Page 1 SECURITY SHED BOQ

ELEMENT NO. 1

SUBSTRUCTURE (ALL PROVISIONAL)

EXCAVATION AND EARTHWORK

A Excavate oversite average 150mm deep to remove topsoil -


vegetable matter and deposit in spoil heap as directed 9.00 Sq.m 900.00 8,100.00

B Excavate trench for foundation starting from strip level and -


not exceeding 600mm deep 5.00 Cu.m 3,000.00 15,000.00

C Excavate pit for column base starting from strip level and not -
exceeding 600mm deep 1.00 Cu.m 3,000.00 3,000.00

D Extra over all kinds of excavations in rock (Provisional) 1.00 Cu.m 3,000.00 3,000.00

E Remove surplus excavated material from site 6.00 Cu.m 2,500.00 15,000.00

F Return, fill in and ram well selected excavated materials -


in trench and pits 4.00 Cu.m 1,500.00 6,000.00

G 300mm thick hardcore filling under floor slab well rammed


and consolidated in 150mm layers 7.00 Sq.m 4,500.00 31,500.00

H 150mm approved earth filling well rammed and compacted 7.00 Sq.m 2,500.00 17,500.00

I Prepare and apply "dieldrex 20" anti termite solution to sides


and bottom of excavation immediately before laying Concrete 7.00 Sq.m 2,200.00 15,400.00

To collection 114,500.00
SUBSTRUCTURE (Contd)

CONCRETE WORK

A 50mm concrete (1:3:6) blinding 7.00 Sq.m 4,500.00 31,500.00

Plain insitu concrete (1:2:4-19mm aggregate)

B Foundation 1.50 Cu.m 45,000.00 67,500.00

Reinforced insitu concrete (1:2:4-19mm aggregate)


filled into formwork and well packed and vibrated
around reinforcement (formwork and reinforcement
measured separately)

C Columns 0.30 Cu.m 45,000.00 13,500.00


-
D Column bases 0.30 Cu.m 45,000.00 13,500.00

E Steps 0.10 Cu.m 45,000.00 4,500.00

F 150mm Bed 6.50 Sq.m 4,500.00 29,250.00

REINFORCEMENT

High tensile bar reinforcement in Column,Column base,


Steps etc. (All Provisional)

G 12mm diameter bars 66.00 Kg 450.00 29,700.00

H 8mm diameter bars 7.00 Kg 450.00 3,150.00

To collection 192,600.00

Page 1 SECURITY SHED BOQ


Page 2 SECURITY SHED BOQ

SUBSTRUCTURE (Contd)

CONCRETE WORK (Contd)

FORMWORK

Sawn formwork to:

A Sides of column bases 2.00 Sq.m 2,500.00 5,000.00

B Sides of Column 3.00 Sq.m 2,500.00 7,500.00

C Risers of steps 150mm high 0.50 Sq.m 2,500.00 1,250.00

D Edge of bed, 150mm high 2.00 Sq.m 2,500.00 5,000.00

BLOCK WORK

Hollow sandcrete block work with cavities filled solid


with plain insitu concrete (1:2:4-20mm aggregate)

E 150mm thick wall 6.00 Sq.m 3,500.00 21,000.00

Clear Polythene sheet damp proof membrane

F 0.26mm Polythene damp proof membrane laid with welted joints


on and including 50mm layer of fine sand (measured net) 11.00 Sq.m 100.00 1,100.00

To collection 40,850.00
SUBSTRUCTURE (Contd)

COLLECTION

114,500.00

192,600.00

40,850.00

ELEMENT NO.1: SUBSTRUCTURE CARRIED TO SUMMARY 347,950.00

ELEMENT NO. 2

SUPERSTRUCTURE

CONCRETE WORK

Reinforced insitu concrete (1:2:4-19mm aggregate)


filled into formwork and well packed and vibrated
around reinforcement (formwork and reinforcement
measured separately)

A Columns 0.30 Cu.m 45,000.00 13,500.00

B Beams 0.40 Cu.m 45,000.00 18,000.00

REINFORCEMENT

High tensile bar reinforcement in Columns and beams


(All Provisional)

C 12mm diameter bars 40.00 Kg 450.00 18,000.00

Page 2 SECURITY SHED BOQ


Page 3 SECURITY SHED BOQ

D 8mm diameter bars 17.00 Kg 450.00 7,650.00

-
FORMWORK
-
Sawn formwork :
-
E To vertical sides of columns 7.00 Sq.m 2,500.00 17,500.00
-
F To sides and soffit of beam 6.00 Sq.m 2,500.00 15,000.00
-

ELEMENT NO. 2 - SUPERSTRUCTURE CARRIED TO SUMMARY 89,650.00

ELEMENT NO. 3

ROOF

ROOF COVERING

0.55mm flagspan deep trough 5 profile or other equal


and approved coloured aluminium corrugated
roofing sheets with one and a half corrugation side
laps and 300mm end laps and fixed in accordance
with manufacturers instruction (measured nett)
to timber purlins at 1200mm centres including
coating all surfaces in contact with other materials
with bitumenous paint

A Roofing 14.10 Sq.m 4,500.00 63,450.00

B Prov ide the provisional sum of N100000 for timber roof purlins,
tie beams and rafters to be expended as directed 100,000.00

To collection below 163,450.00

COLLECTION
163,450.00

ELEMENT NO. 3: ROOF CARRIED TO SUMMARY 163,450.00

ELEMENT NO.4

WALL

BLOCK WORK
-
Hollow sandcrete blockwork laid and jointed in
cement and sand (1:5) mortar -

A 150mm wall 10 Sq.m 3,500.00 35,000.00

ELEMENT NO. 4: WALLS CARRIED TO SUMMARY 35,000.00

ELEMENT NO. 5

Page 3 SECURITY SHED BOQ


Page 4 SECURITY SHED BOQ

DOORS

METAL WORK

Supply and fix approved high quality


steel doors in coloured frames
complete with all ironmongery required
including assembly of components parts plugging
and screwing frame to blockwork or concrete work
and pointing all round the edges in approved
mastic sealant

A Single Swing door size 750mmx 900mm high 1 No. 20,000.00 20,000.00

ELEMENT NO 5: DOORS CARRIED TO SUMMARY 20,000.00

ELEMENT NO. 6
FINISHINGS

INTERNALLY

FLOOR FINISHING

250 X250 X 8mm Polished glazed verified ceramic


tile paving to BS 1286 type B of approved colour
bedded and jointed in cement mortar on screeded bed
(measured separately) and pointed in matching colour
cement

A Tiling 6.50 Sq.m 4,000.00 26,000.00

B 100mm skirting 10.00 m 400.00 4,000.00

BEDS AND BACKINGS


-
Cement and sand (1:3)
-
C 42mm screeded bed 4 Sq.m 1,200.00 4,800.00

Page 4 SECURITY SHED BOQ


Page 5 SECURITY SHED BOQ

D 12mm Screeded backing 100mm high 10 m 360.00 3,600.00

To collection 38,400.00
ELEMENT NO. 6 (Contd)
WALL FINISHING

15mm thick cement and sand (1:4)


-
A Rendering to walls 20 Sq.m 1,500.00 30,000.00

PAINTING

Prepare, prime and apply two coats emulsion paint on

B Rendered walls 20 Sq.m 2,500.00 50,000.00

To collection 80,000.00
ELEMENT NO. 6 (Contd)

CEILING FINISHING
CEILING

A Supply and fix plastic type ceilings as directed by the


Architect including all other accessories 14 Sq.m 1,500.00 21,000.00

To collection below 21,000.00

COLLECTION

38,400.00

80,000.00

21,000.00

ELEMENT NO. 6: FINISHINGS CARRIED TO SUMMARY 139,400.00

SUMMARY Page No.

ELEMENT NO. 1 - Substructure 347,950.00

ELEMENT NO. 2 - Frame 89,650.00

ELEMENT NO. 3 - Roof 163,450.00

ELEMENT NO. 4 - Walls 35,000.00

ELEMENT NO. 5 - Doors 20,000.00

ELEMENT NO. 6 - Finishings 139,400.00


BILL NO. 1 -PROPOSED SECURITY SHED
CARRIED TO GENERAL SUMMARY 795,450.00