Sl.

No Description of Item UNIT RATE Co - eff Amount REMARKS


Providing and laying Plum concrete 1: 5: 10. wherever specified using river sand, 40mm and down size metal and
boulders of 150mm (proportion 60: 40 for concrete : boulder) including sub grade preparation, leveling, all leads and
lifts, rough
P.C.C. FOR finishing at the top surface,
BELOW FOOTINGS, PLINTHcuring,
BEAMSand shuttering
& GRADE SLABif necessary etc., complete.
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)
Cement Constant per Cum 2.70
Cement Bags 210.00 2.78 584.01
Sand Cum 1,450.00 - -
Robo Sand Cum 728.00 0.52 379.10
Aggregates
20mm Cum 698.00
12mm Cum 606.00
40mm Cum 661.00 0.90 594.90
Machinery Cost 150.00
Labour for Curing 30.00
Labour for Cement Feeding and laying 250.00
d.Labour Cost for spreading 75.00
Shuttering 80.00
Provision towards RMC -
Sub Total RATE PER CUM 2,143.01

Providing and laying P.C.C. 1:4:8 of specified thickness wherever specified using river sand, 40mm and down size
metal including sub-grade preparation, levelling, all leads and lifts, rough finishing at the top surface, curing, and
shuttering
P.C.C. FORifBELOW
necessary etc.,
FOOTINGS, PLINTH BEAMS & GRADE SLAB

GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co - eff M7.5 (1:4:8)
Cement Constant per Cum 3.40
Cement Bags 210.00 3.50 735.42
Sand Cum 1,450.00 - -
Robo Sand Cum 728.00 0.52 381.91
Aggregates
20mm Cum 698.00
12mm Cum 606.00
40mm Cum 661.00 0.90 594.90
Machinery Cost 150.00
Labour for Curing 30.00
Labour for Cement Feeding and laying 250.00
d.Labour Cost for spreading 75.00
Shuttering 80.00
Provision towards RMC -
Sub Total RATE PER CUM 2,297.23

Providing and laying P.C.C. 1:3:6 of specified thickness wherever specified using river sand, 20mm and down size
metal including base preparation, Compaction, levelling, all leads and lifts, curing and shuttering if necessary etc.,
complete.
P.C.C. FOR BELOW FOOTINGS, PLINTH BEAMS & GRADE SLAB
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co - eff M10 (1:3:6)
Cement Constant per Cum 4.40
Cement Bags 210.00 4.53 951.72
Sand Cum 1,450.00 - -
Robo Sand Cum 728.00 0.51 370.68
Aggregates
20mm Cum 698.00 - -
12mm Cum 606.00 - -
40mm Cum 661.00
a.Machinery Cost 150.00
Labour for Curing 30.00
Labour for Cement Feeding and laying 250.00
d.Labour Cost for spreading 75.00
Shuttering 80.00
Provision towards RMC -
Sub Total RATE PER CUM 1,907.40

Providing and laying PCC 1:2:4 for Cills/Coping or at places wherever specified using river sand, 20mm and downsize
metal including shuttering etc., complete at all heights
P.C.C. FOR BELOW FOOTINGS, PLINTH BEAMS & GRADE SLAB

Page 1 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co - eff M15 (1:2:4)
Cement Constant per Cum 6.60
Cement Bags 210.00 6.80 1,427.58
Sand Cum 1,450.00 - -
Robo Sand Cum 728.00 0.51 370.68
Aggregates
20mm Cum 698.00 - -
12mm Cum 606.00 - -
40mm Cum 661.00
a.Machinery Cost 150.00
Labour for Curing 30.00
Labour for Cement Feeding and laying 250.00
d.Labour Cost for spreading 75.00
Shuttering 80.00
Provision towards RMC -
Sub Total RATE PER CUM 2,383.26

Providing, batching, mixing, transporting through transit mixers, pumping and laying controlled Reinforced Cement
Concrete of specified grade at all levels and heights specified below using ordinary Portland cement of grade 53 from
approved manufacturer,
RMC For Retaining Raftsriver sand,
& Walls, 20mm and down size coarse aggregates, necessary admixtures approved by
Villa
Footings

Grade of Concrete
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
M201:1.5:3 M25
Cement Constant per Cum
RMC PRICE 3,400.00 3,550.00
Add Wastage 2% 68.00 71.00
Hessian Cloth 50.00 50.00
Labour for Curing 30.00 30.00
Labour for Finishing 30.00 30.00
Labour Cost for spreading 400.00 400.00
Scoflding Charges for Concrete Pipies 30.00 30.00
Sub Total RATE PER CUM 4,008.00 4,161.00
TOTAL LABOUR COMPONENT 490.00 490.00
TOTAL MATERIAL COMPONENT 3,518.00 3,671.00

RMC FOR COLUMNS, PEDASTALS &


STAIRCASE

GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR Remarks
M20 M25 (1:1:2) M30 M35
Cement Constant per Cum
RMC PRICE 3,400.00 3,550.00 3,870.00 4,050.00
Add Wastage 2% 68.00 71.00 77.40 81.00
Hessian Cloth 50.00 50.00 50.00 50.00
Labour for Curing 30.00 30.00 30.00 30.00
Labour for Finishing 30.00 30.00 30.00 30.00
Labour Cost for spreading 500.00 500.00 500.00 500.00
Scoflding Charges for Concreting 30.00 30.00 30.00 30.00
Sub Total RATE PER CUM 4,108.00 4,261.00 4,587.40 4,771.00
TOTAL LABOUR COMPONENT 560.00 560.00 560.00 560.00
TOTAL MATERIAL COMPONENT 3,548.00 3,701.00 4,027.40 4,211.00

RMC For BEAMS & SLAB

Grade of Concrete
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
M20 M25
Cement Constant per Cum
RMC PRICE 3,400.00 3,550.00
Add Wastage 2% 68.00 71.00
Labour for Curing 30.00 30.00
Mortar Bands 40.00 40.00
Labour for Finishing 30.00 30.00
Labour Cost for spreading 150.00 150.00
Scoflding Charges for Concrete Pipies 30.00 30.00
Sub Total RATE PER CUM 3,748.00 3,901.00
TOTAL LABOUR COMPONENT 250.00 250.00
TOTAL MATERIAL COMPONENT - - 3,498.00 3,651.00

Page 2 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)

Providing and laying Reinforced cement concrete of the following grade at all levels and heights using river sand,
20mm and down size coarse aggregates, including all leads and lifts, vibrating, scaffolding wherever necessary,
curing and hacking
M-20 GRADE as directed,
SITE MIX CONCRETE etc., but excluding cost of shuttering, centering etc., complete. at all levels.
FOR FOOTINGS, BEAMS, SLABS
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
M20 Site mix RCC Footings, Slab &
1
Beams
Cement Bags 210.00 6.40 1,344.00
Sand Cum 1,450.00 0.60 870.00
20mm Aggregate Cum 698.00 0.55 383.90
12mm Aggregate Cum 606.00 0.35 212.10
Admixture Lts 30.00 1.60 48.00
Hessian Cloth Ls 50.00 1.00 50.00
Mixing Charges Cum 100.00 1.00 100.00
Labour Charges Cum 400.00 1.00 400.00
Scoflding Charges for Concreting Ls 30.00 1.00 30.00
Misc Ls 3,438.00 0.05 171.90

Sub Total RATE PER CUM 3,610.00

M-20 GRADE SITE MIX CONCRETE


FOR PEDASTALS, STAIRCASE, FINS,
CHAZZAS,ETC,.
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
1 M20 Site mix RCC Columns
Cement Bags 210.00 6.40 1,344.00
Sand Cum 1,450.00 0.60 870.00
20mm Aggregate Cum 698.00 0.55 383.90
Admixture Lts 30.00 1.60 48.00
Hessian Cloth Ls 50.00 1.00 50.00
12mm Aggregate Cum 606.00 0.35 212.10
Mixing Charges Cum 100.00 1.00 100.00
Labour Charges Cum 500.00 1.00 500.00
Scoflding Charges for Concreting Ls 30.00 1.00 30.00
Misc Ls 3,538.00 0.05 176.90

Sub Total RATE PER CUM 3,715.00

M-25 GRADE SITE MIX CONCRETE


FOR FOOTINGS, BEAMS & SLABS
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
M25 Site mix RCC Footings, Slab &
1
Beams
Cement Bags 210.00 6.80 1,428.00
Sand Cum 1,450.00 0.60 870.00
20mm Aggregate Cum 698.00 0.55 383.90
12mm Aggregate Cum 606.00 0.35 212.10
Admixture Lts 30.00 1.60 48.00
Hessian Cloth Ls 50.00 1.00 50.00
Mixing Charges Cum 100.00 1.00 100.00
Labour Charges Cum 400.00 1.00 400.00
Scoflding Charges for Concreting Ls 30.00 - -
Misc Ls 2,942.00 0.05 147.10

Sub Total RATE PER CUM 3,639.00

M-25 GRADE SITE MIX CONCRETE


FOR COLUMNS, PEDASTALS,
STAIRCASE
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
Cement Bags 210.00 6.80 1,428.00
Sand Cum 1,450.00 0.60 870.00
20mm Aggregate Cum 698.00 0.55 383.90
12mm Aggregate Cum 606.00 0.35 212.10
Admixture Lts 30.00 1.65 49.50
Hessian Cloth Ls 50.00 1.00 50.00
Mixing Charges Cum 100.00 1.00 100.00
Labour Charges Cum 500.00 1.00 500.00
Scoflding Charges for Concreting Ls 30.00 1.00 30.00

Page 3 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)
Misc Ls 2,943.50 0.05 161.01

Rate Per Cum 3,785.00

REINFOR
CEMENT

Unit Quantity Rate Amount Remarks


1 Material
a Cost of Steel ( Basic) MT 1.00 48,000.00 48,000.00
b Add Wastage MT 0.03 48,000.00 -
d 18 Gauge GI Binding wire Kgs 0.87 53.00 45.85
e PVC Cover Blocks Nos. 125.00 1.00 -
2 Labour
a Labour cost fabrication & fixing MT 1.00 1,500.00 1,500.00
3 Plant
a Cost of Machinary MT 1.00 265.09 -
Rate over material
Sub Total 49,545.85
Less Material Cost 1,546.00

Providing and constructing Size stone masonry (CRS) for foundation/Superstructure using size stones in CM 1:6 with
necessary quoin, through bond stone and Header stone at regular intervals including dressing the stone and edge
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
Size stone per No 4.00 140.00 560.00
Through bond stones Per nos 14.00 7.00 98.00
Cement per Bag 210.00 1.50 315.00
Sand per Cum 1,450.00 0.19 274.05
Robo Sand per Cum 728.00 0.19 137.59
Scaffolding per Cum 50.00 1.00 50.00
Curing per Cum 10.00 1.00 10.00
Labour charges per Cum 400.00 1.00 400.00
Rate per Cum 1,845.00 per Cum

Providing and constructing 300mm thick Solid Concrete block work at all levels in walls, piers and architectural
features using approved solid blocks of strength 35kg/sqcm in cement mortar 1:6 with minimum crushing strength of
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
1 Blocks 300mm thick in CM 1:6 per Sqm
Blocks (35 Kgs/Sq Cm) per No 38.00 12.50 475.00
Cement per Bag 210.00 0.19 39.06
Sand per Cum 1,450.00 0.02 33.98
Robo Sand per Cum 728.00 0.02 17.06
Scaffolding per Sqm 10.00 1.00 10.00
Curing per Sqm 10.00 1.00 10.00
Block Shifting per No 2.00 12.50 25.00
Labour per Sqm 107.60 1.00 107.60

Rate per Sqm 718.00 per Sqm

Providing and constructing 200mm thick Solid Concrete block work at all levels in walls, piers and architectural
features using approved solid blocks of strength 35kg/sqcm in cement mortar 1:6 with minimum crushing strength of
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
2 Blocks 200mm thick in CM 1:6 per Sqm
Blocks (35 Kgs/Sq Cm) per No 32.00 12.50 400.00
Cement per Bag 210.00 0.12 26.04
Sand per Cum 1,450.00 0.02 22.65
Robo Sand per Cum 728.00 0.02 11.37
Scaffolding per Sqm 10.00 1.00 10.00
Curing per Sqm 10.00 1.00 10.00
Block Shifting per No 2.00 12.50 25.00
Labour per Sqm 107.60 1.00 107.60

Page 4 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)

Rate per Sqm 613.00 per Sqm

Providing and constructing 150mm thick Solid Concrete block work at all levels in walls, piers and architectural
features using approved solid blocks of strength 35kg/sqcm in cement mortar 1:6 with minimum crushing strength of
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
3 Blocks 150mm thick in CM 1:6 per Sqm
Blocks (35 Kgs/Sq Cm) per No 25.00 12.50 312.50
Cement per Bag 210.00 0.09 19.53
Sand per Cum 1,450.00 0.01 16.99
Robo Sand per Cum 728.00 0.01 8.53
Scaffolding per Sqm 10.00 1.00 10.00
Curing per Sqm 10.00 1.00 10.00
Block Shifting per No 2.00 12.50 25.00
Labour per Sqm 107.60 1.00 107.60
Rate per Sqm 510.00 per Sqm

Providing and constructing 100mm thick solid concrete block wall at all levels including a concrete band of 75mm thick
with 2-nos of 8mm dia reinforcement rod (RI Steel shall be measured in relevant steel item) at every fifth course with
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
4 Blocks 100mm thick in CM 1:4 per Sqm
Blocks (35 Kgs/Sq Cm) per No 18.00 12.50 225.00

Cement per Bag 210.00 0.10 21.63

Sand per Cum 1,450.00 0.01 12.55


Robo Sand per Cum 728.00 0.01 9.45
Concrete Band M-20 per Cum 4,108.00 0.01 27.57
Scaffolding per Sqm 10.00 1.00 10.00
Curing per Sqm 10.00 1.00 10.00
Block Shifting per No 2.00 12.50 25.00
Labour per Sqm 96.84 1.00 96.84
Rate per Sqm 438.00 per Sqm

Preparing the surface and plaster the ceilings, in cement mortar 1:4, upto 12mm thick with smooth finish to line and
level at all levels including lead and lift of materials, hydrating the lime 24 hours before starting of work with necessary
scaffoldin
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS

Cement per Bag 210.00 0.11 23.10


Sand per Cum 1,450.00 0.02 26.80
Scaffolding per Sqm 10.00 1.00 10.00
Curing per Sqm 10.00 1.00 10.00
Hacking per Sqm 5.00 1.00 5.00
Labour Charges per Sqm 64.56 1.00 64.56
Rate per Sqm 139.00 per Sqm

Preparing the surface and plaster all internal RCC / Masonry surface in cement mortar 1:6, upto 20mm thick in a 2 coat
of 12mm and 8mm thk, smooth finished to line and plumb at all levels including lead and lifts with necessary
scaffolding, curing, etc.,
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS

Cement CM (1:6) 12mm thk per Bag 210.00 0.07 15.72


Sand per Cum 1,450.00 0.02 27.36
GI Mesh per Sqm 14.84 1.00 14.84
Electrical conduits chased area filling with
per Sqm 450.00 0.01 4.95
CM 1:6
Scaffolding per Sqm 10.00 1.00 10.00
Curing per Sqm 10.00 1.00 10.00
Labour Charges per Sqm 102.00 1.00 102.00

Page 5 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)
Hacking & nails/clamps/screw LS 5.00 1.00 5.00
Rate per Sqm 190.00 per Sqm

Preparing the surface and plaster 25mm to all external RCC / Masonry surface in cement mortar 1:4, in two coats, sand
finished to required line and plumb at all levels including lead and lifts with necessary scaffolding, curing,
waterproofing compound, u
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
Cement CM (1:4) 12mm thk per Bag 210.00 0.11 23.10
Sand per Cum 1,450.00 0.02 22.33
Cement CM (1:4) 12mm thk per kg 210.00 0.11 23.10
Sand per Cum 1,450.00 0.02 22.33
GI Mesh per Sqm 14.84 1.00 14.84
Water Proof Compound per Sqm 8.00 1.00 8.00
Scaffolding per Sqm 15.00 1.00 15.00
Curing per Sqm 10.00 1.00 10.00
Labour Charges per Sqm 118.36 1.00 118.36
Hacking & nails/clamps/screw & Misc. etc per Sqm 10.00 1.00 10.00

Rate per Sqm 267.00 per Sqm

Preparing the surface and providing rough plaster in CM 1:6 on RCC/Masonry surface at all levels, to required level,
line and plumb at all levels including lead and lifts with necessary scaffolding, curing etc, complete.

Single coat 10mm thick Rough


Plastering in CM(1:6)
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
Cement per Bag 210.00 0.06 13.02
Sand per Cum 1,450.00 0.02 22.65
Scaffolding per Sqm 10.00 1.00 10.00
Labour Charges per Sqm 64.56 1.00 64.56
Curing per Sqm 10.00 1.00 10.00
Rate per Sqm 120.00 per Sqm

Preparing the surfaces and Providing waterproof plaster with 20 mm thk water proof compound admixture (Fosroc or
equivalent) as per manufacturer's instructions in cement mortar 1:4 at all levels for retaining walls
Water proof plaster in CM 1:4,20mm thick For any Walls internal

S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS


Cement per Bag 210.00 0.18 36.75
Sand per Cum 1,450.00 0.02 31.97
water Proof Compound per ltr 8.00 1.00 8.00
Scaffolding per Sqm 10.00 1.00 10.00
Curing per Sqm 10.00 1.00 10.00
Labour Charges per Sqm 107.60 1.00 107.60
Hacking & Other Misc. etc per Sqm 10.00 1.00 10.00
Rate per Sqm 214.00 per Sqm

Providing and fixing in position galvanized expanded metal mesh 20 gauge (ARPITHA make or equivalent) at junctions of concrete and masonry and
other locations as called for including fixing with GI nails. (For walls chased by service contractor)

Arpitha G.I Mesh


GI Mesh per Sqm 10.82 0.15 72.16
Scaffolding per Sqm 10.00 1.00 10.00
Labour Charges per Sqm 50.00 1.00 50.00
Hacking & nails/clamps/screw LS 5.00 1.00 5.00
Rate per Sqm 137.00 per Sqm

Providing architectural groove in external plastering (Walls,Columns, Pedestals etc.,)at all heights (other than grooves
at junctions of RCC and masonry) for specified width and depth as follows:
25X12mm

S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS


Cement per Bag 210.00 0.07 15.00
Sand per Cum 1,450.00 0.01 14.50

Page 6 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)
Cement Slurry per Bag 4.20 1.50 6.30
Scaffolding per Sqm 15.00 1.00 15.00
Curing per Sqm 10.00 1.00 10.00
Labour Charges per Sqm 20.00 1.00 20.00
Rate per Sqm 81.00 per Sqm
Rate per Rmt 40.50 per Rmt

Providing architectural Band in external plastering at all heights for specified width, depth upto 150mm and 20mm thk
as per the Architectural drawings and specifications
Cement per Bag 210.00 0.29 61.88
Sand per Cum 1,450.00 0.04 59.81
Scaffolding per Sqm 15.00 1.00 15.00
Curing per Sqm 10.00 1.00 10.00
Labour Charges per Sqm 80.00 1.00 80.00
Rate per Sqm 227.00 per Sqm
Rate per Rmt 90.80 per Rmt

Providing waterproofing Surface method. The first part consists of application of two layer of Mastrseal-550(BASF)/
Hydrocem/ Brush Bond RFX or Equivalent waterproof coating (1.8 Kg/sqm) after base preparation, cleaning, brushing
and removal of flacky materials, grouting the porous area with cementations grout, fixing of weep holes using
RFX or Equivalent waterproof coating

S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS


Cement per Bag 210.00 0.10 21.00
Sand per Cum 1,450.00 - -

Hydrocem including Labour Charges per Sqm 210.00 1.00 210.00

Rate per Sqm 231.00

Providing waterproofing plastering over polymercoat in CM 1:4 of thickness 35mm for floor, 25mm for walls till floor
level and 18mm till 300mm above floor level with water proof admixture (Rheomac 707) with a minimum guarantee
period of 10 years.Note:-
Water Proofing 35mm CMOnly
(1:4)Plan area shall be measured for payment
Cement per Bag 210.00 0.22 46.20
Sand per Cum 1,450.00 0.04 55.83

Other Chemicals including Labour


per Sqm 115.00 1.00 115.00
Charges

Rate per Sqm 217.00

GROUTING:
Cleaning the surface making dust free
and grouting the pipe outlets of different No's 200.00
diameters with non-shrink free flow grout
at Toilets, Balcony & Utility etc complete.

BRICK BAT FILLING:


Collecting, filling and levelling of approved quality of Brick bat in sunken portions of Toilets, Utilities & Balcony/ Sit out
area's as per specifications and direction and satifaction of the EIC etc., complete. Filling is 250mm deep
Water Proofing 35mm CM (1:4)
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
Cement per Bag 210.00 - -
Sand per Cum 1,450.00 - -

Brick Bats (1 MT = 1.13CUM) Cum 750.00 1.13 662.25


Add Wastage 5% Cum 37.50 1.00 37.50

Other Miscellaneous including Labour


per Sqm 800.00 1.00 800.00
Charges

Rate per Sqm 1,500.00

TERRACE WATER PROOFING


The first part consists of removal of loose particles, cleaning brushing the concrete making dust free surface. Testing
and treatment for construction joints, leakages & honeycombs and cement grouting the porous area with FLOW
CABLE 50admixture 250gms per

Page 7 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)
RFX or Equivalent waterproof coating
Cement per Bag 210.00 0.10 21.00
Sand per Cum 1,450.00 - -

Hydrocem including Labour Charges per Sqm 210.00 1.00 210.00

Rate per Sqm 231.00

The second part consists of water proofing the terrace by surface method of average thickness of 115mm, with
waterproofing admixture as per manufacturer’s specification approved by consultants with a minimun guarantee
period of 10 Years. Cost to include application of cement slurry with water proofing compound over the surface with
S.NO DESCRIPTION UNIT RATE Co - eff AMOUNT REMARKS
Terrace Water Proofing
Cement per Bag 210.00 0.44 92.40
Sand per Cum 1,450.00 0.08 116.12
Brick bat coba
Brick bats 3.75 45.00 168.75
Other Miscellaneous including Labour
200.00 1.00 200.00
Charges
labour

Rate per Sqm 577.00

FINISHING WORKS RATE ANALYSIS

Sl. No Description Unit Rate Co - eff Amount in Rs. Remarks

Providing and laying Vitrified tile of size 600X600mm flooring of approved colour and make over minimum 20mm thick cement mortar bed of 1:4 mix
including 3MM spacers & grouting with the Epoxy shade to match with the tile colour and as approved by architect, including spreading P.O.P over
Tarpolin sheet for protection and removing the same with mild diluted acid washing and disposing the debris as directed etc. complete.
Cost of tiles incl. Wastage Sqm 510.00 1.03 525.30
Cement Bag 210.00 0.24 50.40
Sand Cum 1,450.00 - -
Robo Sand Cum 728.00 0.04 29.35
Cement Slurry Kgs 4.20 3.30 13.86
Epoxy Grouting Kgs 350.00 0.10 34.13
PVC Spacers No.s 1.00 6.00 6.00
POP (Tarpolin, Jute, Laying & Removing) Sqm 100.00 1.00 100.00
Acid Wash Sqm 8.07 0.75 6.05
Labour charges Sqm 90.00 1.00 90.00
MISC. LS 855.09 0.03 21.38
Sub Total Rate/Sqm 876.00

Same as item No D1.2 above but for Skirting


upto 100mm
Cost of high.
tiles incl. Wastage Sqm 510.00 1.10 561.00
Cement Sqm 210.00 0.24 50.40
Sand Sqm 1,450.00 0.00 0.00
Robo Sand Cum 728.00 0.04 29.35
Cement Slurry Kgs 4.20 3.30 13.86
Epoxy Grouting Kgs 350.00 0.10 34.13
PVC Spacers No.s 1.00 6.00 6.00
Acid wash Sqm 8.07 0.75 6.05
Add for Laying charges 90.00 1.00 90.00
Misc. Sqm 790.79 0.05 39.54
Sub Total per Sqm 830.33
Rate per Rmt 83.03
Sub Total Rate/Rmt 95.49

Providing and laying Amalgamated Marble flooring of approved colour and make over minimum 20mm thick cement mortar bed of 1:4 mix including
grouting with the Epoxy shade to match with the tile colour and as approved by architect, with floor guard for protection and removing the same
Cost of tiles incl. Wastage Sqm 1,550.00 1.10 1,705.00
Cement Bag 210.00 0.24 50.40
Sand Cum 1,450.00 - -
Robo Sand Cum 728.00 0.04 29.35
White Cement Kgs 6.50 3.30 21.45
Epoxy Grouting Kgs 350.00 0.10 35.00
Polishing Sqm 162.00 1.00 162.00
protection Sqm 140.00 1.00 140.00
Labour charges Sqm 323.00 1.00 323.00
MISC. LS 2,466.20 0.05 123.31
Sub Total Rate/Sqm 2,590.00

Page 8 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)
Providing and laying Amalgamated Marble flooring of approved colour and make over minimum 20mm thick cement mortar bed of 1:4 mix including
grouting with the Epoxy shade to match with the tile colour and as approved by architect, with floor guard for protection and removing the same
disposing the debris as directed etc. complete.
Cost of tiles incl. Wastage Sqm 1,550.00 1.15 1,782.50
Cement Sqm 210.00 0.24 50.40
Sand Sqm 1,450.00 - -
Robo Sand Cum 728.00 0.04 29.35
White Cement Kgs 6.50 3.30 21.45
Epoxy Grouting Kgs 350.00 0.10 35.00
Add for Laying charges Sqm 323.00 1.00 323.00
Misc. Sqm 2,241.70 0.05 112.09
Sub Total per Sqm 2,353.79
Rate per Rmt 235.38
Sub Total Rate/Rmt 235.00

Providing and laying wooden laminate floor for master Bed Room at areas as directed and to specifications of the manufacturer. The cost to include
necessary screed over the raw floor and finishing level to required level so that finished floor shall match adjacent tiled floor. The cost to include fixing
Flooring
Wood incl wastage Sqm 635.00 1.05 666.75
Screed Sqm 2,345.80 0.08 175.94
Labour charges Sqm 107.60 1.00 107.60
Misc. LS 950.29 0.05 47.51
Sub Total Rate / Sqm 998.00

Skirting upto 100mm high.


Wood incl wastage Sqm 635.00 1.05 666.75
Screed Sqm 2,345.80 0.08 175.94
Epoxy Grouting Kgs 350.00 0.10 34.13
Labour charges Sqm 107.60 1.00 107.60
Misc. LS 984.41 0.05 49.22
Sub Total Rate / Sqm 1,034.00
Sub Total Rate / RMT 103.40

Providing and laying Vertified glazed balsam brown Asian tiles flooring For Sitouts of approved colour and make over minimum 20mm thick cement
mortar bed of 1:4 mix including 3MM spacers & grouting with the Epoxy shade to match with the tile colour and as approved by architect, including
Flooring
Cost of tiles incl. Wastage Sqm 320.00 1.03 329.60
Cement Bag 210.00 0.24 50.40
Sand Cum 1,450.00 - -
Robo Sand Cum 728.00 0.04 29.35
Cement Slurry Kgs 4.20 3.30 13.86
Epoxy Grouting Kgs 350.00 0.17 59.50
PVC Spacers No.s 1.00 6.00 6.00
POP (Tarpolin, Jute, Laying & Removing) Sqm 100.00 1.00 100.00
Acid Wash Sqm 8.07 0.75 6.05
Labour charges Sqm 90.00 1.00 90.00
MISC. LS 684.77 0.05 34.24
Sub Total Rate/Sqm 719.00

Skirting upto 100mm high.


Cost of tiles incl. Wastage Sqm 320.00 1.10 352.00
Cement Sqm 210.00 0.24 50.40
Sand Sqm 1,450.00 - -
Robo Sand Cum 728.00 0.04 29.35
Cement Slarry Kgs 4.20 3.30 13.86
Epoxy Grouting Kgs 350.00 0.17 59.50
PVC Spacers No.s 1.00 6.00 6.00
Acid wash Sqm 8.07 0.75 6.05
Add for Laying charges 90.00 1.00 90.00
Misc. Sqm 607.17 0.05 30.36
Sub Total per Sqm 637.53
Rate per Rmt 63.75
Sub Total Rate/Rmt 73.32

Providing and laying Ceramic tile For Maid/Servant Room of size 300X300mm flooring of approved colour and make over minimum 20mm thick cement
mortar bed of 1:4 mix including 3MM spacers & grouting with the Epoxy shade to match with the tile colour and as approved by architect, including
Flooring
Cost of tiles incl.wastage Sqm 320.00 1.03 329.60
Cement Bag 210.00 0.24 50.40
Sand Cum 1,450.00 - -
Robo Sand Cum 728.00 0.04 29.35
Cement Slurry Kgs 4.20 3.30 13.86
Epoxy Grouting Kgs 350.00 0.17 60.38
PVC Spacers No.s 1.00 6.00 6.00
POP (Tarpolin, Jute, Laying & Removing) Sqm 100.00 1.00 100.00
Acid Wash Sqm 8.07 0.75 6.05
Laying charges Sqm 90.00 1.00 90.00
MISC. LS 685.64 0.06 37.71
Sub Total Rate/Sqm 723.00

Skirting upto 100mm high.

Page 9 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)
Cost of tiles incl.wastage Sqm 320.00 1.10 352.00
Cement Bag 210.00 0.24 50.40
Sand Cum 1,450.00 - -
Robo Sand Cum 728.00 0.04 29.35
Cement Slurry Kgs 4.20 3.30 13.86
Epoxy Grouting Kgs 350.00 0.17 60.38
PVC Spacers No.s 1.00 -
Acid wash Sqm 8.07 0.75 6.05
Add for Laying charges SQM 90.00 1.00 90.00
MISC. LS 602.04 0.03 15.05
Sub Total per Sqm 617.09
Rate per Rmt 61.71
Sub Total Rate/Rmt 70.97

Providing and laying Antiskid acid resistant ceramic tile of approved make and colour for size 300X300mm, in floors etc. over 1:4 cement mortar
(20mm) base including border tile, finishing joints grouting with the Epoxy shade to match with the tile colour and as approved by architect, washing

FOR TOILETS & UTILITY AREA

Cost of tiles incl.wastage Sqm 264.00 1.03 271.92


Cement Sqm 210.00 0.24 50.40
Sand Sqm 1,450.00 - -
Robo Sand Sqm 728.00 0.04 29.35
Cement Slurry Kgs 4.20 3.30 13.86
Epoxy Grouting Kgs 350.00 0.17 60.38
PVC Spacers No.s 1.00 6.00 6.00
Acid Wash Sqm 8.07 0.75 6.05
Laying charges Sqm 90.00 1.00 90.00
MISC. LS 527.96 0.05 26.40
Sub Total Rate/Sqm 554.00

Same as Item No.D1.9 but for Glazed Ceramic Tiles for Dadoing 7' for Bathroom/Toiltes on walls etc., complete (300X450mm)
Cost of tiles incl.wastage Sqm 501.00 1.03 516.03
Cement Sqm 210.00 0.24 50.40
Sand Sqm 1,450.00 - -
Robo Sand Sqm 728.00 0.04 29.35
Epoxy Grouting Kgs 65.00 0.43 27.98
PVC Spacers No.s 1.00 5.00 5.00
Acid Wash Sqm 8.07 1.00 8.07
Laying charges Sqm 117.00 1.00 117.00
MISC. LS 753.83 0.05 37.69
Sub Total Rate/Sqm 792.00

KITCHEN & UTILITY DADOING


Cost of tiles incl.wastage Sqm 288.00 1.03 296.64
Cement Sqm 210.00 0.24 50.40
Sand Sqm 1,450.00 - -
Robo Sand Sqm 728.00 0.04 29.35
Epoxy Grouting Kgs 65.00 0.43 27.98
PVC Spacers No.s 1.00 5.00 5.00
Acid Wash Sqm 8.07 1.00 8.07
Laying charges Sqm 117.00 1.00 117.00
MISC. LS 534.44 0.05 26.72
Sub Total Rate/Sqm 561.00

Providing and laying of Natural Stone tiles for Elevation Cladding (Make to be Approved by Architect), over 1:4 cement mortar (20mm) base including
border tile, finishing joints with matching colour pigment cement, etc., complete.
Cost of tiles incl.wastage Sqm 805.00 1.03 829.15
Epoxy Adhesive Sqm 19.46 5.38 104.69
Epoxy Grouting Kgs 65.00 0.17 11.05
Labour charges Sqm 164.00 1.00 164.00
MISC. LS 1,108.89 0.05 55.44
Sub Total Rate/Sqm 1,164.00

Providing and fixing Granite counters 20mm thick for kitchen including MS tubular support made by using 40 X 40 mm 14 gauge MS tubular section,
with necessary anchor fasteners etc., complete for finished item of work to the satisfaction of Engineer in charge
cost of stone sqm 1,250.00 1.15 1,437.50
bull nosing Rmt 135.25 3.60 486.90

edge polishing Rmt 60.00 3.60 216.00

Kitchen Platform Kgs 70.00 40.00 2,800.00

Hamali & Frieght @ Rs. 1/- per Kg 40.00 40.00


Erection @ 2/- per Kg 80.00 80.00

Page 10 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)
Local Transportation @ Rs. 1/- 40.00 40.00
Anchor Bolts Nos 20.00 14.00 280.00
Metal paste LS 10.00 10.00
fixing charges LS 260.00 1.00 260.00
Misc. LS 5,650.40 0.03 169.51
Sub Total Rate/Sqm 5,820.00

Providing and laying Rough Tandoor Blue of 20 - 30mm thk for paving in parking area as specified in the drawings and as direction, with minimum
20mm thick CM 1:4 with joints groove pointed neatly including curing and as per drawing, direction etc., complete for finished item of work to the
Tandoor stone incl wastage Sqm 195.00 1.05 204.75
Cement Sqm 210.00 0.24 50.40
Sand Sqm 1,450.00 - -
Robo Sand Sqm 728.00 0.04 29.35
Cement Slurry Kgs 4.20 3.30 13.86
Epoxy Grouting Kgs 350.00 0.10 35.00
Labour charges Sqm 221.09 1.00 221.09
MISC. LS 554.45 0.05 27.72
Sub Total Rate/Sqm 582.00

Providing and laying of Polished Marble flooring, laid over 20mm thick cement mortar bed of 1:4 (to make up required finished floor level) with joints
filled including polishing and finished neat with cement slurry with an admixture of pigment to match the shade of stone complete, for Staircase.
For flooring in landings (Marble stones)
Polished Marble incl wastage Sqm 1,550.00 1.08 1,666.25
Cement Sqm 210.00 0.24 50.40
Sand Sqm 1,450.00 - -
Robo Sand Sqm 728.00 0.04 29.35
White Cement Kgs 6.50 3.30 21.45
Epoxy Grouting Kgs 350.00 0.10 35.00
Polishing Sqm 162.00 1.00 162.00
Labour charges Sqm 323.00 1.00 323.00
MISC. LS 2,287.45 0.05 114.37
Sub Total Rate/Sqm 2,402.00

-do- for skirting 100mm high


Polished Marble incl wastage Sqm 1,550.00 1.10 1,705.00
Cement Sqm 210.00 0.24 50.40
Sand Sqm 1,450.00 - -
Robo Sand Sqm 728.00 0.04 29.35
Epoxy Grouting Kgs 350.00 0.10 35.00
MISC. LS 1,819.75 0.05 90.99
Sub Total per Sqm 1,910.74
Rate per Rmt 191.07
Add for Laying charges 32.30
Sub Total Rate/Rmt 223.00

In treads of steps - allow for rounding and bull


nosing of edge including smooth polishing.
Polished Marble incl wastage Sqm 1,550.00 1.10 1,705.00
Cement Sqm 210.00 0.24 50.40
Sand Sqm 1,450.00 - -
Robo Sand Sqm 728.00 0.04 29.35
White Cement Kgs 6.50 3.30 21.45
Bull Nosing Rmt 295.20 2.00 590.40
Groove Cutting Rmt 49.20 2.00 98.40
Epoxy Grouting Kgs 350.00 0.10 35.00
Labour charges Sqm 274.00 1.00 274.00
Misc. LS 2,804.01 0.05 140.20
Sub Total Rate/Smt 2,944.00

In risers of steps, finely fitted between treads.


Polished Marble incl wastage Sqm 1,550.00 1.10 1,705.00
Cement Sqm 210.00 0.24 50.40
Sand Sqm 1,450.00 - -
Robo Sand Sqm 728.00 0.04 29.35
Epoxy Grouting Kgs 350.00 0.10 35.00
Labour charges Rmt 164.00 2.00 328.00
Misc. LS 2,147.75 0.05 107.39
Sub Total Rate/Sqm 2,255.00

Providing and fixing of clay Roof tiles of best quality in approved make and color/design, laid to pattern as per drawing, set in rich cement mortar 1:4 (1
Cement : 4 Coarse Sand), min 20mm thk bedding and mixed with 2% integral waterproof compound laid in sloped Roof slab, jointed with neat cement
Cost of tiles incl. Wastage Sqm 550.00 1.03 566.50
Cement Bag 210.00 0.24 50.40
Sand Cum 1,450.00 - -
Robo Sand Sqm 728.00 0.04 29.35
Cement Slurry Kgs 4.20 3.30 13.86

Page 11 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)
Epoxy Grouting Kgs 350.00 0.10 35.00
Labour charges Sqm 130.00 1.00 130.00
MISC. LS 825.11 0.05 41.26
Sub Total Rate/Sqm 866.00

Providing and fixing First class Teakwood door frames of size 125mm X 65mm and 35mm/30mm thick panalled Shutters to perfect lines and levels
including the cost of concrete 300 x 200 x 200mm thick concrete of M 20 grade for hold fasts etc., Including hard ware fittings complete to the

MD (1100X2100)
Frame With Shutter Nos 14,802.00 1.00 14,802.00
Hardwares Nos 2,344.00 1.00 2,344.00

Cost of Foam 750ml 840.00 0.40 336.00

Cost of Foam remover 750ml 820.00 0.05 41.00

Labour charges for frame including foam Nos 270.00 1.00 270.00

Shutter fixing incl.hardware Nos 350.00 1.00 350.00


Fixing charges for Architrave Nos 100.00 1.00 100.00

Rs/No 18,243.00
D1 (1000X2100)
Frame With Shutter Nos 13,740.00 1.00 13,740.00
hardwres Nos 1,971.00 1.00 1,971.00

Cost of Foam 750ml 840.00 0.40 336.00

Cost of Foam remover 750ml 820.00 0.05 41.00

Labour charges for frame including foam Nos 270.00 1.00 270.00

Shutter fixing incl.hardware Nos 350.00 1.00 350.00


Fixing charges for Architrave Nos 100.00 1.00 100.00

Rs/No 16,808.00
D2 (900X2100)
Frame With Shutter Nos 13,385.00 1.00 13,385.00
hardwres Nos 1,971.00 1.00 1,971.00

Cost of Foam 750ml 840.00 0.40 336.00

Cost of Foam remover 750ml 820.00 0.05 41.00

Labour charges for frame including foam Nos 270.00 1.00 270.00

Shutter fixing incl.hardware Nos 350.00 1.00 350.00


Fixing charges for Architrave Nos 100.00 1.00 100.00

Rs/No 16,453.00
D2T (900X2100)
Frame With Shutter Nos 6,300.00 1.00 6,300.00
hardwres Nos 1,780.00 1.00 1,780.00

Cost of Foam 750ml 840.00 0.40 336.00

Cost of Foam remover 750ml 820.00 0.05 41.00

Labour charges for frame including foam Nos 270.00 1.00 270.00

Shutter fixing incl.hardware Nos 350.00 1.00 350.00


Fixing charges for Architrave Nos 100.00 1.00 100.00

Page 12 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)

Rs/No 9,177.00
D3 (850X2100)
Frame With Shutter Nos 13,031.00 1.00 13,031.00
hardwres Nos 1,597.00 1.00 1,597.00

Cost of Foam 750ml 840.00 0.40 336.00

Cost of Foam remover 750ml 820.00 0.05 41.00

Labour charges for frame including foam Nos 270.00 1.00 270.00

Shutter fixing incl.hardware Nos 350.00 1.00 350.00


Fixing charges for Architrave Nos 100.00 1.00 100.00

Rs/No 15,725.00
D3T (850X2100)
Frame With Shutter Nos 13,031.00 1.00 13,031.00
hardwres Nos 1,780.00 1.00 1,780.00

Cost of Foam 750ml 840.00 0.40 336.00

Cost of Foam remover 750ml 820.00 0.05 41.00

Labour charges for frame including foam Nos 270.00 1.00 270.00

Shutter fixing incl.hardware Nos 350.00 1.00 350.00


Fixing charges for Architrave Nos 100.00 1.00 100.00

Rs/No 15,908.00
D4 (750X2100)
Frame With Shutter Nos 12,677.00 1.00 12,677.00
hardwres Nos 1,597.00 1.00 1,597.00

Cost of Foam 750ml 840.00 0.40 336.00

Cost of Foam remover 750ml 820.00 0.05 41.00

Labour charges for frame including foam Nos 270.00 1.00 270.00

Shutter fixing incl.hardware Nos 350.00 1.00 350.00


Fixing charges for Architrave Nos 100.00 1.00 100.00

Rs/No 15,371.00
D4V (750X2100)
Frame With Shutter Nos 6,000.00 1.00 6,000.00
hardwres Nos 780.00 1.00 780.00

Cost of Foam 750ml 840.00 0.40 336.00

Cost of Foam remover 750ml 820.00 0.05 41.00

Labour charges for frame including foam Nos 270.00 1.00 270.00

Shutter fixing incl.hardware Nos 350.00 1.00 350.00


Fixing charges for Architrave Nos 100.00 1.00 100.00

Rs/No 7,877.00
PD (1200X2100)
Frame With Shutter Nos 14,802.00 1.00 14,802.00
hardwres Nos 2,344.00 1.00 2,344.00

Page 13 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)

Cost of Foam 750ml 840.00 0.40 336.00

Cost of Foam remover 750ml 820.00 0.05 41.00

Labour charges for frame including foam Nos 270.00 1.00 270.00

Shutter fixing incl.hardware Nos 350.00 1.00 350.00


Fixing charges for Architrave Nos 100.00 1.00 100.00

Rs/No 18,243.00

Providing and fixing UPVC windows at all levels with perfect lines and level including the cost of filling materials etc complete to the
satisfaction of the PMC / Clients.
SLD (2400 X 2100)
Material Cost Nos 10,734.00 1.00 10,734.00
Fixing Charges LS 2,684.00 1.00 2,684.00

Rs/No 13,418.00
SLD (2000 X 2100)
Material Cost Nos 9,182.00 1.00 9,182.00
Fixing Charges LS 2,295.00 1.00 2,295.00

Rs/No 11,477.00
W1 (1500 X 1250)
Material Cost Nos 4,321.00 1.00 4,321.00
Fixing Charges LS 1,080.00 1.00 1,080.00

Rs/No 5,401.00
W2 (1200 X 1250)
Material Cost Nos 3,704.00 1.00 3,704.00
Fixing Charges LS 926.00 1.00 926.00

Rs/No 4,630.00
W3 (900 X 1250)
Material Cost Nos 3,086.00 1.00 3,086.00
Fixing Charges LS 772.00 1.00 772.00

Rs/No 3,858.00
W4 (600 X 1250)
Material Cost Nos 2,712.00 1.00 2,712.00
Fixing Charges LS 678.00 1.00 678.00

Rs/No 3,390.00
KW1 (1500 X 900)
Material Cost Nos 3,630.00 1.00 3,630.00
Fixing Charges LS 908.00 1.00 908.00

Rs/No 4,538.00
KW2 (1200 X 900)
Material Cost Nos 2,904.00 1.00 2,904.00
Fixing Charges LS 726.00 1.00 726.00

Rs/No 3,630.00
KW3 (900 X 900)
Material Cost Nos 2,419.00 1.00 2,419.00
Fixing Charges LS 605.00 1.00 605.00

Rs/No 3,024.00
KW4 (600 X 900)
Material Cost Nos 2,097.00 1.00 2,097.00
Fixing Charges LS 524.00 1.00 524.00

Rs/No 2,621.00
SW (900 X 1250)
Material Cost Nos 2,178.00 1.00 2,178.00
Fixing Charges LS 544.00 1.00 544.00

Rs/No 2,722.00
FG (1250 X1250)
Material Cost Nos 3,525.00 1.00 3,525.00
Fixing Charges LS 1,035.00 1.00 1,035.00

Page 14 of 15
GRADE OF CONCRETE
Sl.No MACHINE+MATERIAL+LABOUR UNIT RATE Remarks
Co-eff M5 (1:5:10)
Rs/No 4,560.00
CW1 (2580 X 650)
Material Cost Nos 4,438.00 1.00 4,438.00
Fixing Charges LS 1,109.00 1.00 1,109.00

Rs/No 5,547.00
CW2 (1950 X 1250)
Material Cost Nos 7,529.00 1.00 7,529.00
Fixing Charges LS 855.00 1.00 855.00

Rs/No 8,384.00
V1 (900X600)
Material Cost Nos 1,854.00 1.00 1,854.00
Fixing Charges LS 463.00 1.00 463.00

Rs/No 2,317.00
V2 (600X800)
Material Cost Nos 1,545.00 1.00 1,545.00
Fixing Charges LS 386.00 1.00 386.00

Rs/No 1,931.00
V3 (450X800)
Material Cost Nos 1,158.00 1.00 1,158.00
Fixing Charges LS 290.00 1.00 290.00

Rs/No 1,448.00

Page 15 of 15