PROPOSED TIME SCHEDULE FOR CONSTRUCTION OF NEW 33 KV SWITCHING STATION # 7725

ID Task Name Dur. START Finish Nov. 2011 Dec. 2011 Jan. 2012 Feb. 2012 March2012 Apr.2012 May. 2012 Jun. 2012 July. 2012 Aug. 2012 Sept. 2011 Oct. 2012 Nov. 2012 Dec. 2012 Jan. 2013
18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 1 8 15 22 29 6 13 20 27 4 11 18 25 2 9 16 23 30 1 8 15 22 29 6 13 20 27 4 11 18 25 2 9 16 23 30 7 13 20 27 4 11 18
1 CONTRACT DURATION 420 11/18/2011 1/18/2012
2 CONTRACT START DATE 420 11/18/2011 1/18/2012
3 SITE SURVEY 8 11/25/2011 12/2/2011
4 MOBILIZATION 21 12/2/2012 12/23/2011
5 DESIGN AND ENGINERING 90 12/16/2012 17/03l12
6 CIVEL WORKS 210 01/02l12 8/30/2012
7 BASE DESIGN SUBMITTALS FOR APRPROVAL 60 01/02l12 3/30/2012
8 DETAIL DESIGN SUBMITTALS FOR APRPROVAL 30 4/1/2012 4/30/2012
9 CIVIL WORK for foundation 150 2/1/2012 6/30/2012
10 FINISHING FOR INSIDE BULDING 120 5/1/2012 8/30/2012
11 EARTHING SYSTEM 210 2/1/2012 8/30/2012
12 DESIGN AND CALCULATION 60 2/1/2012 3/30/2012
13 DELIVERY TO SITE 10 2/1/2012 2/10/2012
14 INSTALLATION 190 2/10/2012 8/30/2012
15 HVAC EQUIPMENT 240 3/1/2012 11/30/2012
16 DESIGN AND CALCULATION 90 3/1/2012 5/30/2012
17 DELIVERY TO SITE 10 11/20/2012 11/30/2012
18 INSTALLATION 60 10/1/2012 11/30/2012
19 INSIDE AND OUTSIDE LIGHTING 21o 4/1/2012 10/30/2012
20 DESIGN AND CALCULATION 60 4/1/2012 5/1/2012
21 DELIVERY TO SITE 14 9/1/2012 9/14/2012
22 INSTALLATION 46 9/14/2012 10/30/2012
23 33 KV. SWITCHGEAR 347 2/1/2012 1/18/2013
24 DESIGN,MANUFACURE & FACTORY TEST 90 2/1/2012 4/30/2012
25 DELIVERY TO SITE 14 9/20/2012 10/4/2012
26 ERECTION 34 10/4/2012 11/30/2012
27 AUX.TRF (500KVA) 210 4/1/2012 10/30/2012
28 DESIGN,MANUFACURE & FACTORY TEST 90 4/1/2012 6/1/2012
29 DELIVERY TO SITE 8 8/22/2012 8/30/2012
30 ERECTION 30 8/30/2012 9/30/2012
31 BATTERIES & BATTERY CHARGER 225 3/1/2012 10/15/2012
32 DESIGN,MANUFACURE & FACTORY TEST 90 3/1/2012 5/30/2012
33 DELIVERY TO SITE 8 9/20/2012 9/30/2012
34 ERECTION 14 10/1/2012 10/14/2012
35 ACDB&DCDB 180 4/1/2012 9/30/2012
36 DESIGN,MANUFACURE & FACTORY TEST 90 4/1/2012 6/30/2012
37 DELIVERY TO SITE 7 9/20/2012 9/27/2012
38 ERECTION 33 9/27/2012 10/30/2012
39 CAPACITOR BANK 210 4/1/2012 10/30/2012
40 DESIGN,MANUFACURE & FACTORY TEST 120 4/1/2012 7/30/2012
41 DELIVERY TO SITE 26 10/4/2012 10/30/2012
42 ERECTION 30 11/1/2012 11/30/2012
43 MULTI-CORE CABLES 90 9/1/2012 11/30/2012
44 MANUFACURE & FACTORY TEST 17 9/13/2012 10/30/2012
45 DELIVERY TO SITE 8 11/1/2012 11/8/2012
46 LAYING & TERMINATON 21 11/9/2012 11/30/2012
47 PROTECTION & CONTROL PANEL 210 6/1/2012 12/30/2012
48 DESIGN,MANUFACURE & FACTORY TEST 90 6/1/2012 8/30/2012
49 DELIVERY TO SITE 13 9/1/2012 9/13/2012
50 ERECTION 55 9/14/2012 11/9/2012
51 FIRE FIGHTING EQUIPMENT 180 7/1/2012 12/30/2012
52 DESIGN,MANUFACURE & FACTORY TEST 90 7/1/2012 9/30/2012
53 DELIVERY TO SITE 5 10/25/2012 10/30/2012
54 ERECTION 30 10/30/2012 11/30/2012
55 TELECOM.EQUIPMENT & SCADA 166 8/1/2012 1/11/2013
56 DESIGN,MANUFACURE & FACTORY TEST 90 8/1/2012 10/30/2012
57 DELIVERY TO SITE 7 11/1/2012 11/7/2012
58 ERECTION 52 11/8/2012 12/30/2012
59 TESSTING & COMMISSIONING 73 11/1/2012 1/18/2013
60 PRE-COMMISSINING 30 12/1/2012 12/30/2013
61 FINAL-COMMISSIONING 28 12/20/2013 1/18/2013