Vous êtes sur la page 1sur 3

Ref. No.: BPS-121214-F.

RP

CIKARANG POWER STATION PROJECT


Babelan, Bekasi, Jakarta, Indonesia

No. 164

PROGRESS REPORT

26th June 2019

Prepared by DELUGE

Cikarang Power Station Project Babelan,


Bekasi, Indonesia
Page 1 of 3
1. SAFETY & SECURITY
Manpower :
PT Deluge Engineering Construction Staff :3
Deluge direct Worker :2
Total Manpower :5

2. Manpower (PT Deluge Site Project Management)


a) James Abarca (Project Manager – Ph. 0813 9836 8251)
b) Eko Kurniawan (Construction Manager – Ph. 081293961612)
c) Bekti (Admin – Ph. 081548698276)

3. SITE FACILITIES
- No Issues

4. QA/ QC
Balance Punchlist;
1. High Vibration Electric Pump Power Island
2. High Vibration Dust Suppression Pump #2

5. Engineering Issues
- No Issues

6. Aboveground
High Vibration Electric Pump Power Island;
- Deluge has start to install Flexible Coupling on Discharge Pipe, and do replacement of
welded tee become grooved tee. Installation expected to be done by this week.
- Pump Performance Test; Deluge’s Pump Engineer from Singapore has checked and saw
Electric Fire Pump on running condition.
Summary of check report;
a. No visual vibration to be seen on the discharge pipes during test run.
b. Measuring vibration on Pump Bearings area.

Immediate action is to install Flexible Coupling on Discharge Pipe.

FHS Pump Room : Transducer Line correction will done after Power Island Pump normal.

7. Underground
- Hydrant Line new pipe leak found at BC-07A area next to TT-13 on Saturday 18 May
2019 has repaired and completed by 26 May 2019.
- Backfill with add soil on every underground pipe repaired area. Work has done at TT-8
area, TT-13 Area.

8. Fire Alarm
- No Activity

Cikarang Power Station Project Babelan,


Bekasi, Indonesia
Page 2 of 3
9. Dust Suppression
- High Vibration Dust Suppression Pump #2;
Deluge’s Pump Engineer from Singapore has checked and saw Dust Suppression Pump
#2 on running condition.
Summary of check report;
a. Rough noise coming from casing internal, most likely caused by water turbulence in the
piping system.
b. No problem on the motor.
c. Remeasuring of the vibration shows that the vibration is located within the pump
bearing housing DE & NDE bearings .

Options action to take is :

a. Repair the pump


- Rebalance the impeller and/or
- Check the concentricity of the shaft, rebuild or replace if necessary.

c. Replace with new impeller and shaft.


d. Replace the pump (keep the motor)

10. This Week Plan


10.1. Electric Fire Pump Power Island
- Continue to install Flexible Coupling on Discharge Pipe, and do replacement of welded
tee become grooved tee. Installation expected to be done by this week.

10.2. Underground
- No Activity.

10.3. Fire Alarm


- Test which has been repaired with PTCL

10.4. Dust Supression


- Pump #2; send out requests for pump repair costing to vendors

Cikarang Power Station Project Babelan,


Bekasi, Indonesia
Page 3 of 3

Vous aimerez peut-être aussi