ME 6703 - Computer Integrated Manufacturing Systems
CIM / SFC / R PRADEEP KUMAR AP/MECH 6
SHOP FLOOR CONTROL
• Shop floor control is concerned with the
release of production orders to the factory, monitoring and controlling • the progress of the orders through the various work centers, and acquiring current information on the status of the orders.
CIM / SFC / R PRADEEP KUMAR AP/MECH 7
SHOP FLOOR CONTROL • Order release. • order scheduling. • Order progress.
CIM / SFC / R PRADEEP KUMAR AP/MECH 8
CIM / SFC / R PRADEEP KUMAR AP/MECH 9 Order Release • Collection of document is sometimes called the shop packet. • Route sheet. • Material requisitions. • Job cards. • Move tickets. • Parts list.
CIM / SFC / R PRADEEP KUMAR AP/MECH 10
Order Scheduling • Machine loading • job sequencing.
Priorities for production orders:
• First-come-first serve. • Earliest due date. • Shortest processing time. • Least slack time. • Critical ratio.
CIM / SFC / R PRADEEP KUMAR AP/MECH 11
• Priorities of the different orders. • Lower or higher than expected demand for certain products. • Equipment breakdowns that cause delays in production, • Cancellation of an order by a customer, • Defective raw materials that delay an order.
CIM / SFC / R PRADEEP KUMAR AP/MECH 12
Order Progress • Work order status reports. • Progress reports. • Exception reports.
CIM / SFC / R PRADEEP KUMAR AP/MECH 13
Factory Data Collection System • Factory data collection system. • To supply status and performance data to the shop floor control system. • To provide current information to production foremen, plant management. and production control personnel.
Manual (Clerical) Data Input Techniques.
• Job traveler. • Employee time sheets. • Operation tear strips. • Prepunched cards. CIM / SFC / R PRADEEP KUMAR AP/MECH 14 Automated and Semi-Automated Data Collection Systems.