Vous êtes sur la page 1sur 3

LUSAKA CITY COUNCIL

OFFICE OF THE TOWN CLERK


Telephone: +260 211 252997
Civic Centre, Independence Avenue Telefax: +260 211 252141
P O Box 30077 Email: lusakacitycouncil@mlgh.gov.zm
10101 Lusaka, Zambia www.lcc.gov.zm
Our ref: ESD/5/3/29/BB/bcb 16th July 2019

The Managing Director


Lusaka Water and Sewerage Company
P.O. Box 90182
LUSAKA

Dear Sir/Madam

RE: AUTHORITY FOR ROAD CUTTING ON GREAT NORTH ROAD

Reference is made to the above captioned matter and your letter in which you
requested for permission to carry out road cutting on the Great North road.

I wish to inform you that your request to carry out replacement and repairing of
a water pipe on part of the road reserve has been granted for the road as per
schedule.

Nevertheless, permission is based on the following conditions:


i. Lusaka City Council reserves the right to enter upon the land, if need arise,
for any future road works or installation of other services at no cost to the
Council.
ii. Reinstatement must be done upon completion of the works failure to which
you will be charged fivefold the cost of reinstatement.
iii. You make arrangements to control and direct traffic during the period of
works which should also include road signage. Furthermore, all detour
routes should be identified and prepared before road cutting works begin.
iv. Liaise with other stake holders/utility entities that have/may have their
network underlying along the site you propose.
v. You are required to inform our Engineering Services Department as soon
as you are ready to commence works so as to ensure that standards are
adhered to.
vi. You are therefore required to pay required to pay a total of Sixteen
Thousand Seven Hundred Kwacha, Fifty-Six Ngwee, K16,700.56, which
shall be deposited directly to the account details given below. Note that
failure by the applicant to provide proof of payment deems this authority
invalid.
Bank Name: ZANACO
Account Name: LCC Roads Board
Account No: 0244345500172
Branch: Civic Centre
Sort Code: 010067
Swift Code: ZNCOZMLU

Thanking you in anticipation that works will be carried out accordingly.

Yours faithfully
LUSAKA CITY COUNCIL

Alex Mwansa
TOWN CLERK

cc: Director of Engineering Services


cc: Director of Finance
Attn: Chief Revenue Accountant
LUSAKA CITY COUNCIL
ENGINEERING SERVICES DEPARTMENT
ROADS AND DRAINAGE SECTION
REF: ESD/5/3/29/BB/
COST ESTIMATES FOR ROAD CUTTING AND REINSTATEMENT
Road Name No. of cuttings
1. Great North Road 1
Client
Lusaka Water and Sewarage Company
P.O. Box 90182, Lusaka
Item Description Unit Qty Rate Amount
a Road Cutting
Mobilization and
1 Demobilization LS ZMW 1,000.00
2 Cutting of edges m 18 ZMW 75.00 ZMW 1,350.00
3 Excavation of soft material in
readiness to lay cables/ pipes/
ducts m3 12 ZMW 350.00 ZMW 4,200.00
Excavation of hard material in
readiness to lay cables/ pipes/
4 ducts m3 Ls ZMW - ZMW -
5 Backfilling and compacting m3 12 ZMW 250.00 ZMW 3,000.00
6 Cement Stabilising of 150mm
thick Gravel m3 1.2 ZMW 480.00 ZMW 576.00
7 Apply MC 30 Primer m2 8 ZMW 180.00 ZMW 1,440.00
8 Bituminous surface
reinstatement with Hot Asphalt
(70mm Thick) Tons 1 ZMW 2,400.00 ZMW 2,400.00
Total Carried Forward ZMW 13,966.00

b Application Fee 1 ZMW 431.03 ZMW 431.03

SUB TOTAL: ZMW 14,397.03


VAT 16% ZMW 2,303.53
TOTAL ZMW 16,700.56

NOTE:
All excavations along the road reserve to be reinstated within 24hours
Reinstatement of the Walkway and kerbs shall be the sole responsibility of the client
Excavation of hard material in readiness to lay cables/ pipes/ ducts, should need arise is client's
responsibility.
Attach a completed "Excavation & Road Cutting Permit" form
Quote valid for 14 days