Vous êtes sur la page 1sur 45

1

FOODSERVICE
DESIGN
jdsanoria
2

LEARNING OBJECTIVES

• After this lesson, the students will learn to:


• Explain the role of each member of the foodservice design team.
• Describe the sequence of steps involved in the design of a
foodservice facility.
• Illustrate the work typically done by a food facilities design
consultant.
• Describe the method of compiling a cost estimate for a food
facility project.

jdsanoria
jdsanoria 3

PROJECT TEAM
4

PROJECT TEAM
• Owner’s Representative
• Architect
• Engineers
• Foodservice Design Consultant
• Interior Designer
• General Contractor
• Foodservice Equipment Contractor

jdsanoria
5

OWNER’S REPRESENTATIVE
• Responsibilities of the owner’s representative:
• Selecting design professionals (architects, engineers, etc.),
establishing the scope of their services, and negotiating fees.
• Determining the operational objectives of the project to guide the
design.
• Setting the budget for the project.
• Evaluating the designs prepared by the project team in light of
the operational objectives for the project.
• Accepting (or rejecting) the selections of furniture, fixtures, and
finishes recommended by the design professionals.
jdsanoria
6

ARCHITECT
• Serves as the overall leader of the design and construction
process.

• Coordinates the work of all the design professionals on the


project team and supervises the work of the contractors who
build and equip the facility.

jdsanoria
7

ARCHITECT
• Roles of the Architect:

• Principal in charge – responsible for negotiating the terms of


the design contract and ultimately responsible for successful
completion of the project.

• Design architect – works closely with the owner’s


representative in the early stages of the project, guiding the
planning and design process.

jdsanoria
8

ARCHITECT
• Roles of the Architect:

• Project manager – responsible for the day-to-day workings of


the design and construction process.

• Site architect – coordinates the work of the contractors and


their tradespeople throughout the construction process.

jdsanoria
9

ARCHITECT
• Factors considered in the selection of the
architect:

• Experience with similar projects


• Experience with foodservice facilities
• Performance on past projects
• Experience of the architect’s team
• Chemistry
jdsanoria
10

ENGINEERS
• Structural engineers – design systems to support the structure of
the building and to protect its integrity.
• Electrical engineers – design the systems that supply electricity as
needed in the facility.
• Mechanical engineers – design the plumbing, heating, ventilation,
and air conditioning systems within the facility.
• Civil engineers – typically design roads, bridges and similar
structures.
• Involved in foodservice projects only when the building site must
be developed and made ready for new construction.
jdsanoria
11

ENGINEERS

jdsanoria
12

ENGINEERS

jdsanoria
13

FOODSERVICE FACILITIES
DESIGN CONSULTANT
• Possess knowledge of operations, layout and design, engineering, and equipment.

jdsanoria
14

FOODSERVICE FACILITIES
DESIGN CONSULTANT
• Services provided by the consultants:
• Comprehensive planning and concept development

• Program: a foodservice facility program (architectural program)


translates the concept into a description of the functional spaces and
systems required.
• Program – a narrative presentation of the way a particular projected facility in
intended to operate.
• Systems – series of interacting parts (subsystems) that must be evaluated to achieve
the most satisfactory and efficient result

• Foodservice facility evaluations – assesses the strengths and weaknesses


jdsanoria
of an operation in relation to its intended objectives.
15

INTERIOR DESIGNER
• Gives the food service
operation its distinctive
visual character and
theme through the
design of interior
spaces, the selection of
colors, and the
specification of
furniture and finishes.

jdsanoria
16

INTERIOR DESIGNER

jdsanoria
17

INTERIOR DESIGNER

jdsanoria
18

INTERIOR DESIGNER

jdsanoria
19

INTERIOR DESIGNER

jdsanoria
20

GENERAL CONTRACTOR
• Builds the facility as it was designed by the architect, engineers, foodservice
consultant, and interior designer.
• Schedules, coordinates, and oversees the work of the subs and thus is
accountable for building, equipping, and furnishing the facility in accord with
the intentions of the owner and designers.

• Two other approaches to organizing the project team for the construction of
the facility:
• Using a construction manager rather than a general contractor.
• Using a design-build firm that has architectural, engineering, and
construction capabilities all within one organization.
jdsanoria
21

FOODSERVICE EQUIPMENT
CONTRACTOR
• Firm that provides foodservice equipment for the project.

jdsanoria
jdsanoria 22

DESIGN SEQUENCE
23

Foodservice
Facility Design
Sequence

jdsanoria
24

DESIGN SEQUENCE
• Five phases of the design sequence:

• Phase I: Schematic design (includes programming and space


analysis)
• Phase II: Design development
• Phase III: Construction documents
• Phase IV: Bidding and Contract Award
• Phase V: Construction administration (includes inspection and
acceptance)

jdsanoria
25

SPACE ANALYSIS

• Objective: To determine the size of each functional area


and the relationships among functional areas, according
to the owner’s operational objectives.

jdsanoria
26

SPACE ANALYSIS

Adjacency
Diagram

jdsanoria
27

SPACE ANALYSIS
DRY STORAGE OFFICES
PREPARATION
DINING
ROOM
REFRIGERATED
STORAGE BANQUET
ROOM

WARE
RECEIVING WASHING BAR ENTRY

TRASH BAR
HOLDING STORAGE
Bubble Diagram
jdsanoria
28

SPACE ANALYSIS

Example of
Summary of Space
Estimated from a
Program Statement

jdsanoria
29

SCHEMATIC DESIGN
• Primary purpose: to show the shape of the building, the entrances
and flow patterns, and the location of the dining rooms, kitchen, and
other major components of the foodservice facility.

• Architect’s drawings: will show elevations of the outside of the


building, site plans for the building lot, and the location of roads,
sidewalks, and parking lots.

• Foodservice design consultant’s drawings: show the shape,


size, arrangement, and major equipment items, for all of the
jdsanoria
foodservice and related areas.
30

SCHEMATIC DESIGN

Schematic Design
for a Production
Kitchen

jdsanoria
31

SCHEMATIC DESIGN
• Final cost estimate compiled by the architect includes:
• Land acquisition
• Site preparation
• Building construction
• Electrical, plumbing, and other mechanical systems
• Foodservice equipment
• Interior design and furnishings
• Construction loan interest costs
• Professional fees and other costs that will occur during planning
and construction
jdsanoria
32

DESIGN DEVELOPMENT
• The phase of the project when the owner’s representative,
architect, engineers, foodservice design consultant, and interior
designer flesh out the design of the project through increasingly
detailed drawings.

• Foodservice design consultant typically prepares:


• Detailed floor plans showing the location of each piece of
equipment.
• Utility plans (electrical, plumbing, ventilation) showing the
location of each utility connection and the load imposed by each
piece of equipment.
jdsanoria
33

DESIGN DEVELOPMENT
• Foodservice design consultant typically prepares:
• A book of catalog sheets (often called cut sheets or buyout
brochures) for each equipment item to be purchased from a
manufacturer.
• Elevations, sections, and/or detail drawings for each piece of
custom-fabricated equipment.
• Detail drawings of any special construction required for
foodservice equipment.
• Preliminary specifications.

jdsanoria
34

DESIGN
DEVELOPMENT

Design Development for a


Conference Center
Kitchen

jdsanoria
35

DESIGN
DEVELOPMENT

Examples of
Elevation
Drawings

jdsanoria
36

DESIGN
DEVELOPMENT

Design
Development
Utility Drawing
(Mechanical) for a
Small Scramble
Servery

jdsanoria
37

DESIGN DEVELOPMENT

Example of a
Foodservice
Equipment Catalog
Sheet

jdsanoria
38

DESIGN
DEVELOPMENT

jdsanoria
39

CONSTRUCTION DOCUMENTS
• Drawings – showing construction of the new or renovated facility, including all
site work, structural systems, rooms and other spaces, utility systems,
equipment, finishes and details.

• Specifications – describing the materials and products, the standards of


workmanship, the methods of fabrication and construction, the applicable code
requirements, and the methods of installation, cleaning and testing.

• General conditions of the contract – defining terms, assigning responsibility,


establishing payment schedules, describing how changes are to be handled, and
listing the specific project conditions.

jdsanoria
40

CONSTRUCTION DOCUMENTS

• Three basic types of specifications:

1. Descriptive specifications – completely identify all the


important characteristics of the material or product.
2. Proprietary specifications – identify the product by reference
to a manufacturer and model number, and require the
contractor to provide that item and no other.
3. Performance specification – establish performance criteria
that are relatively independent of the specific description of
the item.
jdsanoria
41

BIDDING AND CONTRACT AWARD

• Substitutions – are proposals to provide materials,


products, equipment, or systems from a manufacturer
other than the one named in the specifications (the base
bid).

• Alternates – are proposals to provide materials, products,


equipment, or systems different from what was described
in the specifications, generally at a significantly lower
price.
jdsanoria
42

CONSTRUCTION COORDINATION

• During the construction phase, the foodservice design


consultant performs these tasks:

• Submittal review
• Coordination
• Review changes to the work
• Attend job site meetings
jdsanoria
43

INSPECTION/ACCEPTANCE

• Punch list – describes all work that


remains to be done to complete the
project according to the plans and
specifications.

jdsanoria
44

INSPECTION/ACCEPTANCE
• First site visit – occurs when the walk-in systems have been erected,
the hoods have been hung from the ceiling, and the rough-in
connections for utility services are complete.

• Second visit – occurs after all the equipment has been set in place and
most of the pieces are connected to their respective utility services.

• Final visit – made after all equipment has been connected and tested
and is ready for food preparation.

jdsanoria
45

IMPLEMENTATION AND TRAINING

jdsanoria

Vous aimerez peut-être aussi