CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

Mes 1 Mes 2 Mes 3


Item Descripción Und. Metrado P.U. (S/.) P.P. (S/.)
Parcial % Parcial % Parcial
01.01 OBRAS PROVISIONALES 3,786.93 3,786.93 100.00%
01.01.01 CARTEL DE IDENTIFICACION DE OBRA DE 3.60X2.40M und 1.00 600.00 600.00 600.00
01.01.02 ALMACEN PROVISIONAL mes 3.00 300.00 900.00 900.00
01.01.03 DESMONTAJE DE COBERTURA DE CALAMINA m2 123.27 2.96 373.51 373.51
01.01.04 DESMONTAJE DE MADERAMEN p2 1,374.25 0.95 1,415.48 1,415.48
01.01.05 DEMOLICION DE PISO DE CONCRETO m2 87.82 5.54 497.94 497.94
01.02 OBRAS PRELIMINARES 315.77 24.89 7.88% 290.88 92.12%
01.02.01 LIMPIEZA DE TERRENO MANUAL m2 155.55 0.16 24.89 24.89
01.02.02 TRAZO Y REPLANTEO PRELIMINAR m2 155.55 1.74 290.88 290.88
01.03 MOVIMIENTO DE TIERRAS 4,784.78 1,093.48 22.85% 3,691.30 77.15%
01.03.01 CORTE SUPERFICIAL MANUAL m3 9.12 11.77 107.34 35.71 71.63
01.03.02 EXCAVACION MANUAL PARA ZAPATAS m3 20.95 11.77 246.58 246.58
01.03.03 EXCAVACION MANUAL PARA CUNETAS m3 12.96 11.77 152.54 152.54
01.03.04 EXCAVACION MANUAL PARA CIMIENTOS CORRIDOS m3 23.70 11.77 278.95 278.95
01.03.05 EXCAVACION MANUAL PARA PISOS Y VEREDAS m3 20.37 11.77 239.75 239.75
01.03.06 RELLENO COMPACTADO CON MATERIAL PROPIO m3 7.05 13.66 97.71 97.71
01.03.07 RELLENO COMPACTADO CON MATERIAL GRANULAR m3 6.78 127.07 863.30 863.30
01.03.08 RELLENO COMPACTADO CON AFIRMADO m3 14.91 123.05 1,838.55 1,838.55
01.03.09 ACARREO DE MATERIAL EXCEDENTE D>=50MT m3 93.21 10.30 960.06 960.06
01.04 OBRAS DE CONCRETO SIMPLE 10,015.12 1,380.03 13.78% 8,635.09 86.22%
01.04.01 SOLADO PARA ZAPATAS C:H 1:10 E=0.10 MT m2 15.52 26.80 419.97 419.97
01.04.02 CIMIENTOS CORRIDOS: CONCRETO C:H 1:10 + 30% P.G. m3 11.02 296.23 3,293.33 3,293.33
01.04.03 CONCRETO 1:8+25% P.M. EN SOBRECIMIENTOS m3 1.80 313.11 568.31 568.31
01.04.04 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2 27.77 26.89 811.72 811.72
01.04.05 CONCRETO F'C=140 KG/CM2 EN FALSO PISO E=4" m3 12.56 364.41 4,644.31 4,644.31
01.04.06 ENCOFRADO Y DESENCOFRADO PARA FALSO PISO m2 11.95 21.57 277.48 277.48
01.05 OBRAS DE CONCRETO ARMADO 31,585.58 3,997.65 12.66% 26,679.79 84.47% 908.14
01.05.01 ZAPATAS 4,301.23 4,301.23
01.05.01.01 CONCRETO F'C= 210 KG/CM2 EN ZAPATAS m3 7.76 434.77 3,405.79 3,405.79
01.05.01.02 ACERO Fy=4,200 kg/cm2 EN ZAPATAS kg 196.80 4.38 895.44 895.44
01.05.02 VIGAS DE CIMENTACION 8,501.90 8,501.90
01.05.02.01 CONCRETO F'C=210 KG/CM2 PARA VIGAS DE CIMENTACION m3 6.87 434.77 3,015.17 3,015.17
01.05.02.02 ACERO Fy=4,200 kg/cm2 EN VIGAS DE CIMENTACION kg 705.80 4.38 3,211.39 3,211.39
01.05.02.03 ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACION m2 54.96 38.04 2,275.34 2,275.34
01.05.03 COLUMNAS 7,136.55 7,136.55
01.05.03.01 CONCRETO F'C=210 KG/CM2.PARA COLUMNAS m3 4.18 435.67 1,838.32 1,838.32
01.05.03.02 ACERO Fy=4,200 kg/cm2 EN COLUMNAS kg 820.68 4.38 3,734.09 3,734.09
01.05.03.03 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 47.47 29.59 1,564.14 1,564.14
01.05.04 COLUMNETAS 1,364.64 1,364.64
01.05.04.01 CONCRETO f'c= 175 kg/cm2 , PARA COLUMNETAS m3 0.71 406.29 291.39 291.39
01.05.04.02 ACERO Fy=4,200 kg/cm2 EN COLUMNETAS kg 128.51 4.38 584.72 584.72
01.05.04.03 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 13.01 34.25 488.53 488.53
01.05.05 VIGAS 9,502.95 3,868.32 4,726.49 908.14
01.05.05.01 CONCRETO F'C=210 KG/CM2.PARA VIGAS m3 6.87 433.67 3,007.62 3,007.62
01.05.05.02 ACERO Fy=4,200 kg/cm2 EN VIGAS kg 850.24 4.38 3,868.59 3,868.32 0.27
01.05.05.03 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 78.34 30.23 2,626.74 1,718.60 908.14
01.05.06 VIGUETAS 648.98 648.98
01.05.06.01 CONCRETO f'c= 175 kg/cm2, PARA VIGUETAS m3 0.32 374.61 121.19 121.19
01.05.06.02 ACERO Fy=4,200 kg/cm2 EN VIGUETAS kg 69.79 4.38 317.54 317.54
01.05.06.03 ENCOFRADO Y DESENCOFRADO DE VIGUETAS m2 4.85 39.23 210.25 210.25
01.05.07 LAVADERO 129.33 129.33
01.05.07.01 CONCRETO f'c= 175 kg/cm2, PARA LAVADERO m3 0.09 374.75 33.98 33.98
01.05.07.02 ACERO Fy=4,200 kg/cm2 EN LAVADERO kg 10.83 4.45 50.03 50.03
01.05.07.03 ENCOFRADO Y DESENCOFRADO DE LAVADERO m2 1.24 32.43 45.32 45.32
01.06 MUROS Y TABIQUES 7,983.32 7,855.86 98.40% 127.46 1.60%
01.06.01 MURO DE LADRILLO KK CONCRETO TIPO SOGA m2 106.06 73.38 7,855.86 7,855.86
01.06.02 MURO DE LADRILLO KK CONCRETO TIPO CANTO m2 2.41 52.37 127.46 127.46
01.07 ESTRUCTURAS DE MADERA Y COBERTURAS 8,641.57 8,641.57
01.07.01 TIJERAL DE MADERA TORNILLO T-1 und 1.00 1,333.07 1,366.03 1,366.03
01.07.02 CORREAS DE MADERA TORNILLO 2"x4" m 233.28 16.67 3,984.42 3,984.42
01.07.03 COBERTURA CON CALAMINA GALVANIZADA m2 150.34 19.85 3,109.03 3,109.03
01.07.04 CUMBRERA CON CALAMINA GALVANIZADA m 12.96 13.88 182.09 182.09
01.08 REVOQUES Y ENLUCIDOS 7,434.77 7,358.78 98.98% 75.99
01.08.01 TARRAJEO DE MUROS INTERIORES C:A 1:5 E=1.5CM m2 126.89 12.88 1,808.18 1,807.98 0.20
01.08.02 TARRAJEO DE MUROS EXTERIORES C:A 1:5 E=1.5CM m2 96.67 12.88 1,377.55 1,377.55
01.08.03 TARRAJEO DE COLUMNAS C:A 1:5 E=1.5CM m2 51.37 17.47 1,029.97 1,029.97
01.08.04 TARRAJEO DE VIGAS C:A 1:5 E=1.5CM m2 78.34 29.45 2,710.56 2,710.56
01.08.05 VESTIDURA DE DERRAMES C:A 1:5 E=1.5CM m2 3.78 17.47 75.79 75.79
01.08.06 CONTRAZOCALO H=0.20mt C:A 1:5 E=1.5CM m2 19.66 18.58 432.72 432.72
01.09 PISOS Y VEREDAS 2,601.31 2,601.31 100.00%
01.09.01 PISO DE CONCRETO PULIDO E=2" S/COLOREAR Y BRUÑADO m2 117.60 20.80 2,601.31 2,601.31
01.10 ZOCALOS Y ENCHAPES 2,594.97 1,508.13 58.12% 1,086.84
01.10.01 BRUÑAS EN MUROS m 78.30 4.12 403.25 403.25
01.10.02 BRUÑAS EN PISOS m 138.75 4.12 714.56 714.56
01.10.03 CERAMICO EN ZOCALOS 20x30 CM m2 21.19 49.57 1,086.84 1,086.84
01.10.04 CERAMICO EN PISOS 30x30 CM m2 7.61 49.57 390.32 390.32
01.11 DRENAJE PLUVIAL 6,451.20 6,451.20 100.00%
01.11.01 CONCRETO F'C=140 KG/CM2 EN CUNETAS m3 5.38 337.04 1,824.36 1,824.36
01.11.02 ENCOFRADO Y DESENCOFRADO PARA CUNETAS m2 35.85 20.44 806.63 806.63
01.11.03 TARRAJEO DE CUNETAS C:A 1:5 E=1.5CM m2 41.74 18.07 861.51 861.51
01.11.04 CANALETA DE CALAMINA GALVANIZADA D=6" m 25.92 52.50 1,360.80 1,360.80
01.11.05 MONTANTE CIRCULAR PVC-SAP 4" und 2.00 95.39 194.90 194.90
01.11.06 REJILLA METALICA m 10.00 138.24 1,403.00 1,403.00
01.12 CIELORRASOS 5,558.09 5,558.09 100.00%
01.12.01 CIELORRASO CON SUPERBOARD 4'x8'x6MM m2 119.59 43.91 5,374.37 5,374.37
01.12.02 FRISOS CON SUPERBOARD 4'x8'x6MM m2 3.85 46.35 183.72 183.72
01.13 CARPINTERIA DE MADERA 6,648.19 6,648.19
01.13.01 PUERTA DE MADERA TIPO TABLERO m2 5.39 376.00 2,026.64 2,026.64
01.13.02 PUERTA DE TRIPLAY TIPO CONTRAPLACADA m2 4.90 192.00 940.80 940.80
01.13.03 VENTANA DE MADERA CEDRO C/VARILLAS SEGURIDAD m2 21.81 150.00 3,271.50 3,271.50
01.13.04 PIZARRA ACRILICA DE 1.20x3.00mt m2 3.60 112.94 409.25 409.25
01.14 PINTURA 3,035.34 2,351.75 77.48% 683.59
01.14.01 PINTURA LATEX 2 MANOS EN CIELO RASO m2 123.44 5.88 811.00 811.00
01.14.02 PINTURA LATEX EN MUROS INTERIORES m2 126.89 4.78 658.56 658.56
01.14.03 PINTURA LATEX EN MUROS EXTERIORES m2 93.10 4.78 483.19 482.99 0.20
01.14.04 PINTURA LATEX EN COLUMNAS m2 51.37 5.19 293.32 293.32
01.14.05 PINTURA LATEX EN VIGAS m2 78.34 5.19 447.32 447.32
01.14.06 PINTURA LATEX EN DERRAMES m2 3.78 5.88 24.83 24.83
01.14.07 PINTURA ESMALTE EN CONTRAZOCALOS 2 MANOS m2 19.66 15.10 317.12 317.12
01.15 INSTALACIONES ELECTRICAS 3,229.31 2,932.79 90.82% 296.52 9.18%
01.15.01 SALIDA PARA CENTROS DE LUZ pto 7.00 86.94 644.63 644.63
01.15.02 SALIDA PARA TOMACORRIENTE pto 7.00 97.93 721.56 721.56
01.15.03 COLOCACION DE LUMINARIAS und 7.00 40.30 296.52 296.52
01.15.04 TABLERO DE DISTRIBUCION METALICO und 1.00 425.40 466.60 466.60
01.15.05 POZO PUESTA A TIERRA und 1.00 1,100.00 1,100.00 1,100.00
01.16 INSTALACIONES SANITARIAS 11,995.69 1,965.93 16.39% 10,029.76 83.61%
01.16.01 SISTEMA DE AGUA 534.04 534.04
01.16.01.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" pto 6.00 45.13 301.68 301.68
01.16.01.02 TUBERIA PVC SAP 3/4" m 10.00 4.18 44.40 44.40
01.16.01.03 TUBERIA PVC SAP 1/2" m 10.00 3.92 41.80 41.80
01.16.01.04 VALVULA COMPUERTA DE BRONCE DE 3/4" und 1.00 142.73 146.16 146.16
01.16.02 SISTEMA DE DESAGUE 955.10 955.10
01.16.02.01 SALIDA DE DESAGUE EN PVC 4" pto 3.00 116.75 365.70 365.70
01.16.02.02 SALIDA DE DESAGUE EN PVC 2" pto 4.00 77.75 331.60 331.60
01.16.02.03 SALIDA PARA VENTILACION EN PVC 2" pto 2.00 15.30 34.72 34.72
01.16.02.04 SUMIDERO DE BRONCE DE 2" und 2.00 22.40 55.10 55.10
01.16.02.05 REGISTRO DE BRONCE DE 4" und 1.00 47.60 52.75 52.75
01.16.02.06 CAJA DE REGISTRO DE DESAGUE 12" X 24" und 1.00 113.17 115.23 115.23
01.16.03 APARATOS Y ACCESORIOS SANITARIOS 1,021.80 1,021.80
01.16.03.01 LAVATORIO DE PARED BLANCO 1 LLAVE und 2.00 175.00 360.00 360.00
01.16.03.02 INODORO TANQUE BAJO NIÑOS und 2.00 325.75 661.80 661.80
01.16.04 SISTEMA DE TRATAMIENTO DE AGUAS SERVIDAS 9,484.75 1,431.89 8,052.86
01.16.04.01 BIODIGESTOR 7000 lts 6,748.54 6,748.54
01.16.04.01.01 EXCAVACION MANUAL DE ZANJA m3 26.20 11.77 308.37 308.37
01.16.04.01.02 RELLENO COMPACTADO CON EQUIPO, MATERIAL PROPIO m3 9.54 14.64 141.57 141.57
01.16.04.01.03 TUBERIA PVC SAL D=4" m 22.00 6.42 144.10 144.10
01.16.04.01.04 INSTALACION DE BIODIGESTOR 7000 LTS und 1.00 6,138.02 6,154.50 6,154.50
01.16.04.02 CAMARA DE EXTRACCION DE LODOS 1,032.40 1,032.40
01.16.04.02.01 EXCAVACION MANUAL DE ZANJA m3 3.24 11.77 38.13 38.13
01.16.04.02.02 RELLENO COMPACTADO CON AFIRMADO m3 0.32 123.05 39.46 39.46
01.16.04.02.03 CONCRETO F'C=140 KG/CM2 EN CAMARAS m3 1.30 364.41 480.70 480.70
01.16.04.02.04 CONCRETO FC=175 kg/cm2 EN TAPA CAMARA m3 0.14 442.21 62.49 62.49
01.16.04.02.05 ENCOFRADO Y DESENCOFRADO DE CAMARA m2 6.75 20.44 151.88 151.88
01.16.04.02.06 ACERO Fy=4,200 kg/cm2 EN TAPA CAMARA kg 26.88 4.34 120.42 120.42
01.16.04.02.07 TARRAJEO DE CAMARA C:A 1:5 E=1.5CM m2 6.75 18.07 139.32 139.32
01.16.04.03 ZANJA DE INFILTRACION 1,703.81 1,431.89 271.92
01.16.04.03.01 EXCAVACION MANUAL DE ZANJA m3 21.98 11.77 258.70 258.70
01.16.04.03.02 RELLENO CON GRAVA GRUESA m3 4.00 126.57 507.32 507.32
01.16.04.03.03 RELLENO CON GRAVA FINA m3 1.60 126.57 202.93 202.93
01.16.04.03.04 RELLENO CON ARENA FINA m3 0.80 126.57 101.46 101.46
01.16.04.03.05 TUBERIA CRIBADA PVC-SAL D=2" m 20.00 11.28 229.20 229.20
01.16.04.03.06 RELLENO CON MATERIAL PROPIO m3 15.49 8.37 132.28 132.28
01.16.04.03.07 ACARREO DE MATERIAL EXCEDENTE D>=50MT m3 26.40 10.30 271.92 271.92
01.17 FLETE TERRESTRE 59,809.77 59,809.77 100.00%
01.17.01 FLETE TERRESTRE GLB 1.00 59,809.77 59,809.77 59,809.77
01.18 VARIOS 2,390.08 1,882.70 78.77% 507.38
01.18.01 SELLADO DE JUNTAS EN PISOS E=1" m 27.03 23.74 643.58 643.58
01.18.02 SELLADO DE JUNTAS EN MUROS E=1" m 16.50 22.95 379.83 379.83
01.18.03 SELLADO DE JUNTAS EN CUNETAS E=1" m 52.02 23.75 1,239.12 1,239.12
01.18.04 LIMPIEZA FINAL DE OBRA m2 155.55 0.79 127.55 127.55
COSTO DIRECTO 178,861.79 82,847.32 86,104.32 9,910.12
GASTOS GENERALES 10% CD 17,886.18 8,284.73 8,610.43 991.01
SUPERVISION DE OBRA 5% CD 8,943.09 4,142.37 4,305.22 495.51
MONTO DE INVERSION TOTAL 205,691.06 95,274.42 46.32% 99,019.97 48.14% 11,396.64
Mes 3
%

2.88%
1.02%

41.88%
100.00%

22.52%
21.23%

5.54%