RP
No. 164
PROGRESS REPORT
Prepared by DELUGE
3. SITE FACILITIES
- No Issues
4. QA/ QC
Balance Punchlist;
1. High Vibration Electric Pump Power Island
2. High Vibration Dust Suppression Pump #2
5. Engineering Issues
- No Issues
6. Aboveground
High Vibration Electric Pump Power Island;
- Deluge has start to install Flexible Coupling on Discharge Pipe, and do replacement of
welded tee become grooved tee. Installation expected to be done by this week.
- Pump Performance Test; Deluge’s Pump Engineer from Singapore has checked and saw
Electric Fire Pump on running condition.
Summary of check report;
a. No visual vibration to be seen on the discharge pipes during test run.
b. Measuring vibration on Pump Bearings area.
FHS Pump Room : Transducer Line correction will done after Power Island Pump normal.
7. Underground
- Hydrant Line new pipe leak found at BC-07A area next to TT-13 on Saturday 18 May
2019 has repaired and completed by 26 May 2019.
- Backfill with add soil on every underground pipe repaired area. Work has done at TT-8
area, TT-13 Area.
8. Fire Alarm
- No Activity
10.2. Underground
- No Activity.