Primavera provide a tool called Progress Line to compare Actual Progress (Activity

% Complete) with Baseline on Gantt chart.

I will show you how to do it.

We have a simple project. It is assigned a Project Baseline.

Compare Actual Progress with Baseline on Gantt chart in Primavera P6 - 8

Then we will update the project.

Compare Actual Progress with Baseline on Gantt chart in Primavera P6 - 1

Activity A finish 2 days late so Activity B start late and now is behind schedule.

Activity C finish 2 days early so Activity D start early and now is ahead schedule.

Now we want to see the current progress in compare with baseline.

We can right click on Gantt chart -> Bar chart option.

Compare Actual Progress with Baseline on Gantt chart in Primavera P6 - 2

Go to Progress Line tab -> Select �By connecting progress points based on
activity�s� and �Percent Complete�

Compare Actual Progress with Baseline on Gantt chart in Primavera P6 - 3

Click OK. Go to menu View -> Progress Line.

Compare Actual Progress with Baseline on Gantt chart in Primavera P6 - 4

Now Primavera will show a vertical red line.

The line will go left if the activity is behind schedule.

The line will go right if the activity is ahead schedule.

Compare Actual Progress with Baseline on Gantt chart in Primavera P6 - 5

The point (where the red line connect) represent the Activity % Complete. But now
it show on Baseline bar so that we know the activity is late or early.

Activity B is 30% complete, then the progress line will be drawn 30% of the way
along the baseline bar.

Activity D is 70% complete, then the progress line will be drawn 70% of the way
along the baseline bar.

Compare Actual Progress with Baseline on Gantt chart in Primavera P6 - 6

So now by display the Progress Line we can quickly see which activity is behind
schedule and which activity is ahead schedule.

Note :

Normally the Progress line is only used to analyze on-going activity. It will be
drawn at same place with Data Date if:
The activity is a Milestone.
The activity does not exist in the baseline.
The activity is completed.
The activity is not started, and the baseline start is after or on the Data Date
How about �Remaining Duration� option

Compare Actual Progress with Baseline on Gantt chart in Primavera P6 - 9

If you select the �Remaining Duration� option, then the progress point will be
calculated as:
Progress Point = Baseline Finish � Remaining Duration.

Compare Actual Progress with Baseline on Gantt chart in Primavera P6 - 10

Progress point of Activity B = 03/Sep � 7 day = 28/Aug

Progress point of Activity D = 03/Sep � 3 day = 01/Sep

With this option we can also quickly see which activity is behind schedule and
which activity is ahead schedule.