel and cabinet installation


The cabinet (panel) shall be installed on the foundation steel bar in turn according to the layout of
construction drawing. The unit cabinet (panel) only aligns the verticality of cabinet face and side. After
the display cabinets (panel) are in position, align the cabinets at both ends, and stretch a line tight at
the position of two thirds of height from bottom of cabinet, and then align the cabinets one by one.

41
When the bus is connected via bolt, place the connecting bolt of bus horizontally and insert it from
down to up, in other conditions, the nut will be placed at the maintenance side, and screw thread will
protrude the nut by 2~3 threads after the bolt is fastened.

The current circuit wire in the cabinet shall adopt the copper-core insulated wire with voltage not less
than 1000V, and the section shall not be less than 2.5mm2. Other circuit section shall not be less than
1.5mm2.

The unit cabinet (panel) only aligns the verticality of cabinet face and side. After the display cabinets
(panel) are in position, align the cabinets at both ends, and stretch a line tight at the position of two
thirds of height from bottom of cabinet, if the cabinet isn’t standard, the cabinet face will be final.
After all the electric appliances of distribution box (panel) are installed, measure the insulation of line
via 500Vmegohmmeter. PE line shall be installed reliably, and the wire is selected as follows:

11.8. Light fixture installation

Check light Assemble Light fixture Light fixture


fixture light fixture insulation check installation

Construction Sequence

Construction requirement: specific installation mode and connection mode shall be performed
according to the product description, rules and specification. For the light fixture in the suspended
ceiling or the light fixture with weight over 3 Kilograms, the top plate must be installed with
independent hanger rod or embedded part, to bear the total weight of light fixture, the ceiling joist
can't bear the load of light fixture. If the installation height above ground of light fixture is lower than
or equal to 2.5M, the metal shell must be connected with protection grounding wire.

Switch socket installation: specific installation mode and connection mode of switch socket shall be
performed according to the product description, rules and specification. Reserve 15cm wire from the
box, cut the wire core and don't damage the wire core, wind the wire on the corresponding wiring
terminal of switch and socket according to clockwise direction, and then fasten the pressure head,
and push the switch or socket panel into the box (if the box depth is big more than 2.5cm, the sleeve
box shall be installed), align the screw hole of connection box, fix reliably with machine bolt, when it's
fixed, the panel shall be aligned and flush with the wall surface.

42
12. INSTALLATION OF DUCTS (CONDUIT)
12.1. Installation techniques and procedures
Duct-line routes should be selected to balance maximum flexibility with minimum cost and to avoid
foundations for future buildings and other structures. Where it may be necessary to run
communication lines along with electric power distribution lines, two isolated systems in separate
manhole compartments should be provided. Where possible, ducts should be installed in the same
concrete envelope. Electric and communication ducts should be kept clear of all other underground
utilities, especially high temperature water or steam pipes.

12.2. Duct materials


Acceptable standard materials for ducts include fibre, asbestos-cement, tile, and plastic. Rigid steel
conduit may also be installed below grade and should be provided with field or factory applied
coatings where required.

12.3. Size of ducts


Size of conduits in a duct bank should be not less than 10cm inside diameter except that ducts for
communication lines with a minimum diameter of 7.5cm are acceptable.

12.4. Installation of ducts without concrete encasement


Trenches for single-duct lines should be not less than 15cm or more than 30cm wide, and the trench
for two or more ducts installed at the same level should be proportionately wider. Trench bottoms for
ducts without concrete encasement should be made to conform accurately to grade so as to provide
uniform support for the duct along its entire length. A layer of fine earth material at least 75mm thick
(loose measurement) should be placed in the bottom of the trench as bedding for the duct. The
bedding material should consist of soft dirt, sand, or other fine fill, and it should contain no particles
larger than 6 mm diameter. The bedding material should be tamped until firm. When two or more
ducts are installed in the same trench without concrete encasement, they should be spaced not less
than 75mm apart (measured from outside wall to outside wall) in a horizontal direction or not less
than 75mm apart in a vertical direction. Rigid steel and heavy wall conduit may be direct earth buried.
All other conduits should be encased.

12.5. Installation of ducts encased in concrete


All ducts installed in concrete encasement should be placed on a layer of concrete not less than 7.5cm
thick. Where two or more ducts are encased in concrete they should be spaced not less than 75mm
(measured from outside wall to outside wall). As the duct laying progresses, concrete not less than
75mm thick should be placed around the sides and top of the duct bank. Flared ends of ducts or
couplings should be installed flush with the concrete encasement or inside walls of manholes or

43
handholds. Interlock spacers should be used at not more than 1.5m spacing to insure uniform spacing
between ducts. Joints in adjacent ducts should be staggered a minimum of 60cm apart and should be
made waterproof prior to concreting. No duct having a defective joint should be installed. Concrete-
encased duct or rigid steel conduit should be installed so that the top of the concrete envelope or
conduit is not less than 40cm below the bottom of the paving where it is installed under roadways,
railroads, runways, taxiways, other paved areas, and ditches and not less than 40cm below the finished
grade elsewhere.

12.6. Ducts and flexible tubing


When doing installation of cable in a duct system, the cables should be grouped. Flexible duct [tubing]
is placed in trench as shown in figure below.

Ducts and Flexible Tubing

12.7 Grounding bushings


Where rigid steel conduit enters or leaves a manhole or handhold a grounding bushing should be
provided for all conduits.

12.8 Arrangement of duct banks


An arrangement of two ducts wide or high should be used for best heat dissipation. Correspondingly,
the duct banks may be several ducts high or wide. (This may be impossible where a large number of
ducts are involved.) The vertical two conduit-wide arrangements enables the cables to be more easily
racked on manhole walls but may not be as economical as the horizontal two conduit-high
arrangement.

12.9 Drainage
All duct lines should be laid so as to slope toward handholds, manholes and duct ends for drainage.
Grades should be at least 2.5mm per meter. Where it is not practicable to maintain the slope all one
way, the duct lines may be sloped from the center in both directions toward manholes, handholds, or
duct ends. Pockets or traps where moisture may accumulate should be avoided.

44
12.10 Pull wire
Each spare duct installed should be provided with a copper-clad steel pull wire of not less than 5mm2
in area. Alternatively, a polypropylene pull rope which will not rot or support mold in the wet
duct/base can/manholes may be used. The open ends of the spare ducts should be plugged with
removable tapered plugs. The plug should secure the pull wire firmly.

12.11 Spare capacity


Sufficient ducts for planned installations, future expansion, plus a minimum of 25 percent of spare
ducts, should be included for all new underground systems.

13. MANHOLES AND HANDHOLDS


13.1. Selection
Factors bearing on the choice of manholes and handholds are number, direction, and location of duct
runs; cable rack arrangements; method of drainage; adequacy of work space (especially if equipment
is to be installed in the manhole); and the size of the opening required to install and remove
equipment.

13.2. Location
Manholes or handholds should be placed where required for connections or splices and where conflict
with other utilities will be avoided. Manhole separation should not exceed 200m on straight runs and
100m on curved duct runs. Spacing should be decreased where necessary to prevent installation
damage during pulling of cables. Strain should be limited during installation to a point that will not
damage cable insulation or deform the cable.

13.3. Hardware
Hardware applicable to the installation should be chosen. Where flared ends of ducts are provided,
cable-duct shields are necessary only for protection of metallic-sheathed cables.

14. INSTALLATION OF UNDERGROUND CABLES


14.1. Preparation of ducts
After the duct installation is completed, the cables are installed by drawing or pulling into the ducts.
The duct should be open, continuous, and clear of debris before the cable is installed. The cable should
be installed in a manner to prevent harmful stretching of the conductor, injury to the insulation, or
damage to the outer protective covering. The ends of all cables should be sealed with moisture-seal
tape before installing, and they should be kept sealed until connections are made. Where more than

45
one cable is to be installed in a duct or conduit, all cable should be installed at the same time. In no
case should a splice or connection be placed in a duct or conduit.

14.2. Method of pulling


The cable to be installed in the duct be pulled by a power winch or by hand. An adequate amount of
cable pulling compound should be used on all pulls. Petroleum grease should not be used. The surface
of any cable sheath or jacket should not be damaged to a depth greater than 1/10th its original
thickness. The cable should not be flattened out of round more than 1/10th its outside diameter. Any
combination of a group of cables to be pulled into a duct should not exceed the sum of individual
allowable tension of each cable plus 15 percent.

Maximum pulling tensions for cables not listed should be obtained from the manufacturer of the
cable.

14.3. Length of pull


To minimize splicing, the longest practicable lengths of cable should be pulled into the ducts at one
time. Unless otherwise required, manholes and handholds should be as far apart as practicable for the
type of cable being installed, but under no condition should the distance between handholds or
manholes exceed 200 meters.

Several cables installed in one duct. The following are applicable to the installation of two or more
cables in the same duct.

 Power cables of the same voltage may be installed in the same duct.
 Power cables of less than 600 volts may be installed in the same duct.
 Power cables of less than 600 volts should not be installed in the same duct with control,
telephone, or coaxial type cables.
 Power cables of more than 600 volts should not be installed in the same duct with control,
telephone, coaxial or power cables of less than 600 volts.
 Control, telephone, and coaxial cables may be installed in the same duct.
 Power, control, and telephone cables may be installed in the same duct system, subject to
provisions of sub-paragraphs g) and h).
 Cable installation in manholes or handholds. Power and control cables should be installed in
separate manholes and handholds unless required otherwise. If space is available, cable slack
sufficient for one splice for each cable should be left in each manhole.
 Separation of cables in manholes and handholds. When it is not possible to install power and
other type cables in separate manholes or hand-holes, they should be installed in separate
compartments or on opposite sides of the manhole or handhold.
 Installation of cables in manholes and handholds

46
14.4. Cable racks
Cables should be carefully formed around the interior of manholes or handholds avoiding sharp bends
or kinks. All splices and cables should be tied to cable racks using 3.2mm diameter nylon line. Handhold
and manhole racks should be the plastic type or provided with porcelain insulators. Splices or
connectors should be a minimum of 0.6m from the mouth of the duct opening into the manhole or
handhold. Where feasible, splices in different cables should be staggered.

14.5. Cable terminations


Termination of all control, telephone, and coaxial cables should be as required. Termination of all
power cables rated above 5000 volts should be made with a stress relief device. Where potheads are
used, strict conformance to manufacturer's recommendations should be followed. Where
terminations are made at transformer bushings, exposed conducting surfaces on both high- and low-
voltage sides should be taped for full voltage and painted with a high insulation water-resistant
coating.

14.6. Cable grounding


The following conditions apply to the grounding of cables.

All shielded power cables should have the shield grounded at each end. The grounding conductor
should be connected to a ground rod by means of a grounding connector specifically designed for this
purpose. The shields or armor on direct earth-buried power cables should be grounded on each end,
but not at the splices.

47
15. SAFETY PLAN
15.1. Safety assurance

15.2. Security plan


We will contact the relevant local departments and personnel as required or at the request of the
owner or relevant department to provide guards to protect the safety of the project manager and
other relevant personnel.

Security guards must patrol day and night to avoid damage or theft of all materials, machinery, tools,
materials, etc. on the construction site.

Labor protection: All on-site staff members who are employed by us will be issued by the project
manager department according to the working environment, type and characteristics and in
accordance with the local labor protection law, including helmets, safety belts and overalls. , gloves,
water shoes, raincoats, hand lights, etc.

Mandatory safety requirements and measures

 The project department provides uniform helmets for all on-site management personnel and
construction personnel. Employees who do not wear protective equipment are not allowed
to enter the construction site.
 All mechanical moving parts, equipment or power tools must be equipped with a protective
cover to prevent accidental contact with the human body.

48
 The grounding insurance must be installed in the temporary distribution box, and the
electrical equipment must be well grounded.
 Electrical equipment such as generators, distribution boxes, etc. must be protected against
rain, sun and wind.
 All equipment must be operated by the person who obtained the operation qualification
certificate.
 Warning signs shall be set up beside all distribution boxes and generators. When power failure
is checked, “closed switch must be hanged beside the power distribution box”.
 Stop mechanical construction work in windy, foggy and heavy rains above level 6.

15.3. Electrical Safety


Strictly abide by the provisions of the temporary safety rules for electrical construction on the
construction site to ensure the safe operation of the project.

 The bare wire is generally not installed in the wiring construction site. If the line is a bare
conductor, measures shall be taken according to the construction conditions. The horizontal
distance between the overhead line and the building shall not be less than 10 meters; the
vertical distance from the ground shall not be less than 6 meters; when crossing the building,
the vertical distance from the top shall not be less than 2.5 meters.
 All kinds of insulated wires should be laid overhead. A jacketed cable shall be used for
unconditional sections of overhead lines. Protective measures should be taken for the cable
segments that are vulnerable to damage. The erection of high-voltage lines was commissioned
by the local power supply department.
 Various distribution lines are not allowed to be laid on trees. Bundling of various insulated
wires should not use bare wires. The end of each branch of the distribution line shall be
equipped with a disconnect switch and effective short circuit and overload protection.
 The metal casing of all electrical equipment and the metal frame to which the electrical
equipment is connected must be protected against grounding or protective zeroing. Multi-
strand copper wire should be used for grounding and zeroing line. It is forbidden to use single-
strand aluminum wire. When working zero wire and zero-connection protection, the neutral
wire should be no less than 1/2 of the phase line cross section. Switches and fuses must not
be installed on the neutral line. There must be no joints between the grounding wire or the
zeroing wire. It must be securely and reliably connected to the equipment and terminals. The
crimping points should generally be located at obvious points and the wires should not be
subjected to tensile forces.
 Single-phase electrical equipment protected by zero line shall be provided with separate
protection and zero connection, and shall not use the working zero line of the equipment
itselfAlso do zero protection.
 Lightning protection and typhoon protection devices are installed in the construction site and
temporary living area facilities.
 The distribution box should be sturdy, complete and tight, and the door should be painted
with a red “electric” or hazard symbol. All wiring in the distribution box should be well
insulated, arranged neatly, and fixed on the panel after being tied. The wires must not be too
long and securely connected. The operating parts of the distribution box and the operating

49
surface of the disc shall not have exposed electric objects. No debris is allowed in the
distribution box in use.
 The selection of various switches, fuses, thermal relays, etc., the switch contactor should be
flexible, the contacts should be in good contact, and there should be no ablation.
 The distribution box on or near the pole shall be securely installed and shall be easy to operate
and maintain. The distance between the electrical equipment and the distribution box should
generally not exceed 5 meters. The distance between the fixed distribution box and the flow
lock box should not exceed 40 meters.
 When using general wires, they should be protected by plastic hoses or rubber hoses.
 The laying of the lighting lines of the construction site and temporary facilities shall be set
separately or through the pipe, except for the expansion of the cable. 12) All electrical
equipment used in the open air should have good rain resistance or proper rain protection
measures.
 On-site electricity must be implemented with “one machine and one brake” system. It is
strictly forbidden to control two or more power devices with one switch.

15.4. Fire safety


We will conscientiously implement certain provisions on safety and fire prevention, and carry out
safety and fire prevention work in conjunction with the actual situation of the project management
department, "prevention first, prevent and eliminate integration, prevent problems before they
occur" to ensure that state property is not lost.

 Establish a safety fire prevention organization. Each office must have a special fire prevention
person in charge. Based on the principle of “who is in charge and who is responsible”, the
management is in place and the responsibility is to the people; the fire prevention system
must be on the wall.
 Organize fire prevention publicity and education, popularize fire protection knowledge, and
enable all personnel to reach the "three sessions" and "four energy." (Three sessions: First,
will alarm; second, will use fire equipment; third, will fight the initial fire. Four can: First, can
publicize; second, can check; third, can find and rectify fire risk in time; fourth, can effectively
extinguish Initial fire.)
 Set up full-time firefighters, set up fire commandos, and conduct fire drills and training on a
regular basis.
 Establish a regular fire inspection system, conduct fire inspections on living areas and site
sites, and eliminate hidden dangers in the bud.
 Equipped with sufficient fire-fighting equipment for emergency use. The type and power of
the fire-fighting equipment should meet the needs of the fire-fighting mission, and be
inspected and maintained at any time, so that it is always in a good standby state.
 Do a good job of ventilation of the generator room and cooling of the generator.
 Control the degree of explosion to avoid affecting adjacent buildings.
 Especially work before, during and after blasting to eliminate potential safety hazards.

50

Vous aimerez peut-être aussi