Académique Documents
Professionnel Documents
Culture Documents
Do you know the requirements for the disconnecting means and overcurrent protection of services?
In Part 1 of this two-part series, we addressed the general requirements for services. In
Part 2, we’ll address the requirements for the disconnecting means (Art. 230, Part VI)
and the overcurrent protection (Art. 230, Part VII) of services.
While these requirements are not particularly difficult to follow, they are often violated.
In many cases, the requirements were met with the initial installation but later violated
because of some modification. Usually, such modifications are in response to equipment
changes as the facility adjusts to changing needs. Thus, this article applies to both
existing and new services.
Service Disconnects
The service disconnect must open all service-entrance conductors from the building
premises wiring [Sec. 230.70]. Where you put it matters because it’s the means by which
first responders de-energize the power infrastructure. You don’t want firefighters trying
to figure out where you hid the disconnect, you want them to find it right away. So for
every building, that switch is in a readily-accessible location nearest the point where the
service conductors enter (either outside the building or inside it) [Sec. 230.70(A)(1)]
(Fig. 1).
Fig. 1. The service disconnect must open all service-entrance conductors from the building premises wiring.
Related: Services and the NEC — Part 1 of 2
You don’t want first responders checking the bathroom for the service disconnect. Aside
from the proximity to water, that location would not be readily accessible, nor would it
be nearest the conductor entry point. In addition, the NEC explicitly prohibits this [Sec.
230.70(A)(2)].
You can’t have more than six service disconnects for each service permitted by Sec.
230.2, or for each set of service-entrance conductors permitted by Sec. 230.40,
Exceptions 1, 3, 4, or 5 [Sec. 230.71(A)]. The reason is the same reason that each
disconnect must be readily accessible and close to the entrance: time. First responders
have only so much time, especially in the crisis that originally brought them to the site.
The service disconnecting means can consist of up to six switches or circuit breakers
mounted in a single enclosure, in a group of separate enclosures, in or on a switchboard,
or in switchgear. The rule is six disconnecting means for each service, not for each
building. If the building has two services, there can be a total of 12 service disconnects
(six per service).
Note also that a PV disconnect on the supply side of service equipment isn’t a service
disconnect. Don’t count this when you’re determining the number of service disconnects
[Sec. 230.82(6)]. Furthermore, disconnecting means used for the only following aren’t
considered service disconnects [Sec. 230.71(A)]:
Fig. 2. Grouping disconnects allows first responders to locate them all quickly.
Grouping
When installing the disconnects for a given service, group them [Sec. 230.72(A)] (Fig.
2). This way, when first responders find one, they’ve found them all. There is no need to
spend time searching.
However, you don’t want to lose the power to your fire pumps [Art. 695], emergency
systems [Art. 700], legally required standby systems [Art. 701], or optional standby
systems [Art. 702]. So for this equipment, you must locate the disconnect(s) remote
from the disconnects for normal service [Sec. 230.72(B)]. Because emergency systems
are just as important as fire pumps and standby systems, ensure they have the same
safety precautions to prevent unintended interruption of power.
Occupant Access
The service disconnect must indicate whether it’s in the OFF (open) or ON (closed)
position [Sec. 230.77]. And it can consist of [Sec. 230.76]:
(1) A manually operable switch or circuit breaker equipped with a handle or other
suitable operating means.
(2) A power-operated switch or circuit breaker, if it can be opened by hand in the event
of a power supply failure. (Fig. 3).
Fig. 3. The service disconnect must indicate whether it’s in the OFF (open) or ON (closed) position.
The disconnecting means rating must be at least that of the calculated load per Art. 220,
and in no case less than [Sec. 230.79]:
(A) One-circuit installation. For installations consisting of a single branch circuit, the
disconnect must have a rating of at least 15A.
(B) Two-circuit installation. For installations consisting of two 2-wire branch circuits,
the disconnect must have a rating of at least 30A.
(C) One-family dwelling. For a one-family dwelling, the disconnect must have a rating of
at least 100A, 3-wire.
(D) Other installations. For all other installations, the disconnect must have a rating of
at least 60A.
Note that a shunt-trip button doesn’t qualify as a service disconnecting means because it
doesn’t meet any of the above requirements.
Connections
When connecting the service conductors to the service disconnecting means, you must
use pressure connectors, clamps, or other means approved by the authority having
jurisdiction. You cannot use solder to make these connections [Sec. 230.81].
Only the nine types of electrical equipment listed in Sec. 230.82(1) through (9) can be
connected to the supply side of the service disconnecting means. That’s equipment such
as meter sockets and instrument transformers rather than utilization equipment. Also,
some electric utilities require a disconnect switch ahead of the meter enclosure for
277/480V services to enhance safety for electric utility personnel.
• Type 1 surge protective devices can be connected to the supply side of the service
disconnect enclosure. A Type 1 surge protective device is listed to be permanently
connected on the line side of service equipment [Sec. 285.23].
• Taps used to supply legally required and optional standby power systems, fire pump
equipment, fire and sprinkler alarms, and load (energy) management devices can be
connected to the supply side of the service disconnect enclosure.
Each ungrounded service conductor must have overload protection [Sec. 240.21(D)].
The NEC doesn’t require service conductors to have short-circuit or ground-fault
protection, but the feeder overcurrent protection device provides overload protection for
the service conductors.
The rating of the overcurrent protection device cannot be more than the ampacity of the
conductors [Sec. 230.90(A)]. However there are several exceptions, such as:
Exception No. 3: The combined ratings of two to six service disconnecting means can
exceed the ampacity of the service conductors if the calculated load (per Art. 220)
doesn’t exceed the ampacity of the service conductors.
Exception No. 5: Overload protection for 120/240V, 3-wire, single-phase dwelling unit
service conductors can be per Sec. 310.15(B)(7).
Location
Where circuit breakers are used for service overcurrent protection, they must be integral
with, or immediately adjacent to, the service disconnecting means [Sec. 230.91].
Because the NEC provides the minimum requirements for the protection of people and
property [Sec. 90.1], conforming to its requirements for services is only part of doing a
good job with a service installation.
Several related industry standards exist, as do industry best practices. Things such as
commissioning a breaker coordination study and providing excellent lighting for
switchgear maintenance are well worth the investment. Also, consider specifying
infrared windows when specifying the service panels — an investment that hugely
slashes maintenance costs.
Also, always perform baseline testing of the service equipment and conductors. This is
one of the most cost-effective measures that can be taken with a new installation. It can
be very costly to “save money” by skipping it.