Académique Documents
Professionnel Documents
Culture Documents
EXECUTIVE SUMMARY
1 Executive Summary
1.1 Background
Ministry of Road Transport and Highways (Govt. of India) has embarked upon massive up-gradation
of its road network in the State of Assam through PWD NH Works, Assam with the purpose of
development of highways and any other infrastructure projects thereon entrusted to it and as part of this
endeavor, the PWD NH Works, Assam has been mandated to undertake improvement and up-gradation
of various State Highways and Major District Roads at different locations in Assam.
In view of the above work PWD NH Works, Assam has appointed Alliance Engineers & Consultants
to carry out Consultancy Services for preparation of Project Report for proposed Mangaldai Bypass
starting from chainage at Ch. 26+400 Km of NH 15 (Baniyaojhapara) and terminating at Ch. 41+480
Km of NH 15 (Khatoniyapara) passing through revenue village of Barkumarpara, Gurimari 1st & 2nd
part, Mowamari Chapori, Baghpori Chapori, Bundia Chapori & Gelaidiang Chapori (Length 15.26
Km).
1.3 Traffic
To establish the traffic characteristics along the project road, Consultants have carried out 7 days
Classified Traffic Volume Counts.
The Average Annual Daily Traffic (AADT) in the base year 2016 on the three (3) locations is presented
in Table 1.2.
The traffic growth rates are considered as 6.5% as per Clause 4.2.2 of IRC: 37-2012.
The projected traffic considering the above growth rate are given in Table1.3.
KM 30 (Punia) KM 41 (Dakechowki)
Year
NOS PCU NO PCU
The width of the carriageway is 7.0m throughout the entire length with 1.50m paved Shoulder
All the Bridges are proposed to be constructed.
43 Nos. of Culverts are proposed to be constructed as R.C.C Box Culverts.
The entire road is designed as Flexible Pavement.
Major and 30 minor junctions are proposed to be developed.
Road furniture like Road Signs, Markings, Metal Beam Crash Barrier, Guard posts, KM
Stones, Hectometer and 5th KM stones etc. are proposed for the road stretch.
Zebra crossings are proposed to be provided where there are bus stops, market and Shopping
Places
Pick-up Bus stops are provided at 8 locations (4 Left and 4 Right Sides).
Design Traffic
The Design cumulative standard axles calculated from the traffic survey is found to be 98.16 msa.
Therefore, for pavement design a design traffic of 100 msa is considered.
The minimum CBR of subgrade for pavement design is should to be 8% as per IRC 37 clause 5.1.
Pavement Composition
The following pavement thickness is proposed for the development of the project bypass.
Bituminous Concrete : 50 mm
Total : 615 mm
7 No. of minor bridges are proposed to be constructed. The proposals for Bridges are as follows:
1.6.3 Junctions
There are about 32 Nos. of major and minor junctions out of which 8 nos. T Junctions, and 24 nos. Y-
Junctions at various locations. Among the Y-junctions 3 nos. are major junction and remaining are
minor junctions. The list of junctions along the project road is given in Table 0.6.
1.6.7 Others
1.6.8 Highway Lighting
Street Lights are provided in built-up areas.
Solar lights blinkers are proposed at major & minor junctions and bus shelters.
Shifting of utilities such as, Electrical poles, Telephone poles relevant documents are to be
submitted to respective departments by the consultants only after proposed development of
project road finalization.
Forest and Environmental clearance of the project is under process.
Length = 15.36 Km
Bill Cost
Item of works and Sub-Heads Unit Quantity
No (Rs. lakhs)
2 EARTH WORK
6 DRAINAGE WORKS
CHAPTER 2
PROJECT DESCRIPTION
2 Project Description
2.1 District Covered
The project road is located in the State of Assam. Assam is located in North Eastern part of India,
comprising of valleys, hills and the perennial River of Brahmaputra and Barak. Assam shares its internal
boundaries with West Bengal, Tripura, Manipur, Meghalaya, Mizoram, Nagaland and Arunachal
Pradesh, while Bangladesh, Myanmar (Burma) and China surrounds the international contours of the
state.
Part of total volume of traffic, which enters via Sri Rampur and Baxirghat that bordering Assam and
West Bengal, moves via NH 15 (old NH 52). Further a sizeable part of traffic volume originating from
Guwahati and other NE States moves towards NH 15 and heading for Lakhimpur, Dhemaji, Jonai,
Pasighat, and Itanagar and other parts of Arunachal Pradesh.
The Project Bypass Road starts at 26+400 Km of NH 15 (Baniyaojhapara) and ends at 41+480 Km of
NH 15 (Khatoniyapara). The total length of the project road is 15.26 Km.
The Project corridor is a part of National Highway No 15 from Baihata Chariali to the major District in
Assam like Darrang, Sonitpur, Lakhimpur, Dhemaji and other part of Arunachal Pradesh. The proposed
bypass at Mangaldai will ease the free flow of traffic movement by avoiding the thickly populated
Mangaldai town.
The entire proposed project road passes through plain terrain and is a low laying area which passes
through mostly cultivated and Government land barring a few built up area. The river Brahmaputra is
located about one kilometer away in the Southern side of the proposed alignment. The highest flood
level of the Mangaldai town is 55.70 meter from the Mean Sea level.
All the settlements found along the corridor, which is listed below in Table 3.1.
The entire project road does not pass through any Reserve Forest or Wild Life Sanctuary.
2.3.2 Geometry
Horizontal alignment is fair in general and there are a few mild curves and adequate super elevation
and radii have been designed as per IRC norms. Provision of extra widening is carried out at very few
locations.
The list of junctions along the project road is given in Table 3.2.
2.4.5 Pavement
There is no existing pavement as the project bypass is totally a new alignment passes mostly through
open govt. land.
2.4.6 ROB
There are no railway level crossings / ROB along the project road.
Water supply pipe lines to Town/ Village under water supply scheme.
HT lines, Electric and Telephone Poles, Transformers.
Water supply lines are located near Town and villages portion. Electric Poles are laid throughout Project
Corridor.
2.4.9 Miscellaneous
The project road is having following features along road sides:
Primary schools
Religious Structure
Shops
The cross-sectional elements (lane/shoulder width etc.) are as per standards specified in geometric
design manual. Following typical cross sections have been envisaged for the subject project as
mentioned below.
14.000
10.000
G.L.
G.L.
50mm THICK BC
C
L
115mm THICK DBM
250mm THICK WMM
200mm THICK GSB
500mm THICK SUBGRADE
Traffic signs and pavement markings includes roadside signs, overhead signs; curve mounted signs and
road marking along the project highway. The locations for these provisions are based as per IRC: 35-
2015 and IRC: 67-2012 respectively.
Road Delineators
Pedestrian Guard Railing
Metal Beam Crash Barrier
Traffic safety Devices wherever required
Boundary Stones
Kilometer Stones
Information board
CHAPTER 3
DETAILED METHODOLOGY
3.1 GENERAL
The project involves a series of inter-related activities, both in the field and in the design office. Various
engineering surveys and investigations are carried out to gather data and information of existing road
to develop an adequate supportive database for selecting and preparing the most appropriate proposal
to meet the functional and structural efficiency and safety requirements. The engineering investigations
and surveys have been carried out in line with the specifications laid out in relevant IRC codes. The
major aspects of surveys and investigations relevant to the present study cover the following:
underpasses
Design Standards
Geometric Design
Environmental Screening
Establishing benchmark for baseline conditions
Analysis of Alternatives
Study of Environmental Enhancement measures
Preparation of BOQ
Establishing monitoring network mechanisms
EMP
Clearance for forestry and environment
viii. Estimation of Quantities and Project Costs
2-Wheeler Bi-Cycle
3-Wheeler Cycle-Rickshaw
Standard Bus
LCV LCV-Passenger
LCV-Freight
Articulated
1. The traffic count data was analysed to depict hourly and daily variations.
2. The traffic volume count per day has been averaged to show a weekly Average Daily Traffic
(ADT) by vehicle type. The Annual Average Daily Traffic (AADT) was worked out by
applying seasonal factors.
3. The relevant traffic volume data were compiled from secondary sources also. The salient
features of traffic volume characteristics brought out and variations if any were explained
suitably.
4. The Abstract of traffic data for each survey station has been provided in a separate chapter.
1. The basic objective of the topographic survey is to capture the essential ground features
along the alignment in order to consider improvements and for working out improvements,
rehabilitation and upgrading costs. The detailed topographic surveys were taken up after
the completion of reconnaissance surveys.
2. Carrying out of topographic surveys is one of the most important and crucial field tasks
under the project. The detailed field surveys have been carried out using high precision
instruments i.e. Total stations. The data from the topographic surveys has been available in
(x, y, z) format for use in a sophisticated digital terrain model (DTM). The Consultants is
fully responsive for any inaccuracy in surveys.
3. The detailed field surveys include the following activities:
i. Topographic Surveys along the Existing Right of Way (ROW): Running a continuous
open Traverse along the existing road and realignments, wherever required, and
fixation of all cardinal points such as horizontal intersection points (HIP’s), centre
points and transit points etc. and properly referencing the same with a pair of
reference pillars fixed on either side of the centre-line at safe places within the ROW.
ii. Collection of all features such as structures (bridges, culverts etc.) utilities, existing
roads, electric and telephone installations (both O/H as well as underground), huts,
buildings, fencing and trees (with girth greater than 0.3 metre) oil and gas lines etc.
in detail falling within the extent of survey.
4. The width of survey corridor was generally being as given under:
i. The width of the survey corridor has been decided considering the existing alignment
including the extent of embankment and cut slopes and the general ground profile.
While carrying out the field surveys, the widening scheme (i.e. right, left or
symmetrical to the centre line of the existing carriageway) will be taken into
consideration so that the topographic surveys cover sufficient width beyond the
centre line of the proposed divided carriageway. Normally the surveys has been
extended to a minimum of 45 m beyond either side of the centre line of the proposed
divided carriageway or land boundary whichever is more.
ii. In case the reconnaissance survey reveals the need for bypassing the congested
locations, the traverse lines would be run along the possible alignments in order to
identify and select the most suitable alignment for the bypass. The detailed
topographic surveys along the bypass alignment approved by NHIDCL have been
i. Longitudinal section levels along final centre line at every 25 m interval, at the locations
of curve points, small streams, and intersections and at the locations of change in
elevation.
ii. Cross sections at every 50 m interval in full extent of survey covering sufficient number of
spot levels on existing carriageway and adjacent ground for profile correction course and
earth work calculations. Cross sections have been taken at closer interval at curves.
iii. Longitudinal section for cross roads for length adequate for design and quantity
estimation purposes.
iv. Longitudinal and cross sections for major and minor streams as per recommendations
contained in IRC Special Publication No. 13 (Guidelines for the Design of Small Bridges
and Culverts) and IRC:5-1998 (“Standard Specifications & Code of Practice for Road
Bridges, Section 1 – General Features of Design”).
The cross section data has been presented with Detailed Project Report.
1. Detailed road inventory surveys have been carried out to collect details of all existing
road and pavement features along the existing road sections. The Performa for road,
culverts and bridge inventory & other structures is provided at Annexure attached:
The inventory data include the following but not be limited to:
2. The deviation(s), if any, towards the scheme presented above has been got approved by
NHIDCL.
3. However, where a study of geo-technical reports and information available from adjacent
crossings over the same waterway (existing highway and railway bridges) indicates that
subsurface variability is such that boring at the suggested spacing is insufficient to
adequately define the conditions for design purposes, and finalised the bore hole locations
in consultation with the NHIDCL officers.
4. Sub-soil investigations has been done as per IRC 78-2000.
5. The scheme for the borings locations and the depth of boring has been prepared by the
Consultants and submitted to NHIDCL for approval. These may be finalized in
consultation with NHIDCL.
6. The sub-soil exploration and testing has been carried out through the Geotechnical
Consultants who have done Geo-technical investigation work in similar project. In case of
outsourcing Geo-Technical Investigation, the firm selected by the Consultant for this
purpose has been got approved from NHIDCL before start of such works. The soil testing
reports has been in the format prescribed in relevant IRC Codes.
7. For the road pavement, bore holes at each major change in pavement condition or in
deflection readings or at 2 km intervals whichever is less has been carried out to a depth
of at least 2 m below embankment base or to rock level and are to be fully logged.
Appropriate tests to be carried out on samples collected from these bore holes to determine
the suitability of various materials for use in widening of embankments or in parts of new
pavement structure.
3.3.6.5 Material Investigations:
Suitable quarries for Granular Sub-Base Course, which is naturally occurring and generally available
in the Project Corridor, have been identified. Since these materials, in original grading do not satisfy
the grading requirement as per MORT&H Specifications proposed for the project (Grading-II) these
These naturally occurring materials for GSB have been tested for CBR Liquid Limit and Plasticity Index
to meet following requirements:
3.4 Detailed Design of Road and Pavements, Grade separated structures and
underpasses
3.4.1 General
1. Detailed designs and working drawings have been prepared for the following:
a. Design of pavement for the additional lanes, paved shoulders, medians, verges;
b. Bridges, viaduct/subways and structures including ROBs etc.
c. At-grade and grade-separated intersections, interchanges (if required);
d. Alignment plans, longitudinal sections and cross-sections @ 50m intervals;
e. Designs for road furniture and road safety/traffic control features;
f. Designs and drawings for service road/under passes/overpass / cattle passes tree
planting/fencing at locations where necessary / required
g. Expansion of toll plazas
h. Drainage design showing location of turnouts, out falling structures, separate
drawings sheet for each 5 km. stretch. Innovative type of structures with minimum
joints, aesthetically, pleasing and appropriate to the topography of the region has
been designed wherever feasible.
1. The preliminary environmental screening has been carried out to assess the direct and
induced impacts due to the project.
2. Document baseline conditions relevant to the project with the objective to establish the
benchmarks.
3. The potential significant impacts and identifies the mitigative measures to address these
impacts adequately.
4. Alternatives were analysed incorporating environmental concerns. This includes with and
without scenario and modification incorporated in the proposed project due to
environment considerations.
5. The environmental enhancement measures in the project for the following:
a) Cultural property enhancement along the highways
b) Bus bays and bus shelters including a review of their location,
c) Highway side landscape and enhancement of the road junctions,
d) Enhancement of highway side water bodies, and
e) Redevelopment of the borrow areas located on public land.
6. The bill-of-quantities (BOQ) and technical specifications have been prepared for all items
of work in such a way that these may be readily integrated to the construction contracts.
CHAPTER 4
In view of the above work PWD NH Works, Assam has appointed Alliance Engineers & Consultants
to carry out Consultancy Services for preparation of Project Report for proposed Mangaldoi Bypass
starting from Ch. 26+400 km of NH 52 (Chengeliyapara) and terminating at Ch. 41+480 km of NH 52
(Dakechowki) passing through revenue village of Barkumarpara, Gurimari 1st & 2nd part, Mowamari
Chapori, Baghpori Chapori, Bundia Chapori & Gelaidiang Chapori (Length 15.76 km Approx.).
As part of this study, a systematic methodology has been followed to assess the characteristics of the
traffic on the project road before and after the proposed improvement. The details pertaining to the data
collection, primary as well as secondary, and results from its analysis are presented in the following
sections.
The present Traffic Report presents the existing traffic characteristics of project road.
A part of the total traffic volume that enters via Sri Rampur and Baxirhaat from West Bengal, moves
via NH52. Further a sizeable part of traffic volume originating from Guwahati and other NE States
moves towards NH 52 and heads for Lakhimpur, Dhemaji, Jonai, Pasighat and Itanagar and other parts
of Arunachal Pradesh.
The project corridor under study is a part of National Highway No. 52 from Baihata Chariali to the
Major Districts in Assam like Darrang, Sonitpur, Lakhimpur, Dhemaji and other parts of Arunachal
The entire proposed Project Road passes through mostly agricultural and Government land barring a
few locations of built up areas. The terrain classification of the project road is “plain terrain” with many
low lying and flood prone areas. The River Brahmaputra is located about one Kilometer away in the
Southern side of the proposed alignment. The highest flood level of the Mongaldoi town is 55.70 meter
from the Mean Sea Level.
Survey
Type of Survey Chainage Duration Survey Dates
Location
For carrying out the traffic survey, vehicle classifications, as given in Table 7.2, were adopted. The
vehicle classification used is based on IRC: SP: 19-2001.
2 wheelers Cycle
Bullock Cart
Car/ Jeep/ Van/ Taxi Animal Drawn
Horse
Mini Bus
Bus
Full Bus
LCV
2 – Axle
With Trailer
Agri. Tractor
Without Trailer
The various vehicle types having different sizes and characteristics were converted into equivalent
passenger car unit. Passenger Car Unit (PCU) values are adopted from Indian Road Congress
publication on “Capacity of Roads in Rural areas”, IRC-64-1990 Table 1 and presented in table 4.3.
The directional classified traffic volume counts, observed at the count stations, are analysed to obtain:
Directional distribution
1:00-2:00 0 0 21 2 3 8 37 7 21 0 0 0 0 99 271.5
2:00-3:00 0 0 5 0 2 11 14 6 4 0 0 0 0 42 105.5
3:00-4:00 1 2 15 0 2 3 16 8 4 0 0 0 0 51 118
4:00-5:00 3 1 9 0 2 11 30 8 0 0 0 0 0 64 148
TOTAL Vehicles 3670 183 3636 217 588 886 1028 624 300 16 8 1135 8 12299 16046
PCU 1835 183 3636 325.5 1764 1329 3084 1872 1350 72 12 567.5 16 16046
2:00-3:00 0 0 10 0 4 2 21 20 9 0 0 0 0 66 188.5
3:00-4:00 0 0 1 0 0 2 6 3 7 0 0 0 0 19 62.5
TOTAL Vehicles 3619 129 3409 237 586 699 994 455 260 14 20 936 6 11364 14599.5
PCU 1809.5 129 3409 355.5 1758 1048.5 2982 1365 1170 63 30 468 12 14599.5
2:00-3:00 0 0 7 0 2 3 28 14 9 0 0 0 0 63 184
3:00-4:00 0 0 7 0 5 5 21 7 4 0 0 0 0 49 131.5
TOTAL Vehicles 3400 155 3550 207 555 622 1164 590 327 3 135 912 8 11628 15735
PCU 1700 155 3550 310.5 1665 933 3492 1770 1471.5 13.5 202.5 456 16 15735
4:00-5:00 0 0 11 0 1 7 27 13 3 0 0 0 0 62 158
TOTAL Vehicles 3857 186 3783 273 585 681 1060 759 437 19 169 1186 7 13002 17453
PCU 1928.5 186 3783 409.5 1755 1021.5 3180 2277 1966.5 85.5 253.5 593 14 17453
00:00-1:00 0 0 10 1 0 11 20 18 20 0 0 0 0 80 232
1:00-2:00 0 0 9 0 0 9 29 12 21 0 0 0 0 80 240
2:00-3:00 0 0 7 0 0 9 7 19 5 0 0 0 0 47 121
3:00-4:00 0 0 6 2 0 10 27 20 11 0 0 0 0 76 214.5
4:00-5:00 0 0 11 0 0 10 23 26 26 0 0 0 0 96 290
TOTAL Vehicles 3844 159 3622 288 534 872 938 599 415 16 8 723 5 12023 15979
PCU 1922 159 3622 432 1602 1308 2814 1797 1867.5 72 12 361.5 10 15979
1:00-2:00 0 0 9 0 8 9 35 24 0 0 0 0 0 85 223.5
2:00-3:00 0 0 5 1 7 6 20 29 0 0 0 0 0 68 183.5
3:00-4:00 0 0 11 0 4 3 45 23 0 0 0 0 0 86 231.5
TOTAL Vehicles 3221 134 3318 136 507 770 985 448 141 3 6 1242 5 10916 13529.5
PCU 1610.5 134 3318 204 1521 1155 2955 1344 634.5 13.5 9 621 10 13529.5
00:00-1:00 0 0 10 0 6 15 37 22 0 0 0 0 0 90 227.5
1:00-2:00 0 0 7 0 6 7 33 22 0 0 0 0 0 75 200.5
2:00-3:00 0 0 3 0 5 4 18 27 0 0 0 0 0 57 159
3:00-4:00 0 0 9 0 2 1 43 21 0 0 0 0 0 76 208.5
4:00-5:00 0 2 13 0 12 12 37 17 1 0 0 0 0 94 235.5
TOTAL Vehicles 3166 95 3270 103 459 722 937 400 116 2 1 1208 5 10484 12720
PCU 1583 95 3270 154.5 1377 1083 2811 1200 522 9 1.5 604 10 12720
09-08- 14599.
3619 129 3409 237 586 699 994 455 260 14 20 936 6 11364
2016 5
10-08-
3400 155 3550 207 555 622 1164 590 327 3 135 912 8 11628 15735
2016
11-08-
3857 186 3783 273 585 681 1060 759 437 19 169 1186 7 13002 17453
2016
12-08-
3844 159 3622 288 534 872 938 599 415 16 8 723 5 12023 15979
2016
13-08- 13529.
3221 134 3318 136 507 770 985 448 141 3 6 1242 5 10916
2016 5
14-08-
3166 95 3270 103 459 722 937 400 116 2 1 1208 5 10484 12720
2016
Average
Daily 3540 149 3513 209 545 750 1015 554 285 10 50 1049 6 11674 15152
Traffic
TOTAL
DATE DAY TOTAL PCU
VEHICLES
10000
8000
6000
4000
2000
0
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Day
TOTAL VEHICLES TOTAL PCU
2:00-3:00 0 0 6 0 3 6 21 22 9 0 0 0 0 67 193.5
3:00-4:00 0 0 9 0 2 5 28 16 6 0 0 0 0 66 181.5
4:00-5:00 2 1 12 0 5 12 31 16 11 0 1 1 0 92 238
16:00-17:00
9:00-10:00
00:00-1:00
10:00-11:00
11:00-12:00
12:00-13:00
13:00-14:00
14:00-15:00
15:00-16:00
17:00-18:00
18:00-19:00
19:00-20:00
20:00-21:00
21:00-22:00
22:00-23:00
23:00-00:00
6:00-7:00
7:00-8:00
8:00-9:00
1:00-2:00
2:00-3:00
3:00-4:00
4:00-5:00
5:00-6:00
Time Period
Passenger Vehicle Freight Vehicle
DATE = 10.08.2016
DAY = Wednesday
V-15 = 550
TOTAL Vehicles 3050 275 2591 141 572 1094 1164 894 607 68 96 531 37 11120 17654.5
PCU 1525 275 2591 211.5 1716 1641 3492 2682 2731.5 306 144 265.5 74 17654.5
Cycle Total
BUS LCV TRUCK Agri Tractor Cycle PCU
Three- Rickshaw Vehicle
Two- wheeler /
TIME Car/jeep/van/Taxi
wheeler auto
3- 4-6 With Without
rickshaw Mini FULL 2-Axle
Axle axle Trailer Trailer
TOTAL Vehicles 3061 302 3041 153 627 1322 1150 982 613 117 56 716 24 12164 19138
PCU 1530.5 302 3041 229.5 1881 1983 3450 2946 2758.5 526.5 84 358 48 19138
TOTAL Vehicles 2678 190 2671 122 557 1027 1185 730 473 66 43 673 36 10451 16238
PCU 1339 190 2671 183 1671 1540.5 3555 2190 2128.5 297 64.5 336.5 72 16238
TOTAL Vehicles 2562 174 2450 122 522 957 998 818 588 49 21 859 24 10144 15913
TOTAL Vehicles 2664 171 2646 102 533 1003 1161 706 454 50 276 249 34 10049 15881
PCU 1332 171 2646 153 1599 1504.5 3483 2118 2043 225 414 124.5 68 15881
4:00-5:00 1 0 14 0 0 11 21 13 6 0 0 0 0 66 160
5:00-6:00 5 0 16 0 6 21 22 11 7 0 0 0 0 88 198.5
TOTAL Vehicles 2627 164 2689 122 457 1223 1043 586 379 64 10 755 32 10151 14892
PCU 1313.5 164 2689 183 1371 1834.5 3129 1758 1705.5 288 15 377.5 64 14892
00:00-1:00 0 0 7 0 2 10 24 29 13 0 0 0 0 85 245.5
1:00-2:00 0 1 11 0 0 12 28 15 20 0 0 0 0 87 249
2:00-3:00 0 0 7 0 0 12 21 21 29 0 0 0 0 90 281.5
3:00-4:00 0 0 4 0 0 3 30 19 23 0 0 0 0 79 259
4:00-5:00 4 0 20 0 0 8 21 10 11 0 0 0 0 74 176.5
5:00-6:00 17 3 12 0 3 21 19 11 8 0 0 0 0 94 190
TOTAL Vehicles 2382 171 2454 133 525 1516 932 415 211 63 9 544 36 9391 13496
PCU 1191 171 2454 199.5 1575 2274 2796 1245 949.5 283.5 13.5 272 72 13496
08-08- 17654.
3050 275 2591 141 572 1094 1164 894 607 68 96 531 37 11120
2016 5
09-08-
3061 302 3041 153 627 1322 1150 982 613 117 56 716 24 12164 19138
2016
10-08-
2678 190 2671 122 557 1027 1185 730 473 66 43 673 36 10451 16238
2016
11-08-
2562 174 2450 122 522 957 998 818 588 49 21 859 24 10144 15913
2016
13-08-
2627 164 2689 122 457 1223 1043 586 379 64 10 755 32 10151 14892
2016
14-08-
2382 171 2454 133 525 1516 932 415 211 63 9 544 36 9391 13496
2016
Average
Daily 2718 207 2649 128 542 1163 1090 733 475 68 73 618 32 10496 16173
Traffic
20000
15000
Traffic
10000
5000
0
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Day
TOTAL VEHICLES TOTAL PCU
23:00-00:00 67 580.5
00:00-1:00 56 481.5
2:00-3:00 35 493.5
4:00-5:00 50 370.5
700
600
Traffic (PCU)
500
400
300
200
100
0
10:00-11:00
11:00-12:00
9:00-10:00
00:00-1:00
12:00-13:00
13:00-14:00
14:00-15:00
15:00-16:00
16:00-17:00
17:00-18:00
18:00-19:00
19:00-20:00
20:00-21:00
21:00-22:00
22:00-23:00
23:00-00:00
6:00-7:00
7:00-8:00
8:00-9:00
1:00-2:00
2:00-3:00
3:00-4:00
4:00-5:00
5:00-6:00
Time Period
DATE = 11.08.2018
DAY = Thursday
V-15 = 670
Survey Location KM 30 KM 41
Vehicle Category ADT Vehicles ADT (PCU) ADT Vehicles ADT (PCU)
Cycle Rickshaw 6 12 32 64
Table 4.5: Daily Fuel Sales and Seasonal Correction Factor (SCF) for calculating AADT
Survey Location KM 30 KM 41
Vehicle Category ADT Vehicles ADT (PCU) ADT Vehicles ADT (PCU)
Survey Location KM 30 KM 41
Vehicle Category ADT Vehicles ADT (PCU) ADT Vehicles ADT (PCU)
Trip length
The O-D survey was not limited to only car and buses in passenger vehicles category and trucks (LCV,
2 axle / 3 axle rigid, MAV) in freight vehicle category were too considered. The sample size of the
survey as percentage to the total traffic on the day of OD Survey is presented in Table, Sample Size of
OD Survey. The numbers in the table depicting the modal split for each zone is in percentage.
Zone 1 which consists of the Barpeta town attracts a TAT Two Axle Trucks
high percentage passenger private cars and two
MAT Multi Axle Trucks
wheelers as it is the economic hub of Barpeta district,
so a large number of commuters moves in and out of TWV Two Wheels Vehicles
the town for their day to day business. Zone 5 which
AT Agriculture Tractors
is the Kamrup(M) district provides connection to
Upper Assam districts which is the reason for attracting a large percentage of multi axle trucks. Zones
2 and 5 being in close proximity to Zone 1 and the proposed bypass attracts a huge percentage of slow
moving vehicles that are Two Wheels Vehicles (TWV) and Agriculture Trailers (AT). High volume of
through traffic moving to Zones 2 to 5 indicates the importance of the Project Road section as an
important corridor serving the inter-state traffic.
The next step in the estimation will include Traffic growth, Vehicle Operating Costs, Time saving
because of the proposed highway as well as the economic viability of the project
CHAPTER 5
DEVELOPMENT PROPOSALS
5 Developmental Proposals
5.1 General
As per TOR the concept of development & construction of the project highway for improvement and
capacity augmentation to 2 lane is for reduction in transport cost, enhanced safety & level of service for
road users, superior operation & maintenance ,enabling enhanced operation efficiency, replacement of
weak structure, construction of missing bridges & identification of black spots on project highway and
preparation of mitigation plan, alternative improvement proposals for project road to be prepared. The
existing alignment passes through Toposheet No. of (Scale: 1:50000) 83E5, 83E9 & 83E10. Key plan
& Location Plan are appended with Drawing Volume IX.
A detailed traffic survey for the project road has been conducted in the year August 2016. Detailed
traffic projections over the design life and growth rates obtained for different types of vehicles and
discussed in traffic survey and analysis chapter 4. For the purpose of pavement design, commercial
vehicles of gross vehicle weight more than 3 tonnes has been considered. Such vehicles consisted of
buses, LCVs, 2 axle trucks, 3 axle trucks and multi axle trucks.
Traffic volumes in terms of AADT at survey locations are used for the calculation of design MSA for
pavement design as given in Table 5.1
through revenue village of Barkumarpara, Gurimari 1st & 2nd part, Mowamari Chapori, Baghpori
Chapori, Bundia Chapori & Gelaidiang Chapori (Length 17.17 Km Approx.).
The existing road is of single Lane configurations. Hence for improvement to 2 Lane with Paved
Shoulder, Flexible pavement is proposed. The existing alignment is in serpentine and deteriorated
forma and could not be reused. To cover all the requirements of the pavement for the project road,
designs have been prepared in this Report and are as under.
Design Traffic
The Design cumulative standard axles calculated from the traffic survey is found to be 98.16 msa.
Therefore, for pavement design traffic of 100 msa is considered.
The minimum CBR of subgrade for pavement design is shall to be 8% as per IRC 37 clause 5.1.
Pavement Composition
Bituminous Concrete : 50 mm
Dense Bituminous Macadam : 115 mm
Wet Mix Macadam : 250 mm
Granular Sub-base (full width) : 200 mm
Total : 615 mm
The proposals for cross drainage structures are as follows in Table 5.3:
BOX New-
29 37887 CULVERT 1/23/1 Construction
BOX New-
30 38450 CULVERT 1/23/2 Construction
BOX New-
31 38765 CULVERT 1/33/1 Construction
BOX New-
32 39173 CULVERT 1/54/1 Construction
BOX New-
33 39260 CULVERT 1/54/1 Construction
BOX New-
34 39765 CULVERT 1/64/1 Construction
BOX New-
35 40193 CULVERT 1/54/1 Construction
BOX New-
36 40515 CULVERT 1/23/0 Construction
BOX New-
37 40889 CULVERT 1/23/0 Construction
BOX New-
38 41139 CULVERT 1/22/0 Construction
BOX New-
39 41376 CULVERT 1/22/0 Construction
BOX New-
40 41641 CULVERT 1/22/0 Construction
BOX New-
41 42117 CULVERT 1/22/0 Construction
BOX New-
42 42422 CULVERT 1/22/0 Construction
BOX New-
43 42650 CULVERT 1/22/0 Construction
5.5.6 JUNCTIONS
There are about 32 Nos. of major and minor junctions out of which 8 nos. T Junctions, and 24 nos. Y-
Junctions at various locations. The list of junctions along the project road is given in Table 5.5 below.
1. Traffic Signs and Pavement Markings: Traffic signs and pavement markings includes road
side signs, overhead signs, curve mounted signs and road marking along the project highway.
2. Concrete Crash Barrier, Metal beam crash barrier, Separators (MS railings)
3. The minimum length of 1.10 km Metal beam crash barrier, and minimum length of 13.115
km Separator (M.S. railings) all along built up area is proposed for safety of traffic & users.
4. Boundary Stones are proposed throughout the project road on both sides Hectometre /
Kilometre Stones.
5. Traffic solar blinker signals (L.E.D) are proposed at all intersections in consultation with
Authority’s Engineer.
6. Advertisement and Hoardings: No advertisements / hoardings are allowed to be erected on
Project Highway.
BUS BAY
Sl.No. Chainage Side
1 2300 LEFT
2 2447 RIGHT
3 8968 LEFT
4 9113 RIGHT
TRUCK LAY BYE
Sl.No. Chainage Side
1 12570 RIGHT
2 12779 LEFT
(i) For shifting of utilities such as, Electrical poles, Telephone poles, etc. the relevant
documents have been submitted to respective departments after the finalisation of alignment.
(ii) Strip plans for Land Acquisition have been submitted to the concerned department and the
Land Acquisition work is under process.
(iii) MOEF clearance is under process.
5.7 SCOPE OF WORK
The detailed scope of the work is as follows:
CHAPTER-6
COST ESTIMATES
6 Cost Estimate
6.1 General
Bill of Quantities (BOQ) and the project cost estimates has been prepared considering the various items
of works associated with identified construction proposals so as to assess the total cost of the project.
The cost estimates have been based on the available data/documents supplemented by the consultants’
surveys, site visits and experience in similar type of works. Rate analyses of major item of works have
been worked out to verify the adopted rates.
The proposed bypass at Mangaldai (from Km 26+400 to Km 41+480 of NH-15) is considered for cost
estimation for the project road stretch.
6.2 Methodology
Cost estimate methodology involves the following:
1. Site Clearance
2. Earthworks
3. Granular Base and Sub-Base Course
4. Bituminous Courses
5. Cross Drainage Works
6. Traffic Signals and Road Markings
7. Drainage Works
8. Bridges
Coarse Aggregates
Hard stone aggregate, fulfilling the requirements of concrete works, base, sub base and asphaltic works
are considered from the existing quarry. An average lead of 59 Km is considered for the cost estimation.
Fine Aggregate
Bitumen
Cement
Reinforcement
Rate Analysis for different items of works has been carried out based on Schedule of Rates for Roads,
Bridges and Culvert works for National Highways under Assam P.W. (Building & NH) Dept., for the
year 2013-14.
And, Total Project Cost of the project comes out to be Rs. 228.61 Crores with per km total project cost
is Rs. 13.37 Crores, including contingencies, R & R and LA, environmental etc.
N.B: -The cost considering for environmental and social are tentative and the exact cost for LA and
Environmental will finalized after getting approval/clearance from forest the revenue department.
Therefore, the total cost may vary from this amount.
The Summary of the Cost Estimate of Civil works is attached in Table 6.1 below.
Bill Cost
Item of works and Sub-Heads Unit Quantity
No (Rs. lakhs)
6 DRAINAGE WORKS
a) Longitudinal Drains & covered slab Mtr. 657 75.84
TRAFFIC SIGNS, MARKINGS AND OTHER
7 Km 17.100 43.96
ROAD APPURTENANCES
8 MAJOR / MINOR BRIDGE Mtr. 183.000 2143.998
9 BUSBAYS Nos. 4 451.72
10 TRUCK LAYBY Nos. 2 214.24
11 MAJOR JUNCTION ROAD Nos. 2 184.41
12 MINOR JUNCTION ROAD Nos. 54 906.64
13 SLIP ROAD Nos. 4 178.40
14 Footpath Mtr. 1053 73.36
15 PROTECTION WORK RM 1785 277.51
CHAPTER-7
Decision Model’ (SP – 38, February 1992) and Manual for HDM - 4 Version 1.3 (World Bank, 2000)).
These manuals are accepted by the World Bank, Ministry of Road Transport & Highways (MORT&H)
and National Highways Authority of India (NHAI) for highway projects in India.
The cost – benefit analysis is carried out by using the discounted cash flow (DCF) technique to obtain
the economic internal rate of return (EIRR) and economic net present value (ENPV) for the proposed
investments linked with the project. This is followed by a ‘sensitivity analysis’ carried out by increasing
or decreasing the critical factors affecting the cost and benefit streams of the proposed project, in order
to ascertain their effect on the economic feasibility indicators i.e. ENPV, EIRR. In broad terms, the
society costs pertaining to the highway development, to be considered in this analysis includes:
Agency Costs:
Capital Costs
Recurrent Maintenance Costs (Annual and Periodical)
Salvage Value
Road User Costs:
The lifetime of a road project for the present analysis is considered as the period for which
reliable traffic forecasts can be made. A discount rate is then applied to future economic
costs and benefits to arrive at the Net Present Value (NPV) of the project. The Economic
Internal Rate of Return (EIRR) of the project is also computed.
To analyse the cash flow at constant prices, an allowance is made for relative price inflation.
from road improvement. In HDM-4, economic analysis is carried out using Project Analysis Option,
which is concerned mainly with evaluation of investment options. The economic indicators such as the
EIRR and NPV at the discount rate of 12 % are calculated. In order to evaluate the pavement alternatives
selected, analysis has been carried out using “present value” method. This helps to compare the costs
related to the development using a particular type of pavement on present value terms. For carrying out
the same, all costs are estimated at the anticipated years and have been discounted to the present day
worth using a pre-determined discount rate. The analysis period of the project has considered 15 years
operation period from the completion of the improvements. Base year for the analysis is 2019. Hence
the period from 2019 to 2040 has been considered for economic evaluation for the project road.
Situations Analysed
The following alternatives have been considered in this analysis. The way of evaluating the economic
benefits from a proposed project is to compare the benefits with and without the project.
Case I (Without Project Situation): The first is a ‘without project’ (do minimum) where the
existing two lane project road is considered as such in its present condition and without
widening. In this case, the future traffic volume is assumed to continue to flow along the
existing road only.
Case II (With Project, Existing Road Situation): The second is a ‘with project’ condition
where we analyse the costs related to existing roads with minimum improvements but reduced
traffic flow.
Case III (With Project, Bypass Road Situation): The third situation is a ‘with project’
condition in which traffic diverted to Bypass from existing as well as nearby State Highways
will be evaluated.
By comparing the above alternatives, the net agency costs, the net user costs and the net project benefits
associated with the project during its analysis period of 15 years, are calculated for the proposed
improvement options. These calculations are performed in order to arrive at their economic internal rate
of return (EIRR) and economic net present value (ENPV). Based on the results of the analysis, the
economic feasibility for the project was determined.
The total constructions comes out to be around 93.14 crores. The planning and assumptions for the
construction phase are listed below:
The implementation of the construction phase will be in two periods, with 30% is projected to
be completed in 2020-21 and the remaining
Year Pc Completed Cost In Lakhs
30% will be done in 2021-2022 and 40 % in
2022-23. The division of the funds for the three
2020-21 30% 5853.9
years period construction is shown above.
The base year of calculation will be 2019 and 2021-22 30% 5853.9
the analysis will be done for a period of 15
years. 2022-23 40% 7805.2
Surface Dressing/Resealing
The data tabulated below has been collected from respective dealers, net of taxes and duties. For value
of passenger time as in Rs per hr and value of commodity in transit as Rs per day, recommended values
as per IRC SP-30 is expanded with WPI index and used in model.
Distance Related Factors which includes fuel, lubricants, engine oils, tyres and spare parts.
Time Related Factors which includes depreciation, fixed costs, Wages of crew, value of
passenger’s time and commodity in transit.
The vehicle operating costs for all different classified vehicles were obtained from IRC SP30:2009. The
characteristics of the existing pavement and proposed are required for deriving these unit costs and
those are presented below:
Now the next task will be multiplying the unit costs with the congestion factors for all the three cases
along with the traffic count of each type of vehicle for a year. The difference in VOC for sum of Case
II and Case III subtracted from Case I will give us the benefits from the project.
Capacity of the in- grade intersection connecting the major roads in Mangaldoi Town needs to
be have more traffic capacity as it is the major source of delay. Turn lanes needs to be
provided for a better flow of traffic.
The existing road has a T-Junction and a roundabout junction which consists of about 60
percent of the total road accidents in India
The total accident costs for the base year 2019-2020 is shown below for scenarios ‘Without Project’
and ‘With Project’.
CARS 50 5
BUSES 85 10
TWO WHEELERS 20 0
AGRIL TRACTOR/TRAILER 40 0
The exercise of traffic growth rate estimation has been carried out by us using the elasticity approach.
The elasticity method relates traffic growth to changes in the related economic parameters. According
to IRC: 108 – 2015, elasticity based econometric model for highway projects could be derived in the
following form:
A0 = Regression constant
The main steps followed are: Defining the project influence area from OD analysis of travel pattern.
Estimating the past elasticity of traffic growth from time series of registered vehicles of influencing
state(s). Assessment of future elasticity values for major vehicle groups, namely, car, bus and truck.
Study of past performance and assessment of perspective growth rates of state economies of influence
area. The elasticity values will be obtained by fitting log-log regression between the registered vehicle
types (car, bus and commercial vehicles) and NSDP, Population and Per-capita income of influencing
states and GDP of India. The regression analysis will be carried out using various combinations of
economic indicators and population of registered vehicles and the elasticity values resulted from the
best fit equations will be used in estimating growth rates.
Regression growth
Coefficient rate
forecasted
Population 3.1428 2
7.1.6.4 Results
Taking a weighted average of all the economic indicators we get a vehicle growth rath to be around
5.23%. We will be adding another 1 percent to counter the influence of neighbouring states. The growth
rate from 2022-2037 we will consider to be 6.5%.
The project road will be economically feasible as it satisfies all the necessary criterion:
Risk identification: The process of identifying all the risks associated with the project,
whether during its development phase, or its construction or operational phase.
Risk assessment: The process of determining the likelihood of the identified risks
materialising and the magnitude of their consequences if they do materialise.
Risk allocation: The process of allocating responsibility for dealing with the consequences of
each risk to one of the project stakeholders, or agreeing to share the risks.
Risk mitigation: The process of attempting to reduce the likelihood of the risk occurring and
the degree to its consequences for the risk-taker
The risk identification process can involve, wherever appropriate, participants such as project manager,
project team members, risk management team, subject matter experts from outside the project team,
customers. The project team should be involved in the identification process so that they can develop
and maintain a sense of ownership of the risks and associated risk mitigation actions. The major risks
identified for the project:
Pre Investment: Whether the granting authority can generate the fund for the initial
investments and land acquisition.
Time and Cost overrun in construction: The concessionaire has the right to start
construction at its own risk and will be responsible for excessive delay or cost during
construction.
Natural factors such as flood as the ROW is in low lying plain areas
Case B: Reduction in VOC, Time cost and Accident cost together are considered as project
benefit
Scenarios
Economic Parameters Derived
I II III IV
Net Present Value 4300 lakhs 1705 lakh 2693 lakh 675vlakh
The sensitivity analysis for scenarios I, II and III can be considered okay but for Scenario IV ENPV
takes negative value.
Table 7-h Sensitivity Analysis with VOC, VOT and Accident Costs
Cases
Economic Parameters Derived
A B
Conclusion
The project road section of NH-15 Mongoldoi Bypass economically feasible for the proposed widening
to four lanes considering the positive values of IRR (15.7%) and ENPV (Rs. 4300 Laskhs). It has also
been established that the proposal is economically feasible in the worst-case scenario developed in
sensitivity analysis (EIRR: 12%, ENPV: Rs.657 lakhs)..
CHAPTER-8
through grant. This covers aspects like financing through debt and equity, loan repayment, debt
servicing, taxation, depreciation, etc. The viability of the project is evaluated on the basis of Equity
IRR. The Equity IRR is estimated on the basis of cash flow analysis, where both costs and revenues
have been indexed to take account of inflation.
Fig. below shows the general toll plaza geometry of a 2+2 lane toll plaza. Initially, the numbers of lanes
become equal to the number of tollbooths, which is equal to three in Fig. 1, in the queueing area. After
the vehicle crosses the tollbooth, the number of lanes merges back to the original width of the highway,
i.e. two-lane. A lane for the extra wide and the exempted vehicles is provided at the left hand side of
the highway. Some extra space is also maintained for the scope of future plaza expansion. The design
specifications for the design of the flared portions are as listed below:
Transition - 1 in 10 may be provided from two-lane section to the widened width at Toll Plaza
on either side..
According to peak hourly factor and total traffic volume these will be the salient features of toll plaza:
Toll Plaza will have 4 total fee collection booths with two on each side.
IRC recommended lighting requirements for the toll plaza are followed.
Facilities such as departmental store, restaurants can rented out by the private contractor.
For this study we have considered 9 total scenarios and have derived the EIRR and PIRR for each
condition. The three important scenarios we will be considering:
Government Grant
Parameters
10% 30% 40%
EIRR 1 6 9
PIRR 6 10 12
Government Grant
Parameters
10% 30% 40%
EIRR 3 7 10
PIRR 7 11 13
Government Grant
Parameters
10% 30% 40%
EIRR 5 10 13
PIRR 9 13 15
The results leads us to the result that a Government Grant of 40% will give the Private concessionaire
a buffer region of 60-75 percent of tolled traffic. This will help in mitigating the risks associated with
the investment.