Académique Documents
Professionnel Documents
Culture Documents
June 4, 2004]
DECISION
PUNO, J.:
The case at bar arose from the complaint for damages filed by
spouses Jose Tabusares, Sr. and Rebecca Tabusares against
petitioners, Endreo A. Magbanua, Vallacar Transit, Inc., and/or its
corporate officials for the tragic death of their son, Jury Tabusares, in
a vehicular mishap involving a Ceres Liner Bus owned and operated
by petitioners. The case was docketed as Civil Case No. 4654 before
the Regional Trial Court of Negros Occidental, Branch
48, Bacolod City.
The facts, as found by the trial court, are as follows:
At about 4:30 oclock in the afternoon of October 25, 1986, a Ceres Liner
Bus No. 154 with Plate No. GVG 469, driven by Endreo Magbanua and
owned and operated by Vallacar Transit, Inc., and an Amante Type Jeepney
bearing Plate No. FBN 996, driven by Felipe Palacios and owned by
Salvador Algara, Sr. figured in a vehicular accident along the national road
at Hda. Mabuhay, Gil Montilla, Sipalay, Negros Occidental. The Ceres
Liner Bus bumped the rear portion of the Amante Type Jeepney while both
vehicles were running downhill on the same direction towards the town
of Sipalay from the North. Due to the impact, several passengers of the
Amante Type Jeepney were thrown out and ran over by the Ceres Liner Bus
and died as a result of the injuries they sustained. (O)ne of those killed was
Jury Tabusares, 27 years of age, single, an employee of the Maricalum
Copper Mines as Oiler 2B and was then receiving P1,256.00 monthly salary
plus P510.00 cost of living allowance (COLA) or a total monthly income
of P1,766.00. Jury Tabusares was the son of the plantiffs Jose Tabusares, Sr.
and Rebecca Tabusares. Immediately before the bumping accident, the
Ceres Liner Buss driver, Endreo Magbanua, was trying to overtake the
Amante Type Jeepney ahead of him and he said that he did not apply his
brakes because he cannot overtake if he will slow down. The Amante Type
Jeepney was overloaded with 35 passengers and some of them clinging on
its sides and some were riding on the roof. While the Ceres Liner (B)us was
about one and a half (1) meters from the Amante Type Jeepney, the bus
driver saw that the jeepney went zigzagging on the middle of the road and
since he could not control the bus anymore it bumped the rear portion of the
jeep.
After a careful perusal of the circumstances of the case, the (c)ourt finds that
the Amante Type Jeepney, as testified to by its own driver, Felipe Palacios,
was not a passenger jeepney but a private vehicle which is used by its owner
Salvador Algara, Sr., who is an ambulant peddler in his peddling
business. But, although not for passengers, it was carrying 35 passengers at
the time of the bumping accident on October 25, 1986 as testified to by
Traffic Investigator Pfc. Praxedes Campillanos of the Sipalay Police
Command, Sipalay, Negros Occidental. This jeep had a seating capacity of
only 16 passengers but it was made to accommodate passengers on its roof
and some were clinging on its side. This act is not only gross negligence but
it was violative of the traffic rules and regulations. On the other hand, the
(c)ourt also finds that the driver of the Ceres Liner Bus was driving his
vehicle negligently and recklessly because Endreo Magbanua testified and
admitted that while driving the bus downhill and following the Amante type
Jeepney ahead of him, he did not apply his brakes because he was trying to
overtake when he bumped the jeep on its rear portion. This act was
negligent and reckless because Endreo Magbanua could have avoided the
bumping of the jeepney had he applied his brakes considering that he has the
last clear chance to prevent a collision by slowing down and reducing
speed.[1]
The trial court found that the negligent acts of the drivers of both
the jeepney and the Ceres Liner Bus combined in directly causing the
death of Jury Tabusares. It therefore held both drivers solidarily liable
for damages. The court ruled:
SO ORDERED. [2]
During the pendency of the appeal, Jose Tabusares, Sr. and his
wife, Rebecca, passed away. On May 18, 1999, the Court of Appeals
approved the substitution of the late spouses by their heirs,
namely: Jose Tabusares, Jr., Eva T. Lafiguera, Nona C. Tabusares,
Jun C. Tabusares, Fe C. Tabusares and Jax C. Tabusares. [4]
In the case at bar, the victim Jury Tabusares was twenty- seven (27) years
old at the time of death. With 65 years as the given life expectancy in
the Philippines, the victim was expected to live for another thirty-eight (38)
years. In respect of income, the victim was receiving the amount
of P1,766.00 as total monthly income or a gross yearly income
of P21,192.00. Multiplied by 38, the number of years the victim is expected
to continue living, the amount arrived at is P748,784.00 using the formula
2/3 x [80-27] x 21,192.00. From the said figure must be deducted the
reasonable amount of P374,392.00 or 50% thereof representing the living
and other necessary expenses of the deceased had he continued to
live. Hence, the lost earnings of the deceased should be P374,392.00.
[5]
of Appeals one year and six months after the promulgation of People
vs. Muyco, therefore, the Court should apply the computation in the
latter case.[10]
(the award of damages for loss of earning capacity is) concerned with the
determination of the losses or damages sustained by the private respondents,
as dependents and intestate heirs of the deceased, and that said damages
consist, not of the full amount of his earnings, but of the support they
received or would have received from him had he not died in consequence
of the negligence of petitioners agent. In fixing the amount of that support,
we must reckon with the necessary expenses of his own living, which should
be deducted from his earnings. Thus, it has been consistently held that
earning capacity, as an element of damages to ones estate for his death by
wrongful act is necessarily his net earning capacity or his capacity to acquire
money, less the necessary expense for his own living. Stated otherwise, the
amount recoverable is not loss of the entire earning, but rather the loss of
that portion of the earnings which the beneficiary would have received. In
other words, only net earnings, not gross earning are to be considered that is,
the total of the earnings less expenses necessary in the creation of such
earnings or income and less living and other incidental expenses.
vs. Borja that when there is no showing that the living expenses
[15]
In other words, only net earnings, not gross earnings, are to be considered;
that is, the total of the earnings less expenses necessary in the creation of
such earnings or income, less living and other incidental expenses. When
there is no showing that the living expenses constituted a smaller
percentage of the gross income, we fix the living expenses at half of the
gross income. To hold that one would have used only a small part of the
income, with the larger part going to the support of ones children,
would be conjectural and unreasonable. (emphasis supplied)
YNARES-SANTIAGO, J.,
Chairperson,
CARPIO MORALES,*
- versus - CHICO-NAZARIO,
NACHURA, and
PERALTA, JJ.
MALAYAN INSURANCE Promulgated:
COMPANY, INC.,
Respondent. April 7, 2009
x- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
-x
DECISION
CHICO-NAZARIO, J.:
The instant Petition for Review under Rule 45[1]of the Rules of Court
assails the Decision[2] dated 26 June 2002 of the Court of Appeals in
CA-G.R. SP No. 67297, which granted the Petition for Certiorari of
respondent Malayan Insurance Company, Inc. (MICI) and recalled and
set aside the Order[3] dated 6 September 2001 of the Regional Trial Court
(RTC), Branch 73, of Antipolo City, in Civil Case No. 93-2705. The RTC,
in its recalled Order, denied the Notice of Appeal of MICI and granted
the Motion for the Issuance of a Writ of Execution filed by petitioners
Heirs of George Y. Poe. The present Petition also challenges the
Resolution[4] dated 29 November 2002 of the appellate court denying
petitioners Motion for Reconsideration.
Records show that on 26 January 1996 at about 4:45 a.m., George Y. Poe
(George) while waiting for a ride to work in front of Capital Garments
Corporation, Ortigas Avenue Extension, Barangay Dolores, Taytay, Rizal,
was run over by a ten-wheeler Isuzu hauler truck with Plate No.
PMH-858 owned by Rhoda Santos (Rhoda), and then being driven by
Willie Labrador (Willie).[5] The said truck was insured with respondent
MICI under Policy No. CV-293-007446-8.
To seek redress for Georges untimely death, his heirs and herein
petitioners, namely, his widow Emercelinda, and their children Flerida
and Fernando, filed with the RTC a Complaint for damages against
Rhoda and respondent MICI, docketed as Civil Case No.
93-2705.[6] Petitioners identified Rhoda and respondent MICI, as follows:
Defendant RHODA SANTOS is likewise of legal age, Filipino and a
resident of Real Street, Pamplona, Las Pias, Metro Manila where she
may be served with summons and other court processes.
Other reliefs just and equitable in the premises are likewise prayed
for.[8]
Rhoda and respondent MICI made the following admissions in their Joint
Answer[9]:
Rhoda and respondent MICI denied liability for Georges death averring,
among other defenses, that: a) the accident was caused by the negligent
act of the victim George, who surreptitiously and unexpectedly crossed
the road, catching the driver Willie by surprise, and despite the latters
effort to swerve the truck to the right, the said vehicle still came into
contact with the victim; b) the liability of respondent MICI, if any, would
attach only upon a judicial pronouncement that the insured Rhoda and her
driver Willie are liable; c) the liability of MICI should be based on the
extent of the insurance coverage as embodied in Rhodas policy; and d)
Rhoda had always exercised the diligence of a good father of a family in
the selection and supervision of her driver Willie.
5. P50,000.00 for attorneys fees plus P1,500 per court appearance; and
6. Cost of suit.[19]
Rhoda and respondent MICI received their copy of the foregoing RTC
Decision on 14 March 2000.[20] On 22 March 2000, respondent MICI and
Rhoda filed a Motion for Reconsideration[21] of said Decision, averring
therein that the RTC erred in ruling that the obligation of Rhoda and
respondent MICI to petitioners was solidary or joint and several; in
computing Georges loss of earning capacity not in accord with
established jurisprudence; and in awarding moral damages although it
was not buttressed by evidence.
Resolving the Motion of respondent MICI and Rhoda, the RTC issued an
Order[22] on 24 January 2001 modifying and amending its Decision
dated 28 February 2000, and dismissing the case against respondent
MICI.
Respondent MICI received a copy of the 15 June 2001 Order of the RTC
on 27 June 2001.
Aggrieved by the latest turn of events, respondent MICI filed on 9
July 2001 a Notice of Appeal[28] of the 28 February 2000 Decision of the
RTC, reinstated by the 15 June 2001 Resolution of the same court. Rhoda
did not join respondent MICI in its Notice of Appeal.[29]
After considering the recent pleadings of the parties, the RTC, in its
Order dated 6 September 2001, denied the Notice of Appeal of
respondent MICI and granted petitioners Motion for the Issuance of Writ
of Execution. The RTC reasoned in its Order:
The records disclosed that on February 28, 2000 this Court rendered a
Decision in favor of the [herein petitioners] and against [Rhoda and
herein respondent MICI]. The Decision was said to have been received
by MICI on March 14, 2000. Eight days after or on March 22, 2000,
MICI mailed its Motion for Reconsideration to this Court and granted
the same in the Order dated January 24, 2001. From this Order,
[petitioners] filed a Motion for Reconsideration on February 21,
2001 to which MICI filed a vigorous opposition. On June 15, 2001 this
Court granted [petitioners] motion reinstating the Decision
dated February 28, 2000. According to MICI, the June 15, 2001 order
was received by it on June 27, 2001. MICI filed a Notice of Appeal
on July 9, 2001 or twelve (12) days from receipt of said Order.
[Petitioners] contend that the Notice of Appeal was filed out of time
while [respondent] MICI opposes, arguing otherwise. The latter
interposed that the Order dated June 15, 2001 is in reality a new
Decision thereby giving it a fresh fifteen (15) days within which to file
notice of appeal.
The aforesaid conclusion finds support in Sta. Romana vs. Lacson (104
SCRA 93), where the court, relying on the case of Magdalena Estate,
Inc. vs. Caluag, 11 SCRA 334, held that where the court of origin
made a thoroughly (sic) restudy of the original judgment and rendered
the amended and clarified judgment only after considering all the
factual and legal issues, the amended and clarified decision was an
entirely new decision which superseded (sic). For all intents and
purposes, the court concluded the trial court rendered a new judgment
from which the time to appeal must be reckoned.
I.
II.
The Court first turns its attention to the primary issue for its
resolution: whether the Notice of Appeal filed by respondent MICI before
the RTC was filed out of time.
The period for filing a Notice of Appeal is set by Rule 41, Section
3 of the 1997 Rules of Court:
SEC. 3. Period of ordinary appeal. The appeal shall be taken
within fifteen (15) days from notice of the judgment or final order
appealed from. Where a record on appeal is required, the appellants
shall file a notice of appeal and a record on appeal within thirty (30)
days from notice of the judgment or final order. x x x.
The Court has accentuated that the fresh period rule is not
inconsistent with Rule 41, Section 3 of the Rules of Court which states
that the appeal shall be taken within fifteen (15) days from notice of
judgment or final order appealed from. The use of the disjunctive word or
signifies disassociation and independence of one thing from another. It
should, as a rule, be construed in the sense which it ordinarily
implies.[42] Hence, the use of or in the above provision supposes that the
notice of appeal may be filed within 15 days from the notice of judgment
or within 15 days from notice of the final order in the case.
Applying the fresh period rule, the Court agrees with the Court of
Appeals and holds that respondent MICI seasonably filed its Notice of
Appeal with the RTC on 9 July 2001, just 12 days from 27 June 2001,
when it received the denial of its Motion for Reconsideration of the 15
June 2001 Resolution reinstating the 28 February 2000 Decision of the
RTC.
Hence, the fresh period rule laid down in Neypes was applied by
the Court in resolving the subsequent cases of Sumaway v. Urban Bank,
Inc.,[44] Elbia v. Ceniza,[45]First Aqua Sugar Traders, Inc. v. Bank of the
Philippine Islands,[46] even though the antecedent facts giving rise to said
cases transpired before the promulgation of Neypes.
Since the Court affirms the ruling of the Court of Appeals that respondent
MICI filed its Notice of Appeal with the RTC within the reglementary
period, the appropriate action, under ordinary circumstances, would be
for the Court to remand the case to the RTC so that the RTC could
approve the Notice of Appeal of respondent MICI and respondent MICI
could already file its appeal with the Court of Appeals.
However, considering that the case at bar has been pending for almost
sixteen years,[48] and the records of the same are already before this Court,
remand is no longer necessary.
Jurisprudence dictates that remand of a case to a lower court does not
follow if, in the interest of justice, the Supreme Court itself can resolve
the dispute based on the records before it. As a rule, remand is avoided in
the following instances: (a) where the ends of justice would not be
subserved by a remand; or (b) where public interest demands an early
disposition of the case; or (c) where the trial court has already received
all the evidence presented by both parties, and the Supreme Court is in a
position, based upon said evidence, to decide the case on its
merits.[49] In Lao v. People,[50] the Supreme Court, in consideration of the
years that it had taken for the controversy therein to reach it, concluded
that remand of the case to a lower court was no longer the more
expeditious and practical route to follow, and it then decided the said case
based on the evidentiary record before it.
The consistent stand of the Court has always been that a case should be
decided in its totality, resolving all interlocking issues in order to render
justice to all concerned and to end the litigation once and for all. Verily,
courts should always strive to settle the entire controversy in a single
proceeding, leaving no root or branch to bear the seed of future
litigation.[51] Where the public interest so demands, the court will broaden
its inquiry into a case and decide the same on the merits rather than
merely resolve the procedural question raised.[52] Such rule obtains in this
case.
The complete records of the present case have been elevated to this
Court, and the pleadings and evidence therein could fully support its
factual adjudication. Indeed, after painstakingly going over the records,
the Court finds that the material and decisive facts are beyond dispute:
George was killed when he was hit by the truck driven by Willie, an
employee of Rhoda; and the truck is insured with respondent MICI. The
only issue left for the Court to resolve is the extent of the liability of
Rhoda and respondent MICI for Georges death and the appropriate
amount of the damages to be awarded to petitioners.
The Court now turns to the issue of who is liable for damages for
the death of George.
The Court highlights that in this case, the insurance policy between
Rhoda and respondent MICI, covering the truck involved in the accident
which killed George, was never presented. There is no means, therefore,
for this Court to ascertain the supposed limited liability of respondent
MICI under said policy. Without the presentation of the insurance policy,
the Court cannot determine the existence of any limitation on the liability
of respondent MICI under said policy, and the extent or amount of such
limitation.
Respondent MICI had all the opportunity to prove before the RTC
that its liability under the insurance policy it issued to Rhoda, was limited;
yet, respondent MICI failed to do so. The failure of respondent MICI to
rebut that which would have naturally invited an immediate, pervasive,
and stiff opposition from it created an adverse inference that either the
controverting evidence to be presented by respondent MICI would only
prejudice its case, or that the uncontroverted evidence of petitioners
indeed speaks of the truth. And such adverse inference, recognized and
adhered to by courts in judging the weight of evidence in all kinds of
proceedings, surely is not without basis its rationale and effect rest on
sound, logical and practical considerations, viz:
The presumption that a man will do that which tends to his obvious
advantage, if he possesses the means, supplies a most important test for
judging of the comparative weight of evidence x x x If, on the
supposition that a charge or claim is unfounded, the party against
whom it is made has evidence within his reach by which he may repel
that which is offered to his prejudice, his omission to do so supplies a
strong presumption that the charge or claim is well founded; it would
be contrary to every principle of reason, and to all experience of
human conduct, to form any other conclusion. (Starkie on Evidence, p.
846, Moore on Facts, Vol. I, p. 544)
xxxx
The ordinary rule is that one who has knowledge peculiarly within his
own control, and refuses to divulge it, cannot complain if the court puts
the most unfavorable construction upon his silence, and infers that a
disclosure would have shown the fact to be as claimed by the opposing
party." (Societe, etc., v. Allen, 90 Fed. Rep. 815, 817, 33 C.C.A. 282,
per Taft, C.J., Moore on Facts, Vol. I, p. 561).[63]
The inference still holds even if it be assumed, for argument's sake, that
the solidary liability of respondent MICI with Rhoda is improbable, for it
has likewise been said that:
As regards the award of actual damages, Article 2199 of the Civil Code
provides that [e]xcept as provided by law or by stipulation one is entitled
to an adequate compensation only for such pecuniary loss suffered by
him as he has duly proved x x x.
Article 2206 of the Civil Code provides that in addition to the indemnity
for death caused by a crime or quasi-delict, the defendant shall be liable
for the loss of the earning capacity of the deceased, and the indemnity
shall be paid to the heirs of the latter, x x x. Compensation of this nature
is awarded not for loss of earnings but for loss of capacity to earn
money. Hence, it is proper that compensation for loss of earning capacity
should be awarded to the petitioners in accordance with the formula
established in decided cases for computing net earning capacity, to wit:
Jurisprudence provides that the first factor, i.e., life expectancy, shall be
computed by applying the formula (2/3 x [80 - age at death]) adopted in
the American Expectancy Table of Mortality or the Actuarial of
Combined Experience Table of Mortality.
If:
The RTC also awarded P50,000.00 as death indemnity which the Court
shall not disturb. The award of P50,000.00 as death indemnity is in
accordance with current rulings of the Court.[75]
No costs.
SO ORDERED.
[G.R. No. 134239. May 26, 2005]
DECISION
CHICO-NAZARIO, J.:
1 This lease will be for a period of one (1) year only, from January 1, 1989
and will terminate on the 31st of December 1989 at a monthly rental of
FOUR THOUSAND PESOS (P4,000.00). (Exhibit 1-A-1 De Mesa).
As regards Lot 2948-B of the Daleon brothers, the Villafuertes were not as
lucky. For, instead of obtaining a lease renewal, what they received were
demand letters from the brothers counsel ordering them to vacate the
premises. Instead of complying therewith, the Villafuertes simply ignored
the demand and continued operating the gas station (Exhibits 3-B, 3-C and
3-F, Daleon).
With their problem with the Daleon brothers far from over, the Villafuertes
were apt for another one; their lease contract with Edilberto de Mesa was
not renewed when it expired on December 31, 1989. Nonetheless, and
duplicating what they had done in the case of the property of the Daleon
brothers, the spouses continued to operate their gasoline station and other
businesses on the lot of de Mesa despite the latters demand to vacate.
After hearing the parties in connection with the plaintiffs application for a
writ of preliminary mandatory injunction, the lower court, in its order of
May 23, 1990, ruled that with the expiration of the lease on the defendants
property, the plaintiffs have no more right to stay thereon and, therefore,
cannot pretend to have a clear and unmistakable right to an injunctive writ
and accordingly denied their application therefore (Rec., p. 186). In a
subsequent order of July 30, 1990, the same court denied the Villafuertes
motion for reconsideration (Rec., p. 237).
Later, with leave of court, the Villafuertes amended their complaint to allege,
among others, that the complained acts of the defendants cost them the
following items of actual damages:
TOTAL -- P2,176,293.44
B - Ordering the defendants to pay jointly and severally the plaintiffs the
following:
D - Granting the plaintiffs such other just and equitable remedies to which
they may be entitled under the law and equity. (Orig. Rec., pp. 292-293).
As later events disclosed, the defendants resumed possession of the premises
in question on January 25, 1991 (Rec., p. 333). Four (4) days later, they
obtained a judgment by compromise from the Municipal Trial Court in
Cities, Lucena City in connection with the suit for ejectment they earlier
filed thereat against Petrophil Corporation. In that judgment, Petrophil
bound itself to remove the materials and equipment related to the operation
of the gasoline station on the subject premises. (Rec., pp. 355-356).
After the parties herein had presented their respective evidence, the lower
court came out with the decision now under review. Dated November 13,
1990, the decision dispositively reads:
5. Costs of suit.
and by holding the appellees jointly and severally liable for rental to
appellants Edilberto de Mesa and Gonzalo Daleon in the amount of
P5,500.00 and P39,000.00, respectively.
damages, the claimant bears the onus of presenting before the court
actual proof of the damages alleged to have been suffered, thus:
claimed amounts based on the average of her sales for the month of
January 1990, the number of trips undertaken by their tankers, and
average volume of the gasoline deposit for RECOM IV. Her testimony
on these matters went as follows:
Atty. CAMALIGAN:
May I ask that this List of Unrealized Income, Collectibles and Damages
from Febrauary 1, 1990 to October 30, 1990 be marked as Exhibit AA.
...
Q: Will you explain to the court why this list you made is up to October 30,
1990?
A: I prepared this list until October 10, 1990 in preparation for our first
hearing sometime in November, sir.
Q: I am calling your attention to No. 1 which is I quote, Daily Sales (4,000 to
5,000 liters) at P0.035 per liter mark up P1,750.00 by 270 days
amounting to P472,500.00 will you explain to the court how you incurred
this damage?
(A): After the closure of our gasoline station that was February 1, 1990 and
then until September, 1990 is nine (9) months and that is 270 days. I
went thru my sales for January and the average sales (is) 4,000 to 5,000
liters and so for our daily sales of 4,000 to 5,000 liters sale at P0.35
centavos mark-up, I got P1,750.00 daily so that is times 270 days until
September 1990, the total is P472,500.00, sir.
COURT: That is gross?
A: Yes, your Honor.
COURT: What about the net income to be realized?
A: Your Honor, we will deduct from here the salaries and wages of the
gasoline boys and electric bill, maybe P0.25 centavos per liter.
COURT: Proceed.
Q: Is the mark-up of P0.35 centavos per liter thru (sic), irrespective of amount
of gasoline or value of gasoline per liter?
A: We have different kinds of petroleum products, extra, regular and diesel
and the average mark-up is thirty-five (35) centavos.
...
Q: Calling your attention to No. 2 in the list which refers to storage fee of
petroleum, oil and lubricant from RECOM IV amounting to a total of
ninety thousand pesos (P90,000.00) will you kindly explain how you
arrived at this amount?
A: The military, PC/INP RECOM IV which is stationed at Camp Nakar has
entered into an agreement with us to deposit their petroleum, oil and
lubricant for every quarter, sir.
Q: Under what condition was that deposit made for?
A: That they will be able to withdraw the said products for a certain storage
fee, sir, and the storage fee is 5% which would cover disposing the
products and also certain percent of evaporation.
COURT: Five percent of what?
A: Five percent of the number of liters deposited with us so that if they
deposited one hundred thousand (100,000) liters we are paid in terms of
gasoline also, five thousand (5,000) liters.
Q: What was the average volume of deposit made by the RECOM IV?
A: It is on a quarterly basis, that is one hundred thousand (100,000) liters
quarterly, sir.
Q: On item 3 referring to tires, batteries, accessories, general merchandise is
listed an amount of ninety thousand (P90,000.00) pesos as your losses,
will you please explain how you incurred such losses?
A: Aside from petroleum products we also sell accessories for the motoring
public and they are in kinds like tires, batteries and some additives, how
do you realize income out of this? (sic)
A: We have 20% mark-up on the merchandise and last January 1990 I
average fifty thousand (P50,000.00) pesos gross income on the general
merchandise so for 20% mark-up that is more or less ten thousand
(P10,000.00) pesos and for nine (9) months that is ninety thousand
(P90,000.00) pesos, sir.
Q: In item No. 4 appearing in your list you listed a total amount of one
hundred eight thousand (P108,000.00) pesos, for hauling of petroleum
products for Peewees Petron Powerhouse, will you explain to the court
this hauling?
A: My husband and I run a fleet of gasoline tankers and they are hauling
petroleum products for our gasoline stations and for the military
accounts. We average two (2) deliveries every week so this is already a
net of one thousand five hundred (P1,500.00) pesos per delivery. It is
two thousand eight hundred (P2,800.00) pesos per delivery and
deducting the salaries of the drivers, the fuel consumption and the
depreciation of the tankers, we incur a net of one thousand five hundred
(P1,500.00) pesos per trip. Every month we incur at least eight (8) trips
and that is one thousand five hundred (P1,500.00) pesos times eight (8)
trips times nine (9) months and I got one hundred eight thousand
(P108,000.00) pesos total.
Q: Do you own them?
A: Yes, sir.
Q: In item No. 6 you listed Balloon Business under Sunshine Balloon, you
have given a total amount of two hundred thousand (P200,000.00)
pesos as your losses here, will you please explain to the Court how you
incurred these losses?
...
A: Inside the gasoline station we also operate a balloon business and we
have invested fifty thousand capital on this balloon business. This
business has been thriving for several years and we usually incur six (6)
thousand monthly income from said business, sir. Now that the gasoline
station was closed with all the equipments of the balloon business inside
also, we have totally lost the market for the balloon business and I feel
that two hundred thousand (P200,000.00) pesos would have to be paid
for the total loss of the business.[21]
of their total value. As for the items entrusted to her by the Hermana
Fausta Memorial Foundation of which she was the executive vice
president at that time, petitioner Perlita alleged that the amount of five
thousand pesos represents the production cost of these materials
which the foundation purportedly paid to Imprenta Lucentina. As
regards the amount of P30,000.00 sought as actual damages for the
damaged office equipment, petitioner Perlita stated before the trial
court that she arrived at this figure after computing the acquisition
costs of these equipment which she approximated to [24]
be P35,000.00.
Evidently, in establishing the amount of actual damages for the
merchandise inventory, office equipment, and materials owned by the
Hermana Fausta Memorial Foundation, petitioners relied solely on
their own assessment of the prices of these items as well as the
damage thereto purportedly occasioned by the fencing of the gasoline
station. This is clearly demonstrated by the inconsistent stance of
petitioner Pertlita with regard to the percentage of damaged
merchandise stored in the gasoline station, thus:
ATTY. CAMALIGAN:
Q: I noticed that the total appearing on page 3 of your merchandize inventory
is one hundred forty one thousand thirty six pesos and fifty centavos
(P141,036.50) only while in your list, it is ninety eight thousand seven
hundred twenty five pesos and fifty five centavos (P98,725.55), will you
please explain the same?
WITNESS:
A: This list with the total amount of one hundred forty one thousand thirty six
pesos and fifty centavos (P141,036.50) represent the total value of all
the merchandize but then the reason why we have the ninety eight
thousand seven hundred twenty five pesos and fifty five centavos
(P98,725.55) figure is, this represents seventy percent (70%) of the total
amount because when we retrieved the merchandize, we noticed that
most of them are already defective, so we valued the damages only
seventy percent (70%) of the total value because some of them could
still be sold, sir.
ATTY. CAMALIGAN:
Q: I noticed there is a correction in Item No. 9 from ninety percent (90%) to
seventy percent (70%). When did you make that correction?
A: Only last December 30, 1990 after we have retrieved all the merchandize.
I prepared this list on October 31, 1990 not realizing the extent of the
real damages to the merchandize but when we retrieved them last
December 29 and upon inspection, most of the motor oil have already
leaked because of the plastics that were exposed to sun and rain, so we
changed the estimate to seventy percent (70%), sir.[25]
The appellees failed to adduce convincing evidence that appellants are the
[31]
ones responsible for the loss of the petroleum products in the four (4)
underground tanks (item 1, paragraph 10 of Amended Complaint). Although
the premises which were fenced by the appellants adjoin the lot of Perlitas
[32]
mother and are even secured by appellees guard, the appellees did not
present anyone to testify on the fact of loss of said gasoline products.
Instead, they chose to rely on Perlitas bare assertion that she
lost P249,805.00 in terms of petroleum products that allegedly disappeared.
The sheer volume of the missing fuel makes it difficult for the pilferer to
commit the deed without attracting attention. An unsubstantiated claim of
loss, more so of such a dimension, cannot merit an award therefor.
[33]
charge private respondents for the interest payments for this loan the
proceeds of which were utilized to finance petitioners various
businesses and not solely the settlement of petitioners obligations to
the suppliers of Peewees Petron Powerhouse. In the absence of
actual proof as to how much of the RCBC loan was really used to pay
the creditors of the closed gasoline station, this Court can not affirm
petitioners right to be compensated for the amount of interest
payments they have made to the RCBC.
We find, however, that an award of temperate damages to
petitioners is in order. In lieu of actual damages, temperate damages,
which are more than nominal but less than compensatory damages,
may be awarded where the court finds that some pecuniary loss had
been suffered by the claimant but its amount cannot be proved with
certainty. Undoubtedly, pecuniary loss had been inflicted upon
petitioners in this case, however, due to the insufficiency of evidence
before us, we cannot place its amount with certainty. In this regard,
we find the amount of P50,000.00 to be sufficient.
Petitioners also assail the removal by the Court of Appeals of the
moral damages previously ordered by the trial court. They argue that
contrary to the findings of the appellate court, they came to court with
clean hands as they believed that the lease contract with private
respondent De Mesa was modified and extended. At the same time,
they contend that they had a verbal understanding with private
respondent Daleon wherein the latter permitted them to remain in his
lot for as long as Petron Corporation was not removing its equipment.
Further, petitioners contend that under Article 2219 of the Civil Code,
this Court had awarded moral damages in instances where the
claimants were victims of capricious, wanton, oppressive, malicious,
and arbitrary acts such as petitioners in this case. On this issue, we
agree in the findings of the Court of Appeals that:
The Court must have to disallow the lower courts award of moral damages.
The concept of moral damages, as announced in Article 2217 of the Civil
Code, is designed to compensate the complainant for his physical suffering,
mental anguish, fright, serious anxiety, besmirched reputation, wounded
feelings, moral shock, social humiliation and similar injury occasioned by
the defendants wrongful act or omission. Article 2219 of the same Code
specifies the cases where moral damages may be awarded, to wit:
Art. 2219. Moral damages may be recovered in the following and analogous
cases:
The spouse, descendants, ascendants, and brothers and sisters may bring the
action mentioned in No. 9 of this article, in the order named.
Noticeably, none of the foregoing instances has any relevant bearing to the
case at bench. While Article 2219 comprehends the situation in Article 21 of
the Code, whereunder [A]ny person who willfully causes loss or injury to
another in a manner that is contrary to morals, good customs or public
policy shall compensate the latter for the damages, the appellees cannot
benefit from it. The right to recover moral damages under Article 21 is
based on equity, and those who come to court to demand equity must come
with clean hands (Garciano v. Court of Appeals, 212 SCRA 436 citing
Padilla, CIVIL CODE ANNOTATED, Vol. 1, 1975 Ed., p. 87). The
appellees knew that their lease had expired. Yet, despite such awareness,
they persisted in their unauthorized occupancy of appellants property. Being
partly responsible for their present predicament which is very much within
their power to avoid, appellees cannot receive compensation for whatever
mental anguish or suffering they went thru. [35]
DECISION
JARDELEZA, J.:
The primary question is whether a breach of contract automatically triggers the award of actual or
compensatory damages.
On July 22, 1997, respondent Spouses Sotero Octobre, Jr. and Henrissa A. Octobre (Spouses Octobre)
signed a Reservation Agreement with petitioner Pryce Properties Corporation (Pryce) for the purchase of
two lots with a total of 742 square meters located in Puerto Heights Village, Puerto Heights, Cagayan de
Oro City.1 The parties subsequently executed a Contract to Sell over the lot for the price of
P2,897,510.00 on January 7, 1998.2
On February 4, 2004, Pryce issued a certification that Spouses Octobre had fully paid the purchase price
and amortization interests, as well as the transfer fees and other charges in relation to the property,
amounting to a total of P4,292,297.92.3 But Pryce had yet to deliver the certificates of title, which
prompted Spouses Octobre to formally demand its delivery. Despite repeated demands, Pryce failed to
comply.4 Thus, on May 18, 2004, Spouses Octobre filed a complaint before the Housing and Land Use
Regulatory Board (HLURB), Regional Office No. 10 for specific performance, revocation of certificate of
registration, refund of payments, damages and attorney's fees.5
It appears that the reason why Pryce was unable to deliver the titles to Spouses Octobre is because it had
previously transferred custody of the titles, along with others pertaining to the same development
project, to China Banking Corporation (China Bank) as part of the Deed of Assignment6 executed on June
27, 1996.7 Under this deed, Pryce agreed to assign and transfer its accounts receivables, in the form of
contracts to sell, in the Puerto Heights development project to China Bank as security for the P200 Million
credit facility extended by the latter. Pryce obligated itself to deliver to China Bank the "contracts to sell
and the corresponding owner's duplicate copies of the transfer certificates of title, tax declaration, real
estate tax receipts and all other documents and papers"8 relating to the assigned receivables until such
receivables are paid or repurchased by Pryce. The titles to the lots purchased by Spouses Octobre were
among those held in custody by China Bank.9 When Pryce defaulted in its loan obligations to China Bank
sometime in May 2002, China Bank refused to return the titles to Pryce.10 For this reason, China Bank
was also impleaded in the HLURB complaint.
The HLURB Arbiter rendered a Decision11 dated March 31, 2005 finding that Spouses Octobre had no
cause of action against China Bank and rescinding the contract between Pryce and Spouses Octobre. It
ordered Pryce to refund the payments made by the spouses with legal interest and to pay the latter
compensatory damages amounting to P30,000.00, attorney's fees and costs of suit.12
On appeal, the HLURB Board of Commissioners modified the Decision by ordering Pryce to pay the
redemption value to China Bank so that the latter may release the titles covering the lots purchased by
Spouses Octobre. In default thereof, Pryce shall refund the payments with legal interest. The HLURB
Board upheld the grant of compensatory damages, attorney's fees and costs to Spouses Octobre.13 Pryce
moved for reconsideration and to stay the proceedings on account of Pryce's ongoing corporate
rehabilitation.14 The HLURB Board, however, denied Pryce's motion considering that the stay order of the
rehabilitation court had already been reversed by the Court of Appeals. 15
Thereafter, Pryce appealed the case to the Office of the President, which affirmed16 in full the HLURB
Board's Decision. Undeterred, Pryce elevated the case to the Court of Appeals which denied the petition
for review and affirmed the Office of the President's Decision. The Court of Appeals found that Pryce
acted in bad faith because it "did not disclose [that the titles were in the custody of China Bank] to
respondents Spouses Octobre until the latter demanded delivery of the titles." 17 The Court of Appeals
held that Pryce's contractual breach justified the award of compensatory damages as well as the
payment of attorney's fees and costs of suit.18
Pryce is now before this Court primarily arguing that the Court of Appeals erred in upholding the award
of compensatory damages because Spouses Octobre failed to present competent proof of the actual
amount of loss.19 It also questions the award of attorney's fees and litigation costs because there was
allegedly no finding of bad faith.20 Additionally, as side issues, Pryce questions the Court of Appeals'
finding that the stay order had been reversed and its decision to uphold the finding by the HLURB Board
and Office of the President that the subject properties were mortgaged to China Bank.21
In response, Spouses Octobre maintain that the award of compensatory damages, attorney's fees and
costs were proper because they were forced to litigate to enforce their contractual right as a result of
Pryce's breach.22 With respect to the stay order, Spouses Octobre cite this Court's February 4, 2008
Decision in G.R. No. 17230223 which affirmed the appellate court's reversal of the stay order. Finally,
Spouses Octobre note that the characterization of the Deed of Assignment as a mortgage came from
Pryce's own appeal memorandum filed with the HLURB Board, and that, in any event, whether it is an
assignment or mortgage, the decisive fact is that the titles were delivered by Pryce to China Bank. 24
In its comment, China Bank insists that Pryce only has itself to blame for failing to comply with its
obligation to remit the payments received from the various contracts to sell, including its obligation to
Spouses Octobre. Under the Deed of Assignment, China Bank is entitled to hold custody of the titles
surrendered by Pryce until the assigned receivables are paid or repurchased by Pryce, which to date the
latter has failed to do.25
II
To be entitled to compensatory damages, the amount of loss must therefore be capable of proof and
must be actually proven with a reasonable degree of certainty, premised upon competent proof or the
best evidence obtainable. The burden of proof of the damage suffered is imposed on the party claiming
the same, who should adduce the best evidence available in support thereof.27 Its award must be based
on the evidence presented, not on the personal knowledge of the court; and certainly not on flimsy,
remote, speculative and non-substantial proof.28
It is clear that the amount paid by Spouses Octobre to Pryce as purchase price for the lots has been
adequately proved. There is no dispute that Spouses Octobre are entitled to such amount with legal
interest. The issue being raised by Pryce is only with respect to the P30,000.00 awarded as
compensatory damages.29
The records of this case are bereft of any evidentiary basis for the award of P30,000.00 as compensatory
damages. When the HLURB Arbiter initially awarded the amount, it merely mentioned that "[Spouses
Octobre] are entitled to compensatory damages, which is just and equitable in the circumstances, even
against an obligor in good faith since said damages are the natural and probable consequences of the
contractual breach committed."30 On the other hand, the Court of Appeals justified the award of
compensatory damages by stating that "it is undisputed that petitioner Pryce committed breach of
contract in failing to deliver the titles to respondents [Spouses] Octobre which necessitated the award of
compensatory damages."31 In their comment, Spouses Octobre emphasized that they were "forced to
litigate and seek the intervention of the courts because of Pryce's failure to comply with its contractual
and legal obligation"32 without so much as mentioning any proof that would tend to prove any pecuniary
loss they suffered.
In the absence of adequate proof, compensatory damages should not have been awarded. Nonetheless,
we find that nominal damages, in lieu of compensatory damages, are proper in this case. Under Article
2221, nominal damages may be awarded in order that the plaintiff’s right, which has been violated or
invaded by the defendant, may be vindicated or recognized, and not for the purpose of indemnifying the
plaintiff for any loss suffered. Nominal damages are "recoverable where a legal right is technically
violated and must be vindicated against an invasion that has produced no actual present loss of any kind
or where there has been a breach of contract and no substantial injury or actual damages whatsoever
have been or can be shown."33 So long as there is a violation of the right of the plaintiff—whether based
on law, contract, or other sources of obligations34—an award of nominal damages is proper.35 Proof of
bad faith is not required.36 The HLURB Arbiter and the Court of Appeals appear to have confused nominal
damages with compensatory damages, since their justifications more closely fit the former.
It is undisputed that Pryce failed to deliver the titles to the lots subject of the Contract to Sell even as
Spouses Octobre had already fully settled the purchase price. Its inability to deliver the titles despite
repeated demands undoubtedly constitutes a violation of Spouses Octobre's right under their contract.
That Pryce had transferred custody of the titles to China Bank pursuant to a Deed of Assignment is
irrelevant, considering that Spouses Octobre were not privy to such agreement.
In fine, contractual breach is sufficient to justify an award for nominal damages but not compensatory
damages.
III
Pryce questions the award of attorney's fees and costs of suit because no exemplary damages were
awarded. This contention, however, is clearly unmeritorious because under Article 2208,37 the award of
exemplary damages is just one of 11 instances where attorney's fees and expenses of litigation are
recoverable.
Article 2208(2) allows the award of attorney's fees when the defendant's act or omission has compelled
the plaintiff to litigate with third persons or to incur expenses to protect his interest. The Court has
interpreted that this provision requires a showing of bad faith and not mere erroneous conviction of the
righteousness of a defendant's cause.38 In this case, the Court of Appeals found that Pryce acted in bad
faith when it did not disclose to Spouses Octobre the fact that the certificates of title to the properties
purchased were in the custody of China Bank until Spouses Octobre had fully paid the price and had
demanded delivery of the titles. We agree with this finding and therefore sustain the award of attorney's
fees and costs of suit in favor of Spouses Octobre.
IV
The other side issues raised by Pryce shall be disposed of swiftly since they have no substantial bearing
on the merits of this case. As admitted by Pryce itself, "it is not the entire Decision that is being
assailed"39 but only the portion regarding the award of compensatory damages, attorney's fees and costs
of suit.
When the stay order being invoked by Pryce was reversed and set aside at the first instance by the Court
of Appeals in CA-G.R. SP No. 88479, that stay order was automatically deemed vacated.40 By reversing
the stay order of the rehabilitation court, the Court of Appeals effectively enjoined the execution of such
order as allowed by the 2000 Interim Rules of Procedure on Corporate Rehabilitation41 (which was then
in effect when Pryce filed its petition for rehabilitation in 2004). We affirmed the Court of Appeals'
decision to set aside the stay order in the Decision dated February 4, 200842 and Resolution dated June
16, 2008.43 Although we later reconsidered the Decision on February 18, 2014,44 the same does not
affect the validity of the proceedings already conducted before the HLURB, Office of the President, and
Court of Appeals during the intermediate period that the stay order was vacated. Neither does it affect
our resolution of this petition for review because under the Financial Rehabilitation and Insolvency Act of
201045 (FRIA), the stay order shall not apply to cases already pending appeal in the Supreme
Court.46 Section 146 of the FRIA expressly allows the application of its provisions to pending
rehabilitation cases, except to the extent that their application would not be feasible or would work
injustice.47
The characterization of the Deed of Assignment between Pryce and China Bank as either an assignment
of receivables or a mortgage of real property is irrelevant to Pryce's obligation to Spouses Octobre. The
principal reason why Pryce raises this argument is to elude the applicability of Section 18 of Presidential
Decree No. 957.48 But Spouses Octobre's claim is precisely premised on its contract with Pryce, not this
specific provision of law. Hence, even if the provision is inapplicable, Pryce's contractual liability to deliver
the titles to Spouses Octobre remains.
WHEREFORE, the petition is DENIED. The assailed Decision and Resolution of the Court of Appeals in
CA-G.R. SP N9. 103615 are MODIFIED in that nominal damages in the amount of P30,000.00 are
awarded in lieu of compensatory damages.
SO ORDERED.
DECISION
SERENO, C.J.:
At bench is a review of the damage claims for contractual breach sought by petitioner Universal
International Investment (BVI) Limited (Universal) against respondent Ray Burton Development
Corporation (RBDC). In G.R. No. 185815, Universal contests the Court of Appeals (CA) Decision and
Resolution rejecting its demand for damages against RBDC.1 Petitioner seeks damages for non-delivery
of the properties it had purchased from respondent and the titles thereto. In G.R. No. 182201, Universal
assails the CA Decision and Resolution, which affirmed the discharge of one of respondent's attached
properties meant to secure petitioner's claims for damages.2
FACTUAL ANTECEDENTS
RBDC owned and developed Elizabeth Place, a condominium located at H.V. De la Costa St., Salcedo
Village, Makati City. On 18 October 1996, respondent and petitioner entered into separate Contracts to
Sell3 covering the purchase of 10 condominium units and 10 parking slots in the building. In February
1999, petitioner paid respondent the full purchase price of these properties amounting to
P52,836,781.50.4
Universal issued a letter dated 23 August 2000 to RBDC demanding the cancellation of the sales
transaction after the latter failed to deliver possession of the properties and reneged on its obligation to
transfer the Condominium Certificates of Title (CCTs) to petitioner's name.5 On 6 August 2001,
respondent sent a letter to Universal informing the latter that the construction of the subject properties
had been completed.6 Several demand letters followed.7
RBDC ultimately failed to satisfy the demand of Universal to deliver the properties. Thereafter, petitioner
discovered that the mother title to the lot of Elizabeth Place had been mortgaged to China Banking
Corporation (China Bank) since 31 July 1991.8 Petitioner found that a Mortgage Clearance from the
Housing and Land Use Regulatory Board (HLURB) had been issued on 17 October 1996 9 and the
securities foreclosed by China Bank on 18 May 2001.10
On 29 May 2002, Universal filed with the Expanded National Capital Region Field Office (ENCRFO) of the
HLURB a Complaint for Specific Performance or Rescission of Contract and Damages.11 To secure its
claims, petitioner moved for the issuance of a writ of preliminary attachment against the properties of
RBDC. Universal imputed fraud to respondent for concealing the mortgage with China Bank. On 3 June
2002, a Writ of Attachment was issued by the ENCRFO.12
Universal sought the delivery of (1) the condominium units and (2) their CCTs. In the event that delivery
were to be proven impossible, it prayed for the rescission of the Contracts to Sell with a refund of the
purchase price plus the penalty interest stipulated under Section 6 thereof. The contracts provide for a
1.5% monthly interest on the total purchase price, computed from the date of cancellation of the sale
until full refund of the payments.
RBDC countered13 that Universal could not rightly demand delivery, for the latter had yet to pay transfer
charges under the Contracts to Sell. In the alternative, respondent claimed that it had already delivered
the properties when it sent a letter to petitioner on 6 August 2001.
As regards the CCTs, RBDC argued that petitioner should demand these from China Bank. The CA
summarized that contention of respondent in this wise:14
On 25 March 2003, the ENCRFO issued a Decision15 in favor of Universal. The former found that petitioner
had completed the payment of the total contract price of P52,836,781.50 in February 1999. At that point,
said the ENCRFO, the reciprocal obligation of respondent to deliver possession of the properties and their
CCTs became due and demandable.
On 12 May 2003, RBDC filed a Petition for Review16 before the Board of Commissioners (BOC) of the
HLURB. Respondent also moved for the partial discharge17 of one of its attached properties: the lot in
Lapu-Lapu City with Transfer Certificate of Title (TCT) No. T-29726.
RBDC reiterated its arguments below. Universal likewise echoed its earlier assertions, but additionally
claimed that respondent's Petition for Review lacked the appeal bond needed to perfect an appeal. 18
The BOC did not dismiss respondent's Petition for Review. Instead, on 10 October 2003, it issued an
Order19 directing the remand of the case to the ENCRFO so that the latter could include China Bank in the
proceedings. Universal moved for reconsideration, but to no avail.20
The BOC did not rule upon the motion of RBDC for the discharge of its Lapu-Lapu City property. Therefore,
respondents filed a second Motion for Partial Discharge.21 In its Resolution dated 29 June 2004, the BOC
allowed the discharge of the Lapu-Lapu City property owned by respondent, since the latter was willing
to put up a counterbond.22
Universal successfully appealed its case before the Office of the President (OP).23 In its Decision dated 29
October 2004,24 the OP reversed the ruling of the BOC and held that Universal had a right to rescind the
Contracts to Sell, as well as to refund the purchase price of the properties with the liquidated damages
specified in Section 6 of the contracts. Nonetheless, the OP maintained the validity of the discharge of the
Lapu-Lapu City property.25
Universal assailed the discharge of the Lapu-Lapu City property via a Petition for Certiorari under Rule 65
of the Rules of Court in CA-G.R. SP No. 89578. 26 In its Decision dated 25 June 2007 and Resolution dated
14 March 2008, the CA dismissed the action for lack of merit. Anent the main controversy involving the
non-delivery of the condominium units and parking slots, RBDC filed a Petition for Review 27 under Rule
43 of the Rules of Court in CA-G.R. SP No. 89468. In both proceedings, the parties repeated their
arguments a quo.
During the pendency of the case before the CA, Universal manifested28that China Bank had
released the subject properties, and that petitioner had already obtained their CCTs on 5
January 2005.
On account of this supervening event, RBDC moved that this case be considered moot and academic.29
Universal responded that its acquisition of the condominium units from China Bank resulted only in the
partial satisfaction of the former's claims against RBDC. Petitioner claimed before the CA that respondent
must still pay for the damages specified in Section 6 of the Contracts to Sell on account of the latter's
delayed delivery of the properties. Universal also claimed compensation for property losses amounting to
P19,646,483.72, supposedly to cover the depreciation costs and expenses it had incurred for the release
of the properties from China Bank.
In its Decision dated 31 July 2007, which was maintained in its Resolution dated II December 2008, the
CA wholly denied Universal's entreaty for damages.
PROCEEDINGS BEFORE THIS COURT
The consolidated Petitions for Review on Certiorari filed by Universal under Rule 45 of the Rules of Court,
docketed as G.R. Nos. 182201 and 185815, collectively raise three points.30
First, Universal contends that the CA gravely erred when the latter sustained the OP's discharge of the
Lapu-Lapu City property, notwithstanding the irregularities in the proceedings below.
Second, Universal argues that because RBDC failed to attach an appeal bond when the latter elevated
the ENCRFO Decision to the BOC, that ruling had become final and executory and can no longer be
reviewed by the BOC, the OP, the CA, or this Court.
Third, petitioner claims that the CA gravely erred in refusing to award damages and property losses.
Petitioner seeks damages on account of the contractual breaches of respondent consisting of the latter's
failure to deliver the properties and to transfer their CCTs to the name of Universal. Petitioner also
narrates that RBDC concealed the mortgage of the properties to China Bank.
RBDC stands by the validity of the partial discharge of its Lapu-Lapu City property. In the main, it denies
committing any breach of contract against Universal. Absent any dereliction on its part, respondent
claims that petitioner should not be awarded damages.31
ISSUES
Given the developments in this case, this Court adjudges that the main issues to be resolved are as
follows:
1. Whether the CA incorrectly affirmed the discharge of the Lapu-Lapu City property of RBDC
2. Whether the CA gravely erred in denying the demand of petitioner for the liquidated damages
specified in Section 6 of the Contracts to Sell
3. Whether the CA committed a grievous error in not granting the claims of petitioner for losses
amounting to P19,646,483.72
At the outset, this Court outrightly rejects the argument of Universal regarding the failure of RBDC to
attach an appeal bond when the latter elevated the ENCRFO Decision to the BOC for being moot and
academic. To recall, the appealed ENCRFO Decision required RBDC to deliver the purchased properties
and pay damages to Universal; and if that delivery was no longer possible, to refund the purchase price
plus interests thereon.
The properties and the titles thereto were finally delivered to Universal on 5 January 2005. Hence, its
only existing claim in this case is for damages, which an appeal bond does not secure under Section 3 (c),
Rule XII of the 1996 HLURB Rules of Procedure.32 Since interests, damages, and attorney's fees need not
be covered by an appeal bond, that controversy has come to an end with no practical and effective relief
to be given to petitioner.33
Universal highlights the irregularities that supposedly attended the discharge of the Lapu-Lapu City
property owned by RBDC. First, the BOC Order dated 10 October 2003, which did not rule upon the issue
of the discharge, was improvidently modified by its Resolution dated 29 June 2004. The Order was
modified upon respondent's filing of a second Motion for Partial Discharge, instead of a proper Motion for
Reconsideration. Second, since the BOC had directed the remand of the case to the ENCRFO, the former
lost the jurisdiction to order the discharge. Third, the discharge transpired without notice and hearing.
On the first infirmity, we hold that the CA did not exceed its jurisdiction when it sustained the BOC
Resolution dated 29 June 2004 granting the discharge, even if not through a motion for reconsideration
but via a second Motion for Partial Discharge. The second Motion for Partial Discharge may very well take
the place of a motion for reconsideration, considering that it also sought the reconsideration of the BOC's
failure to resolve the first Motion for Partial Discharge. It is basic that the caption should not be the
governing factor, but rather the allegations contained in the motion or pleading, that should determine
the nature of the action.34
As regards the second and the third irregularities, this Court finds no justification for the exercise of its
discretionary power of appellate review. The CA, which heard the issues under the framework of a special
civil action for certiorari, has thoroughly explained the purported irregularities. We quote with approval
the following excerpt from the assailed CA Decision:35
xxxx
Proceeding to the main controversy of these consolidated cases, Universal asserts that because RBDC
failed to transfer possession of the properties, and their CCTs, petitioner-buyer is entitled to damages by
way of the interest specified in Section 6 of the Contracts to Sell, viz:
If the terms of the contract are clear and leave no doubt upon the intention of the contracting parties, the
literal meaning of its stipulations shall control.36 In this case, the very words of Section 6 of the Contracts
to Sell refer only to situations of (1) force majeure or (2) substantial delay in the condominium project,
Elizabeth Place.
Universal is not alleging either of these two circumstances. Rather, it is claiming damages for RBDC's
failure to deliver possession of the condominium units, parking slots, and their CCTs. Hence, Section 6 of
the Contracts to Sell is clearly inapplicable to petitioner's cause of action.
Universal reiterates its claims for actual damages based on the losses it suffered amounting to
P19,646,483.72. This amount represents the depreciation between the P57,146,483.72 purchase
price of the properties in 1996 and the P37,500,000 market value of the properties appraised at the
time that petitioner obtained the titles from China Bank in 2005.37
Petitioner computes that the purchase price in 1996 totals P57,146,483.72, which is the summation of
the following amounts: P52,836,781.50 total contract price; P770,613.68 condominium dues,
P368,881.63 real estate taxes, and the P3,170,206.91 expenses paid to China Bank for the release of the
properties. In effect, petitioner seeks to recover the depreciation costs and the additional sums it paid to
obtain the release of the properties from China Bank. For lack of legal basis, the CA entirely rejected
petitioner's claims for losses.
Universal now seeks refuge under Article 2200 of the Civil Code to justify its claim for damages:
To adjudicate petitioner's claims, this Court looks into the fundamental elements in recovering damages.
In MEA Builders Inc. v. Court of Appeals,38 We defined damages as follows:
Based on the above definition, in order to recover damages, the claimant must prove (1) an injury or a
wrong sustained (2) as a consequence of a breach of contract or tort and (3) caused by the party
chargeable with a wrong.39 As Universal claims actual damages, it is only entitled to such pecuniary loss
as it has duly proved.40
Petitioner cites Article 2200 of the Civil Code to support its claim for losses equivalent to a
P19,646,483.72 reduction in the market value of the condominium units. This provision speaks of
indemnification for lost profits that would have been obtained by the claimant if not for the injury caused
by the erring party.41 In the present case, however, Universal does not even allege that it is marketing
the properties for profit, either by lease or by sale. Thus, Article 2200 cannot serve as the proper basis
for recovering the value of the condominium units.
In the alternative, assuming that the condominium units were utilized for profit, this Court finds no iota
of evidence as to the amount of profits that Universal would have earned from the properties. To justify
a grant of compensatory damages, it is necessary that the actual amount of loss to be proved with a
reasonable degree of certainty, premised upon competent proof and the best evidence obtainable by the
injured party.42
We cannot consider as unearned profits the P19,646,483.72 difference between the total contract price
and the present market value of the properties. That conclusion presupposes that Universal has (1)
successfully marketed the properties (2) at a favorable retail price that would allow it to recover its
original investment. In National Power Corp. v. Philipp Brothers Oceanic, Inc.,43 this Court explained that
in order to recover actual damages, the alleged unearned profits must not be conjectural or based on
contingent transactions. Speculative damages are too remote to be included in an accurate estimate of
damages.44
Both parties entered into a contract to sell, not a contract of sale. In the former agreement, ownership is
reserved by the vendor.45 Upon full payment of the purchase price, the resulting duties of RBDC as
vendor are found in Section 3 of the subject agreement, viz:
RBDC only has two obligations specified by Section 3: (1) to deliver deeds of absolute sale; and (2) to
deliver the corresponding CCTs. Contrary to the demands of petitioner, respondent did not have any
contractual obligation to surrender possession of the properties. Neither did the latter have to cause the
transfer of the CCTs to petitioner's name.
In Chua v. Court of Appeals,46 we explained the nature and the incidents of a contract to sell as follows:
xxxx
Universal does not base its claim for damages on grounds supported by the Contracts to Sell. Instead, it
argues that respondent's failure to transfer the CCTs and convey possession of the properties caused the
depreciation of their market value. Hence, this Court rules that petitioner's premise for its recovery of
depreciation losses is misplaced.47
The act or omission of respondent must have been the proximate cause, as distinguished from the
remote cause, of the loss sustained by the claimant.48 Proximate cause - determined by a mixed
consideration of logic, common sense, policy, and precedent49 - is that cause which, in natural and
continuous sequence, unbroken by any efficient intervening cause, produces the injury, and without
which the result would not have occurred.50
Applying that definition to the case at bar, Universal must demonstrate that the breaches of RBDC caused
the depreciation of the condominium units; or conversely, that had respondent performed its contractual
obligations, the properties would not have diminished in value.
Universal does not specify how RBDC's non-delivery of the properties resulted in the depreciation of their
value. Neither does petitioner prove that had it possessed the properties, it could have avoided their
decline in the real estate market. At most, it has only been able to show that with the passage of time,
its P57,146,483.72 investment in 1996 was reduced to P37,500,000 in 2005. Therefore, considering the
dearth of proof of causality in this case, this Court cannot justly exact the supposed P19,646,483.72
depreciated value of the 1 0 condominium units and 10 parking slots from RBDC.
As mentioned above, Universal seeks to recover from RBDC the additional sums paid by the former to
obtain the release of the properties from China Bank. Respondent counters that it should not be made to
pay the P770,613.68 condominium dues, P368,881.63 real estate taxes, and P3,170,206.91 expenses,
given that China Bank was the one obliged by the HLURB to release the condominium units.
We agree with RBDC. Respondent correctly argues that it is not chargeable for the alleged expense items.
Clearly - and logically - the HLURB did not require any additional payment for the fully paid buyers of the
condominium units. Hence, Universal should not have paid any additional amount to China Bank. In the
final Judgment Upon Compromise dated 1 August 2002, the HLURB directed the bank to release the titles
to all the units without qualification:51
The affidavits of undertaking of the mortgagee bank are
requirements in the issuance of a clearance to mortgage as
provided for under Section 18 of Presidential Decree No. 957
for the protection of the buyers.
Given that the sums expended by Universal should not have been incurred in the first place, this Court
finds no just reason for petitioner to demand the payment of the expenses, association dues, and realty
taxes from RBDC. Notably, as regards the payment of association dues and realty taxes, the Contracts to
Sell provide that these shall not be shouldered by respondent seller.52
As discussed. respondent had two obligations specified in Section 3 of the Contracts to Sell: ( 1) to deliver
the deeds of absolute sale; and (2) to give the corresponding CCTs. RBDC admittedly failed to perform
these obligations, but invoked the excuse that Universal had defaulted on the payment of transfer
charges under Section 5(a) of the Contracts to Sell. The provision reads as follows:53
The excuse given by RBDC deserves scant consideration. In order that the debtor may be held to be in
default, the following requisite conditions must be present: (1) the obligation is demandable and already
liquidated; (2) the debtor delays performance of the obligation; and (3) the creditor requires the
performance judicially or extrajudicially.54
Nowhere in the records does this Court find a demand from RBDC for Universal to pay any sum under the
above provision. None of the letters of respondent to petitioner resembles a notice requiring the latter to
tender any payment for government charges and expenses connected with the execution of the Deed of
Absolute Sale or the transfer of titles. Moreover, there is no liquidated demand to speak of, as there is no
itemized final computation.55 All in all, this Court does not consider Universal to have defaulted on the
payment of transfer charges.
Section 5(a) must be construed as a whole. Its first paragraph refers to the payment for (1)
government-imposed taxes, fees, and expenses related to the acquisition of the property; and (2)
expenses that may be incurred in connection with the execution of the Deeds of Absolute Sale and the
conveyance or transfer of titles to the buyer.
The second paragraph of Section 5 specifies that in the event the seller handles the registration of the
Deed of Absolute Sale and effects title transfer in the name of the buyer, then that is the time that the
buyer would have to give the seller the payment for those transactions. Specifically, the buyer must
tender payment within five days from receipt of the seller's notice of completion and delivery of the unit.
We appreciate that the charges under Section 5(a) are sums to be expended for the titling of the
properties. However, the obligation to pay these charges specifically to the seller - arises only "in the
event" that the latter elects to handle the titling of the properties. In this case, RBDC has not averred that
it has undertaken that responsibility. Consequently, Universal cannot be obliged to pay the transfer
charges to respondent. RBDC cannot demand performance by Universal without offering to comply with
its own prestation.56
RBDC is then left with no just reason not to perform its obligations to Universal. As early as February
1999, respondent should have (1) executed deeds of absolute sale; and (2) given the CCTs of the
properties to petitioner. RBDC has not at all complied with its duties despite the fact that Universal has
already fully paid the purchase price of the properties.
As explained above, Universal failed to prove its claims for actual damages, both as regards the
liquidated damages under Section 6 of the Contracts to Sell and the alleged losses amounting to
P19,646,483.72.
Nonetheless, petitioner may still be awarded damages in the concept of temperate or moderate damages.
Temperate damages may be recovered when the court finds that some pecuniary loss has been suffered
but the amount cannot, from the nature of the case, be proven with certainty.57 In this case, there is no
doubt that Universal sustained pecuniary loss, albeit difficult to quantify, arising from RBDC's failure to
execute deeds of absolute sale and to deliver the CCTs of the properties.
Had RBDC fulfilled these obligations, its transaction with Universal under the Contracts to Sell would have
been complete.58 After an absolute deed of sale has been signed by the parties, notarized and hence,
turned into a public instrument, then the delivery of the real property is deemed made by the seller to the
buyer.59 Consequently, the buyer would have right away enjoyed the possession of the realties. Likewise,
the titles thereto would have permitted the use of the properties as collateral for further investments.
Universal lost all of these opportunities after RBDC failed to perform the latter's duties as a seller.
Hence, this Court is empowered to calculate moderate damages, rather than let the aggrieved party
suffer without redress from RBDC's wrongful act.60
The calculation of temperate damages is usually left to the sound discretion of the courts.61 We observe
the limit that in giving recompense, the amount must be reasonable, bearing in mind that the same
should be more than nominal, but less than compensatory.62 In jurisprudence, this Court has pegged
temperate damages to an amount equivalent to a certain percentage of the actual damages claimed by
the injured party.63
The plight of the petitioner in Pacific Basin Securities Co., Inc. v. Oriental Petroleum64 is parallel to that
of Universal. In that case, the petitioner was also not given transfer documents for the properties it had
purchased, and the respondent unjustifiably refused to record the transfer of the P17,727,000 worth of
shares purchased by the former. As a result, the petitioner therein was prevented from reselling the
subject shares in the stock market. For that dereliction, this Court awarded the petitioner therein P1
million for temperate damages equivalent to 5% of the actual damages claimed.
Anent the failure to deliver the titles to a purchased property, Government Service Insurance System v.
Spouses Labung-Deang65 is instructive. Similar to petitioners herein, Spouses Labung-Deang were
deprived by the bank of copies of the title to the property that they had purchased. Consequently, the
spouses failed to mortgage it as security for a P50,000 loan that they could have utilized to renovate their
house. As recompense, this Court awarded them P20,000 temperate damages equivalent to 40% of the
amount of their alleged injury.
Aside from those two analogous cases, this Court has reviewed other cases involving the award of
temperate damages for breaches of contract. We have considered the: (1) investment to be lost by the
injured party;66 (2) duration of suffering of the injured party;67 and (3) urgent action undertaken by the
party in breach to remedy the situation.68 Thus, we take into account the following: (1) in 1999,
Universal invested P52,836,781.50 for 10 condominium units and 10 parking slots of Elizabeth Place in
Makati City; (2) Universal asked RBDC about the monthly rental rates of each of the properties, which
turned out be in the range of P20,000 to P48,000;69 (3) for six years, petitioner had no titles to or
possession of the properties; and (4) RBDC could have easily executed deeds of absolute sale as the
templates of these contracts had already been attached to the Contracts to Sell.70
Having laid down all the circumstances obtaining in this case, this Court is of the view that an award for
temperate damages equivalent to 15% of the P52,836,781.50 purchase value of the properties, or
P7,925,517.23, is just and reasonable.
Since petitioner is entitled to temperate damages, then the courts may also examine the propriety of
imposing exemplary damages on respondent.71 Exemplary damages are corrective damages imposed by
way of example or correction for the public good.72 The grant thereof is intended to serve as a deterrent
to or negative incentive for curbing socially deleterious actions. 73 Relevant to this case, this Court
highlights that the State has an avowed policy to protect innocent buyers in real estate transactions. 74
Article 2232 of the Civil Code of the Philippines provides that in contracts, the court may award
exemplary damages if the defendant acted in a wanton, fraudulent, reckless, oppressive, or malevolent
manner. In this case, we find that respondent indeed acted in that manner when, despite demand for and
full payment of the properties,75 it refused to execute deeds of absolute sale and release the CCTs to
petitioner without any sound basis.76 As already discussed, Universal's nonpayment of transfer charges
does not even serve as a potent excuse for RBDC's refusal to execute deeds of absolute sale and to
deliver the titles of the purchased properties.
Moreover, there was no impediment to RBDC's issuance of deeds of absolute sale. As the owner, it could
have still sold the properties even if it mortgaged them to China Bank.77 As for the CCTs, respondent
need not cause their transfer to the name of petitioners. RBDC could have simply turned them over to
Universal in 1999, two years prior the foreclosure of the securities by China Bank in 2001. To make
matters worse, respondent did not categorically deny that it had failed to disclose to petitioner that the
lot of Elizabeth Place had been mortgaged to China Bank prior the execution of the Contracts to
Sell.78 This Court holds that the totality of these circumstances justify the imposition of exemplary
damages on RBDC.
In Cantemprate v. CRS Realty Development Corporation,79 which is fairly akin to the case at bar, the
developer did not deliver the titles to the buyers of the fully paid properties. For failing to comply with its
unequivocal duty, this Court affirmed the HLURB's award of P30,000 exemplary damages and P20,000
attorney's fees to each of the buyers. Considering that ruling vis-a-vis the dereliction of RBDC in the
present case, which also involves the violation of a straightforward obligation to execute the deeds of
absolute sale and to deliver the CCTs for the 1 0 condominium units and 10 parking slots, an award of
P300,000 as exemplary damages is justified to set an example.
Given the award of exemplary damages, this Court likewise finds it just and equitable under the
circumstances to award P200,000 as attorney's fees.80 In addition, all damages awarded shall earn
interest at the rate of 6% per annum from the date of finality of this judgment until full payment.
WHEREFORE, premises considered, in G.R. No. 182201, the Court of Appeals Decision dated 25 June
2007 and Resolution dated 14 March 2008 in CA-G.R. SP No. 89578 are AFFIRMED. In G.R. No. 185815,
the Court of Appeals Decision dated 31 July 2007 and Resolution dated 11 December 2008 in CA-G.R. SP
No. 89468 are AFFIRMED with the MODIFICATION that P7,925,517.23 as temperate damages,
P300,000 as exemplary damages, and P200,000 as attorney's fees are awarded to petitioner Universal
International Investment (BVI) Limited. All damages awarded shall earn interest at the rate of 6% per
annum from the date of finality of this judgment until full payment.
SO ORDERED.
DECISION
LEONEN, J.:
Although the provisions of a contract are legally null and void, the stipulated method of computing
liquidated damages may be accepted as evidence of the intent of the parties. The provisions, therefore,
can be basis for finding a factual anchor for liquidated damages. The liable party may nevertheless
present better evidence to establish a more accurate basis for awarding damages. In this case, the
respondent failed to do so.
This resolves a Petition for Review on Certiorari1 praying that the assailed May 2, 2008 Decision2 and
November 25, 2008 Resolution3 of the Court of Appeals in CA G.R. CV No. 86406 be reversed and set
aside and that the Decision4 dated November 2, 2005 of Branch 108 of the Regional Trial Court of Pasay
City in Civil Case No. 00-0343 be reinstated.
The Regional Trial Court's November 2, 2005 Decision ruled in favor of petitioner Philippine Economic
Zone Authority, which, as plaintiff, brought an action for rescission of contract and damages against the
defendant, now respondent Pilhino Sales Corporation (Pilhino).5 chanroble slaw
The assailed Court of Appeals Decision partly granted Pilhino's appeal by reducing the amount of
liquidated damages due from it to the Philippine Economic Zone Authority, and by deleting the forfeiture
of its performance bond.6 The assailed Court of Appeals Resolution denied the Philippine Economic Zone
Authority's Motion for Reconsideration.7 chanrobleslaw
The facts are not disputed, and all that is in issue is the consequence of Pilhino's contractual breach.
On October 4, 1997, the Philippine Economic Zone Authority published an invitation to bid in the Business
Daily for its acquisition of two (2) brand new fire truck units "with a capacity of 4,000-5,000 liters [of]
water and 500-1,000 liters [of chemical foam,] with complete accessories."8 chanrobleslaw
Three (3) companies participated in the bidding: Starbilt Enterprise, Inc., Shurway Industries, Inc., and
Pilhino.9 Pilhino secured the contract for the acquisition of the fire trucks.10 The contract price was
initially at P3,000,000.00 per truck, but this was reduced after negotiation to P2,900,000.00 per
truck.11
chanroble slaw
The contract awarded to Pilhino stipulated that Pilhino was to deliver to the Philippine Economic Zone
Authority two (2) FF3HP brand fire trucks within 45 days of receipt of a purchase order from the Philippine
Economic Zone Authority.12 A further stipulation stated that "[i]n case of fail[u]re to deliver the . . . good
on the date specified . . . , the Supplier agree[s] to pay penalty at the rate of 1/10 of 1% of the total
contract price for each days [sic] commencing on the first day after the date stipulated above." 13 chanroble slaw
The Philippine Economic Zone Authority furnished Pilhino with a purchase order dated November 6,
1997.14 Pilhino failed to deliver the trucks as it had committed.15 This prompted the Philippine Economic
Zone Authority to make formal demands on Pilhino on July 27, 1998 16 and on February 23, 1999.17 As
Pilhino still failed to comply, the Philippine Economic Zone Authority filed before the Regional Trial Court
of Pasay City a Complaint18 for rescission of contract and damages. This was docketed as Civil Case No.
00-0343 and raffled to Branch 108.19 chanrobleslaw
In its defense, Pilhino claimed that there was no starting date from which its obligation to deliver could
be reckoned, considering that the Complaint supposedly failed to allege acceptance by Pilhino of the
purchase order.20 Pilhino suggested that there was not even a meeting of minds between it and the
Philippine Economic Zone Authority.21 chanroble slaw
In its November 2, 2005 Decision,22 the Regional Trial Court ruled for the Philippine Economic Zone
Authority. The dispositive portion of the Decision reads: ChanRoblesVi rtua lawlib rary
In its assailed May 2, 2008 Decision,24 the Court of Appeals partly granted Pilhino's appeal by deleting the
forfeiture of Pilhino's performance bond and pegging the liquidated damages due from it to the Philippine
Economic Zone Authority in the amount of P1,400,000.00.
The Court of Appeals debunked Pilhino's claim that there was no meeting of minds. It emphasized that
Pilhino "manifested its acquiescence . . . [to] the Purchase Order . . . when it submitted to [the Philippine
Economic Zone Authority] a Performance Bond dated 02 June 1999 and Indemnity Agreement dated 09
June 1998 duly signed by its Vice President."25 It added that in a subsequent letter dated March 29,
cralawred
199926 "signed by [Pilhino's] Hino Division Manager Edgar R. Santiago and noted by VP-Operations
Roberto R. Garcia, [Pilhino] admitted that it can no longer meet the requirements regarding the
specification on the two (2) units of fire truck[s]."27 chanrobleslaw
In this March 29, 1999 letter, Pilhino not only acknowledged its inability to meet its obligations but also
proposed a modified arrangement with the Philippine Economic Zone Authority: ChanRoblesVirtualawl ibra ry
In calibrating the amount of liquidated damages, the Court of Appeals cited Articles 122929 and 222730 of
the Civil Code. It reasoned that through its March 29, 1999 letter, Pilhino made an attempt at rectification
or mitigation:ChanRobles Vi rtua lawlib rary
The Philippine Economic Zone Authority moved for reconsideration of the modifications to the Regional
Trial Court's award. As this Motion was denied in the Court of Appeals' assailed November 25, 2008
Resolution,32 the Philippine Economic Zone Authority filed the present Petition.
Petitioner asks for the reinstatement of the Regional Trial Court's award asserting that it already suffered
damage when respondent Pilhino Sales Corporation failed to deliver the trucks on time;33that the
contractually stipulated penalty of 1/10 of 1% of the contract price for every day of delay was neither
unreasonable34 nor contrary to law, morals, or public order;35 that the stipulation on liquidated damages
was freely entered into by it and respondent;36 and that the Court of Appeals' computation had no basis
in fact and law.37 Regarding respondent's supposed attempt at mitigation, petitioner notes that by the
time the offer was made, the Complaint for rescission and damages had already been filed 38 and was,
therefore, inconsequential and hardly a remedy.
Commenting on petitioner's Petition,39 respondent raises the question of: ChanRoblesVi rtua lawlib rary
Therefore, respondent suggests that with the rescission of its contract with petitioner must have come
the negation of the contractual stipulation on liquidated damages and the obliteration of its liability for
such liquidated damages.41 chanrobles law
First, the propriety of an award based on contractually stipulated liquidated damages notwithstanding
chanRoble svirtual Lawlib ra ry
Second, on the assumption that such award is proper, the propriety of the Court of Appeals' reduction of
the liquidated damages due to petitioner.
Respondent's intimation that with the rescission of a contract necessarily and inexorably follows the
obliteration of liability for what the same contracts stipulates as liquidated damages42 is entirely
misplaced.
A contract of. sale, such as that entered into by petitioner and respondent, entails reciprocal obligations.
As explained in Spouses Velarde v. Court of Appeals,43 "[i]n a contract of sale, the seller obligates itself
to transfer the ownership of and deliver a determinate thing, and the buyer to pay therefor a price certain
in money or its equivalent."44 chanrobl eslaw
Rescission on account of breach of reciprocal obligations is provided for in Article 1191 of the Civil
Code: ChanRoblesVirt ualawli bra ry
The injured party may choose between the fulfillment and the
rescission of the obligation, with the payment of damages
in either case. He may also seek rescission, even after he
has chosen fulfillment, if the latter should become
impossible.
Despite the fact that Article 1124 of the old Civil Code from
whence Article 1191 was taken, used the term "resolution",
the amendment thereto (presently, Article 1191) explicitly
and clearly used the term "rescission". Unless Article 1191
is subsequently amended to revert back to the term
"resolution", this Court has no alternative but to apply the
law, as it is written.
Article 1191 itself clearly states that the options of rescission and specific performance come with "with
the payment of damages in either case." The very same breach or delay in performance that triggers
rescission is what makes damages due.
When the contracting parties, by their own free acts of will, agreed on what these damages ought to be,
they established the law between themselves. Their contemplation of the consequences proper in the
event of a breach has been articulated. When courts are, thereafter, confronted with the need to award
damages in tandem with rescission, courts must not lose sight of how the parties have explicitly stated,
in their own language, these consequences. To uphold both Article 1191 of the Civil Code and the parties'
will, contractually stipulated liquidated damages must, as a rule,48 be maintained.
What respondent purports to be the ensuing nullification of liquidated damages is not a novel question in
jurisprudence. This matter has been settled, and respondent's position has been rebuked. In Laperal: ChanRobles Vi rtua lawlib rary
This notwithstanding, the Court does not agree with the Court
of Appeals that, as a consequence of the obligation of mutual
restitution in this case, petitioners should return the
amount of P5,200,833.27 to respondent.
To sustain respondent's claim would be to sustain an absurdity and an injustice. Respondent's position
suggests that with rescission must necessarily come the obliteration of the punitive consequence which,
to begin with, was the product of its own (along with the other contracting party's) volition. Its position
turns delinquency into a profitable enterprise, enabling contractual breach to itself be the means for
evading its own fallout. It is a position we cannot tolerate.
II
In calibrating the amount of liquidated damages, the Court of Appeals relied on how respondent
supposedly attempted to rectify things "by offering to [petitioner] new specifications at P3,600,000.00
per unit; and expressed willingness to shoulder the difference between the original price (based on the
contract) of P2,900,000.00 per unit and the price corresponding to the new specifications."51 chanrobleslaw
As underscored by petitioner, however, this offer was inconsequential and hardly a remedy to the
predicament it found itself in.
Petitioner already suffered damage by respondent's mere delay. Philippine Economic Zone Authority
Director General Lilia B. De Lima's internal memorandum to its Board of Directors emphasized what was,
at the time, the specific urgency of obtaining fire trucks:ChanRoblesVirtualawl ibra ry
1. With the increase in the number of locator-enterprises at
the regular zones, there is a need for additional units of
fire trucks to address any eventuality. The onset of the El
Niño phenomena further makes it imperative that PEZA be more
prepared.
Bataan EZ 2
Baguio City EZ 1
Cavite EZ 1
52
Mactan EZ 2 (Emphasis supplied)
The Court of Appeals itself recognized that "time was of the essence when the contract . . . was awarded
to [respondent] and the non-compliance therewith exposed [petitioner's] operations [at] risk."53 chanroble slaw
Respondent's attempt at rectification came too late and under such circumstances that petitioner was no
longer even in a position to accept respondent's offer. As petitioner notes, by the time respondent made
its offer, the Complaint for rescission and damages had already been filed before the Regional-Trial Court
of Pasay City.54 If at all, the offer was nothing more than a belated reaction to undercut litigation.
By the time respondent made its attempt at rectification, petitioner was no longer capable of
accommodating contractual modifications. Jurisprudence has established the impropriety of modifying
awarded contracts that were previously subjected to public bidding, such as that between petitioner and
respondent: ChanRobles Vi rtual awlib rary
WHEREFORE, the Petition is GRANTED. The assailed May 2, 2008 Decision and November 25, 2008
Resolution of the Court of Appeals in CA G.R. CV No. 86406 are REVERSED and SET ASIDE. The
Decision dated November 2, 2005 of Branch 108 of the Regional Trial Court of Pasay City in Civil Case No.
00-0343 is REINSTATED.
THIRD DIVISION
JARDELEZA, J.:
THE CASE
This is a petition for review on certiorari under Rule 45 of the Revised Rules of Court seeking the reversal
of the Resolution1 of the Former Seventh Division of the Court of Appeals (CA) dated August 23, 2006,
which held respondent entitled to liquidated damages equivalent to 70 days of delay, 10% retention fee,
and payment for expenses for repainting job arising from a construction dispute.
FACTS
Petitioner2 find respondent3 entered into a Construction Agreement, under which petitioner would
construct for respondent a three-story building housing a meat processing plant and a showroom office
in Yakal Street, Makati City. The parties agreed on a contract price of Php 43,800,000.00 and a
completion and delivery date of April 7, 1995.4 Due to several delays, however, petitioner turned over
the building only on August 15, 1995.5 Respondent did not accept the building, asserting it had many
deficiencies. Respondent paid petitioner only Php 38,088,445.00.6 Thus, petitioner filed a complaint for
sum of money against respondent before the Pasig Regional Trial Court (RTC) for the balance of Php
4,771,221.59.7 In addition, petitioner prayed for the payment of Php 141,944.93 representing expenses
incurred due to work on respondent's changes or additional orders, and for a judgment that the
liquidated damages claimed by respondent in the amount of Php 3,066,000.00 was without basis. 8
Petitioner enumerated in its complaint the following reasons why the project was delayed:
1. At the start of the excavation phase, petitioner had to remove two to three layers of concrete
slabs over the construction site, instead of only 1 layer.9 The soil was also found to be extra soft
and had to be filled with boulders. Respondent granted petitioner an extension of only 7 days,
but the remedial work required in the removal of the extra layers of concrete slabs, and in
stabilizing the condition of the soil, took 30 - 40 days to finish.10
3. The building permit was not secured on time. The application for the building permit was not
initially processed by the Building Official of Makati City because respondent failed to timely
secure the required Environmental Clearance Certificate (ECC).12
4. Respondent informed petitioner that the building plan will be revised, such that the locations of
the columns, beams and walls to be put up were to be determined only through the verbal
instructions of respondent's construction manager.13
5. On February 20, 1995, the City Building Office served petitioner with an order to stop all
construction works until a building permit is secured. Despite this "stop work order," respondent
ordered petitioner to continue with the construction discreetly.14
6. It was only on March 23, 1995 or after the lapse of 31 days from the "stop work order" when the
building permit was secured.15
Thus, while the demolition, excavation, and initial construction works started on November 26, 1994,
regular construction works began only 113 days after, or on March 24, 1995.16
Petitioner further alleged that even after the original completion date of April 7, 1995, construction works
continued.17
Respondent even ordered substantial changes and additional works after April 7, 1995, which took 130
days to complete, or until August 14, 1995.18 In total, petitioner claimed it was entitled to an extension
of 243 days, yet asked for only 130 days.19 Respondent, however, granted petitioner with a mere 60-day
extension and held it in default for the remaining 70 days. Consequently, petitioner was charged with
liquidated damages computed at Php 43,800.00 for every day of delay, or a total of Php 3,066,000.00.20
In its defense, respondent attributed the delays to the fault of petitioner. Respondent denied suppressing
information about the existence of the extra layer of concrete slabs and the extra soft condition of the
soil.21 It alleged that petitioner was given this information during the pre-bidding conference, and that
petitioner inspected the site and was present during soil testing.22 Respondent averred that petitioner
was responsible for securing the required permits.23 As to the changes and additional works, respondent
asserted it gave petitioner a 60-day extension, even if these works were merely linear, meaning they
may be performed without interrupting the normal pace of the construction work.24 In sum, respondent
blamed petitioner's poor workmanship, persistent inaction in satisfying respondent's complaints, and
lack of, or defective equipment, for the delays.25 Respondent claimed that due to petitioner's poor
workmanship, the turnover in August 1995 was merely partial because there were several works that
needed to be adjusted and corrected, to which petitioner agreed.26 This poor workmanship on the part of
petitioner pushed the actual turnover to October 15, 1995.27 Nevertheless, respondent maintained that
out of benevolence, it computed delay only from June 6, 1995 to August 15, 1995 (70 days) instead of
up to October 15, 1995.28 Even then, after the turnover, respondent had to hire another contractor to do
corrective and repainting works because of the same poor workmanship of petitioner. Respondent
allegedly incurred additional expenses worth Php 1,202,888.50 for the repainting work of the other
contractor.29
After trial, the RTC ruled in favor of petitioner.30 It duly noted the causes of delay petitioner outlined and
concluded that the 60-day credit respondent allowed for delay was not commensurate to the total
allowable or justifiable delay. Instead, the RTC ruled that petitioner was entitled to a 130-day extension
it requested. Thus, the liquidated damages respondent deducted from the agreed contract price was
baseless and unjustified. The dispositive portion of the RTC's Decision reads:
4. [C]ost of suit.
31
SO ORDERED. ChanRoblesVirtualawlibrary
On appeal, the CA modified the Decision of the RTC and held respondent entitled to its claim of liquidated
damages of Php 3,066,000.00 corresponding to petitioner's 70-day delay. The dispositive portion of the
CA Decision32 reads:
the total sum being payable upon the finality of this decision.
Upon failure to pay on such finality, twelve (12%) per cent
interest per annum shall be imposed upon afore-mentioned
amount from finality until fully paid.
On Motion for Reconsideration, the CA modified its Decision.34 On re-evaluation of the evidence, the CA
ruled that respondent was entitled to the expenses worth Php 1,050,000.00 it incurred for the repainting
job done by another contractor. The CA also granted respondent's claim for a retention fee of 10%. The
CA's new computation35 reads:
Hence, this petition, which argues in the main that the CA misappreciated relevant facts and prays that
the decision of the RTC be reinstated.
OUR RULING
Petitioner raises questions of fact, which generally, we cannot entertain in a Rule 45 petition. We are not
obliged to review all over again the evidence which the parties adduced in the courts below. Of course,
the general rule admits of exceptions, such as where the factual findings of the CA and the trial court are
conflicting or contradictory.36 This exception is present here.
The RTC ruled in favor of petitioner, finding that the delay in the construction was not its fault. The RTC
found the extension of the delivery date of 60 days granted by respondent incommensurate to the total
number of days of justifiable delay. The CA, on the other hand, did not find all the grounds raised by
petitioner as causes for justifiable delay to be meritorious. The CA held petitioner at fault when it did not
adopt measures to arrest soil deterioration.37 The CA also held that petitioner should have notified
respondent that it (petitioner) would stop work until the required building permit was secured.38 Neither
did petitioner inform respondent that the revision of the building plan will cause delay. Thus, such
revision merely required a reorientation of the project.39 This was also true with the change orders and
additional works. The CA gave more credence to the testimony of respondent's witness, Engr. Antonio
Aliño, an engineer of 37 years' experience. Engr. Aliño testified that the change orders and additional
works merely required linear activities that did not affect the construction time.40 The CA then deferred
to the approximation of respondent that petitioner is, under the facts, entitled to only 60 days of
extension of the contracted completion date of April 7, 1995. This meant that the new completion date
can be moved to June 6, 1995.41 Since, however, the turnover was made only on August 15, 1995,
petitioner incurred delay for 70 days. For this, the CA found petitioner liable for liquidated damages for
70 days of delay.42
On reconsideration, the CA also noted that the defects on the painting job, which petitioner
acknowledged and tried to rectify, were not solved at all. In a letter dated May 31, 1996, respondent
informed petitioner that it (respondent) would hire another contractor to do the repainting job. Thus, the
CA found respondent entitled to liquidated damages, retention fee, and reimbursement for the expenses
in the repainting job.43
To recall, petitioner originally claimed it was entitled to a 113 day extension of the contracted delivery
date because of various delays that moved the regular construction date from November 26, 1004 to
March 24, 1995. These various delays were broken down as follows:
Rectification of the extra soft condition of the soil, which took 14 days;
Revision of the building plan, which affected the petitioner's conduct of work for a month, or 30
days;
One month "stop work order" from the City Hall of Makati due to lack of construction permit, or
30 days.
Petitioner argues that respondent concealed the existence of the concrete slabs and the condition of the
soil, which necessitated additional work, expense, and use of sophisticated equipment.44 The building
plan also had to be revised in an attempt to avoid the necessity of submitting an ECC as a measure to
facilitate the approval of the application for a building permit. At the same time, however, the revised
building plan was needed as supporting document to the application for a building permit, such that
without it, the application was put on hold.45 The revision also called for a 180-degree reorientation of the
building floor plan, which stalled the progress of construction for a month because petitioner had to rely
on and await mere verbal instructions from respondent's representatives.46When the revised building
plan was finally submitted to petitioner in January 1995,47 the building permit application was further
delayed because the city hall officials questioned the provisions on the parking area.48 Thus, due to the
lack of building permit, the city hall issued and served a "stop work order" in the construction premises
on February 20, 1995. This caused work to stop for a month, or until March 23, 1995, when the building
permit was finally secured.
Petitioner also claimed it was entitled to a 130-day extension corresponding to various additional works
and change orders from April 7, 1995 to August 14, 1995. The total number of days for extension,
therefore, was 243 days. Petitioner settled for 130 days instead.
In reply to petitioner's request for extension, respondent initially granted 34 days, which were broken
down as follows:
According to respondent, it granted only 7 days for the removal of concrete slabs because the delay was
caused by the frequent breakdown of petitioner's equipment. Respondent also granted only 7 days for
the delay in the construction permit because it did not prevent petitioner from continuing with the
construction. As for the construction of shear walls, a part of the additional works which petitioner
claimed took 30-40 days to finish, respondent granted only 14 days because the work was gradual. The
rest of the additional works and change orders were categorized by respondent as either linear activities
that can be executed simultaneously with the main work or repeat jobs due to petitioner's poor
workmanship and thus, did not merit any extension. On re-evaluation, respondent granted an additional
26 day extension, for a total extension of 60 days.
We stress at the outset that in its decision, the CA found petitioner entitled to extensions of 35 days for
the removal of concrete slabs, and 7 days for the work stoppage brought by a boundary dispute with
Sinclair Paints. The CA then upheld respondent's total grant of a 60 day extension. The computation,
however does not add up. Petitioner would be entitled to a 42 day extension for the concrete slabs and
the boundary dispute alone, leaving an additional extension of 18 days for other causes of delay. While
the CA found petitioner not entitled to any extension for the supposed delay in the building permit, it
ignored the extensions of 14 days for the construction of the shear walls, and 6 days for the holidays
which respondent already granted in favor of petitioner. These would have totalled to an additional
extension of 20 days. In effect, the CA's computation would not jibe with that of the respondent's.
At any rate, in determining whether respondent is entitled to liquidated damages and how much it is
entitled to, we reach a different conclusion than those of the lower courts.
Petitioner is entitled to an extension of 21 days for the delay during the excavation stage
The daily reports49 of respondent's project manager, Engr. Arnulfo Delima, show that petitioner
performed earth and demolition works involving excavation, boulders and gravel filling, and soil
poisoning from December 9, 1994 to February 14, 1995. But in the construction schedule50 petitioner
submitted to respondent, the duration of the earth and demolition works should have only been from and
until mid-December 1994.51 Petitioner accuses respondent of suppressing information about the
existence of the concrete slabs and the extra soft condition of the soil, which were material in petitioner's
determination of the time and cost required by the works. Thus, petitioner asks for a total extension of
approximately 1 and 1/2 months equivalent to the actual period it took petitioner to perform these
earthworks.
We disagree that petitioner is entitled to a full extension of its request (30-40 days for the removal of the
concrete slabs and 14 days for arresting the soil condition). We hold that for these excavation works, it
is fair to grant petitioner with a total extension of only 21 days or three weeks.
The existence of the layers of concrete slabs and the extra soft condition of the soil was not easily
determinable upon site inspection. In fact, these were not included in the Construction Agreement or in
the Minutes of the Pre-Bid Conferences.52 Petitioner would have considered in its bid plan and proposal
the attendant time and costs the measures required to address these conditions had it known about them
from the beginning.53 In Advanced Foundation Construction Systems Corporation v. New World
Properties and Ventures, Inc.,54 we deferred to the expert opinion of the Construction Industry
Arbitration Commission that in practice, removal of underground obstructions is a "major item of work"
that needs to be included in the contractor's scope of work. It cannot be understood as being merely
subsumed under the general heading "miscellaneous."55
Mere, the CA agreed with petitioner that the concrete slabs were unforeseen and their removal caused
delay in the construction phase. The CA also acknowledged that the extra soft condition of the soil cannot
be easily seen with the naked eye. The CA thus held "it is understandable that BFC could not be expected,
upon ocular inspection, to immediately determine the soil condition."56
We rule, however, that the removal of the concrete slabs and the filling of boulders may have taken two
or three more times in effort to accomplish than usual.57 The removal also took time because of the
frequent breakdown of the heavy equipment petitioner used in the process, and petitioner's failure to
provide enough manpower. The daily reports58 support this and Engr. Delima also convincingly testified:
When I supervised the work, our schedules have not been met,
A:
we have some delays in the excavations, madam.
How about the work schedules, the shifting of men during the
Q:
construction?
We also requested the B.F. to add some men for us to be able to
A: work for 24-hour [sic], but still, it took time for them to add men,
madam.59
Petitioner was obliged to provide "all materials, labor, tools, and equipments [sic], and other incidentals
required for the complete and satisfactory completion of the project"60 for the project. Under Section 5 of
the Construction Agreement, "[a]ll materials and labor of every grade and equipment necessary for the
prosecution and termination of the work shall be of the best grade of their respective kind and the quality
of workmanship shall be in accordance with the requirements of the contract and its
Annexes."61 Petitioner was, therefore, obliged to provide the appropriate equipment in good running
condition. Failing on this, petitioner is not entitled to the full extension of 30 - 40 days it requested.
We also disagree that petitioner is entitled to a full extension of 14 days it requested for the delay caused
by the extra soft condition of the soil.
Firstly, we defer to the testimony of Arch. Orencio Sare, Jr., the designer of the building, that the soil
investigation report62 dated September 1994 was not crucial for the contractor's work. Arch. Sare
testified that the report was only instrumental for the designer's work and not for the contractor's
because it was intended to determine the soil bearing capacity.63 Hence, we agree that there was no
malicious intention to suppress the soil investigation report from petitioner, even if it was only furnished
to petitioner alter the contract was awarded in November 1994.64 This is not to say, however, that the
contractor should not be apprised of the actual condition of the soil before bidding. The soil report could
have assisted petitioner in estimating the extent of its excavation works. As Mr. Gerardo
Apoderado65 testified, the extra soft condition of the soil spelled problems because the area cannot be
excavated to the required elevation.66 In its letter dated December 9, 1994,67 petitioner proposed to
respondent that since the actual soil condition is very soft, thicker boulders and a thicker gravel base
should be used. Petitioner then informed respondent that these changes, on top of the demolition of
unforeseen concrete slabs and arresting the soil condition, would result in additional working time and
cost. Respondent did not object to or refute this letter.68
Respondent claims, however, that petitioner was responsible for the delay caused by the soil condition
because it failed to immediately provide remedies when water from a broken drainage nearby seeped
in.69 Thus, in a letter dated January 16, 1995, respondent reminded petitioner of the required bottom
elevation and noted that petitioner's latest excavation was undercut. Respondent also brought to
petitioner's attention the muddy condition of the excavated area.70
We agree with the CA that petitioner should have taken measures to address the problem with the broken
drainage. We note that as of January 16, 1995, petitioner had failed to properly stabilize the soil and
obtain the required elevation of the area.71 This is a lapse which merits a reduction on petitioner's
estimate for extension. We merely reduce the extension on the finding that at most, the broken drainage
only aggravated the soil condition, but doesn't change the fact that it had been extra soft from the start.
It was not even shown when the drainage broke and leaked and whether its effects were visible or known
to petitioner from the beginning. Furthermore, in the same manner that petitioner should answer for the
faulty equipment used in the removal of the concrete slabs, petitioner should also answer for the delay
in the deliveries of the boulders used for filling in the excavated area.72
All told, both parties were responsible for the delay caused by the excavation and earthworks. Thus, even
if petitioner may be held liable for negligence in the performance of its obligation, Article 1172 of the Civil
Code73 provides that such liability may be regulated by the courts according to the circumstances of the
case. Here, the existence of concrete slabs and the extra soft soil remained a condition beyond the
control of petitioner. Since these caused an unforeseen delay in the excavation stage, petitioner should
be credited accordingly. We find that a reduced extension of 21 days for the earth and demolition works
is commensurate and fair.
Petitioner is entitled to an extension of 38 days for the delay in securing the building permit and for the
stop work order issued by the Makati City Hall.
The Construction Agreement provides that the agreed period of completion shall be automatically and
correspondingly extended if the works are suspended to comply with any rule or order of public or
government authorities74. We agree with the CA's explanation that before this provision can be
considered in favor of petitioner, the latter should not be at fault.75 We rule that petitioner was not at
fault.
Under the Construction Agreement, terms and conditions reflected in the minutes of the pre-bid
conferences shall be effective and binding upon the parties as terms and conditions of the Construction
Agreement, except when modified or altered by the latter.76 The minutes of the second pre-bid
conference on November 9, 1994 provided that respondent, through its designer, A.L. Aliño Engineers
and Architects, will initiate securing the building permit, and which activity will be continued by the
winning bidder.77 In other words, although the obligation to obtain the permit will ultimately devolve to
petitioner, respondent had to act first by securing the ECC from the DENR, a prerequisite to the building
permit application. Arch. Sare confirmed this understanding between the parties:
A: Yes, sir.
A: Yes, sir.
xxx
xxx
A: Yes, sir.
The defendant did that precisely because of what appeared in the
Q:
highlights of the meeting on November 9, 1994, am I correct?
A: Yes, sir.
When was that the defendant filed for the issuance of ECC
Q: clearance from the DENR? Was it during the progress of the
construction?
A: Yes, sir.78
Respondent is bound by the foregoing terms in the Construction Agreement and as refelcted in the
minutes. Contracts constitute the law between the parties, and they are bound by its stipulations. For as
long as they are not contrary to law, morals, good customs, public order, or public policy, the contracting
parties may establish such stipulations, clauses, terms and conditions as they may deem convenient.79
In a letter dated December 13, 1994, petitioner informed respondent that it has applied for the building
permit, but that respondent, in turn, has to secure the ECC, which is "vital in the application for [the]
building permit."80 Petitioner reminded respondent that as the owner, it (respondent) was in a better
position to know the process flow of the meat processing plant.81 Thus, it was only logical that
respondent should be the one to file and secure the ECC. The CA has also acknowledged this much,
saying that it was appropriate and understandable that the duty to secure the ECC should devolve upon
respondent because the nature of the business is highly technical.82 However, the CA held that petitioner
should have notified respondent that it (petitioner) would stop construction work until the required
building permit was in order.83
We disagree with the CA that petitioner was not vigilant enough. The December 13, 1994 letter was,
effectively, a reminder from which respondent should have taken its cue. Petitioner stated in the letter
that it has already done its part in the filing of the building permit as required in the contract. But due to
the unavailability of an ECC and other permits, petitioner informed respondent it is losing precious time.
Without a building permit, petitioner cautioned respondent that its works will be limited to those covered
by its existing excavation permit, which were excavation and fencing.84 Despite this reminder,
respondent secured an ECC only on February 22, 1995.85 Respondent should, therefore, bear the effect
of the delay caused by the stop work order from the city hall. This is but fair because it failed in its
obligation to initiate the building permit application.
Respondent should further bear the effect of the delay because its revision of the building plan
contributed to delaying the building permit application.
The building plan, for reasons unclear, had to be revised during the excavation stage.86 Respondent
insists petitioner suggested the idea so the building would be converted from a meat processing plant to
a regular office, thus dispensing with the requirement for an ECC.87 The ECC, however, continued to be
required and was eventually secured and submitted for the building permit application. Petitioner claims
the revision delayed its work for a month because petitioner had to rely mainly on the verbal instructions
of respondent's representatives. Respondent, on the other hand, maintains there was no complete work
stoppage. The lack of building plan did not materially hamper the construction because the revision only
called for a reorientation of the floor plan. Thus, respondent only gave petitioner an extension of 7 days.
We agree with the CA that the revisions merely involved a reorientation of the project, such that
petitioner only had to implement a mirror image of the original plan.88 Engr. Aliño persuasively testified
that there was not much effect in the construction schedule because it was still during the excavation for
the foundation. As such, work can be done through the guidance of the project engineer. Respondent
also gave petitioner a preliminary sketch to guide it on how to continue.89
Arch. Sare corroborated Engr. Aliño's testimony. According to Arch. Sare, the revised building plan is only
a mirror image of the original one.90 Mr. Apoderado, on the other hand, failed to specify how drastically
different the revised plan is from the original. During his cross-examination, Mr. Apoderado admitted that
"not much" had been changed with the plan.91 We, therefore, uphold the original grant of an extension of
7 days.
However, the revision of the. building plan also affected the building permit application because the
building plan was one of its supporting documents.92 The lack of a building permit affected the work of
petitioner in such a way that even though there was no complete work stoppage, the work was done
surreptitiously and intermittently. Petitioner was wary of getting caught for working without a permit and
be penalized accordingly. We find these concerns of petitioner genuine. As early as December 3, 1994,
petitioner reminded respondent, about the revised plan.93 In its subsequent letter dated December 13,
1994, petitioner stressed that "at present, [its] work permit covers only the excavation and fencing of the
work area as authorized by the Municipality of Makati."94 Petitioner further informed respondent that
without the plan and the building permit, its work would be limited to excavation and gravel fill.
Respondent gave petitioner the revised building plan only on January 3, 1995.95 When it was submitted
with the building permit application, the city hall officials questioned petitioner anew on the provisions for
the parking area. It was finally re-submitted on February 27, 1995,96 when the stop work order was
already in force. Thus, it may be true that even without a building permit, petitioner kept working, albeit
discreetly, under respondent's instructions. But it cannot be denied as well that the lack of building
permit prevented petitioner from carrying out its work freely and efficiently. The admission of Engr.
Delima is telling:
Do you know for a fact also that the plaintiff in this case as early
as December 13, 1994 wrote the defendant a letter, through you,
Q: informing the defendant that because of the lack of building
permit the [timetable] or construction time will be considerably
affected?
A: Yes, sir.
A: Yes, sir.97
As such, it is only fair that respondent bear the consequences of the 31 - day stop work order of the city
hall because it failed in its duty of securing the building permit. Thus, for the delay in securing the
building permit, we find that petitioner is entitled to a total extension of 38 days.
Petitioner is entitled to an extension of 40 days for the change orders and extra works.
The CA gave more credence to the testimony of Engr. Alifio that the change orders and extra works
petitioner requested extensions for were mere linear activities that did not affect the construction time.
The CA also held that contrary to Section 16 of the Construction Agreement,98 these change orders and
extra works were done without the written mutual agreement of the parties.99
However, out of the 34-day extension respondent initially granted petitioner, 14 days were allocated for
the construction of shear walls, which was one of the change orders and additional works respondent
allegedly requested from petitioner.100 When petitioner requested for re-evaluation, respondent granted
an additional extension of 26 days, which appear to cover for the alleged change orders and extra
works.101 In its Answer with Counterclaim102 dated October 10, 1997, respondent countered that
"[petitioner] should be grateful for the grant of a [60-day] extension credit because most of [these]
change orders/[revisions] consist of linear activities, i.e., they can be performed simultaneously or
without interrupting the normal pace of the construction work. In fact, [petitioner] was generously given
time extension where credit is not due."103
Furthermore, during cross-examination, Engr. Aliño admitted that "[the] extra work, change orders
would cover canvassing, procurement, installation and fabrication of materials which would necessitate
substantial additional time and money on the part of [petitioner]."104
We hold respondent for the above admissions. Notwithstanding the nonconformity with the literal terms
of Section 16 of the Construction Agreement, respondent liberally granted extensions for the change
orders and extra works. As correctly pointed out by petitioner, "[t]he construction agreement does not
nullify the change orders/extra works that were already completed without any written agreement. In
feet, Werdenberg had partially paid [therefor] leaving an unpaid balance of only P141,944.93."105 In its
Answer with Counterclaim, respondent indeed stated that petitioner is entitled to Php 141,944.93 for the
change orders and additional works.106
Thus, we hold that petitioner is entitled to a total extension of 40 days for the change orders and extra
works.
Finally, we agree with the CA when it held that petitioner is entitled to an extension of 7 days for the work
stoppage ordered by respondent to resolve the boundary dispute with another company, Sinclair
Paints.107 The CA cited the testimony of respondent's witness, Ms. Josephine del Val, confirming that the
work stoppage took 7 days.108 Petitioner should also be entitled to another extension of 6 days, which
respondent granted, to cover the holiday breaks.109
The liability for liquidated damages is governed by Articles 2226 to 2228 of the Civil Code,110 where the
parties to a contract are allowed to stipulate on liquidated damages to be paid in case of breach. It is
attached to an obligation in order to ensure performance and has a double function: (1) to provide for
liquidated damages, and (2) to strengthen the coercive force of the obligation by the threat of greater
responsibility in the event of breach. The amount agreed upon answers for damages suffered by the
owner due to delays in the completion of the project.111
The Construction Agreement provides that upon failure to complete the work agreed upon within the
stipulated time, the contractor agrees to pay the owner Php 43,800.00 for every day of delay. 112 As a
pre-condition to such award, however, there must be proof of the fact of delay in the performance of the
obligation.113
We have already ruled that the parties were mutually at fault. Petitioner is entitled to an extension of only
112 days counted from April 7, 1995 or until July 28, 1995. Thus, from July 28, 1995 to August 15, 1995,
or a period of 18 days, petitioner had already been in default. Consequently, respondent is entitled to Php
788,400.00 as liquidated damages.
Petitioner wrote respondent a letter of turnover dated August 16, 1995.114 On August 18, 1995,
respondent replied, detailing its comments on the turnover list.115 A recurring comment was the need to
either re-paint or to complete the painting job. Respondent rejected the turnover until such time that
petitioner would have "favorably remedied [respondent's] complaints on the defects xxx and generally
on workmanship of the building."116 Petitioner acknowledged these defects in a letter dated October 11,
1995 and informed respondent that it will proceed with repainting.117 Clearly, the defects in the painting
job were covered by the guarantee of petitioner.
However, the repainting job still proved deficient. In a letter dated May 31, 1996,121 respondent informed
petitioner that it has taken the initiative to get an outside contractor for the subsisting deficiencies.
Respondent subsequently contracted Silver Line Builders for the repainting job in the contract price of
Php 1,050,000.00.122 Petitioner should answer for these expenses, pursuant to Article 1167 of the Civil
Code:
WHEREFORE, the petition is PARTLY GRANTED and the assailed Resolution MODIFIED. Petitioner is
entitled to an award of Php 2,767,290.768 computed as follows:
Less:
- liquidated damages by BFC
788,400.00
Php
4,124,767.52
Less:
- expenses for repainting job due to Werdenberg
1,050,000.00
Less:
- 10% retention fee by Werdenberg
307,476.752
Php
- amount due to BFC
2,767,290.768
The amount due BFC shall be with interest of 6% interest per annum from the filing of the complaint until
full payment.127
SO ORDERED.
FIRST DIVISION
DECISION
PERLAS-BERNABE, J.:
Assailed in this petition for review on certiorari1 are the Decision2 dated May 22, 2015 and the
Resolution3 dated December 14, 2015 of the Court of Appeals (CA) in CA-G.R. CV No. 101120, which
affirmed the Decision4 dated October 25, 2012 and the Resolution5 dated January 10, 2013 of the
Regional Trial Court of Quezon City, Branch 99 (RTC) in Civil Case No. Q-95-25680, dismissing the
complaint of Nanito Z. Evangelista (Nanito) for failure to establish his money claims against respondents
Spouses Nereo V. Andolong III and Erlinda T. Andolong (Spouses Andolong) and Rino Amusement
Innovators, Inc. (RAII; collectively, respondents).
The Facts
The instant petition stemmed from a complaint for sum of money, accounting and specific performance
with prayer for issuance of writ of preliminary attachment and damages6 filed on November 22, 1995 by
Nanito against respondents before the RTC, docketed as Civil Case No. Q-95-25680. Nanito alleged that
Spouses Andolong are the majority shareholders of RAII, a domestic corporation engaged in the business
of operating amusement centers.7 On various dates, Nanito and respondents entered into various
memoranda of agreement (MOA),8 as well as deeds of assignment/sale with right to repurchase over
machines, equipment, and amenities, which were used in the operations of amusement centers in
different malls, such as SM Centerpoint in Manila,9 Sta. Lucia East Grand Mall in Cainta, Rizal,10 and
Gaisano Country Mall in Cebu11 (subject contracts).12 In the subject MOA, the parties agreed, inter alia,
that they would equally share, i.e., 50%-50%, from the net profits of said amusement centers and that
respondents would remit Nanito's share on the 15thand 30th of the month. 13 Claiming that respondents
failed to comply with their obligation to remit his share of the net profits, Nanito filed the instant
complaint.14 In support thereof, Nanito presented various computations of the revenues earned by the
amusement centers.15 In an Order16 dated June 27, 1996, the RTC limited Nanito's money claim to
P2,241,632.00, according to the stipulation of the parties in open court.17
After the presentation of Nanito's evidence, respondents filed a Demurrer to the Evidence,18 which was,
however, denied by the RTC.19 Eventually, respondents failed to present their evidence despite the
opportunity to do so; thus, they were deemed to have waived their right thereto. Thereafter, the RTC
directed the parties to file their respective memoranda20 to which they complied.21
During the pendency of the case, Nanito died and, consequently, was substituted by his heirs,
represented by his surviving spouse, Leovigilda C. Evangelista22 (petitioners).
The RTC Ruling
In a Decision23 dated October 25, 2012, the RTC dismissed petitioners' complaint for insufficiency of
evidence. Essentially, the RTC found that Nanito failed to establish his claim against respondents in the
stipulated amount of P2,241,632.00, as all the evidence he presented did not prove his entitlement
thereto. Similarly, the RTC dismissed respondents' counterclaims24 for lack of proof.25
Petitioners filed a motion for reconsideration,26 but the same was denied in a Resolution27 dated January
10, 2013. Aggrieved, petitioners appealed to the CA.28
The CA Ruling
In a Decision29 dated May 22, 2015, the CA affirmed the RTC Ruling in toto. It held that while Nanito's
documentary exhibits were admissible in evidence as they were presumed to have been made in the
ordinary course of business, such documents only disclosed the gross monthly revenue earned by the
amusement centers in their operation and did not show the actual profit earned by said centers.30 In this
regard, the CA pointed out that the respective amounts of gross revenue were still subject to expenses
incurred in relation to the centers' daily operations, as well as the re-infusion of any possible earnings as
capital in order to sustain the maintenance of the machines and equipment therein.31Thus, in view of the
inconclusiveness of the evidence presented in proving the existence of the net profits, the CA concluded
that petitioners failed to prove their cause of action by a preponderance of evidence, warranting the
dismissal of the complaint.32
Petitioners moved for reconsideration,33 which was, however, denied in a Resolution34 dated December
14, 2015; hence, this petition.
The essential issue for the Court's resolution is whether or not the CA correctly held that petitioners failed
to prove their cause of action by a preponderance of evidence.
In civil cases, it is a basic rule that the party making allegations has the burden of proving them by a
preponderance of evidence. Also, parties must rely on the strength of their own evidence, not upon the
weakness of the defense offered by their opponent. This principle equally holds true, even if the
defendant was not given the opportunity to present evidence because of a default order. The extent of
the relief that may be granted can only be as much as has been alleged and proved with preponderant
evidence required under Section 1, Rule 13335 of the Rules of Court.36
"Preponderance of evidence is the weight, credit, and value of the aggregate evidence on either side and
is usually considered to be synonymous with the term 'greater weight of the evidence' or 'greater weight
of the credible evidence.' Preponderance of evidence is a phrase which, in the last analysis, means
probability of the truth. It is evidence which is more convincing to the court as worthier of belief than that
which is offered in opposition thereto."37
In the instant case, it is undisputed that under the subject contracts, Nanito had invested a grand total
of P5,728,800.00.38 Under the subject MOA, he is entitled to receive 50% of the net profits of the
amusement centers and that such profits must be remitted to him on the 15th and the 30th of each
month.39 However and as correctly pointed out by the CA, the documents presented by Nanito only
showed the gross monthly revenue of the amusement centers without taking into consideration their
daily operational expenses, as well as there-infusion of any possible earnings as capital in order to
sustain the maintenance of the machines and equipment. As such, these documents are inconclusive in
proving the existence of any net profits that respondents failed to remit to Nanito.
Be that as it may, the Court recognizes the fact that under the terms of the subject contracts,
respondents have exclusive control over the operations of the amusement centers, with Nanito acting as
a mere investor in the said ventures. Naturally, Nanito had no access to documents that would show the
existence of net profits, considering that all documents pertaining to the operations of the covered
amusement centers, including financial statements, are all in the possession of respondents. Given this
circumstance, Nanito was constrained to rely on the various computations of the revenues earned by the
amusement centers as certified by the mall-owners where they were situated.40 Such computations are
enough to establish the existence of gross revenue from which the net profits may be derived at by
simply subtracting all the operational expenses, as well any other possible deductions thereto such as
any re-infusion of possible earnings as capital.
For respondents' part, they could have easily rebutted petitioners' claim for Nanito's share of net profits
by producing pertinent documents which would show that the aforesaid gross profits were just enough,
or even inadequate, to cover the operational expenses and capital re-infusions to sustain the amusement
centers. Unfortunately, respondents opted not to shed light on the issues at hand as they, unwittingly or
otherwise, waived their right to present evidence in this case. In this light, the Court is thus left with no
option but to rule that the respondents' failure to present the documents in their possession — whether
such failure was intentional or not — raises the presumption that evidence willfully suppressed would be
adverse if produced.41
Under the foregoing circumstances, the Court is convinced that Nanito should have received remittances
representing net profits from respondents, albeit he failed to prove the exact amount he should receive
from the latter. In Seven Brothers Shipping Corporation v. DMC-Construction Resources Inc.,42 the Court
allowed the recovery of temperate damages in instances where it has been established that some
pecuniary loss has been suffered, but its amount cannot be proven with certainty, viz.:
xxxx
As already adverted to, respondents' failure to remit the net profits to Nanito pursuant to the subject
MOA caused some pecuniary loss on the part of the latter, albeit he failed to prove the exact amount of
such loss. In view of such circumstance, the Court deems it reasonable to award temperate damages to
petitioners in the amount of P1,100,000.00, which is roughly half44 of P2,241,632.00, or the amount of
gross revenue claimed to have been earned by the amusement centers. Notably, the award of
P1,100,000.00 shall earn legal interest at the rate of six percent (6%) per annum from the finality of this
Decision until fully paid.
Finally, anent petitioners' other claims, i.e., regarding the monetary value of the arcade machines that
respondents allegedly pulled-out, suffice it to say that petitioners failed to prove their entitlement thereto
since — as correctly pointed out by the CA — the identity of the machines they claim to have been
pulled-out were not established by any competent proof.45
WHEREFORE, the petition is PARTLY GRANTED. The Decision dated May 22, 2015 and the Resolution
dated December 14, 2015 of the Court of Appeals in CA-G.R. CV No. 101120 are
hereby AFFIRMEDwith MODIFICATION, ordering respondents Spouses Nereo V. Andolong III and
Erlinda T. Andolong and Rino Amusement Innovators, Inc. to jointly and solidarily pay petitioners heirs of
Nanito Z. Evangelista, represented by his surviving spouse, Leovigilda C. Evangelista, temperate
damages in the amount of P1,100,000.00 with legal interest at the rate of six percent (6%) per annum
from finality of this Decision until fully paid.
SO ORDERED.