Activity A finish 2 days late so Activity B start late and now is behind schedule.
Activity C finish 2 days early so Activity D start early and now is ahead schedule.
Go to Progress Line tab -> Select �By connecting progress points based on
activity�s� and �Percent Complete�
The point (where the red line connect) represent the Activity % Complete. But now
it show on Baseline bar so that we know the activity is late or early.
Activity B is 30% complete, then the progress line will be drawn 30% of the way
along the baseline bar.
Activity D is 70% complete, then the progress line will be drawn 70% of the way
along the baseline bar.
So now by display the Progress Line we can quickly see which activity is behind
schedule and which activity is ahead schedule.
Note :
Normally the Progress line is only used to analyze on-going activity. It will be
drawn at same place with Data Date if:
The activity is a Milestone.
The activity does not exist in the baseline.
The activity is completed.
The activity is not started, and the baseline start is after or on the Data Date
How about �Remaining Duration� option
If you select the �Remaining Duration� option, then the progress point will be
calculated as:
Progress Point = Baseline Finish � Remaining Duration.
With this option we can also quickly see which activity is behind schedule and
which activity is ahead schedule.